POLICY AND PROCEDURE FOR THE PROCUREMENT OF EQUIPMENT AND SERVICES February 2014 Author: Lead Director: Version No: Implementation Date: Date of Next Review: Vanessa Jinks Martin Sykes 2.0 February 2014 February 2017 Policy and Procedure for the Procurement of Equipment and Services INDEX (Click on the subject to be taken to the relevant part of the document) 1. Introduction 2. Scope 3. Policy Objectives 4. Procedure for the Procurement of Goods and Services less than £5k or covered by existing contract 5. Procedure for the Procurement of Goods or Services in excess of £5k (whole life time costs) not covered by existing contract 6. Advertising within the European Union 7. Contracts 8. Waivers 9. Emergency Orders 10. Ethics and Fraud 11. Equality Impact Assessment 12. Master Indemnity Agreements 13. Frequently Asked Questions Page 2 of 17 Policy and Procedure for the Procurement of Equipment and Services 1. Introduction and Purpose 1.1 This policy is applicable to all FPH staff who are involved in the process of selecting and requisitioning equipment and services 1.2 This policy defines the process involved in the ordering of equipment and services where the funding for the equipment has already been agreed either within a budget, via specific capital funds, charitable funds or as part of a project. The policy is to be followed in conjunction with: Trust Standing Financial Instructions Public Procurement Law European Union Legislation 1.3 In all cases it should be ensured that the Trust achieves best Value For Money (VFM) and that there exists a standardisation of the processes involved in requisition, order and receipt. 1.4 It is important to ensure that the Procurement Department are notified of any purchasing need at the earliest opportunity even if funding has not been assured. Their function is to advise, co-ordinate and process all purchasing activity. Early warning of need allows the buying team time to achieve best VFM. 1.5 Throughout this policy, flowcharts will be used to summarise the chain of activity. The action boxes are colour coded as follows: Indicates Requisitioner activity Indicates Procurement Department activity Indicates Finance Department activity 2. Scope 2.1 This policy will apply to all equipment, goods and services purchased by the Trust from any of the following sources of funds: Revenue budgets Capital budgets Charitable Funds 2.2 Excluded from this policy are the following items ordered direct by purchasers within Estates, Catering, Pharmacy and the Appliance office: Estates day to day hardware and items relevant to the running of the site. Fresh and frozen food. Pharmaceutical Drugs. Patient Appliances. 3. Policy Objectives 3.1 The procurement procedure will ensure that: Value for money is achieved and can be demonstrated, whilst maintaining appropriate quality, Page 3 of 17 Policy and Procedure for the Procurement of Equipment and Services Page 4 of 17 All procurement complies with Trust Standing Financial Instructions and European Union Procurement Legislation, All purchases are in line with the Trust’s strategic and business plans, Goods are obtained with the minimum of delay subject to adherence to Trust SFIs, Medical equipment is purchased in line with the Medical Devices Policy and NHS Pre-Purchase Questionnaire recommended standards, The Procurement Department are involved at the earliest opportunity in the procurement of goods and services. Purchases are made in line with Equality and Diversity Legislation Policy and Procedure for the Procurement of Equipment and Services 4. Procedure for the Procurement of Goods or Services less than £5k or covered by existing contract. 4.1 The requisitioning department must identify exactly what is required. If the goods or services are less than £5k or a current contract for the items exists then it is sufficient to raise a requisition (either on EROS or on the Trust approved non-stock requisition form). 4.2 Appropriate authorisation must be obtained from either the budget holder or their nominated deputy. Note that an authoriser or buyer may not be involved in the receipt of goods. 4.3 Goods or services less than £5k not under contract require two quotations where possible – these may be verbal or written. These quotations will be obtained by the Procurement department and will be informally evaluated by the requisitioning department and Procurement. The cheapest quote should be accepted unless there is a compelling reason not to do so. 4.4 The Procurement department will then raise and despatch the purchase order. 4.5 Summary: Need identified as being below £5k in value or covered by existing contract Requisition input onto EROS (or complete non-stock requisition) Requisition electronically authorised (paper requisition passed to Procurement Dept. if applicable) Are goods under existing contract? No Yes Procurement Dept obtain informal quotes. Requisitioner evaluates quotes and confirms supplier. Procurement Dept place order Page 5 of 17 Policy and Procedure for the Procurement of Equipment and Services 5. Procedure for the Procurement of Goods or Services in excess of £5k (whole life time costs) not covered by existing contract. The following procedure details in full the steps required to purchase goods and services in excess of £5k. Note for goods charged to capital codes this level is increased to £10k. 5.1 Identify Requirement 5.2 Quotes or Tenders Received 5.3 Evaluation and Trial of Equipment if appropriate 5.4 Evaluation of Quotes and Tenders 5.5 E101 Raised 5.6 Purchase Order Raised 5.1 Identify Requirement The requisitioning department should contact the Procurement department detailing the specification of the goods or services required. In many cases the supply of equipment and consumables has been standardised. Department should therefore check with the Procurement department if they are unsure. Account must be taken of whole lifetime costs and this could include: Cost of actual goods. Accessories associated with the product. Any maintenance or service contract costs. Training Costs Delivery and miscellaneous charges. Cost of disposal of items within Environmental procedures. If there is no standardisation in the Trust, then the user is required to produce a specification. The specification should be generic and not show bias to a particular manufacturer. If the user is unsure whether a contract currently exists, they should contact the Procurement department for advice. Where a contract exists all departments are obliged to use it unless they can give valid reasons why it may not be appropriate. 5.2 Quotes or Tenders Received In accordance with Trust SFI’s the Procurement department will obtain quotes as follows (Values exclude VAT): Between £5,000 (£10,000 in the case of Capital purchases) and £50,000 – Three written quotations required. Requests to waiver the requirement for three quotes must be made on the E101 stating a valid reason. The E101 is then approved by the Head of Procurement, the appropriate Management Accountant and finally by the Director of Finance. Between £50,000 and £111,676 – Formal competitive tender required. Requests to waiver the requirement for a tender process must be made on the E101 stating a valid reason. The E101 is then approved by the Head of Procurement, the appropriate Management Accountant and finally by the Director of Finance. Page 6 of 17 Policy and Procedure for the Procurement of Equipment and Services Over £111,676 (current OJEU level as at 1/1/2014) there is a legal requirement to follow the EU procurement rules. Local waivers are NOT allowed (by EU law) by Trust staff. - OJEU Notice followed by full Tender Process. 5.3 Evaluation and Trial of Equipment if appropriate If the requirement is for medical equipment then this must be trialled and evaluated in accordance with the Medical Devices Policy. A Pre-purchase questionnaire (PPQ) for the Equipment must be obtained by Procurement and passed to the EME Department / HSDU / Infection Control for approval as appropriate. 5.4 Evaluation of Quotes and Tenders Quotes and Tenders are evaluated in accordance with the following system outlined in Trust SFI’s: Between £5000 (£10,000 in the case of Capital purchases) and £50,000 – The Procurement department and the end user will evaluate the quotes and should accept the cheapest unless there is a compelling reason not to do so. This reason must be documented on the E101 to the satisfaction of the Procurement Manager and the Director of Finance. Between £50,000 and £100,000 – The tenders will be received and evaluated by the requisitioning and Procurement departments and the outcome of evaluation will be documented with the E101 to the satisfaction of the Director of Finance. Any proposal to waive this would need the approval of the Director of Finance. Over £100,000 - A sub-committee of the Board, which should be formed, comprising, as a minimum, two Executive Directors, will receive the tenders. The Procurement department and the end user will evaluate the tenders and the outcome of evaluation will be reported to the sub-committee of the Board for ratification. The recommendations of the Sub-committee will be submitted by a Director to the CDIC for consideration if the value is over £500,000. The lowest tender must be accepted and any proposal to waive this would need the approval of the Chief Executive for values in excess of £100,000 and the approval of the Trust Board / CDIC for values in excess of £500,000. 5.5 E101 Raised For goods and services over £5,000 (£10,000 in the case of Capital purchases) an E101 must be raised prior to the order being placed. The E101 is completed by the requisitioner and signed by the budget holder. The E101 details the suppliers from whom quotes have been obtained and is then passed to the Procurement Manager for approval. Any request to waive the requirement for three quotes is detailed on the E101 by the requisitioning department. Following Procurement approval, the E101 is passed to Finance to indicate available funding and to obtain final approval from the Director of Finance. 5.6 Purchase Order Raised Following notification of E101 approval the requisitioning department will raise a requisition for the goods either on the Trust official non-stock requisition or on EROS. The Procurement department will then raise the official order and any other appropriate paperwork such as contract schedules etc. Page 7 of 17 Policy and Procedure for the Procurement of Equipment and Services 5.7 Summary Need identified as being in excess of £5k and not under existing contract Procurement Dept contacted with the specification of the goods / services required. Procurement Dept. obtain quotes and tenders in accordance with SFIs / EU law Is the requirement for medical equipment? Yes No Evaluation and Trial of Equipment in accordance with the Medical Devices Policy. Evaluation of Tenders and Quotes Evaluation of Tenders and Quotes PPQ to EME for Approval E101 and requisition raised indicating source of funding (charitable funds, capital or revenue) E101 approved in accordance with SFIs Procurement Dept raise Purchase Order Page 8 of 17 Policy and Procedure for the Procurement of Equipment and Services 6. Advertising within the European Union 6.1 For procurements with a whole life time cost in excess of £111,676 (current level as at 1/1/2014), the Trust is required by European law to carry out a full tender within the regulations laid down in the Public Contracts Regulations SI 2006 No 5. 6.2 The basic process followed for a Restricted procedure using the Trust’s e-tendering portal is detailed below. The mandatory time periods are noted in red: Advert and pre-qualification Questionnaire (PQQ) placed within the Official Journal of the European Union (OJEU) Advert must remain open for 30 days Expressions of Interest Received Shortlisting of suppliers based on PQQs Invitation to Tender documents issued to shortlisted suppliers Tenderers must be given a minimum of 35 days to return their bid. Tenders returned Trust evaluates the equipment / services offered and the tender documents Suppliers notified of Award Contract Concluded A typical timeline is attached at Appendix A Page 9 of 17 A 10-day standstill period applies before the Contract can be concluded. Policy and Procedure for the Procurement of Equipment and Services 7. Contracts 7.1 The Procurement Department will be responsible for drawing up the Contract or Memorandum of Agreement and Schedules with the successful supplier(s). 7.2 The Contract will be drawn up in accordance with UK, European legal requirements and Trust Policies and in accordance with best practice not limited to the legal guidelines and advice found in the following: 7.2.1 7.3 Public Contracts Regulations SI 2006 No 5. http://www.opsi.gov.uk/si/si2006/uksi_20060005_en.pdf Roles and Responsibilities Roles and Responsibilities for managing of contracts will be established during the contract award period and the following table acts as a guideline to these positions: Action Drawing up of contractual documents and advice concerning legal matters during the term of the contract Monitoring and Review of Services provided during the contract (eg SLAs, maintenance) Responsibility Procurement Department Nominated Project lead (usually a senior enduser) Payment Authorisation Budget Holder Payments Finance – Accounts Payable 7.4 7.4.1 Contract Review For contracts that have an ongoing input from the contracted supplier(s) either in the form of a service provided or for requirements such as maintenance then a Contract Review and Monitoring process will be put in place at the time of contract award. 7.4.2 The Review and Monitoring process periods will be determined at the time of contract award but should ideally be: 7.5 7.4.2.1 Quarterly for services that are deemed critical to the Trust and whose reduction or absence will seriously affect all areas (or the area to which the service is being provided). 7.4.2.2 Bi-annually for services that are of lesser importance to the Trust but whose reduction or absence will cause delays or minor interruptions to the running of that area. 7.4.2.3 Annually for services that are of low importance to the Trust whose reduction or absence will cause inconvenience to the running of that area. I.T. Contracts The process for drawing up contractual documents for large (over £50k) IT Contracts will follow the procedure set out by the Informatics Operational Group. Page 10 of 17 Policy and Procedure for the Procurement of Equipment and Services 8. Waivers 8.1 Waivers apply where there are genuine reasons why it would not be appropriate or advantageous to seek competitive tenders. 8.2 Orders under £50,000 may be waived under the following circumstances (Reference: SFI, December 2011, Appendix 1 section 3.2): 8.3 8.2.1 Where the supply of goods (or related goods) is of a special character and does not exceed £5,000. 8.2.2 Where there is only one supplier and no reasonably satisfactory alternative product or service. 8.2.3 Competition would be impractical, impossible or not beneficial. 8.2.4 The requirement is to be ordered under existing contracts. 8.2.5 The work for practical reasons must be of the same manufacture, for instance repairs / spare parts for existing equipment. 8.2.6 Where it is known that a marked financial advantage will accrue to the Trust from making a spot purchase of products subject to quickly changing market conditions. Orders between £50,000 and £100,000 may be waived under the following circumstances (Reference SFI Appendix 1, section 2.1): 8.3.1 Where the requirements are ordered under existing contracts and where in the opinion of the relevant Director: 8.3.2 There is only one supplier and no reasonably satisfactory alternative product / service 8.3.3 Competition would be impractical, impossible or not beneficial; 8.3.4 The work for practical reasons must be of the same manufacture, for instance repairs / spare parts for existing equipment 8.2.7 Where it is known that a marked financial advantage will accrue to the Trust from making a spot purchase of products subject to quickly changing market conditions. These circumstances and opinion must be documented and the E101 authorisation countersigned by the Procurement Manager in confirmation of such circumstances. 8.4 Orders greater than £111,676 may not be waived under any circumstances and are subject to European law. 8.4.1 Waivers should not be used to avoid the tendering process even where there is no apparent competition. Suppliers have the right to challenge Trusts where they believe Public Procurement Rules are not being adhered too and feel that the Trust is not seeking fair and open competition. In any case waivers do not exclude the Trust from following EU Procurement rules. Page 11 of 17 Policy and Procedure for the Procurement of Equipment and Services 9. Emergency Orders 9.1 Emergency orders are those orders, which, due to a pressing operational need, must be placed with the supplier with the utmost speed. There are two types of emergency order: 9.2 Orders needing to be raised out of normal office hours (ie when there is no representative from the Procurement Department on site). Orders urgently required during office hours Emergency Orders for goods or services required out of normal office hours. If goods or services, of an operational nature, are required which cannot be ‘borrowed’ from another area of the hospital then an emergency order may be raised by the requisitioning department. The following process must be used: 9.2.1 Identification of need 9.2.2 Efforts made to source the item or service from existing resources within the Trust. If unsuccessful proceed to: 9.2.3 Authority for procurement of the goods must be given by an authorised signatory for the requisitioning budget whose name appears on the Master List of Authorised Signatories. If no-one is present with this authority, then approval must be obtained by one of the following: For goods or services less than £5k A budget holder Site Manager For goods or services in excess of £5k but less than £50k On-call Manager (reached through Switchboard) Procurement Manager (reached through Switchboard) On-call Director The authority must be given in writing on a green non-stock requisition. Where this is not possible an emailed confirmation is acceptable. The email must state the items and the value being authorised. The non-stock requisition must then be completed retrospectively. Under no circumstances may an order in excess of £50k be placed without the approval of a Director of the Trust. 9.2.4 Place the order with the supplier quoting the order number “EPO[today’s date dd/mm]” Eg an order placed on the 27 April would have order number EPO2704. Supplier’s phone numbers can be found on EROS using the Search function or by the usual means (Yellow pages, internet, directory enquiries) 9.2.5 For goods: when placing the order ensure that the supplier is aware that goods are to be delivered directly to the Department since the hospital loading bay is locked out of hours. 9.2.6 On the next working day ensure that the Procurement Department have a copy of the approved requisition and any delivery notes. Procurement staff will then input the requisition onto EROS using the order number as the requisition number. Retrospective E101s will be raised as required. Page 12 of 17 Policy and Procedure for the Procurement of Equipment and Services 9.3 Orders urgently required during office hours. These orders are placed in the same way as non-urgent orders. 9.3.1 Contact any member of the buying team within the Procurement department stating that you have an urgent requirement. 9.3.2 The requisition must be input on EROS or a non-stock requisition and authorised in the usual way. 9.3.3 Orders over £5k must still have an E101 raised though this may be signed retrospectively. However, verbal or email approval from either the Director of Finance, the Head of Finance or one of the Directors of the Trust must first be obtained. 10. Ethics and Fraud All Trust staff should be aware of the following sections of the Trust’s Standing Financial Instructions December 2011 in as far as they apply to Procurement. 10.1 Acceptance Of Gifts And Hospitality 10.1.1 The acceptance of gifts, hospitality or consideration of any kind from contractors and other suppliers of goods or services as an inducement or reward is not permitted under the Corruption Acts 1906 and 1916. Staff must comply with national guidance ‘Standards of Business Conduct for NHS Staff’ and any guidance and directions issued by the Independent Regulator. 10.1.2 Where offers of goods and services do not involve inducement or reward Officers should not accept gifts from commercial sources other than inexpensive articles such as calendars or diaries. If such gifts arrive unsolicited, the advice of the Director of Finance should be sought. 10.2 Declaration Of Interest 10.2.1 In accordance with Standing Orders, the trust Secretary shall be advised of declared pecuniary interests of members of the Board (Standing Order 7) or Officers (Standing Order 8) for recording in registers he will maintain for that purpose. 10.3 Trust’s Code of Business Conduct 10.3.1 In all cases staff and suppliers must comply with the Trust’s Standards of Business Conduct Standards of Business Conduct.doc 11. Equality Impact Assessment 11.1 The users of this policy will take into account their statutory duty to promote equality and human rights and act lawfully within current equality legislation and guidance. Page 13 of 17 Policy and Procedure for the Procurement of Equipment and Services 11.2 This policy has been equality impact assessed and has been shown to have no adverse impact on any equality group. 11.3 The Trust will continue to monitor its effect and will assess again if negative impact is identified or at the review date. 12. Master Indemnity Agreements 12.1 If a requisitioning department wishes to use a piece of equipment that is either on loan to the Trust or has been gifted (in other words any equipment in use that has not received consideration or payment) then the appropriate Indemnity approvals must be sought. 12.2 The list of Master Indemnity Agreements is held and updated by the Department of Health and the full register of companies can be found at the following link: http://www.dh.gov.uk/en/Publicationsandstatistics/Publications/PublicationsPolicyAndGuidance/DH_117 175 12.3 On each occasion of equipment use the requisitioning department must complete an NHS Delivery Note and return the form to the Procurement department. FPH NHS Delivery Note 12.4 If the company does not appear on the Department of Health registry then one of the following forms must be completed along with the NHS Delivery Note. Forms should be forwarded to the Procurement Department along with a copy of the Suppliers Indemnity certificate. The Procurement department will assist with completion of these forms if required. Items on loan: FPH Indemnity Form A Items gifted: FPH Indemnity Form B Page 14 of 17 Policy and Procedure for the Procurement of Equipment and Services 13. Frequently Asked Questions 13.1 How do I get Quotations/Tenders? Procurement will manage the Quotation/Tender process. Your contribution will be the specification or details of the requirement together with assistance from the EME in the case of medical equipment. If there is significant competition for the equipment then Procurement may be required to produce a PreQualification Questionnaire, which is used to shortlist suppliers. Procurement will co-ordinate all communications with the suppliers during the Quotation/Tender process, this is to ensure that all potential suppliers are treated equally and that the competition is open and fair. All unsuccessful suppliers are entitled to a full de-brief with reasons why they were not selected. Procurement will undertake this on request. 13.2 Can I evaluate and trial equipment before purchase? Equipment trials may be required. A Trial Co-Ordinator should be nominated from the Ward/Dept. They will need to ensure that Trial forms are completed and are returned in time to form part of the tender evaluation process. The EME department should be contacted before electro-medical equipment brought in on trial is put into service. EME will ensure that the equipment is electrically safe and that the Supplier has indemnified the Trust in case of incidents. 13.3 How do I evaluate Quotations/Tenders? (User Evaluation) Depending on the complexity of the quotation/tender summary, a panel may be required to make the final decision. If the decision is with the User then they need to ensure that the tenders meet the specification. Tender responses should be judged against the previously agreed evaluation criteria. At this stage user evaluations should be carried out separately from and without knowledge of the financial evaluation. A record must be kept of all decisions made. 13.4 Who else is involved in the evaluation process? (Financial Evaluation) The appropriate Management Accountant or the Procurement Department will assist with the production of a financial summary of the tenders. The financial summary will be based on the “whole life costs” of the equipment. “Whole-life costing” includes not just the cost of the equipment but the maintenance, consumables and training over the total life of the equipment. The Procurement Department will provide an overview of the tenders and company information where appropriate. Purchasing will also organise presentations from Suppliers and ‘Open Days’ or site visits to view the equipment. Any decision made has to be supported by the evaluation criteria used. Un-successful suppliers have a right to a de-briefing, by the Procurement Department, outlining why they were not successful. It is therefore necessary to have clear reasons to justify the final decision. 13.5 How do I know the equipment meets relevant safety standards and can be decontaminated? Procurement will contact the Supplier to obtain a “Pre-Purchase Questionnaire” (PPQ) either separately or as part of the quotation/tendering process. The PPQ confirms that the equipment meets the relevant standards for electro-medical equipment and gives details of maintenance support. The PPQ is passed to the EME department for approval. Procurement will request additional information related to cleaning and decontamination and pass this to HSDU for approval. Any issues over decontamination will be passed to the Trust’s Decontamination Officer. An order cannot be placed until EME staff has given PPQ approval and that HSDU are satisfied with the cleaning/decontamination instructions. Page 15 of 17 Policy and Procedure for the Procurement of Equipment and Services 13.6 How do I order the equipment? It is the Project/Budget Manager’s responsibility to raise the requisition and to ensure that the requirement is correct. They should also ensure that it is properly authorised (either by electronically authorising the requisition or signing off a paper non-stock requisition) before it is passed to the Procurement Department. You need to ensure you keep a record of the requisition number. 13.7 Who places the order? Procurement are responsible for placing the order and ensuring that the details are correct, as per the quotation/tender and requisition. 13.8 How do I keep track of the order? If the Ward/Dept. needs to track the order, they should contact Procurement with either the requisition or order number. Alternatively you can check the progress of your order by utilising the Order Enquiry field on EROS. Where Procurement are involved with a Capital Equipping Project then they will ensure delivery dates are met. 13.9 What do I do once the order is received? Once the order is received, Receipt and Distribution will notify EME (if applicable), who will check the equipment. The equipment will then be sent to the Ward/Dept for use Page 16 of 17 Appendix A – Sample Procurement Timeline – OJEU route The table below illustrates a typical OJEU procurement timeline. It assumes that a business case for the procurement has been approved and the necessary market intelligence including verification of the route to market has been undertaken. Project Team to establish project plan and agree timetable. Prepare and Post Advert and PQQ on OJEU (open for 30 days) Pull together tender document, spec and draft contract inc means of evaluation Expressions of Interest / PQQ stage closes PQQ Evaluation and Shortlisting Issue Invitation to Tender and Draft Contract Docs (out for minimum 35 days) Tenders received online via e-tendering portal Clarification of tenders if required Evaluation Activity (may include site visits, supplier presentations) Final shortlisting Paper to Sub-committee of the board for approval or CDIC as determined by SFIs Paper to Board of Directors for Approval as determined by SFIs Issue intent to award (10 day standstill period applies) Completion of award including posting of award into OJEU Implementation / Installation / Delivery begins Week 20 Week 19 Week 18 Week 17 Week 16 Week 15 Week 14 Week 13 Week 12 Week 11 Week 10 Week 9 Week 8 Week 7 Week 6 Week 5 Week 4 Week 3 Week 2 OJEU Route Timeline Week 1 Action