PPSTM (Scheduling) Lecture#4 by Hassan Daud

advertisement
Reference: Figure 6.2.
PMBOK® Guide, 5h Ed



Plan Schedule Management – The process of
establishing the policies, procedures, and
documentation for planning, developing, managing,
executing, and controlling the project schedule.
Define Activities – The process of identifying and
documenting the specific actions to be performed to
produce the project deliverables.
Sequence Activities – The process of identifying and
documenting relationships among the project activities.
Schedule Management Plan
Activity Lists and Attributes
• An activity list is a tabulation of activities to be included
on a project schedule. The list should include:
– The activity name
– An activity identifier or number
– A brief description of the activity
• Activity attributes provide more information about each
activity, such as predecessors, successors, logical
relationships, leads and lags, resource requirements,
constraints, imposed dates, and assumptions related to
the activity.
6
Milestones
• A Milestone is a significant event that normally
has no duration.
• It often takes several activities and a lot of work to
complete a milestone.
• Milestones are useful tools for setting schedule
goals and monitoring progress.
• Examples include completion and customer signoff on key documents and completion of specific
products
• High level milestones are given in project charter
• Sequence Activities is the Process of identifying and
documenting relationships among the project activities.
• The key benefit of this process is that the logical
sequence of work to obtain the greatest efficiency
given all project constraints.
• After defining project activities, the next step is
activity sequencing
– Involves reviewing the activity list and attributes,
project scope statement, milestone list and
approved change requests to determine the
relationships between activities
• A dependency or relationship is the sequencing of
project activities or tasks
• You must determine dependencies in order to use
critical path analysis
9
1
Inputs
1. Schedule Management
Plan
2. Activity List
3. Activity Attributes
4. Milestone List
5. Project Scope
Statement
6. Enterprise
Environmental Factors
7. Organizational Process
Assets
____________
2
Tools and
Techniques
1. Precedence
Diagramming
Method (PDM)
2. Dependency
Determination
3. Leads and Lags
____________
3
Outputs
1. Project Schedule
Network Diagrams
2. Project Document
Updates
____________
 Precedence Diagramming Method (PDM)
 Dependency Determination
 Leads and Lags
Precedence Diagramming Method (PDM)
• More popular than ADM method and used by
project management software
• Activities are represented by boxes
• Arrows show relationships between activities
• Better at showing different types of
dependencies
21
Arrow Diagramming Method (ADM)
• Also called activity-on-arrow (AOA) network
diagrams
• Activities are represented by arrows
• Nodes or circles are the starting and ending
points of activities
• Can only show finish-to-start dependencies
• Can omit activities that have no dependencies
Project Time Management
22
A Comparison of AON and AOA Network
Conventions
Activity on
Node (AON)
A
B
C
D
Activity
Meaning
B and C cannot
begin until A is
completed. D
cannot begin
until both B and
C are completed.
A dummy
activity is again
introduced in
AOA.
Activity on
Arrow (AOA)
A
Dummy
activity
B
D
C
Finish-to-Start – Activity A must finish
before Activity B can start
A
B
Start-to-Start – Activity A must start
before Activity B can start
A
B
Finish-to-Finish – Activity A must finish before
Activity B can finish
A
B
Start-to-Finish – Activity A must start
before Activity B can finish
A
B
AON Example
Activity
A
Description
Build internal components
Immediate
Predecessors
—
B
Modify roof and floor
—
C
Construct collection stack
A
D
Pour concrete and install frame
A, B
E
Build high-temperature burner
C
F
Install pollution control system
C
G
Install air pollution device
D, E
H
Inspect and test
F, G
Table 3.1
• Activities are represented by boxes.
• Arrows show relationships between activities.
• Better at showing different types of
dependencies.
29
AON Network
A
Activity A
(Build Internal Components)
B
Activity B
(Modify Roof and Floor)
Start
Start
Activity
Activity A Precedes Activity C
A
C
B
D
Start
Activities A and B
Precede Activity D
F
A
C
E
Start
H
B
D
G
Arrows Show Precedence
Relationships
Three Types of Dependencies
• Mandatory dependencies: inherent in the nature
of the work being performed on a project,
sometimes referred to as hard logic
• Discretionary dependencies: defined by the project
team; sometimes referred to as soft logic and
should be used with care since they may limit later
scheduling options
– Don’t start detailed design work until users sign-off on
all the analysis – good practice but can delay project
• External dependencies: involve relationships
between project and non-project activities
– Delivery of new hardware; if delayed can impact project
34
schedule
Leads and Lags
Leads and Lags
 Project Schedule Network Diagram
 Project Documents Updates




Activity List
Activity Attributes
Milestone List
Risk Register
 Enterprise Environmental Factors
 Organizational Process Assets
Network Diagrams
• Network diagrams are the preferred technique
for showing activity sequencing
• A network diagram is a schematic display of the
logical relationships among, or sequencing of,
project activities
• Two main formats are the arrow and precedence
diagramming methods
41
Develop Network Diagram?
Activity
A
B
C
D
E
F
G
H
Description
Time (weeks)
Build internal components
2
Modify roof and floor
3
Construct structure
2
Pour concrete and install frame
4
Build high-temperature burner
4
Install pollution control system
3
Install air pollution device
5
Inspect and test
2
Total Time (weeks)
25
Activity
A
Description
Build internal components
Immediate
Predecessors
—
B
Modify roof and floor
—
C
Construct collection stack
A
D
Pour concrete and install frame
A, B
E
Build high-temperature burner
C
F
Install pollution control system
C
G
Install air pollution device
D, E
H
Inspect and test
F, G
6.3.3.1 Project Schedule Network Diagram
Thank You
Download