Activity Definition Activity Sequencing Duration

advertisement
Project Time Management
Activity Definition
„ Activity Sequencing
„ Duration Estimating
„ Schedule Development
„ Schedule Control
„
Activity Definition
Input
Tools and Techniques
Output
Work Breakdown
Structure
Decomposition
Activity List
Templates
Supporting Detail
Scope Statement
Historical Information
Constraints
Assumptions
Expert Judgment
Work Breakdown
Structure
Activity Sequencing
Input
Activity List
Product Description
Mandatory Dependencies
Tools and Techniques
Output
Precedence Diagram
Project Network
Diagram
Arrow Diagram
External Dependencies
Conditional Diagram
Method
Milestone
Network Template
Discretionary Dependencies
Activity list update
(Revise Activity list: delete or add
act.)
FS : Finish-to-Start Relationship
FF : Finish-to-Finish Relationship
SS : Start-to-Start Relationship
SF : Start-to-Finish Relationship
GERT
System Dynamics Model: Loop Activity
Duration Estimating
Input
Activity List
Constraint
Assumption
Resource Requirement
Resource Capability
Historical data
Risk Identification
Tools and Techniques
Output
Expert Judgment
Activity duration
estimate
Analogous Estimating
(similar past act)
Quantitative based
duration (unit rate)
Reserve time
Basis of Estimate
Activity List Update
Schedule Development
Input
Project Network Diagram
Tools and Techniques
Output
Mathematical Analysis
Project Schedule
Duration Estimate
Critical Path Method
Resource Requirement
PERT
Resource pool description
Work Calendar
Time Constraint (dead line
or milestone)
Assumption
Lead and Lag Time
Risk Management Plan
Activity Attribute
Simulation
Duration Compression
Bar chart
Network-based Schedule
Support Detail
Resource Leveling
Schedule Management
Plan
Project Management
Software
Resource Requirement
Updates
Coding Structure
Schedule Control
Input
Project Schedule
Performance Report
Change Request
Schedule Management Plan
Tools and Techniques
Output
Schedule change
control system
Schedule Update
Performance
measurement
Lesson learned
Additional Planning
Project Management
Software
Variance Analysis
Corrective Action
Work Breakdown Structure
„
a "check list" of work to be accomplished;
a structured approach;
the scope of the work, broken down into smaller and more specialized work;
a document in which the major project work packages are identified;
a document in which the major project outputs and responsibilities are defined; and
„
an integration of schedule and budget.
„
„
„
„
allow better and more detailed planning;
„ facilitate the budget and schedule preparation process;
„ facilitate assignment of responsibility to organization
and/or functional area; and
„ provide a structure for monitoring and reporting of
project development and progress.
„
„
„
„
„
„
„
Measurable
Clear definition
Deliverable
Resource, Time and Cost assignable
Acceptable duration
Independent task
Aircraft System
„
0.0 Aircraft System
„
„
„
„
„
„
„
„
„
„
„
„
„
„
„
„
„
„
1.0 Air Vehicle
1.1 Airframe
1.2 Propulsion
1.3 Air Vehicle Applications Software
1.4 Air Vehicle system Software
1.5 Communications/Identification
1.6 Navigation/Guidance
1.7 Central Computer
1.8 Fire Control
1.9 Data Display and Controls
1.10 Survivability
1.11 Reconnaissance
1.12 Automatic Flight Control
1.13 Central Integrated Checkout
1.14 Antisubmarine Warfare
1.15 Armament
1.16 Weapons Delivery
1.17 Auxiliary Equipment
„
„
„
„
„
„
„
2.0 Systems Engineering/Program
Management
3.0 System Test and Evaluation
3.1 Development Test and Evaluation
3.2 Operational Test and Evaluation
3.3 Mock-ups
3.4 Test and Evaluation Support
3.5 Test Facilities
„
„
„
„
„
„
„
„
„
„
„
4.0 Training
4.1 Equipment
4.2 Services
4.3 Facilities
5.0 Data
5.1 Technical Publications
5.2 Engineering Data
5.3 Management Data
5.4 Support Data
5.5 Data Depository
„
„
„
6.0 Peculiar Support Equipment
6.1 Test and Measurement
Equipment
6.2 Support and Handling
Equipment
7.0 Common Support Equipment
„
7.1 Test and Measurement
Equipment
„
7.2 Support and Handling
Equipment
„
„
„
„
8.0 Operational/Site Activation
8.1 System Assembly, Installation and
Checkout on Site
8.2 Contractor Technical Support
8.3 Site Construction
8.4 Site/Ship/Vehicle Conversion
„
9.0 Industrial Facilities
9.1 Construction/Conversion/Expansion
9.2 Equipment Acquisition or
Modernization
9.3 Maintenance
„
10.0 Initial Spares and Repair Parts
„
„
„
„
CPM: Critical Path Method
„
„
Deterministic Time
PERT: Program Evaluation and Review Technique
„
„
„
„
„
„
„
Stochastic Time
t = (a + m + b)/6
v = ((b-a)/6)2
a : optimistic time
m : most likely time
b : pessimistic time
Standard Deviation = Square Root (Variance)
„
Non CPM Scheduling
„ Bar Chart
„ Line of Balance
Arrow Diagram
„ Precedence Diagram
„
Download