Managing Director & Partner
BIFM Scottish Regional Chairman
Member of NI PPP Working Strategy Group
Cost Management
• Cost Estimates
• Procurement Advice
• Tender Documentation
• Change Management
• Engineering Services
Dispute Management
• Arbitration / Litigation
• Claims Preparations and Defence
• Dispute Resolution
• Document Services
• Programming Analysis na ti a n l
Re gions
G lo b llia t er
In n ce
Project Management
• Project Management
• Development Management
• Tenant Fit-Out Advisor
• PFI / PPP Advice
• Planning Supervision
• Information Management
Construction Management
• Construction Advice
• Design Management
• Programming
• Procurement of Trade Packages
• Management of Construction Site
• Quality Management
Consultancy
• Banking Support Services
• Construction and Property Tax
• Business Advantage
• Best Value
• Investigation and Analysis
• Research
FM Consultancy
• Life Cycle Costing
• FM Procurement
• Performance Measurement
• Utilities
• PFI/PPP Advice
The Project – Acute Hospital PFI
First operational PFI procured Acute Hospital in Scotland
circa £ 650m over 30 year concession period
circa £ 65m capital value of construction project
circa 350 Acute in-patient beds with circa 50 day care beds
Full diagnostic and clinical support facilities
Completed three months ahead of schedule
250 staff transfer under the provisions of TUPE
Full FM services from Estates, Cleaning, Catering & Security
Integrated Helpdesk and CAFM system controls FM
LIFE CYCLE MANAGEMENT
Design Build
Fees Capex
1 Year 2 Years
Operate
Financing Costs
Running Costs Utilities
Operating Costs
Planned Preventative
Maintenance PPM
Reactive
Periodic
Replacement / Refurbish
Life Cycle
35 Years
Hand
Back
Total
End of
Term
Total
Cost of
Project
Year
35
Total
The Problem to be solved
Project team moved on three years previous – no handover
Interface between FM and Contractor during construction absent
Operational ‘go live’ accelerated by three months
TUPE staff transfer a year ahead of ‘go live’ without penalty
Training on new systems not commenced
Operational precedents not in existence
Commissioning being undertaken without FM input
Construction handover documentation not complete at ‘go live’
Full payment mechanism penalties applied at ‘go live’
The objectives
Delivery of service to appropriate levels prime objective
Fully functioning and operational helpdesk
Production of report to support payment mechanism requirements
Completion of commissioning
Programme of staff training on new systems
Completion of construction handover documentation
Production of management method statements
Gap analysis of built environment to original priced FM
Gap analysis of built environment to original lifecycle
The reasons for setting the objectives
Delivery of service to appropriate levels
PFI / PPP is ALL about long term transfer of risks
Service delivery is largest single aspect of the project
Non-performance WILL escalate into high unavailability deductions
Health & Safety in a clinical environment is critical
Some services such as porters and cleaning are essential to clinical support - i.e. blood delivery, patient movement, hygiene
Clinicians are already under pressure to deliver care
Lifecycle strategy requires service delivery support
The reasons for setting the objectives
Fully functioning and operational helpdesk
The helpdesk is the fulcrum of the service delivery
Short response times require accurate and efficient responses
The asset is of a significant size and diversity
The operation is 24/7 and service levels do not drop at night
PPM needs to link to reactive requests to prevent failures
Essential in preparation of reports and invoices
Information is ‘live’ and the Trust have access to it
The reasons for setting the objectives
Production of report to support payment mechanism requirements
The Trust placed the emphasis on reporting to support invoices
The Trust have a team of managers who scrutinise the report
Un-reported failures reduces trust between the parties
The objective from the Trust was to encourage improvements to service delivery through trend analysis
The FM company requires to spot trends before triggers are hit
From FM point of view it is a risk management tool
From SPV and Funder perspective it is a risk management tool
The reasons for setting the objectives
Completion of commissioning
Required in order to prove systems were functioning to FM
FM cannot safely operate and maintain un-commissioned equipment
Commissioning figures are used as baseline for settings to systems
Commissioning documentation required to complete construction handover documentation
Written requirement of the Project Agreement and carried defaults for failure to complete
Essential to contractor to obtain final payments
The reasons for the objectives
Programme of staff training on new systems
New systems did not compare with old facility systems
Health & Safety issues at top of the Agenda
Commissioning required to be carried out in presence of trained operatives
Service delivery could not be adequately carried out without training
Response times and ultimately mitigation of deductions through failures require training
TUPE breach if training not executed to allow staff to perform their duties
The reasons for the objectives
Completion of construction handover documentation
Essential for the preparation of ALL method statements
Requirement to reconcile ‘as built’ facility with priced project 1998
Requirement to reconcile location of all plant and equipment
O&M manuals and Safety File required to write PPM
HTM’s required to be reconciled with Safety File
‘As built’ facility reconciliation with lifecycle costings
Required to complete commissioning
Required to populate the CAFM system
The reasons for the objectives
Production of management method statements
NOT to be mistaken for ‘operational’ method statements
The objective was to introduce the PFI principles of performance, availability and payment mechanism to the ‘management’ team
Introduce the HTM requirements to the delivery of the service
Cross reference O&M, Safety File and ‘as built’ documentation to original project documentation
Develop overarching management reference tool for on-site team who were not familiar with PFI
Required to satisfy elements of the Project Agreement
The reasons for the objectives
Gap analysis of built environment to original priced FM
Project had gone through usual construction period development
No FM input during construction, consequently no continued reconciliation had taken place
Some elements of D&B type construction approach had ignored original FM calculations
Nuances of ‘as built’ accessibility to plant and equipment needed to be discovered and recorded
Areas had to be recalculated and costs for servicing applied without increase to FM original costs (excluded indexation)
The reasons for the objectives
Gap analysis of built environment to original lifecycle
Project had gone through usual construction period development
No lifecycle input during construction, consequently no continued reconciliation had taken place
Some elements of D&B type construction approach had ignored original lifecycle calculations
Nuances of ‘as built’ accessibility to plant and equipment needed to be discovered and recorded for replacement costings
Areas had to be recalculated and costs for replacement applied without increase to lifecycle original costs (excluded indexation)
How the objectives were met
Delivery of service to appropriate levels
A matrix of the risks to be covered was generated
The risks were associated with individual service delivery types
Performance was analysed and associated to MMS
Health & Safety, specifically HTM requirements were incorporated
Response times were examined in the context of available staff and their ability and target areas generated
Service was put in context of clinician requirements
Lifecycle strategy was related to MMS and service delivery
How the objectives were met
Delivery of service to appropriate levels
Staff training was elevated and accelerated including management
PFI structure was detailed and explained in context of facility
CAFM and Helpdesk systems were populated with all project specific data
FM staff were introduced to construction and commissioning team
Existing service delivery techniques were integrated into project from non-pfi healthcare service delivery projects
Clear delineation of clinical and FM areas of responsibility were agreed with the Trust
How the objectives were met
Fully functioning and operational helpdesk
The helpdesk was made project and site specific by FSI
Response times and priority levels were input
CAFM system populated with accurate ‘as built’ asset data
Competent and responsible helpdesk operatives recruited
PPM linked to reactive requests to prevent failures and spot trends
Crystal reports used to generate accurate reports for invoice support
Constant monitoring of the system introduced with the implementation of a dedicated 24/7 helpdesk manager
How the objectives were met
Production of report to support payment mechanism requirements
Physical monitoring and reporting requirements detailed and proforma created for direct input to CAFM
Reporting format and detail agreed with the Trust
No instance of failure to report deficiencies set at KPI 100%
Report was integrated into MMS which defined how to spot trends, understand default triggers and manage risks
Trends were acted upon and additional rectification reports generated
SPV and Funder together with Trust agreed actions on reports
How the objectives were met
Completion of commissioning
Commission management plan generated and accelerated
Commissioning data incorporated into MMS and operational systems
Commissioning figures published as baseline for system operation
Commissioning team and Construction handover team integrated to produce parallel documentation not sequential
Commissioning management plan agreed with Trust and areas of non-compliance agreed for mitigation
Final payments withheld from Contractor and Commissioning team until documentation completed
How the objectives were met
Programme of staff training on new systems
Manufacturer and installers of systems compelled to train FM staff on correct operation of all systems
Health and Safety related issues given highest priority
Commissioning required to be carried out in presence of FM operatives
Instances of non-performance on PPM issues were charged back to contractor
TUPE requirements were published and put in context of training to avoid instances of breach of conditions
How the objectives were met
Completion of construction handover documentation
Document control room (library) created
Register of all documents both complete and incomplete created
Construction documentation management plan implemented
O&M manuals and Safety File given the highest priority
HTM’s reconciled with Safety File
‘As built’ drawing programme accelerated to completion
Commissioning data cross referenced to construction data
All information provided electronically for input to CAFM system
How the objectives were met
Production of management method statements
NOT to be mistaken for ‘operational’ method statements
MMS extracted information Project Agreement, Output Specification,
Financial Model, O&M’s, Safety File and HTM’s
Written as a quick reference guide for management, placed in the data room (library)
Written in plain english removing legalise
Provided to the Trust as the required method statements and agreed as an accurate reflection of the spirit of the agreements
Intended to be ‘live’ documentation for continual use
How the objectives were met
Gap analysis of built environment to original priced FM
Physical checks made on the ‘as built’ environment – survey
Complete reconciliation of asset’s with original asset schedule
FM re-priced as if starting from scratch – gap analysis undertaken
FM Strategy developed with original costs on ‘as built’ environment with the original output specification standards
Areas had to be recalculated and costs for FM applied without increase to original costs (excluded indexation)
NO erosion of standards was acceptable
New strategy agreed with the Trust
How the objectives were met
Gap analysis of built environment to original lifecycle
Physical checks made on the ‘as built’ environment – survey
Complete reconciliation of asset’s with original asset schedule
Lifecycle re-priced as if from scratch – gap analysis undertaken
Lifecycle re-modelled and strategy put in place with original costs on
‘as built’ environment
Areas had to be recalculated and costs for replacement applied without increase to lifecycle original costs (excluded indexation)
No erosion of standards was acceptable
New strategy agreed with the Trust
Some of the more bizarre revelations
Remeasurement of the checks required on ‘as built’ environment increased possible failure points by 20% to 251,641
Service failures in first month were re-measured using call completion times instead of call start times yielding an increase from
55% completion to 88% completion
The helpdesk received 16,411 calls in the first month of operation
The lessons learned
Create a vehicle for the bid team to articulate the spirit of the agreements to the operational team
Place operational FM management representative within the construction team during the construction period
Continually examine any changes in design or construction with original FM and LCM costs and specifications
Educate construction team on the requirement for complete, accurate
O&M, Safety File and ‘as built’ drawings prior to handover
Make operational FM team part of the commissioning process
Create MMS for non-pfi literate staff and train them