Problem-Solving Examples (Non-Preemptive Case) 5-1 Outline • Job-shop scheduling problem (JSSP) – – – – Problem definition Basic search procedure Heuristics Results • Resource-constrained project scheduling problem (RCPSP) 5-2 JSSP: Problem definition • • • • • Set of machines {M1 ... Mm} Set of jobs {J1 ... Jn} List of operations Oi1 ... Oim(i) for each job Ji Processing time pij for each operation Oij Machine Mij for each operation Oij 5-3 JSSP: Problem variables • Integer variables start(O) and end(O) for each operation O • Optimization criterion makespan = maxi(end(Oim(i))) 5-4 JSSP: Problem constraints • Temporal constraints 0 start(Oij) end(Oij) start(Oij+1) • Duration constraints start(Oij) + pij = end(Oij) • Exclusion constraints Mij = Mkl implies [end(Oij) start(Okl)] OR [end(Okl) start(Oij)] 5-5 JSSP: Decision var. complexity • NP-complete in the strong sense when m = 3 and m(i) 3 for all i • Solvable in polynomial time if m = 2 and m(i) 2 for all i • NP-complete in the ordinary sense when m = 2 and m(i) 3 for all i, or when m = 3 and m(i) 2 for all i • Flow-shop scheduling: NP-complete in the strong sense for m = 3 5-6 JSSP: Basic search procedure • Select a machine M and a set W of operations which require M • For each operation O in W, create a branch where O is set to execute before (or after) all the other operations of W • Select a branch, propagate the decision, and iterate (until a solution is found or no branch remains) 5-7 JSSP: Makespan minimization • Set makespanmin to an obvious lower bound • Set makespanmax to an obvious upper bound • Iterate until makespanmin = makespanmax – Select a value in [makespanmin makespanmax) – Constrain the makespan to be smaller than (or equal to) the chosen value – Run the search procedure: when a solution is found, set makespanmax to the makespan of the solution; if there is no solution, set makespanmin to (value + 1) 5-8 JSSP: Makespan minimization • Example – start with makespanmin obtained by propagation – until a solution has been found, increment the tested value by min(2i-1, (makespanmax - makespanmin) / 2) (after the ith iteration) – after a solution has been found, set the tested value to (makespanmax - makespanmin) / 2 5-9 JSSP: Heuristics • Selection of the machine Find the task interval [startmin(A), endmax(B)] with the highest demand/supply ratio TI = {C | startmin(A) startmin(C) and endmax(C) endmax(B)} demand = SCTI duration(C) supply = endmax(B) - startmin(A) 5-10 JSSP: Heuristics • Branch exploration ordering – First or last? • Always select an operation to execute first • Always select an operation to execute last • Use edge-finding rules to determine the number Nf of operations that can be first and the number Nl of operations that can be last (and select the option with the smallest number of candidates) 5-11 JSSP: Heuristics • Branch exploration ordering – Select the branch on which the operation with the smallest endmax is scheduled first (EDD) – Select the branch on which the operation with the largest startmin is scheduled last – Propagate each alternative in turn and select the one which appears the most constraining 5-12 JSSP: Benchmark results • [Applegate & Cook 91] – Ten instances with 10 jobs and 10 machines (100 operations) – Results (table) taken from [Le Pape 95] • [Vaessens et al 94] – Thirteen instances (one open) with up to 225 operations 5-13 JSSP: Benchmark results Instance MT10 ABZ5 ABZ6 LA19 LA20 ORB1 ORB2 ORB3 ORB4 ORB5 BT 13684 19303 6227 18102 40597 22725 31490 36729 13751 12648 CPU 184.8 226.6 80.3 219.2 407.3 323.7 416.4 488.4 169.9 168.5 BT(PR) 4735 4519 312 6561 20626 6261 14123 22138 1916 2658 CPU(PR) 52.8 49.7 3.8 74.7 186.9 85.3 189.3 277.6 19.0 29.7 5-14 Benchmarks (Applegate & Cook) 215 210 25 MT10 ABZ5 ABZ6 LA19 [Applegate & Cook 91] [Baptiste et al 95] [Le Pape 95] [Caseau & Laburthe 95] [Colombani 96] LA20 ORB1 ORB2 Number of nodes Number of fails Number of choices ORB3 ORB4 ORB5 CPU time (Sparc1) CPU time (RS6000) CPU time (Sparc10) CPU time (Sparc 5) 5-15 Benchmarks (Applegate & Cook) 215 210 25 MT10 ABZ5 ABZ6 LA19 PROOFS OF OPTIMALITY [Applegate & Cook 91] [Baptiste et al 95] [Le Pape 95] [Caseau & Laburthe 95] LA20 ORB1 ORB2 Number of nodes Number of fails Number of fails ORB3 ORB4 ORB5 CPU time (Sparc1) CPU time (RS6000) CPU time (Sparc10) 5-16 Benchmarks (Vaessens et al) 15 10 5 MT10 LA02 LA19 LA21 LA24 [Adams et al 88] [Nuijten & Le Pape 97] [Caseau & Laburthe 95] LA25 LA27 LA29 LA36 LA37 LA38 LA39 LA40 [Mattfeld 96] [Nowicki & Smutnicki 93] [Van Laarhoven et al 92] 5-17 Benchmarks (Vaessens et al) 215 210 25 MT10 LA02 LA19 LA21 LA24 LA25 [Adams et al 88] (Vax780) [Nuijten & Le Pape 97] (RS6000) [Caseau & Laburthe 95] (Sparc10) LA27 LA29 LA36 LA37 LA38 LA39 LA40 [Mattfeld 96] (Sparc10) [Nowicki & Smutnicki 93] (PC) [Van Laarhoven et al 92] (Vax785) 5-18 RCPSP: Problem definition (1) • Given: – – – – m resources R1 ... Rm with given capacities c1 ... cm n activities A1 ... An with given durations d1 ... dn precedence constraints between activities resource requirements qij (for activity i and resource j) assign start and end times to activities so as to satisfy the constraints and minimize the duration of the overall project 5-19 RCPSP: Problem definition (2) • Given: – m resources R1 ... Rm with given maximal capacities c1max ... cmmax – n activities A1 ... An with given minimal durations d1min ... dnmin and maximal durations d1max ... dnmax – precedence constraints between activities – resource requirements qijd (for activity i, resource j and duration d) assign start and end times to activities so as to satisfy the constraints and achieve the "best" tradeoff between the duration of the overall project and the peak capacity of the resources 5-20 RCPSP: Problem variables • Integer variables start(Ai) and end(Ai) for each activity Ai • Integer variables duration(Ai), cj and qij in the variable-duration variable-demand case • Optimization criterion makespan = maxA(end(A)) 5-21 RCPSP: Problem constraints • • • • • Resource capacity constraints (cj) Duration constraints Precedence constraints Resource requirement constraints (qij) Relations between durations and resource requirements 5-22 RCPSP: Search procedure (1) 1 Initialize the set of selectable activities W to the complete set. 2 If all activities have fixed start and end times, exit. Otherwise remove from W those activities which have fixed start and end times. 3 If W is not empty, select an activity from W, create a choice point for the selected activity (to allow backtracking) and schedule the selected activity from its earliest start time to its earliest end time. 4 If W is empty, backtrack to the most recent choice point. (If there is no choice point left, report that there is no problem solution and exit.) 5 Upon backtracking, mark the backtracked activity as not selectable as long as its earliest start and end times have not changed. Then goto step 2. 5-23 RCPSP: Search procedure (2) 1 Initialize the set of selectable activities W to the complete set. 2 If all activities have fixed start and end times, exit. Otherwise remove from W those activities which have fixed start and end times. 3 If W is not empty, select an activity from W, create a choice point for the duration of the selected activity, select a duration, create a choice point for the start and end times of the activity and schedule the selected activity from its earliest start time to its earliest end time. 4 If W is empty, backtrack to the most recent choice point. (If there is no choice point left, report that there is no problem solution and exit.) 5 Upon backtracking on a start/end time choice point, mark the backtracked activity as not selectable as long as its earliest start and end times have not changed. Then goto step 2. 6 Upon backtracking on a duration choice point, select another duration. 5-24 RCPSP: Optimization • Classical minimization scheme • Pareto-optimization (find all Pareto-optimal tradeoffs) 1 Generate a solution which minimizes the first criterion c1. (If there is no solution, exit.) Let v1 be the optimal value for c1. 2 Constrain c1 to be smaller than or equal to v1. Generate a solution which minimizes the second criterion c2. Let v2 be the optimal value for c2. The solution found is Pareto-optimal. 3 Remove the constraint stating that c1 is smaller than or equal to v1. Replace it by a constraint stating that c2 is strictly smaller than v2. Goto step 1. 5-25 RCPSP: Heuristics • Selection of an activity – Select the activity with the smallest endmin • Selection of a duration – Select the shortest possible duration 5-26 RCPSP: Results • Ship loading problem [Aggoun & Beldiceanu 92] – – – – – – 1 resource 34 activities with precedence constraints Fixed-duration fixed-demand fixed-capacity: 0.2s Fixed-duration fixed-demand Pareto-optimization: 0.4s Variable-duration variable-demand fixed-capacity: 0.2s to 0.9s Variable-duration variable-demand Pareto-optimization: 13s • Industrial problem – 2 resources – 40 to 50 activities with precedence constraints – Variable-duration variable-demand fixed-capacity: 1s 5-27 RCPSP: Results • However, the efficiency of RCPSP search procedures is shown to depend a lot on the structure of the precedence network. Much harder instances can be obtained by simple modifications of the ship loading problem. • Additional constraints of real-life problems can make the problem much more simple or much more difficult than the RCPSP. 5-28