TSG Annual Report 2013

advertisement
NATIONAL TRANSMISSION A ND DESPATCH COMPANY LTD
TSG ANNUAL REPORT – 2013 (Jan-Dec, 2013)
TECHNICAL SERVICES GROUP
“PROFESSIONAL O&M PERSONNEL FROM TSG”
ISSUED BYCHIEF ENGINEER TSG NTDCL LAHORE
JANUARY 2014
TSG-AR (T)-001/R1
1
Acknowledgement
The annual report of Technical Services Group for the calendar year 2013 has been
prepared for submission to different stakeholders such as GSO and GSC
Departments of NTDCL/DISCOs, WAPDA Power wing, GENCOs, IPPs,
renowned electrical contractors, etc., for giving a complete picture of the activities
of TSG. The General Manager (Services Division) NTDC wishes to place on
record its appreciation for services rendered by TSG’s staff, JICA and AKC/JICA
Consultants in achieving substantial progress of the Japanese Technical
Cooperation Project for Improvement of Training Capacity on Grid System
Operations and Maintenance in The Islamic Republic of Pakistan.
Gulzar Ahmad Bhatti
General Manager (SD) NTDCL
Foreword
Dear stakeholders, thank you for the continuous support for TSG. It had been 2.5
years passed since starting of the PROJECT. In 2013, TSG has drastically
improved by getting the aid from JICA
All textbooks were improved based on good suggestions from the stakeholder, new
technical information through the TOT (Training of Trainer) in JAPAN and new
equipment supplied by JICA.
And also TSG had occupied a good player as technical consultants in the field of
the P&I, Grids and T/L for the NTDCL and DISCOs. As a result, TSG dispatched
the Skill Enhanced 129 people, Promotion Criteria passed 326 people and refresher
course graduated 7 people. In addition, TSG held 7 seminars/workshops for the
related 249 people. Next year, TSG will continue to improve the training contents
and consulting power for the stakeholder.
Mohammad Arshad Mirza
Chief Engineer TSG
2
Table of Contents
Sr. No.
1
1.1
1.2
2
2.1
2.2
2.3
3
3.1
3.2
4
4.1
4.2
4.3
4.4
4.5
4.6
5
6
Description
Page
Introduction of TSG
4
Capacity Building of TSG
4
Basic Policy of TSG
5
Trainings
6
Training Purposes
7
Condition of Trainees for getting TSG Training
7
Tabulated & Statistical Data of Trainees
9
Technical Services
13
Scope of Technical Services/Consultancy Services
14
Tabulated & Statistical Data of Services Rendered
16
Achievements in the Year 2013
17
Progress on TSG/JICA Project for Capacity Building of
17
TSG NTDCL
Refresher courses
24
External Meetings
24
Seminars/Workshops
24
Special Promotion Criteria (PC) training course for
25
Telecommunication Department of NTDCL
Training Facilities Up-gradation
25
Organizational Changes during the Year 2013
26
Summary of Report
26
3
1. INTRODUCTION OF TECHNICAL SERVICES GROUP
Technical Services Group, hereinafter called “TSG” was established in June 1985
vide an agreement between WAPDA (Govt. of Pakistan) and CIDA (Canadian
International Development Agency-Govt. of Canada) with the objective to improve
capabilities for maintaining the GSO system in WAPDA. The joint project of
CIDA-WAPDA was completed in 1990. Thereafter TSG was working without any
external support or assistance till the project under technical cooperation of JICA
(Japan) started in April, 2011 for capacity building of TSG. Since 2005, TSG is
functioning under the Services Division NTDCL.
1.1 Capacity Building of TSG
On 30.04.2005, an agreement was signed between Govt. of Pakistan and Govt. of
Japan for improvement of training capacity on grid system operation and
maintenance in Pakistan. Then the need of improvement of training capacity of
TSG NTDC was identified during the visit of a fact finding mission of JICA (Japan
International Cooperation Agency) Japan.
A team of AKC (Asia Kyodo-Sekkei Consultant)/JICA experts, arrived at TSG
Lahore in April 2011 for 1st survey visit of TSG NTDCL to undertake and start the
project. The 3-years project started in April 2011 and will be completed in
December 2014
Japanese Technical Cooperation Project for Improvement of Training
Capacity on Grid System Operations and Maintenance in The Islamic
Republic of Pakistan
The following three main objectives were set for the project:
a) Provision of new and modern training equipment by JICA
b) Revision/up-gradation of the old training course books and facilities based on
the knowledge and skills acquired through TOT
c) Training of trainers (TOT) of TSG engineers and instructors in Japan
4
1.2 Basic Policy of TSG
TSG Policy
To contribute to the continuous improvement in performance of grid system
in Pakistan through the basic technical education and the advanced
technology
Activities for achievement of target objectives of TSG Policy:
By maintaining a competent team of engineers and technicians in TSG as
technical expert as well as trainer,
By having an effective and numerically clear Annual Plan and Long Term
Plan of Trainings and Technical services,
By having an effective Maintenance & Management System of Training
Equipment and Facilities,
By introducing a culture of personal safety, fellow’s safety and equipment
safety not only while on the work but also in the general public,
By having a system of feedback, evaluation and technical information
sharing among all the stakeholders of TSG i.e. trainees, their supervisors and
management of GSO field of NTDCL/DISCOs & IPPs through meetings,
seminars, technical workshops, etc.
Through training of each technical employee of grid system operation and
maintenance, for improvement of his professional skill and better
contribution towards the development,
Through providing on-job trainings, technical services and consultancy in all
the three major fields of grid system i.e. Substation Equipment,
Transmission Lines and Protection & Instrumentation,
By having a regular time based as well as need based system of up-gradation
and revision of training courses at TSG training centers to keep them in-line
with the requirement of grid system operation and maintenance.
“PROFESSIONAL O&M PERSONNEL FROM TSG”
5
2. TRAININGS
Scene of Seminar on Condition Monitoring of
Power Transformer by M/s. Prescon Engineering Lahore
Scene of Grid Maintenance training Class
GC-129 at NKLP Training Center
6
Trainings
To accomplish the target objectives based on TSG basic policy, TSG conducts
training courses mainly for GSO technical staff.
TSG training courses are of two basic categories, Skill Enhancement (SE) trainings
and Promotion Criteria (PC) trainings. Each category has three fields i.e., Grids
Operation and Maintenance, Protection & Instrumentation (P&I), and
Transmission Line (T/L).
Refresher courses and seminars/workshops are also conducted time to time along
with these trainings.
2.1 Training Purposes
Each training course of TSG has its specified purpose as described below:
Skill enhancement (SE) course is to learn applied theory of relevant courses
such as Grids Maintenance, P&I and Transmission Line maintenance
(Dead line & Live line) with practical in workshop / laboratory and
enhance technical skill for hands on working on the actual job.
Promotion Criteria (PC) course is to refresh the knowledge in relevant field
(grid maintenance, grid operation, P&I, T/L, etc.) through lectures and
fields visits of grid system.
Refresher Course/Short Course is to relearn about the specific equipment
through the lectures & demonstrations by TSG instructors or
manufacturer’s experts.
Seminar/Workshop is to learn about the new technologies presentations by
the manufacturer’s representatives.
2.2 Condition of Trainees for getting TSG Trainings
The conditions and entitlement criteria of trainees for getting TSG training is as
under:
7
For Skill Enhancement training: The trainee must be a regular technical
employee of GSO NTDLC/DISCOs/GENCOs/WAPDA and IPPs preferably with
1-year experience in the relevant field. The trainees having 3-years Diploma or
Bachelor of Engineering need no previous experience of GSO.
For Promotion Criteria training: The trainee should be a regular employee of
GSO NTDCL/DISCOs/GENCOs/WAPDA, should have passed departmental
promotion examination and should be in the zone of promotion as per his
company’s (NTDCL or DISCO) promotion rules and seniority list.
8
2.3 Tabulated & Statistical Data of Trainings
2.3.1 Table-1 Total Data Trained Personnel
Sr. No. Training Discipline
No. of Trained Grand
Personnel During Total
the Year-2013
since
2001
Skill Enhancement Training
1
Grid Station Maintenance
2
Protection & Instrumentation
3
Transmission Lines (Dead Line)
4
Transmission Lines (Live Line)
Promotion Criteria Training
1
Grid Station Maintenance
1.1
ASSA-to-Fitter-II/Elect-II
1.2
Fitter-II/Elect-II -to- Fitter-I/Elect-I
1.3
Fitter-I/Elect-I -to- AFM
1.4
AFM -to- FM
1.5
Under Matric Officials
2
Grid Station Operation
2.1
ASSA-to-SSA
2.2
SSA-to-SSO-II
2.3
SSO-II – to - SSO-I
3
Protection & Instrumentation
4
Transmission Lines
5
Telecommunication Department (NTDCL)
5.1
Mechanic-to-Supervisor
6
Refresher Courses
6.1
DC Battery Chargers
6.2
Energy Meters
6.3
Protection Relays
4.4
Safety & First Aid
7
Seminars/workshops
Total*1)
9
54
30
8
37
634
308
347
99
22
27
8
7
-
166
154
153
126
10
48
19
85
29
71
366
645
718
243
678
10
40
7
249
711
22
10
7
23
249
4998
*Notes:
Target training programs for SE are based on the training schedule which is course
end in the calendar year as follows.
i) Group-47, 48 and 49 for P&I
ii) GC-126, 127, 128 and 129 for Grids
iii) DLC-70 for T/L
10
2.3.2 Table-2 Company vise (NTDCL/DISCOs) Data of Trained Personnel
Sr. No.
Training Discipline
No. of Trained
Personnel
During
the
Year-2013
Skill Enhancement Training
1
Grid Station Maintenance
2
Protection & Instrumentation
3
Transmission Lines (Dead Line)
4
Transmission Lines (Live Line)
Promotion Criteria Training
1
Grid Station Maintenance
1.1
ASSA-to-Fitter-II/Elect-II
1.2
Fitter-II/Elect-II -to- Fitter-I/Elect-I
1.3
1.4
Fitter-I/Elect-I -to- AFM
AFM -to- FM
2
Grid Station Operation
11
Total
NTDCL
IESCO
LESCO
FESCO
QESCO
NTDCL
HESCO
IESCO
MEPCO
LESCO
QESCO
GEPCO
NTDCL
TESCO
PESCO
HESCO
FESCO
GEPCO
43
4
1
3
3
22
3
1
1
1
1
1
7
1
16
7
7
7
54
NTDCL
PESCO
IESCO
NTDCL
TESCO
PESCO
NTDCL
NTDCL
SEPCO
15
6
1
15
2
10
8
4
3
22
30
8
37
27
8
7
2.1
ASSA-to-SSA
2.2
SSA-to-SSO-II
2.3
SSO-II – to - SSO-I
3
Protection & Instrumentation
4
Transmission Lines
5
5.1
6
6.1
7
Telecommunication (NTDCL)
Mechanic-to-Supervisor
Refresher Courses
Protection Relays
Seminars/workshops
12
NTDCL
TESCO
PESCO
SEPCO
NTDCL
PESCO
IESCO
SEPCO
NTDCL
PESCO
HESCO
SEPCO
NTDCL
LESCO
MEPCO
HESCO
QESCO
IESCO
PESCO
NTDCL
PESCO
TESCO
QESCO
17
2
10
19
11
4
3
1
13
5
35
32
21
1
2
2
1
1
1
41
25
2
3
48
NTDCL
10
10
NTDCL
QESCO
NTDCL
LESCO
GEPCO
FESCO
5
2
140
100
5
4
7
19
85
29
71
249
3. TECHNICAL SERVICES
Scene of 132kV SF6 Gas CB Installation Training
by SIEYUAN China Experts at 132kv G/S
Rewaz Garden LESCO Lahore
Scene of 132kV SF6 Gas CB Installation Training
by SIEYUAN China Experts at 132kv G/S
Rewaz Garden LESCO Lahore
13
Technical Services
Besides providing training to the workforce of GSO, it is also a primary objective
of TSG to provide technical services/ consultancy services to them to improve their
performance capability and reliability of the grid system as and when demanded.
The quality standard of services is in accordance with the well-recognized
international/national
standards
and
the
equipment
manufacturer’s
recommendations. Safety of the personal as well as of the equipment is given
priority number one.
3.1 Scope of Technical Services/Consultancy Services
The present scope of technical services/ consultancy services of TSG includes:
- Erection, testing and commissioning of grid station equipment such as
Transformers, Circuit breakers, Disconnecting switches/Isolators, DC battery bank,
etc.,
- Trouble shooting and overhauling of grid station equipment such as overhauling
of circuit breakers, overhauling of on load tap changers (OLTC) of power
transformers, etc.,
- Testing, commissioning and trouble-shooting control and protection &
instrumentation (P&I) relays and devices,
- Repair of different types of auxiliary equipment such as battery chargers,
protection relays, testing sets, etc.,
- Testing and commissioning of line bays, transformer bays and complete grid
station of all voltage levels, such as 500kV, 220kV, 132kV, 66kV, etc. The testing
package includes:
i) Current Transformers (CT): Current ratio test, Excitation/Saturation
characteristics/Knee-point test, Winding resistance test, Polarity test, Insulation
resistance test, C&DF test, etc.
ii) Potential Transformers (PT/VT): Voltage ratio test, Insulation resistance test,
etc.
14
iii) Capacitor Voltage Transformers (CVT): Voltage ratio test, Insulation resistance
test, C&DF test, etc.
iv) Protection Relays: Programming and Functional testing, etc.
v) Transformers: TTR test, C&DF test, Insulation resistance test, Winding
resistance test, Oil testing, Short circuit test, Open circuit test, Zero sequence
impedance test, Bushing CT tests, etc.
vi) Shunt Reactors: C&DF test, Insulation resistance test, Winding resistance test,
Oil testing, Bushing CT tests, etc.
vii) Circuit Breakers: Open / close Timing test, Contact resistance test, insulation
resistance test, Hi-pot test, SF6 gas tests, etc.
viii) Isolator / Disconnect Switches: Insulation resistance test, Contact resistance
test, etc.
ix) Station Grounding System: Earth resistance test, Earth mesh integrity test, etc.
x) DC Battery Banks: Ampere Hour (AH) capacity test, Impedance test, etc.
xi) Any other machine or equipment subject to the available facilities.
- Technical studies and condition assessment studies of grid system equipment, and
investigation of their failures, etc.
- Technical vetting of requirements of spare parts of grid station equipment.
- Issuance and up-gradation of the SOP (Standard Operating Procedures) for
inspection and maintenance of grid system.
- Thermovision survey of grid stations and transmission lines.
- Technical audit of grid stations and transmission lines.
- Testing and calibration of energy meters at cut off points in NTDCL, DISCOs,
GENCOs, WAPDA and IPPs as per requirements of WPPO Department
- Any other task subject to the available facilities.
15
3.2 Tabulated & Statistical Data of Technical Services Rendered
TECHNICAL SERVICES AND CONSULTANCY SERVICES RENDERED
DURINING THE YEAR-2013
Sr. No. Description of Services
Quantity
1
Technical Audit of Grid Stations
2
2
Impedance Test of DC Battery Banks
89
3
Overhauling of OLTCs of 450MVA, 500/220kV
2
Auto Transformer Bank
4
Installation of DC Battery Bank
1
5
Thermovision Survey of Transmission Lines
50km
6
Repairing and Calibration of DC Battery Chargers
8
7
Testing and Calibration of Energy Meters
331
8
Pre-commissioning Testing Complete/Partial Grid
5
Stations
9
Pre-commissioning
Testing
Complete/Partial
7
Transmission Lines
10
Testing and Commissioning of Protection Relays
15
11
Testing of Bushing CTs
40
12
500kv Shunt Reactors
1
13
Capacitor Voltage Transformers (CVT)
11
14
Potential Transformers (PT)
3
15
Current Transformers (CT)
14
16
Overhead Bus Bars
2
17
Condition Assessment Studies and Inspections of
31
Grid Station Equipment
16
4. ACHIEVEMENTS IN THE YEAR-2013
The main achievement by TSG are related to the project of capacity building of
TSG which was started in April 2011 with the cooperation of JICA Japan beside
the routine training program and technical services/consultancy services program
of TSG. The salient achievements during the year-2013 are as mentioned below:
4.1 Progress of the TSG/JICA Project for Capacity Building of TSG NTDCL
As per implementation strategy of the Project, the Project is being executed in two
ways i.e. indirect supervision of AKC/JICA Experts/Consultants from Japan and
site visits survey of AKC/JICA Experts/Consultants to TSG NTDCL Lahore
Pakistan. Progress on objectives and performance activities in this regard is as
under:
4.1.1 Outcome of the three main objectives of TSG/JICA Project
i) With the commencement of 3rd and last batch of TSG engineers and instructor’s
training of trainers (TOT) in February, 2013 in Japan, the objective of TOT
completed successfully. TOT of 1st batch and 2nd batch has already been
commenced in Japan in October, 2011 and November, 2012 respectively.
ii) The objective of provision of new and modern training equipment by JICA,
completed in 2013. All the proposed 45 items of training purpose testing
equipment have been received and deployed at TSG training centers NKLP
Lahore, Tarbela and Gatti Faisalabad.
iii) Revision/up-gradation of the old training course books of all the skill
enhancement courses has been completed in the year 2013. New books have been
printed partially and implemented.
Placement of TSG documents (Basic policy of TSG, Annual Plan for TSG
Trainings for the year 2013, Annual Report for the year 2012, Long Term
Strategy of TSG, SOP for TSG Trainings, SOP for Operation and
Maintenance of Grid System) on the website of NTDCL
(download: www. ntdc. com. pk / services / publications)
17
4.1.2 List of Training Equipment
Sr.
No.
Name of Equipment
Pictures of Equipment
Transformer Turn Ratio
1
(Single Phase) (TTR)
Test Set
Transformer Turn Ratio
2
(3 Phase) (TTR)
Test Set
3
Digital Low Resistance
Ohm Meter
For Contact Resistance
Universal Relay Test Set
4
5
FREJA 306
Secondary Injection
Test Set Model: SVERKER 780
6
7
AC/DC Clamp-on Meter
AC Clamp-on Meter
18
Digital Multi Meter
8
Leakage Current Monitor
9
for Lighting Arrestors
Energy Meter Test Set/3-Phase
10
Full Automatic Test System
Model: MT786 Make: ZERA
(Germany)
Digital Oscilloscope
11
Insulation Resistance Test Set
12
Oil Di-electric Test Set
13
(0-100KV)
VARIAC,
14
Single Phase (0-240V)
19
VARIAC,
15
Three Phase (0-500V)
Phase Angle Measuring Set
16
(Digital)
Line Impedance Test Set
17
CT Analyzer
18
Analog Multi Meter
19
DC Hi-pot Test Set
20
(160KV)
C&DF Test Set (2.5KV)
21
Circuit Breaker Open/Close
22
Timing Test Set TM 1600
20
Winding Resistance Test Set
23
Distance Protection Relay
24
[7SA-6125, Siemens]
Over Current Relay
25
[7SJ6005, Siemens]
Over Current Relay
26
[SPAJ 140C, ABB]
Differential Protection Relay
27
[7UT6125]
Motor Drive Unit for
28
On Load Tap Changer Type ED100
Earth Resistance Tester
29
Personal Protective Equipment
30
Kit for Trainees (PPE)
D.C Voltage Power Supply Set
31
21
Primary Injection Test Set
32
Sweep Frequency Response
33
Analyzer (SFRA)
SF6 Gas Handling Plant
34
SF-6 Gas Leakage Detector
35
SF-6 Gas Purity Test Set
36
SF-6 Gas Dew Point Test Set
37
D.C Supply Grounding
38
Detecting Test Set Earth Fault
Detector
22
Distance Protection Relay
39
[P443, Alstom]
Distance Protection Relay
40
[REL650, ABB]
Differential protection relay
41
[P642, Alstom]
Over Current Relay
42
[P14, Alstom]
DC Battery Impedance Test Set
43
DC Battery AH Capacity Test Set
44
Vacuum Checker for VCB
45
4.1.3 Activities on Objectives of the TSG/JICA Project
i) 6th visit survey of TSG NTDCL in January, 2013.
ii) 7th visit survey of TSG NTDCL in June, 2013. The visit survey also includes
meetings/presentations with GSO FESCO Faisalabad, WAPDA Engineering
Academy Faisalabad, GSO NTDCL Circle Gatti Faisalabad, GSO MEPCO
23
Multan, GSO NTDCL Multan, for information sharing about Capacity Building
Project of TSG and its benefits to GSO O&M personnel.
iii) 8th visit survey of TSG NTDCL in September, 2013. The visit survey also
includes 4th JCC (Joint Coordination Committee) meeting at MoWP Islamabad
iv) 9th visit survey of TSG NTDCL in December, 2013 The visit survey also
includes meetings/presentations with GSO GEPCO, in addition special external
meeting (GSO summit) with GSO NTDC Lahore, GSO NTDCL Multan, GSO
LESCO, GSO GEPCO, GSO FESCO, GSO MEPCO in December, 2013
4.2 Refresher Courses/Short Courses
TSG conducted the following refresher courses/short courses in the year 2013:
i. Protection Relays
The course contents were as under:
Theory, interfacing and testing with FEJA 306 (Programma) and Doble F6150
Universal relay test sets of Distance Protection Relay P443 (Alstom), Distance
Protection Relay 7SA5111 (Siemens), Differential Protection Relay P642
(Alstom), Differential Protection Relay 7UT5125 (Siemens), Over Current
Protection Relay P145 (Alstom)
4.3 External Meetings
TSG conducted the following external meetings in the year 2013:
i. Information sharing sessions regarding TSG’ Capacity Building under
TSG/JICA Project and TSG’ New Training Programs, its benefits to GSO and
introduction of Training Evaluation and Quality Assurance and Feedback System
held by JICA/AKC experts and TSG counterpart experts at the following locations:
- FESCO Headquarter Faisalabad in June, 2013
- WAPDA Engineering Academy Faisalabad in June, 2013
- 500 kV GSO Circle NTDCL Gatti Faisalabad in June, 2013
- CE GSO Region NTDCL Multan in June, 2013
24
- MEPCO HQ Multan in June, 2013
- GEPCO HQ Gujranwala in December, 2013
- GSO NTDCL Lahore, GSO NTDCL Multan, GSO LESCO, GSO GEPCO, GSO
FESCO, GSO MEPCO in December, 2013
4.4 Seminars/Workshops
TSG conducted the following seminars and technical workshops in the year 2013:
i. Seminar on Condition Monitoring of Power Transformers and SFRA by M/s.
Prescon Engineering Lahore in March, 2013
ii. Seminar on Training Demonstration of OMICRON CT Analyzer, and Line
Impedance Test Set by M/s. Omicron Expert Austria in May, 2013
iii. Seminar on Low Loss Conductor (Aluminum clayed) by M/. JPS Japan in June,
2013
iv. Seminar on Training Demonstration of SFRA Test Set Model FRAX150 by
M/s. Megger Expert UK in June, 2013
v. Seminar on CDM (Clean Development Mechanism) awareness by the
Consultant Planning Power NTDCL in July, 2013
vi. Seminar on Training Demonstration of GE make, Numerical Protection Relays
by M/s. EPISOL Lahore in August, 2013
vii. Seminar on SIEYUAN China make, 132 kV SF6 Gas Circuit Breakers, CTs,
PTs, CVTs, Disconnect Switches, GIS by M/s. SIEYUAN China Experts in
September, 2013
4.5 Special Promotion Criteria (PC) training course for Telecommunication
Department of NTDCL
TSG arranged special promotion criteria training course at NKLP CENTER
Lahore for Telecommunication Department of NTDCL upon the request of CE
Telecommunication NTDCL WAPDA House Lahore for telecommunication
technicians. Telecommunication NTDCL engineers imparted the training. The
course contents were as under:
25
Basic electronics, SCADA (Supervisory Control and Data Acquisition), SDH
(Synchronous Digital Hierarchy), PDH (Plesiochronous Digital Hierarchy), Optical
Fiber, Switching equipment, Power Line Career (PLC) (Analogue/Digital).
4.6 Training Facilities Up-gradation
a) Conference room at NKLP training center has been furnished properly.
b) Air conditioners, Photo copy machine, multimedia have been provided at NKLP
Center.
5. Organizational Change during the Year 2013
a) CE TSG was changed from Mr. Nawab Din to Mr. Mohammad Arshad Mirza
b) Mr. Khalid Mehmood Manager Grid TSG was promoted and transferred/posted
as Chief Engineer System Protection NTDCL Lahore
c) Mirza Muhammad Akram Additional Manager was posted as Manager Grids
TSG on current charge bases
d) Mr. Tariq Ali Shah Additional Manager was posted as Manager TL TSG on
current charge bases
e) Mr. Muhammad Mustafa Additional Manager was posted as Manager P&I TSG
on current charge bases
f) Mr. Amir Zamir Khan Additional Manager was posted as Manager R&D TSG
on current charge bases
g) Naeem Akhtar Additional Manager was posted as Principal GSO Training
Center Tarbela on current charge bases
6. Summary of Report
i) Training of Trainers (TOT)
3rd (last) batch of TSG engineers and instructor’s training of trainers (TOT) has
been completed successfully for the improvement of the TSG instructors, and the
Action Plan made during TOTs has been effective to TSG improvement for
training program and technical services.
ii) New and modern training equipment
26
The provision of new and modern training equipment by JICA has been completed
in the middle of 2013. All the proposed 45 items of training purpose testing
equipment have been received and deployed at TSG training centers NKLP
Lahore, Tarbela and Gatti Faisalabad.
iii) Revision/up-gradation of the training course books
Revision/up-gradation of the old training course books of all the skill enhancement
courses has been completed in the year 2013. New books have been printed
partially and implemented.
iv) Number of trainees
Comparison of increase or decrease in numbers of trainees with the previous year
i.e. 2012 and 2013 is as follows:
In addition of regular training program such as skill enhancement and promotion
criteria, several refresher/short courses, seminars/workshops and special promotion
criteria had been conducted in this year, consequently TSG could achieve the 94%
increment of trainee’s number.
Total trained personnel in
2012
Total trained personnel in
2013
% increase or decrease
366
100%
711
194%
94% increase
v) Monitoring system with evaluation sheets (feedback)
TSG has a quality assurance program for evaluation of training quality at training
centers and its effectiveness in the field. Feedback of trainees and their supervisors
is obtained through a prescribed format of questionnaires upon the completion of
each training course. The grading criteria for overall quality rating of training is as
under:
Quality Assurance and Evaluation Grading Criteria for TSG Trainings
“4” for Very good
“3” for Good
“2” for Average “1” for Not good
The annual average grading rating for the year-2013 is ‘3.3’.
The grading ratings for each directorate are 3.4 for Grid, 2.9 for P&I and 3.6 for
TL respectively.
27
Mailing Address
Chief Engineer (TSG) NTDCL
TSG Training Center
220kV Grid Station, NKLP, Feroze Pur Road Lahore
Telephone: 042 35821418
Fax: 042 35821498
28
29
Download