Iain Murray Presentation

advertisement

Presentation to BIFM NI

‘A PFI case study’

Iain A. Murray

Managing Director & Partner

BIFM Scottish Regional Chairman

Member of NI PPP Working Strategy Group

Cost Management

• Cost Estimates

• Procurement Advice

• Tender Documentation

• Change Management

• Engineering Services

Dispute Management

• Arbitration / Litigation

• Claims Preparations and Defence

• Dispute Resolution

• Document Services

• Programming Analysis na ti a n l

Re gions

G lo b llia t er

In n ce

Project Management

• Project Management

• Development Management

• Tenant Fit-Out Advisor

• PFI / PPP Advice

• Planning Supervision

• Information Management

Construction Management

• Construction Advice

• Design Management

• Programming

• Procurement of Trade Packages

• Management of Construction Site

• Quality Management

Consultancy

• Banking Support Services

• Construction and Property Tax

• Business Advantage

• Best Value

• Investigation and Analysis

• Research

FM Consultancy

• Life Cycle Costing

• FM Procurement

• Performance Measurement

• Utilities

• PFI/PPP Advice

The Project – Acute Hospital PFI

 First operational PFI procured Acute Hospital in Scotland

 circa £ 650m over 30 year concession period

 circa £ 65m capital value of construction project

 circa 350 Acute in-patient beds with circa 50 day care beds

 Full diagnostic and clinical support facilities

 Completed three months ahead of schedule

 250 staff transfer under the provisions of TUPE

 Full FM services from Estates, Cleaning, Catering & Security

 Integrated Helpdesk and CAFM system controls FM

LIFE CYCLE MANAGEMENT

Design Build

Fees Capex

1 Year 2 Years

Operate

Financing Costs

Running Costs Utilities

Operating Costs

Planned Preventative

Maintenance PPM

Reactive

Periodic

Replacement / Refurbish

Life Cycle

35 Years

Hand

Back

Total

End of

Term

Total

Cost of

Project

Year

35

Total

The Problem to be solved

 Project team moved on three years previous – no handover

 Interface between FM and Contractor during construction absent

Operational ‘go live’ accelerated by three months

TUPE staff transfer a year ahead of ‘go live’ without penalty

 Training on new systems not commenced

 Operational precedents not in existence

 Commissioning being undertaken without FM input

Construction handover documentation not complete at ‘go live’

Full payment mechanism penalties applied at ‘go live’

The objectives

 Delivery of service to appropriate levels prime objective

 Fully functioning and operational helpdesk

 Production of report to support payment mechanism requirements

 Completion of commissioning

 Programme of staff training on new systems

 Completion of construction handover documentation

 Production of management method statements

 Gap analysis of built environment to original priced FM

 Gap analysis of built environment to original lifecycle

The reasons for setting the objectives

 Delivery of service to appropriate levels

 PFI / PPP is ALL about long term transfer of risks

 Service delivery is largest single aspect of the project

 Non-performance WILL escalate into high unavailability deductions

 Health & Safety in a clinical environment is critical

 Some services such as porters and cleaning are essential to clinical support - i.e. blood delivery, patient movement, hygiene

 Clinicians are already under pressure to deliver care

 Lifecycle strategy requires service delivery support

The reasons for setting the objectives

 Fully functioning and operational helpdesk

 The helpdesk is the fulcrum of the service delivery

 Short response times require accurate and efficient responses

 The asset is of a significant size and diversity

 The operation is 24/7 and service levels do not drop at night

 PPM needs to link to reactive requests to prevent failures

 Essential in preparation of reports and invoices

Information is ‘live’ and the Trust have access to it

The reasons for setting the objectives

 Production of report to support payment mechanism requirements

 The Trust placed the emphasis on reporting to support invoices

 The Trust have a team of managers who scrutinise the report

 Un-reported failures reduces trust between the parties

 The objective from the Trust was to encourage improvements to service delivery through trend analysis

 The FM company requires to spot trends before triggers are hit

 From FM point of view it is a risk management tool

 From SPV and Funder perspective it is a risk management tool

The reasons for setting the objectives

 Completion of commissioning

 Required in order to prove systems were functioning to FM

 FM cannot safely operate and maintain un-commissioned equipment

 Commissioning figures are used as baseline for settings to systems

 Commissioning documentation required to complete construction handover documentation

 Written requirement of the Project Agreement and carried defaults for failure to complete

 Essential to contractor to obtain final payments

The reasons for the objectives

 Programme of staff training on new systems

 New systems did not compare with old facility systems

 Health & Safety issues at top of the Agenda

 Commissioning required to be carried out in presence of trained operatives

 Service delivery could not be adequately carried out without training

 Response times and ultimately mitigation of deductions through failures require training

 TUPE breach if training not executed to allow staff to perform their duties

The reasons for the objectives

 Completion of construction handover documentation

 Essential for the preparation of ALL method statements

Requirement to reconcile ‘as built’ facility with priced project 1998

 Requirement to reconcile location of all plant and equipment

 O&M manuals and Safety File required to write PPM

HTM’s required to be reconciled with Safety File

‘As built’ facility reconciliation with lifecycle costings

 Required to complete commissioning

 Required to populate the CAFM system

The reasons for the objectives

 Production of management method statements

NOT to be mistaken for ‘operational’ method statements

 The objective was to introduce the PFI principles of performance, availability and payment mechanism to the ‘management’ team

 Introduce the HTM requirements to the delivery of the service

Cross reference O&M, Safety File and ‘as built’ documentation to original project documentation

 Develop overarching management reference tool for on-site team who were not familiar with PFI

 Required to satisfy elements of the Project Agreement

The reasons for the objectives

 Gap analysis of built environment to original priced FM

 Project had gone through usual construction period development

 No FM input during construction, consequently no continued reconciliation had taken place

 Some elements of D&B type construction approach had ignored original FM calculations

Nuances of ‘as built’ accessibility to plant and equipment needed to be discovered and recorded

 Areas had to be recalculated and costs for servicing applied without increase to FM original costs (excluded indexation)

The reasons for the objectives

 Gap analysis of built environment to original lifecycle

 Project had gone through usual construction period development

 No lifecycle input during construction, consequently no continued reconciliation had taken place

 Some elements of D&B type construction approach had ignored original lifecycle calculations

Nuances of ‘as built’ accessibility to plant and equipment needed to be discovered and recorded for replacement costings

 Areas had to be recalculated and costs for replacement applied without increase to lifecycle original costs (excluded indexation)

How the objectives were met

 Delivery of service to appropriate levels

 A matrix of the risks to be covered was generated

 The risks were associated with individual service delivery types

 Performance was analysed and associated to MMS

 Health & Safety, specifically HTM requirements were incorporated

 Response times were examined in the context of available staff and their ability and target areas generated

 Service was put in context of clinician requirements

 Lifecycle strategy was related to MMS and service delivery

How the objectives were met

 Delivery of service to appropriate levels

 Staff training was elevated and accelerated including management

 PFI structure was detailed and explained in context of facility

 CAFM and Helpdesk systems were populated with all project specific data

 FM staff were introduced to construction and commissioning team

 Existing service delivery techniques were integrated into project from non-pfi healthcare service delivery projects

 Clear delineation of clinical and FM areas of responsibility were agreed with the Trust

How the objectives were met

 Fully functioning and operational helpdesk

 The helpdesk was made project and site specific by FSI

 Response times and priority levels were input

CAFM system populated with accurate ‘as built’ asset data

 Competent and responsible helpdesk operatives recruited

 PPM linked to reactive requests to prevent failures and spot trends

 Crystal reports used to generate accurate reports for invoice support

 Constant monitoring of the system introduced with the implementation of a dedicated 24/7 helpdesk manager

How the objectives were met

 Production of report to support payment mechanism requirements

 Physical monitoring and reporting requirements detailed and proforma created for direct input to CAFM

 Reporting format and detail agreed with the Trust

 No instance of failure to report deficiencies set at KPI 100%

 Report was integrated into MMS which defined how to spot trends, understand default triggers and manage risks

 Trends were acted upon and additional rectification reports generated

 SPV and Funder together with Trust agreed actions on reports

How the objectives were met

 Completion of commissioning

 Commission management plan generated and accelerated

 Commissioning data incorporated into MMS and operational systems

 Commissioning figures published as baseline for system operation

 Commissioning team and Construction handover team integrated to produce parallel documentation not sequential

 Commissioning management plan agreed with Trust and areas of non-compliance agreed for mitigation

 Final payments withheld from Contractor and Commissioning team until documentation completed

How the objectives were met

 Programme of staff training on new systems

 Manufacturer and installers of systems compelled to train FM staff on correct operation of all systems

 Health and Safety related issues given highest priority

 Commissioning required to be carried out in presence of FM operatives

 Instances of non-performance on PPM issues were charged back to contractor

 TUPE requirements were published and put in context of training to avoid instances of breach of conditions

How the objectives were met

 Completion of construction handover documentation

 Document control room (library) created

 Register of all documents both complete and incomplete created

 Construction documentation management plan implemented

 O&M manuals and Safety File given the highest priority

HTM’s reconciled with Safety File

‘As built’ drawing programme accelerated to completion

 Commissioning data cross referenced to construction data

 All information provided electronically for input to CAFM system

How the objectives were met

 Production of management method statements

NOT to be mistaken for ‘operational’ method statements

 MMS extracted information Project Agreement, Output Specification,

Financial Model, O&M’s, Safety File and HTM’s

 Written as a quick reference guide for management, placed in the data room (library)

 Written in plain english removing legalise

 Provided to the Trust as the required method statements and agreed as an accurate reflection of the spirit of the agreements

Intended to be ‘live’ documentation for continual use

How the objectives were met

 Gap analysis of built environment to original priced FM

Physical checks made on the ‘as built’ environment – survey

Complete reconciliation of asset’s with original asset schedule

 FM re-priced as if starting from scratch – gap analysis undertaken

FM Strategy developed with original costs on ‘as built’ environment with the original output specification standards

 Areas had to be recalculated and costs for FM applied without increase to original costs (excluded indexation)

 NO erosion of standards was acceptable

 New strategy agreed with the Trust

How the objectives were met

 Gap analysis of built environment to original lifecycle

Physical checks made on the ‘as built’ environment – survey

Complete reconciliation of asset’s with original asset schedule

 Lifecycle re-priced as if from scratch – gap analysis undertaken

 Lifecycle re-modelled and strategy put in place with original costs on

‘as built’ environment

 Areas had to be recalculated and costs for replacement applied without increase to lifecycle original costs (excluded indexation)

 No erosion of standards was acceptable

 New strategy agreed with the Trust

Some of the more bizarre revelations

 Remeasurement of the checks required on ‘as built’ environment increased possible failure points by 20% to 251,641

 Service failures in first month were re-measured using call completion times instead of call start times yielding an increase from

55% completion to 88% completion

 The helpdesk received 16,411 calls in the first month of operation

The lessons learned

 Create a vehicle for the bid team to articulate the spirit of the agreements to the operational team

 Place operational FM management representative within the construction team during the construction period

 Continually examine any changes in design or construction with original FM and LCM costs and specifications

 Educate construction team on the requirement for complete, accurate

O&M, Safety File and ‘as built’ drawings prior to handover

 Make operational FM team part of the commissioning process

 Create MMS for non-pfi literate staff and train them

www.gtfm.org

www.gardiner.com

Download