ERI-CEE-08-04

advertisement
8th IG-Meeting
Coordinated Auctioning, Auction Office
and Organisational Issues
Christian Todem
Vienna
11.09.2007
Agenda
State of Play
Antitrust and Merger Regulation Issues
Documents requested by CEE-Regulators
Updated Project Plan
Project Office
Open Topics
Conclusions
2
State of Play
Managing director/MD contract
Cost sharing agreement
Business plan, budget and shareholder‘s loan (
)
Not yet started
Started
In implementation
Completed
Articles of association
Bank account
Staff recruiting (Project Team) /employment contracts / accountant service
Office (
)
Founding procedure, necessary TSOs‘ confirmations, proxy issue
Antitrust and Merger/Cartel regulation issues
Service Level Agreement (inter TSO contract)
Software (common coordinated capacity calculation and allocation)
Communication infrastructure and IT hardware
Auction Rules, external data transfer (MLA)
3
Antitrust & Merger Regulation Issues I/II
Several antitrust & merger regulations could be relevant:
 Antitrust regulations following art. 81/82 of EC contract
 Mergers following merger Regulation 139/2004
 Antitrust and merger regulations under national (German) laws
Previous steps, 1st letter to the Commission:
 CEE TSOs have already submitted a letter, on 26th March,
regarding antitrust & merger issues to the Commission.
 The answer of the Commission puts the burden of final judgement of
the notification need on TSOs’ shoulders.
4
Antitrust & Merger Regulation Issues II/II
Previous steps, 2nd letter to the Commission:
 CEE TSOs have submitted a second letter, on 10th July, to the
Commission for final clarification – whether the Commission is
responsible or national competition authorities.
 A questionnaire has been submitted to CEE TSOs by the
Commission for helping them to clarify the situation.
5
Documents requested to Regulators
At the last IG-meeting (June 12th in Vienna) the CEE Regulators
requested:
Updated Project Plan
Articles of Association
Basic Business Plan figures
Documents have been submitted to CEE-lead Regulator after
receiving the approvals of all TSOs by end of August.
6
7
Project Office
Creation of an permanent project structure:
 In order not to lose time and to avoid further delay a Project Office will
be established.
 If the antitrust & merger regulation issues are clarified the Auction
Office (as a independent legal entity) can immediately be established.
Project coordination:
 The Project Office (managed by the designated MD of the future AO)
coordinates the work and acts as the overall project management.
 A permanent project staff works part/full-time for establishing and
developing the future allocation system.
 The already established structure (Working Groups) will assist the
Project Office.
 Also a external consultant has been chosen to support the work!
8
Open topics I/II
Scheduling, Curtailment:
 Comprehensive concept has already been elaborated and experts
of involved TSOs are going to finalise it during the next month.
 Also different concepts and possibilities of curtailment are under
investigation.
Test calculations, Long Term Concept (Y,M auctioning):
 First test calculations have been performed (only for D concept).
 Long term concept is still under elaboration; first concept test
calculations are currently in progress.
 The Consultant will also assist in performing test calculations.
9
Open topics II/II
IT:
 IT-Tender for capacity calculation and auctioning is under
preparation.
 Delay is obvious.
 Experience of similar projects shows that development will take
about 6 months.
10
Conclusion I/II
Statement 1 at last IG meeting:
“It’s obvious that still problems (e.g. Y, M concept and improvement of
transparency in D cap. calculation) have to be solved.”
CEE TSOs have chosen to take external consultant support, especially
for improving the transparency in D capacity calculation.
First promising inputs and suggestions have already been made for
improving the methodology in terms of transparency.
11
Conclusion I/II
Statement 2 at last IG meeting:
“To start with flow-based D (and M) auctions within 2008 is the realistic
case. However additionally has to be solved: How to proceed with
especially Y auction for 2008 in order not to “block” flow-based D (and
M) auctions in advance (support of regulators)?”
CEE TSO have elaborated two options and ask Regulators for their
opinion:
Option 1: Maintain the present method – bilateral (coordinated) auctions –
for the whole year 2008.
Option 2: Let the possibility of FBA introduction during the year 2008 and
shift offered capacities for 2008 from yearly to monthly and daily
in the whole CEE region.
12
Implementation of load flow-based auctions in CEE
Option 1 (January 2009):
 Consistent package for Y/M/D can be developed from the scratch
 Sufficient time for proper testing
Option 2 (September 2008):
 Any delay will cause new change
 Consistency of 2008 NTC approach for Y/M with FBA for D needs to
be investigated
 Capacities for Y/M most likely have to be decreased to safeguard
FBA for D
13
Thank you
for your attention
14