Operations Management Supplement 7 – Capacity Planning PowerPoint presentation to accompany Heizer/Render Principles of Operations Management, 6e Operations Management, 8e © 2006 Prentice Hall, Inc. Hall, Inc. © 2006 Prentice S7 – 1 Outline Capacity Design and Effective Capacity Capacity and Strategy Capacity Considerations Managing Demand Capacity Planning © 2006 Prentice Hall, Inc. S7 – 2 Outline – Continued Breakeven Analysis Single-Product Case Multiproduct Case Applying Decision Trees to Capacity Decisions © 2006 Prentice Hall, Inc. S7 – 3 Outline – Continued Applying Investment Analysis to Strategy-Driven Investments Investment, Variable Cost, and Cash Flow Net Present Value © 2006 Prentice Hall, Inc. S7 – 4 Learning Objectives When you complete this supplement, you should be able to: Identify or Define: Capacity Design capacity Effective capacity Utilization © 2006 Prentice Hall, Inc. S7 – 5 Learning Objectives When you complete this supplement, you should be able to: Describe or Explain: Capacity considerations Net present value analysis Break-even analysis Financial considerations Strategy-driven investments © 2006 Prentice Hall, Inc. S7 – 6 Capacity The throughput, or the number of units a facility can hold, receive, store, or produce in a period of time Determines fixed costs Determines if demand will be satisfied Three time horizons © 2006 Prentice Hall, Inc. S7 – 7 Planning Over a Time Horizon Long-range planning Add facilities Add long lead time equipment Intermediaterange planning Subcontract Add equipment Add shifts Short-range planning Add personnel Build or use inventory * Modify capacity * Schedule jobs Schedule personnel Allocate machinery Use capacity * Limited options exist Figure S7.1 © 2006 Prentice Hall, Inc. S7 – 8 Design and Effective Capacity Design capacity is the maximum theoretical output of a system Normally expressed as a rate Effective capacity is the capacity a firm expects to achieve given current operating constraints Often lower than design capacity © 2006 Prentice Hall, Inc. S7 – 9 Utilization and Efficiency Utilization is the percent of design capacity achieved Utilization = Actual Output/Design Capacity Efficiency is the percent of effective capacity achieved Efficiency = Actual Output/Effective Capacity © 2006 Prentice Hall, Inc. S7 – 10 Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls © 2006 Prentice Hall, Inc. S7 – 11 Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls © 2006 Prentice Hall, Inc. S7 – 12 Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls Utilization = 148,000/201,600 = 73.4% © 2006 Prentice Hall, Inc. S7 – 13 Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls Utilization = 148,000/201,600 = 73.4% © 2006 Prentice Hall, Inc. S7 – 14 Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls Utilization = 148,000/201,600 = 73.4% Efficiency = 148,000/175,000 = 84.6% © 2006 Prentice Hall, Inc. S7 – 15 Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Design capacity = (7 x 3 x 8) x (1,200) = 201,600 rolls Utilization = 148,000/201,600 = 73.4% Efficiency = 148,000/175,000 = 84.6% © 2006 Prentice Hall, Inc. S7 – 16 Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Efficiency = 84.6% Efficiency of new line = 75% Expected Output = (Effective Capacity)(Efficiency) = (175,000)(.75) = 131,250 rolls © 2006 Prentice Hall, Inc. S7 – 17 Bakery Example Actual production last week = 148,000 rolls Effective capacity = 175,000 rolls Design capacity = 1,200 rolls per hour Bakery operates 7 days/week, 3 - 8 hour shifts Efficiency = 84.6% Efficiency of new line = 75% Expected Output = (Effective Capacity)(Efficiency) = (175,000)(.75) = 131,250 rolls © 2006 Prentice Hall, Inc. S7 – 18 Capacity and Strategy Capacity decisions impact all 10 decisions of operations management as well as other functional areas of the organization Capacity decisions must be integrated into the organization’s mission and strategy © 2006 Prentice Hall, Inc. S7 – 19 Managing Demand Demand exceeds capacity Curtail demand by raising prices, scheduling longer lead time Long term solution is to increase capacity Capacity exceeds demand Stimulate market Product changes Adjusting to seasonal demands Produce products with complimentary demand patterns © 2006 Prentice Hall, Inc. S7 – 20 Average unit cost (dollars per room per night) Economies and Diseconomies of Scale 25 - Room Roadside Motel Economies of scale 25 © 2006 Prentice Hall, Inc. 50 - Room Roadside Motel 75 - Room Roadside Motel Diseconomies of scale 50 Number of Rooms 75 Figure S7.2 S7 – 21 Capacity Considerations Forecast demand accurately Understanding the technology and capacity increments Find the optimal operating level (volume) Build for change © 2006 Prentice Hall, Inc. S7 – 22 Tactics for Matching Capacity to Demand 1. Making staffing changes 2. Adjusting equipment and processes Purchasing additional machinery Selling or leasing out existing equipment 3. Improving methods to increase throughput 4. Redesigning the product to facilitate more throughput © 2006 Prentice Hall, Inc. S7 – 23 Complementary Demand Patterns Sales in units 4,000 – By combining both, the variation is reduced 3,000 – Snowmobile sales 2,000 – 1,000 – JFMAMJJASONDJFMAMJJASONDJ Time (months) © 2006 Prentice Hall, Inc. Jet ski sales Figure S7.3 S7 – 24 Approaches to Capacity Expansion Expected demand Demand (c) Capacity lags demand with incremental expansion New capacity Expected demand Demand New capacity (b) Leading demand with one-step expansion New capacity Expected demand (d) Attempts to have an average capacity with incremental expansion Demand Demand (a) Leading demand with incremental expansion New capacity Expected demand Figure S7.4 © 2006 Prentice Hall, Inc. S7 – 25 Approaches to Capacity Expansion (a) Leading demand with incremental expansion Demand New capacity Expected demand 1 © 2006 Prentice Hall, Inc. 2 3 Time (years) Figure S7.4 S7 – 26 Approaches to Capacity Expansion (b) Leading demand with one-step expansion New capacity Demand Expected demand 1 © 2006 Prentice Hall, Inc. 2 3 Time (years) Figure S7.4 S7 – 27 Approaches to Capacity Expansion (c) Capacity lags demand with incremental expansion New capacity Demand Expected demand 1 © 2006 Prentice Hall, Inc. 2 3 Time (years) Figure S7.4 S7 – 28 Approaches to Capacity Expansion (d) Attempts to have an average capacity with incremental expansion Demand New capacity Expected demand 1 © 2006 Prentice Hall, Inc. 2 3 Time (years) Figure S7.4 S7 – 29 Break-Even Analysis Technique for evaluating process and equipment alternatives Objective is to find the point in dollars and units at which cost equals revenue Requires estimation of fixed costs, variable costs, and revenue © 2006 Prentice Hall, Inc. S7 – 30 Break-Even Analysis Fixed costs are costs that continue even if no units are produced Depreciation, taxes, debt, mortgage payments Variable costs are costs that vary with the volume of units produced Labor, materials, portion of utilities Contribution is the difference between selling price and variable cost © 2006 Prentice Hall, Inc. S7 – 31 Break-Even Analysis Assumptions Costs and revenue are linear functions Generally not the case in the real world We actually know these costs Very difficult to accomplish There is no time value of money © 2006 Prentice Hall, Inc. S7 – 32 Break-Even Analysis – Total revenue line 900 – 800 – Cost in dollars 700 – Break-even point Total cost = Total revenue Total cost line 600 – 500 – Variable cost 400 – 300 – 200 – 100 – Fixed cost | | | | | | | | | | | – 0 100 200 300 400 500 600 700 800 900 1000 1100 | Figure S7.5 © 2006 Prentice Hall, Inc. Volume (units per period) S7 – 33 Break-Even Analysis BEPx = Break-even point in units BEP$ = Break-even point in dollars P = Price per unit (after all discounts) x = Number of units produced TR = Total revenue = Px F = Fixed costs V = Variable costs TC = Total costs = F + Vx Break-even point occurs when TR = TC or Px = F + Vx © 2006 Prentice Hall, Inc. F BEPx = P-V S7 – 34 Break-Even Analysis BEPx = Break-even point in units BEP$ = Break-even point in dollars P = Price per unit (after all discounts) x = Number of units produced TR = Total revenue = Px F = Fixed costs V = Variable costs TC = Total costs = F + Vx BEP$ = BEPx P F = P P-V F = (P - V)/P F = 1 - V/P Profit = TR - TC = Px - (F + Vx) = Px - F - Vx = (P - V)x - F © 2006 Prentice Hall, Inc. S7 – 35 Break-Even Example Fixed costs = $10,000 Direct labor = $1.50/unit Material = $.75/unit Selling price = $4.00 per unit $10,000 F BEP$ = = 1 - [(1.50 + .75)/(4.00)] 1 - (V/P) © 2006 Prentice Hall, Inc. S7 – 36 Break-Even Example Fixed costs = $10,000 Direct labor = $1.50/unit Material = $.75/unit Selling price = $4.00 per unit $10,000 F BEP$ = = 1 - [(1.50 + .75)/(4.00)] 1 - (V/P) $10,000 = = $22,857.14 .4375 $10,000 F BEPx = = = 5,714 4.00 - (1.50 + .75) P-V © 2006 Prentice Hall, Inc. S7 – 37 Break-Even Example 50,000 – Revenue Dollars 40,000 – Break-even point 30,000 – Total costs 20,000 – Fixed costs 10,000 – | – 0 © 2006 Prentice Hall, Inc. | | 2,000 4,000 | 6,000 Units | | 8,000 10,000 S7 – 38 Break-Even Example Multiproduct Case BEP$ = where © 2006 Prentice Hall, Inc. V P F W i F ∑ Vi 1x (Wi) Pi = variable cost per unit = price per unit = fixed costs = percent each product is of total dollar sales = each product S7 – 39 Multiproduct Example Fixed costs = $3,500 per month Item Sandwich Soft drink Baked potato Tea Salad bar © 2006 Prentice Hall, Inc. Price $2.95 .80 1.55 .75 2.85 Cost $1.25 .30 .47 .25 1.00 Annual Forecasted Sales Units 7,000 7,000 5,000 5,000 3,000 S7 – 40 Multiproduct Example Fixed costs = $3,500 per month Annual Forecasted Item Price Cost Sales Units Sandwich $2.95 $1.25 7,000 Soft drink .80 .30 7,000 Baked potato 1.55 .47 Annual 5,000 Weighted % of Contribution Tea Selling Variable .75 .25Forecasted 5,000 Item (i) Price (P) Cost (V) (V/P) 1 - (V/P) Sales $ Sales (col 5 x col 7) Salad bar 2.85 1.00 3,000 Sandwich Soft drink Baked potato Tea Salad bar © 2006 Prentice Hall, Inc. $2.95 .80 1.55 $1.25 .30 .47 .42 .38 .30 .58 .62 .70 $20,650 5,600 7,750 .446 .121 .167 .259 .075 .117 .75 2.85 .25 1.00 .33 .35 .67 .65 3,750 8,550 $46,300 .081 .185 1.000 .054 .120 .625 S7 – 41 BEP Example = Multiproduct V ∑ 1 - P x (W ) F $ i i i Fixed costs = $3,500 per month $3,500 x Forecasted 12 Annual = = $67,200 .625 Item Price Cost Sales Units Sandwich $2.95 $1.25 7,000 $67,200 Daily Soft drink .80 .30 7,000 = = $215.38 sales 312 days Baked potato 1.55 .47 Annual 5,000 Weighted % of Contribution Tea Selling Variable .75 .25Forecasted 5,000 Item (i) Price (P) Cost (V) (V/P) 1 - (V/P) Sales $ Sales (col 5 x col 7) Salad bar 2.85 1.00 3,000 .446 x $215.38 = 32.6 .259 33 Sandwich $2.95 $1.25 .42 .58 $20,650 .446 $2.95 sandwiches Soft drink Baked potato Tea Salad bar © 2006 Prentice Hall, Inc. .80 1.55 .30 .47 .38 .30 .62 .70 5,600 7,750 .75 2.85 .25 1.00 .33 .35 .67 .65 3,750 8,550 $46,300 .121 .075 per day .167 .117 .081 .185 1.000 .054 .120 .625 S7 – 42 Decision Trees and Capacity Decision -$14,000 Market favorable (.4) Market unfavorable (.6) $100,000 -$90,000 $18,000 Market favorable (.4) Medium plant Market unfavorable (.6) $60,000 -$10,000 $13,000 Market favorable (.4) Market unfavorable (.6) $40,000 -$5,000 $0 © 2006 Prentice Hall, Inc. S7 – 43 Strategy-Driven Investment Operations may be responsible for return-on-investment (ROI) Analyzing capacity alternatives should include capital investment, variable cost, cash flows, and net present value © 2006 Prentice Hall, Inc. S7 – 44 Net Present Value (NPV) F P= (1 + i)N where © 2006 Prentice Hall, Inc. F P i N = future value = present value = interest rate = number of years S7 – 45 NPV Using Factors F P= = FX N (1 + i) where Portion of Table S7.1 © 2006 Prentice Hall, Inc. Year 1 2 3 4 5 X = a factor from Table S7.1 defined as = 1/(1 + i)N and F = future value 5% .952 .907 .864 .823 .784 6% .943 .890 .840 .792 .747 7% .935 .873 .816 .763 .713 … 10% .909 .826 .751 .683 .621 S7 – 46 Present Value of an Annuity An annuity is an investment which generates uniform equal payments S = RX where © 2006 Prentice Hall, Inc. X = factor from Table S7.2 S = present value of a series of uniform annual receipts R = receipts that are received every year of the life of the investment S7 – 47 Present Value of an Annuity Portion of Table S7.2 Year 1 2 3 4 5 © 2006 Prentice Hall, Inc. 5% .952 1.859 2.723 4.329 5.076 6% .943 1.833 2.676 3.465 4.212 7% .935 1.808 2.624 3.387 4.100 … 10% .909 1.736 2.487 3.170 3.791 S7 – 48