Pesticide Handling Areas and Biobeds

advertisement
Ver1.4
Pesticide Handling Areas and
Biobeds
A presentation for farmers,
operators and advisers
CAUTION
Seek Regulatory Advice
Before Building a Biobed
Contact the Environment Agency's
Agricultural Waste Line for advice
0845 6033113
Developed for the Crop Protection Association and Agricultural Industries
Confederation by ADAS. The assistance of the Environment Agency, SEPA &
the Farming Unions is also acknowledged. This is part of the voluntary initiative
to minimise the environmental impact of pesticides
2
Contents
Main issues
Options for Pesticide Handling Areas
Sizing
Management and operation
Likely costs
Final water disposal
3
Background
 High levels of some pesticides have been found in
surface water
 In UK water companies now need to mix or treat water
to comply with the EC Drinking Water Directive
 Sprayer use, and in particular pesticide handling areas,
can be a significant source of water contamination.
 The Water Framework Directive identifies priority
substances and the need to meet good ecological
status thus indicating a further need for compliance.
Sources of pesticides in the environment
Sources of pesticides in the environment
Deposition
Atmospheric
output,
volatilisation
Residues in soil,
water, crop, food,
livestock,wildlife
Crop protection
products
Leaching
to groundwater
Veterinary
medicines
Drainage/
runoff to
surface
waters
Biocides
Borehole
Residues in water
sediments/biota
Biocides
Consented
discharges
Garden &
amenity
pesticides
5
Catchment Studies
 In UK, Germany and Sweden
– 20-70% pesticide load in surface water catchment is
derived from point sources
 UK - River Cherwell study 1998-2000
– Funded by Bayer CropScience (UK) Ltd
– 40% of catchment pesticide load originated from
concrete handling/washdown area
6
Pesticides in water:
sources of contamination
Pesticides in water
Diffuse
Point Source
Non-crop use
drift
tank filling
roads
drainflow
waste disposal
pavements
surface flow
washings
railways
interflow/base
seepage
leaching
faulty equipment other hard
surfaces
spillages
amenity areas
7
Sources of Farmyard
Pesticide Pollution
Spillage while
mixing
28 %
8%
12 %
Tank Rinse
Water
Foil Seals
Mud from tractor
wheels
17 %
25 %
10 %
Tractor exterior
washings
Spillage of container
washings
Results from Year 1 Aventis Cherwell Study
Bayer CropScience Cherwell Study
8
Concrete Filling Areas
Typical concrete
filling areas
showing
contamination and
run off
9
Best Practice - Aims
 Minimise contamination incidents through good
operational routine
– Limit contamination spread from inadvertent actions
– Minimise water volumes (rain and washings) on handling
area
– Store empty containers safely and upright after use
– Dispose of containers frequently and safely as permitted.
Through best practice
pesticide contamination of water from
handling areas can be reduced
by as much as 99%
Always comply with advice
in Codes of Practice
10
Sprayer loading area - Options
Concrete
– with / without portable bund
– with permanent bund
» drained to sump
» drained to treatment -biobed or chemical
Soil / grass
Drive over system
» drained to sump
» drained to treatment - biobed or chemical
11
Concrete
 Portable bund
– localises any spills
– collect and transfer back to sprayer tank.
 Permanent bund
– ensure area does not receive other drainage water
– construct a 100mm lip/bund around filling area
– Direct drainage off concrete away from normal drains to...
Containment
Minimise rainfall
Match tank size
to collection quantities
Disposal
through a licensed
disposal contractor..
Treatment
Consider a Biobed
12
Portable Bund
Available from
www.spillsave.co.uk
13
Homemade Splash Catcher
14
Soil / Grass
 Where site allows, filling the sprayer over a permeable
surface can be useful. Natural breakdown of the
pesticides is achieved by microbial action in the soil
 BUT
– Site >10m away from field drains and
watercourses;>50m from springs, wells and boreholes
– Prevent soil compaction by use of drive over grid or
hardcore
– May need to move site around periodically if compaction
occurs
– Avoid use on heavy clay
15
Handling Area - with a biobed
 A well planned, designed and operated area linked
to a biobed will allow pesticides to be retained and
degraded by a considerable amount (10,000 100,000 fold reduction)
 A pesticide handling area (mixing and sprayer
loading only) may be linked to a biobed without
the need for a Groundwater Authorisation from the
local environment agency.(See sprayer washing
note on next slide)
16
Sprayer Washdown - Special note
 Best Practice for tank washings and sprayer
exterior surfaces is to carry this out in the field
– Any washings should be discharged onto the previously
sprayed cropped area
– Observing maximum dose for that area
– Follow Statutory (Green) Code advice
If sprayer washdown is intended at the pesticide handling
area with disposal to land elsewhere, unless a lined
biobed is being used, a Groundwater Authorisation must be
obtained from the your local environment agency
17
Biobeds and The Law
 EA and SEPA support Lined Biobeds as
significant improvement over current
practice
NEW Regulatory advice for England
and Wales from EA
– Groundwater Authorisation (GWA) not required for
lined Biobed
– Water from lined Biobed can be “irrigated” or reused without GWA
– Site will have to be registered with EA in the future
but is expected that registration will be free and can
be done on line
– Scotland check with SEPA
– Northern Ireland check with EHS
Biobeds
Design, Construction, Use and
Maintenance
19
Biobed System Components
1 An area (bunded) where the sprayer stands
2 Drainage from that area to a biobed
3 The biobed
4 Drainage from the biobed
• either direct to the soil
• or to a designated disposal area
20
Biobed Design Types
 Offset - the sprayer mixing and loading area is
separate from the biobed area
– Features:
• Bunded concrete,
• Slope of 1:100 to silt trap
• Drain - to supply biobed
 Direct - the sprayer mixing and loading area is directly
over the biobed area
– Features
• Direct - bunded
• Steel drive over grid or wheel tracks
21
Pesticide Handling Areas
linked to Biobeds
 What do the designs look like?
– Offset - A separate area,
bunded concrete, where the
sprayer stands and any
liquids drain to a biobed
– Direct - A drive over grid all
liquids drain directly to the
biobed below the grid.
 Both designs may use
lined or unlined biobeds;
but only lined biobeds are
suitable for washdown
22
Suitable for
OFFSET LINED wash
down if
with disposal area Registered
Offset Biobed with Disposal Area
Bunded area
Disposal by drip
or sprinkler
Turf over
BIOBED
LINER
Pump
23
DRIVE OVER LINED
-with disposal area
Direct Lined Biobed with drive over
Suitable for
wash down if
Registered
Disposal by drip
or sprinkler
Turf over
Steel
Grid
BIOBED
Line
r
Pump
24
Location.. Location.. Location..
 Close to sprayer water filling point, chemical
store and electricity supply
 Away from other traffic / access routes,
footpaths etc.
 Avoiding collecting extra rainfall - check yard
contours, other drain routes and overflow
issues
 Separate from other drains / watercourses
(>10m;>50m)
 Groundwater Risks?
25
Pesticide Handling Area Dimensions
Concrete
pad
W
L
300 mm
Bund
100 mm
Drain via
silt trap to
pump
chamber
W = Sprayer
transport
width + 2 m
L = Sprayer
length + 1.5
m
26
Sprayer loading area - Direct
Size - as for offset
Grid - to support total
full sprayer weight
Mesh must be
removable for biomix
annual top-up
Grid size 100 x 40
mm to suit foot safety
and soil/mud flow
27
The Biobed -What is it?
 Normally a hole in the ground filled
with:
– Either a composted mix 50% by volume straw,
25 % soil, 25% peat-free compost (biomix)
with turf on top
– Or aThe
friable
loamy
soil
with
turf
on
top
hole may be lined with an impermeable liner or not, dependant on system function, soil type,
local drains, local environment agency advice etc.
28
Biobeds - Function, location and size
 How do they work?
– By locking up the pesticides and then providing conditions
for enhanced microbial degradation of the active ingredients
over time
 Location
– A biobed can be sited independently from the loading area,
taking account of local drainage, access, groundwater risks,
contours etc.
 Size
– Where a 24 m, 3000 l sprayer has been used then
5 x 4 x 1 m deep bed has been satisfactory, though local
rainfall and frequency of use will influence final size.
Biobeds should always
be at least 1m deep
29
Biobeds - Components
 The biomix materials could be varied from the mix
suggested. Guidance must be sought to ensure required
properties exist.
 Turf cover over the biomix is vital to encourage the
biological activity of the mix and assist in the management
of the moisture status of the biomix.
 Efficient distribution of the water over the biobed surface is
considered critical, drip irrigation is suggested at 400 mm
spacing
Drip
header
pipe
Good turf
growth
30
Sizing Summary
Loading area with working allowances, guidance
only, best to measure unit on site.
Sprayer type
Self propelled
Trailer
Mounted
Overall
length (m)
7
7
4
Overall
width (m)
5
5
5
Biobed - excavated in soil, 1 m deep, 300 batter on
sides, 5 x 4 m area suggested as suiting most
situations.
Rule of thumb: Biobed area should be at least two/thirds
of the area from which it is receiving liquids
31
Offset - System Plumbing
 From offset loading area, install pump in small
chamber, e.g. 0.75 x 0.75 x 1m deep.
 Pump, with integral float switch - approx. 40 l/min@6m
head, installed to appropriate regulations.
Site all pipe runs for adequate frost protection.
Pipe to optional holding tank or direct to drip over
biobed.
 Excavate biobed and liner with sealed drain as
appropriate. Liner to be 1.5mm geotextile membrane
on specified inner liner and/or sand as detailed.
32
Direct System Design
 Design and construct grid to adequately support
spray vehicle and ensure safe operator use.
– Operator should be kept off biobed surface for functional
and safety reasons.
– Allow for grid to be removed in sections for annual biomix
top-up.
 Construct foundations, as appropriate, avoiding
support on biobed liner if used.
 Excavate biobed and liner with sealed drain as
appropriate.
 Liner to be 1.5 mm geotextile membrane on
specified inner liner and/or sand as detailed.
See further biobed installation notes
33
Biobed - Installation 1
 Biobed can either be a biomix - straw, soil and
peat-free compost, or loamy soil
 Biobed will need lining where washdown is to be
practised (with Groundwater Authorisation)
 Lining must be sealed to outlet drain effectively
with coarse filter over drain inlet, e.g. 6 mm mesh
 Where unlined, ensure that subsoil is
uncompacted
 Lining should overlap top of side batter by
approx. 300 mm thereby preventing unnecessary
rainfall reaching biobed
34
Biobed Installation - 2
 Direct drain to optional tank or small pump chamber
as before, or to pump to final disposal area
 Biomix must be composted for 4-6 weeks before use
and evenly loaded into hole. Overfill hole to allow for
early sinkage
 Turf should be laid at time of filling to encourage
growth. Turf does not need to be high quality and is
laid over the surface of the biomix, watering early to
encourage growth
 Install drip irrigation, hard hose type best, laid onto
the biobed turf surface as well as the final disposal
area, lightly anchor drip lines
 Test pump system before use
35
Biobed Management - short term
 Biobed irrigation will maintain regular
watering of turf and thus control biomix
moisture condition
 Grass growth will encourage moisture use
and thus evapo-transpiration from biobed
 Check weekly for condition and function.
Investigate any tendency for waterlogging.
 Any foliage cut from biobed turf cover to be
mulched over biobed area
36
Biobed management - long term 1
 Where biomix is used, material will degrade
and level sinks by approx. 300 mm per year
 Biomix top-up annually necessary.
Dependent on turf growth, turf may be
peeled back (with adequate operator
protection) and new mix added to restore
level, replace turf.
 Soil based systems probably will not
‘shrink’ as fast.
 Check irrigation function
37
Biobed management - long term 2
 Biomix material in the hole will probably have a life
of 6 -8 years before replacement or recycling
 Removal of biomix should be done carefully (with
appropriate operator protection) to a concrete area
for further composting for one year. Research
suggests any pesticides remaining are fully
degraded in that period.
 Drainage from this area should be preferentially
routed to the replenished biobed.
 Final disposal of the spent biomix material must
be in accordance with advice from local
environment agency.
38
Water distribution - disposal area
 Where drip irrigation used, lay hard hose
pipes at 400 mm spacing with drippers at
around 1.5 l/h flow rate.
– 1-1.5 running hours per day applies 2-4 mm of
water, dependant on equipment used.
 Set controls, e.g. level switch and any
timers, to achieve this, allowing for
override in intense rainfall
– buffer available from optional tank if installed
39
Typical Costs - Offset
 Sprayer loading area - depends on whether
adequate concrete present with bund
added or new material - range £300 - £850
 Each chamber £140, pump £60
 Biobed, excavation and materials £500
 Liner, if needed with drain £1000
 Drip irrigation to biobed and final disposal,
depends on areas £200- £400
40
Typical Costs - Direct
 Sprayer vehicle grid - range £2000 - £5000
 Biobed, excavation and materials /
foundations £800
 Liner, if needed, with drain £1000
 Each chamber £140, pump £60
 Drip irrigation to final disposal, depends on
area £300
41
More Information
 www.biobeds.info
 www.voluntaryinitiative.org.uk
– choose Library, then publications then Best Practice Guides,
• Pesticide handling areas
• Biobeds
• Biobed Manual
 ADAS Gleadthorpe
 Cranfield University
 Environment Agency
– www.environment-agency.gov.uk/farming
 Scottish Environment Protection Agency
– PEPFAA Do’s and Don’t’s Guide
42
CPD
BASIS CPD Points AP/032/034/d =
1AP
NRoSO CPD Points N0340530c = 1AP
Practical Simple
Solutions
Protecting the
Environment
Download