The Project Schedule and Budget
Chapter 7
7-1
Copyright 2012
John Wiley & Sons, Inc.
Learning Objectives
Describe the Project Management Body of Knowledge (PMBOK®) area
called project cost management.
Develop a Gantt chart.
Develop a project network diagram using the activity on the node
(AON) technique.
Identify a project’s critical path and explain why it must be controlled
and managed.
Develop a PERT diagram.
Describe the concept of precedence diagramming and identify finish-tostart, start-to-start, finish-to-finish, and start-to-finish activity
relationships
7-2
The Importance of Project Cost Management
IT projects have a poor track record for meeting budget goals
A 2011 Harvard Business Review study reported an average
cost overrun of 27 percent. The most important finding
was the discovery of a large number of gigantic overages
or “black swans”
Examples of how not to mange costs
The U.S. government (e.g. IRS)
The United Kingdom’s National Health Service IT
http://www.bbc.co.uk/news/uk-15014288
http://www.bbc.co.uk/news/uk-politics-24130684
http://www.hsj.co.uk/news/technology/rising-cost-of-nhsit-fiasco/5063357.article#.UlbD8NKsh8E
4
Project Cost Management Processes
Process
Group
Planning
Monitoring
and
Controlling
Cost Management Process
Major
Output
CP1: Planning Cost Mgmt
Cost Management Plan
CP2: Estimating Costs
Activity Cost Estimates
CP3: Determining the Budget
Cost Performance Baseline
MC1: Controlling Costs
Work Perf. Measurements
Budget Forecasts
5
What is Cost and Project Cost Management?
6
Project Cost Management Processes
Scope
Baseline
Schedule
Baseline
Estimate
bases
Determine
Budget
Estimate Costs
Activity
Cost
Estimates
Project
Funding
Req.
Control Costs
Cost
Baseline
PMBOK® Project Cost Management
Estimate Costs
Focuses on the processes to estimate the monetary resources
needed to complete the project work or activities.
Determine Budget
Aggregating the individual cost for each of the project activities
or work package components to determine the cost baseline or
overall project budget.
Control Costs
Updating the project’s status while monitoring the project’s
budget and managing any changes to the baseline plan.
7-8
The Project Planning Framework
7-9
Budget and Schedule Development
7-10
Developing the Project Schedule
Project Management Tools
7-11
Gantt Chart for Planning
7-12
Gantt Chart Reporting: Project’s Progress
7-13
Project Network Diagram:
Activity Analysis for AON
Activity
Description
Estimated
Duration (Days)
Predecessor
A
Evaluate current technology
platform
2
None
B
Define user requirements
5
A
C
Design Web page layouts
4
B
D
Set-up Server
3
B
E
Estimate Web traffic
1
B
F
Test Web pages and links
4
C,D
G
Move web pages to
production environment
3
D,E
H
Write announcement of
intranet for corp. newsletter
2
F,G
I
Train users
5
G
J
Write report to management
1
H,I
7-14
Activity on the Node (AON)
Network Diagram
7-15
Possible Activity Paths
Possible Paths
Path
Total
Path 1
Path 2
Path 3
Path 4
Path 5
7-16
Critical Path
7-17
PERT
7-18
Activity Analysis for PERT
Activity
Predecessor
Optimistic
Estimates
(Days)
Most Likely
Estimates
(Days)
Pessimistic
Estimates
(Days)
A
None
1
2
4
B
A
3
5
8
C
B
2
4
5
D
B
2
3
6
E
B
1
1
1
F
C,D
2
4
6
G
D,E
2
3
4
H
F,G
1
2
5
I
G
4
5
9
J
H,I
.5
1
3
Expected
Duration
7-19
Activity Analysis for PERT
7-20
Possible PERT Activity Paths
Possible Paths
Path 1
Path 2
Path 3
Path 4
Path 5
Path
Total
Precedence Diagramming Method - PDM
Based on 4 fundamental relationships
7-22
Lead and Lag times
Lead is starting the next task before the first task is complete
Lag (or negative lead) is the adding of a buffer of time
before the next task begins
7-23
Critical Path Analysis (with slack time)
7-24