Rehabilitation of Gaza Water Wells

advertisement
United Nation Development Program
Emergency Water Supply and Rehabilitation Programme
PAL 10-00052737
CONSTRUCTION OF TAL EL-SULTAN BOOSTER STATIONSRafah
Cost Estimate
Center for Engineering and Planning (CEP)
&
Engineering & Management and Planning (EMCC)
BILL NO. 1
CIVIL WORKS
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
1.1.0
1.1.1
1.1.2
Description
Excavation & Concrete Works
Excavate for foundations (Pumps room and service
building) including removing excavated material from
the site to the location approved, all according to
Drawings, Specifications and instructions of the
Engineer.
Backfilling from the selected excavated material
Unit
Qty.
M3
60
M3
40
Unit
Price
(US$)
Total
(US$)
over and around foundation and to make up levels
for the site in layers 25cm thick (M.D.D 98%)
according to Eng. instructions and specifications.
1.1.3
Supply and cast ready mix plain concrete B200 below
foundations (Pumps room and service building), base
and concrete supports for pipes, anchor blocks or others
according to Drawings, Specifications and instructions
of the Engineer.
M3
7.5
1.1.4
Supply and cast ready mix reinforced concrete B300 for
foundations (Pumps room and service building), base
including reinforcement and shuttering, according to
Drawings, Specifications and instructions of the
Engineer.
M3
30
1.1.5
Supply and cast ready mix reinforced concrete B300 for
columns, including reinforcement and shuttering,
according to Drawings, Specifications and instructions
of the Engineer.
M3
8
1.1.6
Supply and cast ready mix reinforced concrete B300 for
ground beams including reinforcement and shuttering,
according to Drawings, Specifications and instructions
of the Engineer.
M3
11
1.1.7
Supply and cast ready mix concrete B250 for pumps
room Ground Slab of 10m thickness including steel
reinforcement
( 10 mm every 15 cm in both
directions), and base coarse layer 15cm thick according
to Drawings, Specifications and instructions of the
Engineer.
M2
60
1.1.8
Supply and cast concrete B250 for service building
Ground Slab of 10cm thickness including steel
reinforcement ( 8 mm every 20 cm in both directions),
and base coarse layer 10cm thick, and Nylon sheet
according to Drawings, Specifications and instructions
of the Engineer.
M2
80
2
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
1.1.9
Description
Unit
Qty.
Supply and cast ready mix concrete B250 for pumps
room and service building Ribbed Slabs of 23cm
thickness including reinforced steel hollow block
(25x40x17cm), drop beams, , and electrical conduits
and all other materials according to Drawings,
Specifications and instructions of the Engineer.
M2
180
1.1.10
Supply and lay one layer of plasticized bitumen roofing
membrane with chipping 4 mm thick, the work includes
supplying and spreading prime Light weight concrete
surface prior to laying with average thickness 8 cm
dressing into rain water outlets to form water proofing
seal and cover with angle fillets. The rate includes
verticals parts skirting as per specification and
drawings.
M2
200
1.2.0
1.2.1
Block, Plastering & Painting Works
Supply and construct walls from hollow concrete
blocks, (20x20x40cm) including supplying and casting
reinforced concrete B250 for Lintels & Posts all
according to Drawings, Specifications and instructions
of the Engineer.
M2
290
1.2.2
Ditto, but for hollow concrete block (10x20x40cm)
M2
10
1.2.3
Supply and make internal plastering 13 mm thick to
walls and ceiling, after rough primer nail rendering
works include all material needed according to
technical specifications.
M2
450
1.2.4
Supply materials and make external plastering two
faces and final face with tyrolean plaster including two
coats of emulsion paints (Supercryl) all according to
Drawings, Specifications and instructions of the
Engineer.
Supply materials and make emulsion paint (Supercryl)
two coats and base coat for all internal walls and
ceiling, all according to Drawings, Specifications and
instructions of the Engineer.
M2
270
M2
450
1.2.5
1.3.0
Unit
Price
(US$)
Total
(US$)
Metal Works
3
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
1.3.1
Description
Unit
Qty.
Supply and install galvanized metal door 200x 450 cm
(type D1) with new double sheet (2-mm) complete with
frame, ironmongery, ventilation louvers for pumps
room. The price should include painting with two coats
and base coat and union or equivalent type lock all
according to Drawings, Specifications and instructions
of the Engineer.
No.
1
1.3.2
Supply and install galvanized metal door 160x 220 m
(type D2) with new double sheet (2-mm) complete with
frame, ironmongery, for service building. The price
should include painting with two coats and base coat
and union type lock or equivalent, all according to
Drawings, Specifications and instructions of the
Engineer.
No.
2
1.3.3
Ditto, but 90x220 cm (type D3).
No.
2
1.3.4
Ditto, but 80x220 cm (type D4).
No.
1
1.3.5
Supply and install galvanized metal window
120x140cm (type W1) with ventilation louvers for
pumps room and service building. The price should
include painting with two coats and base coat, all
according to Drawings, Specifications and instructions
of the Engineer.
No.
6
1.3.6
Ditto, but 80x60cm (type W2).
No.
1
1.3.7
Ditto, but 100x200cm (type W3).
No.
3
1.3.8
Supply and fix colored aluminum window Kalil
Type7000 or equivalent size 120X140 cm (type W4),
two sliding leave complete with one sliding fly screen
leaf, frame, clear glass 4mm thick, all according to
Drawings, Specifications and instructions of the
Engineer.
No.
2
1.3.9
Supply and fix steel protection grate for window overall
size100x200cm for window type (W4). The price
should include painting with two coats and base coat,
all according to Drawings, Specifications and
instructions of the Engineer.
No.
2
1.3.10
Supply and install galvanized steel ladder all according
to Drawings, Specifications and instructions of the
Engineer. The price should include painting with two
coats and base coat, all according to Drawings,
Specifications and instructions of the Engineer.
No.
1
1.4.0
Tiling Works
4
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
1.4.1
Description
Unit
Qty.
Supply and install terrazzo floor tiles size 25x25x2.5cm
for service building. The price should include 2.5cm
mortar bed and 5cm thick sand bed, terrazzo skirting of
same kind color of the floor tiles size 25x7x1cm thick
laid on 1cm mortar backing, all according to Drawings,
Specifications and instructions of the Engineer.
M2
60
1.4.3
Supply and install non-slipping white ceramic floor
tiles size 20x20x0.8 cm. The price should include
2.5cm mortar bed and 5cm thick sand bed, all
according to Drawings, Specifications and instructions
of the Engineer.
M2
15
1.4.2
Supply and install white glazed wall tiles size
20x20x0.6 cm. The price should include mortar
backing up to lintel level, all according to Drawings,
Specifications and instructions of the Engineer.
M2
40
1.4.3
Supply and install local marble size 25cm x 3cm thick
for window sills, doors including 2.5cm mortar bed, all
according to Drawings, Specifications and instructions
of the Engineer.
LM
27
1.4.4
Supply and erect marble 3 cm thick for cupboards 60
cm wide and 90 cm high including vertical dividers,
internal horizontal shelves, back of cupboards, floors
and granite (Tiger eye) for the top surface with round
edges, skirting 10 cm high and making the needed
opening for basins as shown in drawings.
L.S
1
1.4.5
Supply, spread, level and compact of 40cm thick of
approved selected material (Kurkar) type A to be
spread & compacted on layers 20cm to get
{98%M.D.D) prior to subsequent interlock tiling
including soil grading leveling as per specifications and
drawings.
M3
270
1.4.6
Supply & cast ready mix concrete B250 kg/cm2
chamfered edge beam 15x20 for interlock tiling as per
specifications and drawings.
M3
2
1.4.7
Supply, spread, land, interlock tiles size 8x10x20cm
price includes 5 cm clean sand as per specification and
drawing.
M2
650
1.5.0
Plumping Works
5
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
1.5.1
Description
Unit
Qty.
Supply, and install. Vitreous China, European type
W.C. First Class size (48x36x40cm), completed with 2
Gallon capacity flush reservoir, china roll holder,
chrome plated angle valves and flexible connections,
supports, welding, hand spray with flexible chrome
connection and all necessary fittings, waste pipes
diameters 4", thickness 3.2mm connected to the nearest
riser, heavy duty cover, rubber connector on WC outlet
to the drain pipes.
No.
1
1.5.2
Supply, install, test and commission Vitreous China
wash basin (51x38cm), First Class, completed with
chrome plated mixer, bottle trap, soap tray, chrome
plated angle valves, flexible tubes, wall fixed mirror
and all accessories, waste pipes d 2", connected to the
nearest floor drain, fittings, supports and hangers.
No.
2
1.5.3
Supply and install white fire clay sink Harza Type or
equivalent size 54x42 cm including trapped waste
fittings, plug and chain, steel brackets supports and the
drainage line to the floor trap, chromium plated water
tap 1/2" diameter Hamat type or equivalent including
cold water supply lines 1/2" dia., all according to
Drawings, Specifications and instructions of the
Engineer.
No.
1
1.5.4
Supply and install white glazed fire clay squatting WC
suite (Asiatic WC) complete with flushing cistern, 4"
dia. UPVC drainage pipe to the nearest Manhole and
white glazed toilet paper holder, chromium plated water
pillar valve 1/2" dia including 1/2" water supply pipe
and 100cm long rubber hose inside the toilet, all
according to Drawings, Specifications and instructions
of the Engineer.
No.
1
1.5.5
Supply and install 4/2” PVC floor drain including 4”
PVC pipe to nearest manhole all according to
Drawings, Specifications and instructions of the
Engineer.
L.S.
2
1.5.6
Supply and install 60cm concrete manhole complete
including all necessary works all according to
Drawings, Specifications and instructions of the
Engineer.
No.
2
6
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
1.5.7
Description
Unit
Qty.
Supply and install 100cm internal diameter precast
circular reinforced concrete sewage manholes
complete with reinforced concrete base, cast iron
cover (25 tons capacity), frame and rings, The item
also includes B300 benching, shuttering, inside
cast-iron steps each step 30 cm maximum and
safety measures, excavation in any type of soil to
any depth, plain concrete, two external bitumen
coating, internal epoxy coating, and backfilling in
layers 25 cm maximum using suitable material
with watering, and compaction the price includes
repairing the damage of the existing asphalt layers,
base course layers, curb stone, side walks tiles to
the original condition. as described in
Specifications and as shown in Drawings and
directed by the Engineer
No.
2
1.5.8
Supply and install 3” PVC drainage pipes including all
necessary bends connections and making good, all
according to Drawings, Specifications and instructions
of the Engineer.
LM
18
1.5.9
Supply and fix 3/4" dia. Galvanized steel water supply
pipes from the fire hydrant feeder to the service
building roof top tank and from the tank to toilet
fixtures and pumps room fixture and including valves,
jointing and fittings, all according to Drawings,
Specifications and instructions of the Engineer.
L.S.
1
1.5.10
Supply and install plastic water storage tank 1 M3
capacity complete with lockable cover, float valve 1/2"
dia., cleaning opening with plug 3/4" dia., overflow
pipe 3/4" dia., steel base and the connection with the
feeding and distribution lines, all according to
Drawings, Specifications and instructions of the
Engineer.
Supply and lay 4" UPVC sewage pipes including
excavation, bedding, jointing, backfilling, Asphalt
reinstatement testing and connect to the municipal
sewage system, all according to Drawings,
Specifications and instructions of the Engineer.
L.S.
1
LM
35
Supply and lay 8" UPVC, SN-8 sewage pipes including
excavation, bedding, jointing, backfilling, Asphalt
reinstatement testing and connect to the municipal
sewage system, all according to Drawings,
Specifications and instructions of the Engineer.
L.M
80
1.5.11
1.5.12
Unit
Price
(US$)
Total
(US$)
Total Carried to Summary (Bill No. 1)
7
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
BILL NO. 2
MECHANICAL WORKS
8
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
Description
Unit
Qty
Unit
Price
(US$)
Total
(US$)
Notes:
*All the following notes are on the contractor
expense:
 The Contractor shall, when pricing this Bill,
take into consideration all costs or expenses of
all requirements stipulated in the section
entitled “General and Preambles” preceding
this Bill.
 The exact lengths of the required pipes, the
exact number of the required valves will be
determined during the implementation of the
Works.
 All the works should be done by coordination
with the municipality water department.
 Submission of shop drawing to be approved by
the Engineer before starting any work activity.
 Making trial pits for identifying existing
services, connecting existing water pipelines if
required.
 Excavation at any depth in any kind of soil at
indicated trench depth.
 Removal and transport at any distance of
excess or unsuitable materials to approved
landfill.
 Repair any damage of any service at full
satisfaction of relevant Service Authority.
 Restoring the existing surface to original status
and approval of the Engineer.
 Testing, flushing and disinfections of the new
pipeline.
 All works should be executed in accordance to
drawings, specifications and as instructed by
the Engineer.
 Any cut of asphalt layers must be by using
special saw and restoring the asphalt by using
two layers of 15 cm (each) base coarse and one
layer of asphalt 6 cm thick.
2.1
Buried Pipes
Supply and install underground pipelines complete
but not limited to following: excavation in all types
of soil and disposal of excess material to locations
acceptable to the Engineer, bedding, pipe laying
9
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
Description
Unit
Qty
Unit
Price
(US$)
Total
(US$)
including all piping works such as welding, cutting
and shaping, supplying and installing all kinds of
fittings (flanges and blind flanges, etc.), testing,
bedding material surround the pipe, backfilling and
compaction, disinfection and reinstatement,
complete all as described in the Specifications and
as shown on the Drawings and as directed by the
Engineer.
2.1.1
18” diameter X 3/16” thickness Steel pipes coated
externally with Epoxy primer and two layers of
extruded polyethylene coating and internal cement
mortar lining (Suction side of PS-7 Booster Station).
LM
20
2.1.2
Ditto, but 14” diameter (Discharge side of PS-7
Booster Pumps).
LM
26
2.1.3
Ditto, but 12” diameter (Suction and Discharge sides
of PS-6 Booster Pumps).
LM
28
2.1.4
Ditto, but 10” diameter (Suction sides of PS-7 and
PS-6 Booster Pumps).
LM
4
2.1.5
4'' diameter X 5/32'' thickness Steel pipes coated
externally with Epoxy primer and two layers of
extruded polyethylene coating and internal cement
mortar lining (Feeder of fire hydrant).
Non-Buried Pipes
Supply and install pipelines complete including but
not limited to: pipe laying including all piping works
such as welding, cutting and shaping, supplying and
flanges, testing, disinfection and supports including
concrete bases, complete all as described in the
Specifications and as shown on the Drawings and as
directed by the Engineer.
LM
15
2.2.1
14” diameter X 3/16” thickness Steel pipes coated
externally with Epoxy coating and internal cement
mortar lining (Discharge side of PS-7 Booster
Pumps).
LM
6
2.2.2
12” diameter X 3/16” thickness Steel pipes coated
externally with Epoxy coating and internal cement
mortar lining (Discharge side of PS-6 Booster
Pumps).
LM
6
3.2.3
10” diameter X 3/16” thickness Steel pipes coated
externally with Epoxy coating and internal cement
mortar lining (Suction side of PS-7 Booster Pumps).
LM
9
2.2.4
Ditto, but 10” diameter (Suction side of PS-6
Booster Pumps).
LM
6
2.2
10
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
2.3
Description
Unit
Qty
No.
1
Unit
Price
(US$)
Total
(US$)
Valves in Chambers
Supply and install valves in chambers complete
including but not limited to the following:
excavation in all types of soil, reinforced concrete
chamber, chamber cover and ring, and pipe
connections, valve, fittings, flanged coupling, bolts,
gaskets, concrete support, concrete paving,
backfilling and compaction and reinstatement,
complete all as described in the Specifications and
as shown on the Drawings and as directed by the
Engineer.
2.3.1
2.4
Butterfly Valve, 18'' – PN 16 bar (Suction line of
PS-7 & PS-6 Booster Stations).
Non- Buried Valves
Supply and install valves complete including but not
limited to the following: valves, fittings, fixed, jack
and concrete supports, complete all as described in
the Specifications and as shown on the Drawings
and as directed by the Engineer.
2.4.1
Gate Valve, 10'' – PN 16 bar (Suction and Discharge
lines of PS-7 Booster Pumps).
No.
6
2.4.2
Gate Valve, 10'' – PN 16 bar (Suction and Discharge
lines of PS-6 Booster Pumps).
No.
4
2.4.3
Check Valve, ARI or equivalent, 10'' – PN 16 bar
(Discharge lines of PS-7 Booster Pumps).
No.
3
2.4.4
Check Valve, ARI or equivalent, 10'' – PN 16 bar
(Discharge lines of PS-6 Booster Pumps).
No.
2
2.4.5
Air Release and Vacuum Release Valve, 80 mm, PN
10 bar, ARI or equivalent, with the 80 diameter Arca
bronze gate valve or equivalent connected to it with
drain pipe and all accessories required – (Discharge
side of PS-7 Booster Pumps).
No.
1
2.4.6
Air Release and Vacuum Release Valve, 80 mm, PN
10 bar, ARI or equivalent, with the 80 diameter Arca
bronze gate valve or equivalent connected to it and
with all accessories required – (Discharge side of
PS-6 Booster Pumps).
No.
1
2.5
Fittings and Others
Supply and install Fittings, Tees and Bends,
Reducers, Increasers, Couplings, Expansion Joints,
11
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
Description
Unit
Qty
Unit
Price
(US$)
Total
(US$)
and gauges complete all as described in the
Specifications and as shown on the Drawings and as
directed by the Engineer.
2.5.1
Supply and install buried 18"x18'' steel tee with
external extruded polyethylene coating and internal
cement mortar lining factory made (Suction side of
PS-7 & PS-6 Booster Stations).
No.
2
2.5.2
Ditto, but 18"x10'' (Suction side of PS-7 Booster
Station).
No.
3
2.5.3
Ditto, but 12"x10'' (Suction side of PS-6 Booster
Station).
No.
2
2.5.4
Ditto, but 14"x4'' (For fire hydrant feeder)
No.
1
2.5.5
Ditto, but flanged 10"x14'' (Discharge side of PS-7
Booster Station).
No.
3
2.5.6
Ditto, but flanged 14"x14'' (Discharge side of PS-7
Booster Station).
No.
1
2.5.7
Ditto, but flanged 10"x12'' (Discharge side of PS-6
Booster Station).
No.
2
2.5.8
Ditto, but flanged 12"x12'' (Discharge side of PS-6
Booster Station).
No.
1
2.5.9
Supply and install 18''x12'' concentric steel reducer
with external extruded polyethylene coating and
internal cement lining factory made (Suction Side of
PS-6 Booster Station and Pump Station Bypass).
No.
2
2.5.10
Supply and install 10''x5'' eccentric flanged steel
reducer with external epoxy coating and internal
cement lining factory made (Suction lines of PS-7
Booster Pumps).
Ditto, but 10''x6'' (Suction lines of PS-6 Booster
Pumps).
No.
3
No.
2
2.5.12
Supply and install 4''x10'' concentric flanged steel
increaser with external epoxy coating and internal
cement lining factory made to fit outlet of pump
flange (Discharge lines of PS-7 Booster Pumps).
No.
3
2.5.13
Ditto, but 5''x10'' (Discharge lines of PS-6 Booster
Pumps).
No.
2
2.5.14
Supply and install 10” diameter complete flanged
coupling (Suction & Discharge lines of PS-7
Booster Pumps).
No.
6
2.5.11
12
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
Description
Unit
Qty
2.5.15
Supply and install 10” diameter complete flanged
coupling (Suction & Discharge lines of PS-6
Booster Pumps).
No.
4
2.5.16
Supply and install 10” diameter complete flexible
joint coupling (Discharge lines of PS-7 Booster
Pumps).
No.
3
2.5.17
Supply and install 10” diameter complete flexible
joint coupling (Discharge lines of PS-6 Booster
Pumps).
No.
2
2.5.18
Supply and install buried 18'' steel 90o elbow with
external extruded polyethylene coating and internal
cement mortar lining factory made (Suction side of
PS-7 & PS-6 Booster Stations).
No.
1
2.5.19
Ditto, but 14'' steel 45o (Discharge side of PS-7
Booster Pumps).
No.
1
2.5.20
Ditto, but 12'' steel 45o (Discharge side of PS-6
Booster Pumps).
No.
1
2.5.21
Supply and install non-buried 10'' steel 90o flanged
elbow with external epoxy coating and internal
cement mortar lining factory made (Suction lines of
PS-7 Booster Station).
No.
3
2.5.22
Ditto, but for (Suction lines of PS-6 Booster
Station).
No.
2
2.5.23
Ditto, but 14'' steel 45o (Discharge side of PS-7
Booster Pumps).
No.
1
2.5.24
Ditto, but 12'' steel 45o (Discharge side of PS-6
Booster Pumps).
No.
1
2.5.25
Supply and install ½x4” pressure gauge (0-10 bar)
with all necessary fittings and accessories required
as shown in the Drawings and described in the
Specifications and as directed by the Engineer
(Discharge lines of PS-7 Booster Pumps).
No.
3
2.5.26
Supply and install ½x4” pressure gauge (0-10 bar)
with all necessary fittings and accessories required
as shown in the Drawings and described in the
Specifications and as directed by the Engineer
(Discharge lines of PS-6 Booster Pumps).
No.
2
2.5.27
Supply and install pressure switch on the main
Lump
3
13
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
Description
Unit
Qty
header connected to PLC panel, the switch shall be
adjustable (0-10 bars). (Discharge lines of PS-7
Booster Pumps).
sum
Supply and install pressure switch on the main
header connected to PLC panel, the switch shall be
adjustable (0-10 bars). (Discharge lines of PS-6
Booster Pumps).
Lump
sum
2
2.6
Booster Pumps
Supply and install horizontal centrifugal booster
pumps and motors, installed and tested complete
including pump, drilled hole, pipe connections,
fittings, all manufacturer's recommended spare parts,
supports and protection of surfaces, subsurface
installations, including concrete bases and all parts
needed for proper installation and operating of the
pump in its place, all according to Drawings,
Specifications, catalogues of manufacturer and
instructions of the Engineer.
2.6.1
Pump for Booster Station PS-6, model (FHF 125270/1320) as manufactured by LOWARA, or
equivalent of discharge 320 m3/hr for each, total
dynamic head 88 m, complete with the drive motor
100 KW rated power, speed of pump = 2950 rpm.
No.
2
2.6.2
Pump for Booster Station PS-7, model (FHS 100200/370) as manufactured by LOWARA, or
equivalent of discharge 280 m3/hr for each pump,
total dynamic head 38 m, complete with the drive
motor 36 KW rated power, speed of pump = 2950
rpm.
No.
3
2.7
Flow Meter Set
Supply and install flow meter set complete including
but not limited to the following: flow meter, steel
piping and pipe connections, gate valve, fittings,
reducers, coupling, flanges, bolts, gaskets, jacking
and concrete supports, complete all as described in
the Specifications and as shown on the Drawings
and as directed by the Engineer.
2.7.1
Flow meter, 10'' – PN 16 bar ABB type or
equivalent with possibility for remote data transferdata loggering including cable, ductbanks and
connections (Discharge side of PS-7 Booster
Station).
Lump
sum
1
14
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
Description
Unit
Qty
2.7.2
Flow meter, 8'' – PN 16 bar ABB type or equivalent
with possibility for remote data transfer-data
loggering including cable, ductbanks and
connections (Discharge side of PS-6 Booster
Station).
Lump
sum
1
2.8
Fire Hydrant
Supply and install Fire hydrant 80mm diameter
including stand post with flanged ends 4”/3”. The
price shall include buried gate valve 4” with flanged
couplings and box chamber and the provision and
installation of 4”steel pipes (5/32” wall thickness,
internally cement lined and externally polyethylene
coated) with elbow, flanges and all necessary works
including anchor blocks as shown in the drawings
and directed by the engineer.
Lump
sum
1
2.9
Monorail hoist
Supply and install electrical monorail hoist 1.5 ton
capacity complete with "I" beam (300x150mmx42.2
kg/m), the base, the hook, the chain, the stopper, the
fixing rods, painting and all necessary parts required
for proper installation and operation, all as described
in the Specifications and as shown on the Drawings
and directed by the Engineer.
Lump
sum
1
2.10
Fuel Tank
Supply and install cylindrical steel fuel tank with 4
m3 capacity and 6 mm thickness complete with all
the required valves, fittings, fuel pump, float, pipe
works, excavation, concrete foundation and
backfilling all according to Drawings, Specifications
and instructions of the Engineer.
Lump
sum
1
Lump
1
2.11
2.11.1
Pipe Connection (Provisional Items)
Connection of the 12'' and 14 '' discharge pipes of
PS-6 & PS-7 respectively to the adjacent trunk and
distribution lines. The connection should include
but not limited to the following: Supply and install
dresser and necessary fittings complete but not
limited to following: excavation and disposal of
excess material to locations acceptable to the
Engineer, bedding, all piping works such as
welding, cutting and shaping, testing, bedding
material surround the pipe, backfilling and
compaction, and disinfection, complete all as
directed by the Engineer. Before commencement,
the contactor should adjust the alignment of pipes to
be connected in order to reduce the use of elbows.
Connection of the 12'' steel discharge pipe of PS-6,
15
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
No.
2.11.2
Description
Unit
to the adjacent 12'' new pipeline that connects the
existing 10'' trunk line to ST-16, ST-17, ST-18A &
18B storage tanks.
Connection of the 14'' steel discharge pipe of PS-7,
to the adjacent 14'' new pipeline that Tal El-Sultan
distribution network.
sum
Lump
sum
Qty
Unit
Price
(US$)
Total
(US$)
1
Total Carried to Summary(Bill No. 2)
BILL NO. 3
Electrical WORKS
Item
Description
Unit
Qty.
Unit
Price
(US$)
Total
(US$)
The items in general shall also include conduits,
connection boxes, controls, wires, connectors, clamps,
bolts, and connecting the cables to switchboards and
common electric network are included in the unit
price.
 Contractor shall submit shop drawings for all
electrical works to be approved by the Engineer
before executing the work.
 As-built drawings shall be submitted after
handing over the work.
 All the electrical works shall be executed
16
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
according
to
Standards,
specifications
and
supervisor
instructions.
Unit
Qty.
No.
1
Total
(US$)
drawings,
engineer
3.1
3.1.1
Lightings Fittings
Supply, install, connect and test fluorescent lighting
fixture 2x36w complete with lighting tubes 36W, chock,
condensers, starters, rigid PVC conduits, J. boxes,
fixing screws (Galv.) and wiring. (Type is GA'ASH No.
50540 or equivalent).
3.1.2
Ditto, as (1) but with emergency back up power built in,
for duration 3 hours.
No.
1
3.1.3
Ditto, as (1) but water and dust proof IP65. (Type is
GA'ASH No. 52940 or equivalent).
No.
16
3.1.4
Ditto, as (3) but with emergency back up power built in,
for duration 3 hours.
No.
2
3.1.5
Supply, install, connect and test incandescent lighting
fixture with 75W lamp, wires, conduits, j. boxes and
fixing screws for ceiling mounted. (Type is GA'ASH
No. 552100 or equivalent).
No.
5
3.1.6
Supply, install, connect and test 6" Extractor fan with
movable louvers, 250cfm, complete with PVC conduits,
J. boxes, wiring, and all necessary accessories. (Type is
VENTA or equivalent).
No.
1
3.2
3.2.1
External Security lighting
Supply, install external security lighting fixture with
150w bulb, HPS, chock, ignitor, condenser, 1.5" hot
galvanized arm 2m,10A mcb, long 3X2.5sq. mm NYY
cable and terminal blocks cables, (Type is GA'ASH No.
576003 or equivalent).
No.
11
3.2.2
Supplying and erecting B200 concrete for pole base,
including digging and lattice 4x1.25" bolts to fix the
pole, the dimension of the concrete base is
80X80X100cm.
No.
10
3.2.3
Supplying and erecting 8m long octal lighting pole, with
1cm thick base, the pole is made of 4-5mm thick hot
galvanized sheet steel, including 20x12cm insulating
fiberglass.
No.
10
3.2.4
Supply, laying and termination of XLPE cable, (5X6)
mm2 for external lighting including 3" pipe (flexible),
100cm digging and backfilling, and a warning tape the
work.
L.M.
140
3.3
Unit
Price
(US$)
Switches and Sockets
17
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
Unit
Qty.
3.3.1
Supply, install connect and test single pole one way
switch, 220v, 13A, complete with PVC conduits, J.
boxes, wiring, cover and all necessary accessories.
(Type is GEWISS or equivalent).
No.
1
3.3.2
Ditto, but water proof.
No.
2
3.3.3
Ditto, but one way, two pole switch.(Type is GEWISS
or equivalent).
No.
3
3.3.4
Ditto, but water proof.
No.
2
3.3.5
Supply, install connect and, testing single socket outlet
16A, 220v, 2p+E for flush or surface mounting,
complete with PVC conduits, J. boxes, wiring, and all
necessary accessories. (Type is GEWISS or equivalent).
No.
10
3.3.6
Ditto, but water proof type.
No.
8
3.3.7
Supply, install connect and, testing switched socket
outlet 230V, 20A, with pilot lamp, flush type for water
heater.(Type is GEWISS or equivalent).
No.
1
3.3.8
Supply, install connect and, testing three phase socket
outlet 3X16A, 380v, 3p+N+E, IP65 for flush or surface
mounting, complete with PVC conduits, J. boxes,
wiring, and all necessary accessories. (Type is GEWISS
or equivalent).
No.
2
3.3.9
Supplying and erecting telephone socket outlet, flush
type, including 6 wire telephone cables.
No.
1
3.4
Grounding system
Supply, install and commission complete grounding
system including all required galvanized 35x3 mm steel
sheet, cables, earthing pits according to drawings,
specification and engineers instructions.
L.S.
1
No.
1
No.
7
3.5
3.5.1
3.5.2
Fire Alarm System
Supply, install and commissioning fire alarm system as
per drawings including fire resist PVC pipes, pull boxes
special wires including :
Fire alarm control panel 4 zones complete with batteries
and all necessary accessories.(Type is TELEFIRE or
equivalent).
Lionization smoke detector, the detectors shall be twinchamber with latching electronic circuitry, two wire
connection.(Type is TELEFIRE or equivalent).
18
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
Unit
Qty.
3.5.3
Ditto, but heat detector.
No.
1
3.5.4
Supply, install break glass cal point as per drawings the
unit shall be standard type for interior use with key
operated test facility, with plastic coated glass.
No.
4
3.5.5
Supply, install 95 db electronic horn ultra sound for
indoor and outdoor used. (Type is TELEFIRE or
equivalent).
No.
2
3.6
Main Distribution Board (MDB)
Supply, install and commission main distribution panel
board (MDB) as specified and as shown on drawings,
factory assembled wired and tested in accordance with
international standards, including 2mm Galv. steel
frame with anti static paint including busbars, neutral
bus bar and earthing terminal and all necessary civil
works for foundations , cable trenches and handing over
clean, tested and in operating conditions. (Type is
MOELLER or equivalent).
Set
1
3.6.1
Over-load, current limiting switch, with over load and
short circuit releases, adjustable 4-6A. (Type is
MOELLER PKZM0-6 or equivalent).
No.
4
3.6.2
Signal lamps R.S.T with 25 Resistance 220V.
Set
3
3.6.3
3.6.4
3.6.5
Current transformer 3x (630/5A).
Kwh meter 3 phases 3x5A.
KVAR meter, 3 phases 3x5A.
Set
No.
No.
7
1
1
3.6.6
Kwh meter, 1 phase 1x5A.
No.
3
3.6.7
Ammeter 0-1000A.
No.
9
3.6.8
Frequency meter (47-53Hz).
No.
3
3.6.9
Voltmeter 0-500V with 7 positions selector switch.
Set
3
3.6.10
Molded case circuit breaker with (over load protection)
MCCB 4x630FA/4X630TA. (Type is MOELLER
NZMH4-4-AE630 or equivalent).
No.
2
3.6.11
MCCB 3x400FA/3X250TA. (Type is MOELLER
NZMN3-AE400 or equivalent).
No.
1
3.6.12
MCCB3x160FA/3X160TA. (Type
NZMN2-A160 or equivalent).
MOELLER
No.
1
3.6.13
MCCB 3x100FA/3X100TA. (Type is MOELLER
NZMN1-A100 or equivalent).
No.
2
is
19
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
Unit
Qty.
3.6.14
MCCB 3x40FA/3X40TA. (Type
NZMN1-A40 or equivalent).
is
MOELLER
No.
3
3.6.15
MCCB 3x25FA/3X25TA. (Type
NZMN1-A25 or equivalent).
is
MOELLER
No.
1
3.6.16
Ditto but MCB 3X40A. (Type is MOELLER FAZC40/3 or equivalent).
No.
2
3.6.17
Ditto but MCB 3X32A. (Type is MOELLER FAZC32/3 or equivalent).
No.
2
3.6.18
Ditto but MCB 3X25A. (Type is MOELLER FAZC25/3 or equivalent).
Ditto but MCB 3X20A. (Type is MOELLER FAZC20/3 or equivalent).
No.
1
No.
2
3.6.20
Panel ventilation system including, four extract fans,
thermistor relay, temperature sensors (30-70 OC), 16A
contactor, mcb 1X10A.
Set
1
3.6.21
3 poles, 380V, 40kVAr, with 2 auxiliary contacts,220V
coil, AC3 category (Type is MOELLER DIL2MKV-00
or equivalent).
No.
2
3.6.22
3 poles, 380V, 20kVAr, with 2 auxiliary contacts, 220V
coil, AC3 category (Type is MOELLER DIL1MK-10 or
equivalent).
No.
3
3.6.23
No.
1
3.6.24
3 poles, 380V, 10kVAr, with 2 auxiliary contacts, 220V
coil, AC3 category (Type is MOELLER DIL00MK-02
or equivalent).
Three phase static capacitor bank 30Kvar.
No.
2
3.6.25
Three phase static capacitor bank 15Kvar.
No.
3
3.6.26
Three phase static capacitor bank 10Kvar.
No.
1
3.6.27
Toggle switch 10A, 230VAC (1, 0, 2) with indication
lamp.
Set
6
3.6.28
Supply and install surge protection at the incoming
feeder 3- phase including connection to the ground. The
system shall protect the switch panel against the
lightning shocks. (Type Furse or equivalent).
No.
1
3.6.29
LTL fuse 3x160A/100A.
No.
1
3.6.30
Three-phase mains/generator automatic change over
switch, motorized type, made of two 630A 400V
4poles switches with electrical and mechanical interlock
K.Moller or equivalent ,the work includes
automatic changeover unit (ACU) ADMAR type or
No.
1
3.6.19
20
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
Unit
Qty.
3.6.31
Ditto but manual change over switch 4x630A K.Moller
or equivalent.
No.
1
3.7
3.7.1
Motor Control Center (MCC)
Supply, install and commission MCC panel board as
specified and as shown on drawings, factory assembled
wired and tested in accordance with international
standards, including 2mm Galv. steel frame with anti
static paint including burbars, neutral bus bar and
earthing terminal and all necessary civil works for
foundations, cable trenches and handing over clean,
tested and in operating conditions. (Type is MOELLER
or equivalent).
Set
1
3.7.2
Current transformer 3x (400/5A).
Set
4
3.7.3
Ammeter 0-400A.
No.
2
3.7.4
Ammeter 0-100A.
No.
3
3.7.5
Electrical digital hour counter 3.5 digits, supply voltage
24V dc and/or 230V ac, panel mounting.
No.
5
3.7.6
3.7.7
3.7.8
Toggle switch 10A, 24V dc and/or 230V ac, (1,0,2).
Emergency push button switch.
MCCB3x400FA/3X400TA. (Type is MOELLER
NZMN3-AE400 or equivalent).
No.
No.
No.
5
5
2
3.7.9
MCCB3x400FA/3X400TA. (Type
NZMN1-A100 or equivalent).
MOELLER
No.
3
3.7.10
Three poles, 380V, 132KW, with 2 auxiliary contacts,
220V coil, AC3 category (By-pass). (Type is
MOELLER DILM 250/22 or equivalent).
No.
2
3.7.11
Three poles,380V, 43KW, with 2 auxiliary
contacts,220V coil, AC3 category (By-pass). (Type is
MOELLER DIL2M /22 or equivalent).
No.
3
3.7.12
Three-phase solid state reduced voltage starter, 310A,
for pump, fully featured, digital microprocessor based,
with its control, as per specifications and engineer's
instructions (Type is Solcon. RVS-D-310).
Three-phase solid state reduced voltage starter, 105A,
for pump, fully featured, digital microprocessor based,
with its control, as per specifications and engineer's
instructions (Type is Solcon. RVS-D-105).
No.
2
No.
3
Motor protective circuit breaker 3X10A. (Type is
MOELLER PKZM0-10 or equivalent).
No.
5
Unit
Price
(US$)
Total
(US$)
equivalent.
3.7.13
3.7.14
is
21
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
Unit
Qty.
3.7.15
MCB 2X20A. (Type is MOELLER FAZ-C 20/2 or
equivalent).
Panel ventilation system including, three extract fans,
thermistor relay, temperature sensors (30-70 OC), 16A
contactor, mcb 1X10A.
No.
1
Set
1
Set
1
3.7.16
3.8
3.8.1
PLC Cabinet
Supply, install and commission PLC panel board as
specified and as shown on drawings, factory assembled
wired and tested in accordance with international
standards, including 2mm Galv. steel frame with anti
static paint including burbars, , terminal blocks and all
necessary civil works for foundations , cable trenches
and handing over clean, tested and in operating
conditions. (Type is MOELLER or equivalent).
3.8.2
Programmable logic controller PLC, 128 I/O points,
with hand programmer, computer software and
interface, with sufficient updated RAM, and memory
packs, logic memory. The unit shall be as per drawings,
specifications, and engineer's instructions and the new
version manufactured at the time of tendering. The work
includes programming the PLC to operate the pumping
station with 4 pumps(3-duty/1-standby), as specified
by the engineer and according to the sequence to
operate the pumps equal times, including all necessary
extra relays and/or switches, cables and conductors,
according to specifications and engineer's instructions.
Phase failure, loss of phase, under voltage, and phase
sequence relay, with the necessary control.
L.S.
1
No.
1
3.8.4
Time delay electronic relay, with one N.O. and one
N.C. 10A output contacts, and 2 sensor input points,
supply voltage 24V dc and/or 230V ac, according to
specifications and engineer's instructions.
No.
7
3.8.5
Control relay, with N.O. and N.C. 10A output contacts,
supply voltage 24V dc and/or 230V ac, according to
specifications and engineer's instructions.
No.
25
3.8.6
Push button switch with N.C. and N.O. contacts 10A,
24V and/or 230V AC.
set
5
3.8.7
Supplying and erecting uninterruptible power supply
U.P.S. 1000W rating, 50-60 minutes full load
discharging time, 230V sine wave output, with all
protection and indicators, as per specifications, and
engineer's instructions.
No.
1
3.8.8
Isolating transformer 380/220V of 2000VA capacity.
No.
1
3.8.9
Ditto but 220/24V of 700VA capacity.
No.
1
3.8.3
22
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
Unit
Qty.
3.8.10
Manual change over switch 2X16A.
No.
1
3.8.11
Indication lamps with 25 Resistance 220V.
set
35
3.8.12
Over-load, current limiting switch, with over load and
short circuit releases, adjustable 4-6A. (Type is
MOELLER PKZM0-6 or equivalent).
set
1
3.8.13
MCB 2X20A. (Type is MOELLER FAZ-C 20/2 or
equivalent).
No.
1
3.8.14
MCB 2X16A. (Type is MOELLER FAZ-C 16/2 or
equivalent).
No.
1
3.8.15
MCB 2X10A. (Type is MOELLER FAZ-C 10/2 or
equivalent).
No.
1
3.8.16
MCB 2X6A. (Type is MOELLER FAZ-C 6/2 or
equivalent).
No.
1
3.8.17
Ditto but MCB 1X6A. (Type is MOELLER FAZ-C 6/1
or equivalent).
No.
4
3.8.18
Humidity sensitive relay, with N.O. and N.C. 10A
output contacts, supply voltage 24V dc and/or
230V ac, according to specifications and engineer's
instructions.
No.
5
3.8.19
Temperature control relay, with N.O. and N.C. 10A
output contacts, supply voltage 24V dc and/or
230V ac, according to specifications and engineer's
instructions.
(Type is MOELLER EMT6 or equivalent )
No.
5
3.9
3.9.1
Sub-Distribution Boards (DB-P)
Supply, install sub-distribution board consists of
lockable board frames as per specifications including
2m Galv. steel sheets with anti-static paint, bus bars for
incoming cables, neutral and earthing terminal with all
necessary accessories and material to hand over clean
and tested ad in operating conditions. (Type is
MOELLER or equivalent).
No.
1
3.9.2
Miniature Circuit Breaker MCB 3X50A. (Type is
MOELLER FAZ-B 50/3 or equivalent).
No.
1
3.9.3
Miniature Circuit Breaker MCB 3X25A. (Type is
MOELLER FAZ-B 25/3 or equivalent).
No.
6
3.9.4
Ditto but MCB 1X16A. (Type is MOELLER FAZ-B
16/1 or equivalent).
No.
3
3.9.5
Ditto but MCB 1X10A. (Type is MOELLER FAZ-B
No.
4
23
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
Unit
Qty.
3.9.6
Ditto but residual current circuit breaker 4X40/0.03A.
(Type is MOELLER FI-40/4/003-A or equivalent).
No.
1
3.9.7
Ditto but residual current circuit breaker 4X25/0.03A.
(Type is MOELLER FI-25/4/003-A or equivalent).
Sub-Distribution Boards (DB-S)
Supply, install sub-distribution board consists of
lockable board frames as per specifications including
2m Galv. steel sheets with anti-static paint, bus bars for
incoming cables, neutral and earthing terminal with all
necessary accessories and material to hand over clean
and tested ad in operating conditions. (Type is
MOELLER or equivalent).
No.
1
No.
1
Miniature Circuit Breaker MCB 3X50A. (Type is
MOELLER FAZ-B 50/3 or equivalent).
Miniature Circuit Breaker MCB 3X40A. (Type is
MOELLER FAZ-B 40/3 or equivalent).
No.
1
No.
1
3.10.4
Miniature Circuit Breaker MCB 3X16A. (Type is
MOELLER FAZ-B 16/3 or equivalent).
No.
1
3.10.5
Ditto but MCB 1X16A. (Type is MOELLER FAZ-B
16/1 or equivalent).
No.
6
3.10.6
Ditto but MCB 1X10A. (Type is MOELLER FAZ-B
10/1 or equivalent).
No.
5
3.10.7
Ditto but residual current circuit breaker 4X40/0.03A.
(Type is MOELLER FI-40/4/003-A or equivalent).
No.
1
3.10.8
Ditto but residual current circuit breaker 4X25/0.03A.
(Type is MOELLER FI-25/4/003-A or equivalent).
No.
1
3.10.9
External lighting control unit including contractor(DIL
1AM ), selector switch 10A, photocell (KAJA type),
24 hours timer, 1X6A MCB.
Set
1
3.11
3.11.1
Sub-Distribution Boards (DB-P)
Supply, install sub-distribution board consists of
lockable board frames as per specifications including
2m Galv. steel sheets with anti-static paint, bus bars for
incoming cables, neutral and earthing terminal with all
necessary accessories and material to hand over clean
and tested ad in operating conditions. (Type is
MOELLER or equivalent).
No.
1
3.11.2
Miniature Circuit Breaker MCB 3X40A. (Type is
MOELLER FAZ-B 40/3 or equivalent).
No.
1
3.11.3
Miniature Circuit Breaker MCB 3X16A. (Type is
No.
2
Unit
Price
(US$)
Total
(US$)
10/1 or equivalent).
7.10
3.10.1
3.10.2
3.10.3
24
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
Unit
Qty.
3.11.4
MOELLER FAZ-B 16/3 or equivalent).
Ditto but MCB 1X16A. (Type is MOELLER FAZ-B
16/1 or equivalent).
No.
2
3.11.5
Ditto but MCB 1X10A. (Type is MOELLER FAZ-B
10/1 or equivalent).
No.
2
3.11.6
Ditto but residual current circuit breaker 4X25/0.03A.
(Type is MOELLER FI-25/4/003-A or equivalent).
Cables and conduits
Supply, laying under ground PVC piping system for the
under ground electrical network as per drawings. The
work includes manholes, excavation, laying pipes,
warning tapes , backfilling ,new junction manhole and
all required cable joints and cable extensions for the
existing building cables.
Supply, laying and termination of XLPE cable,
(3X240+120) mm2.
No.
1
L.S
1
L.M
230
3.12
3.12.1
3.12.2
3.12.3
Ditto, but NYY 1X185 mm2.
L.M
125
3.12.4
Ditto, but XLPE 3X25+16 mm2.
L.M
120
3.12.5
Ditto, but XLPE 5X10 mm2.
L.M
50
3.12.6
3.12.7
Ditto, but XLPE 5X6 mm2.
Ditto, but XLPE 5X4 mm2.
L.M
L.M
90
10
3.12.8
Ditto, but control cable 12X2.5 mm2.
L.M
100
3.12.9
Ditto, but control cable 4X2.5 mm2.
L.M
110
3.13
3.13.1
Miscellaneous
Supplying and erecting complete lightning protection
system including air terminal, copper conductors , pvc
chairs, inspection boxes, earthing pit according to
specifications,
drawings
and
engineer's
instructions.(Type is PuLSAR 45 or equivalent).
L.S.
1
3.13.2
Supplying and erecting micro-switches connected to
NVRs on the check valves.
No.
5
3.13.3
Supplying and erecting electrical bell with flashing
rotary lamp , 24V dc and or 220V ac, IP55 category, for
out side use (external).
No.
2
3.13.4
Supplying and erecting local isolated On/Off switch
3X400A rating lockable type for maintenance purpose
to be installed close to the wet well inside weather proof
enclosure (60X80X25cm). Type K. Moller or
equivalent.
No.
2
25
Unit
Price
(US$)
Total
(US$)
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
Unit
Qty.
3.13.5
Ditto but 3X100A.
No.
3
3.13.6
Supply and install pressure switch on the main header
connected to PLC panel, the switch shall be adjustable
(0-10 bars).
No.
3
3.13.7
Supplying and erecting electrical float switch inside the
sewage and the storm water wet wells, IP 65 category,
with N.O. and N.C. 10A contacts points, supply voltage
24V and/or 230V ac, according to specifications and
engineer's instructions.
No.
3
3.13.8
Supplying and erecting cables tray, MTK type or
equivalent, 50cm width, with all fittings and
accessories.
No.
15
3.13.9
Ditto but lader type cables tray 50cm width.
No.
25
3.13.10
Ditto but 30cm width.
No.
10
3.13.11
Ditto but 20cm width.
No.
10
3.13.12
Ditto but 10cm width.
No.
10
3.13.13
Supplying and erecting IP54 category connection boxes,
with the needed metal and/or PVC 2" pipes and
accessories for cables connections. The boxes shall
contain the control and power connection separately
outdoor use.
No.
2
L.S
1
L.S
1
3.14
Total
(US$)
Generator Set
Supplying and erecting electrical generator and connect
it to the storage fuel tank, the item shall include
automatic start and stop, exhaust system, fuel pump and
control, with automatic float, control, protection and
control panel, sensors for heat, speed, under voltage,
over voltage, oil pressure, phase sequence and phase
failure, measuring instruments, air duct, built in fuel
tank, alternator, diesel engine, exciter, automatic
charger, main
circuit breaker, sound attenuated
enclosure (original) as recommended by the
manufacturer. All fittings and fixing materials and
control needed are included in the price. The generator
shall be rated 400kVA standby rating. The price shall
include also the supply and install of the generator steel
shed, concrete pad and foundation, excavation for
foundation and all works associated as shown in the
Drawings and described in the Specifications and as
directed by the Engineer.
3.15
Unit
Price
(US$)
Transformer Substation
Supply, install and test sub-station with all equipments,
the work should be executed according to GEDCO
26
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
Item
Description
Unit
Qty.
Unit
Price
(US$)
Total
(US$)
applications. The contractor must take into
consideration all the coast required by GEDCO and
other authorities for implementing this item. He must
know that GEDCO will implement this work as a subcontractor under his responsibility applying all
conditions on his regarding. The work includes all
required steel arms and prackets,22 KV Pin & Tension
Type Insulator, Wires & Clamps, Steel Bolts, UGC
Components, 24 KV Switch gear SF6 (CTC), including
3 (22 KV) potsalan Fuses 60 A., Indoor Distribution
Transformer 400 KVA and all other Accessories
Total Carried to Summary (Bill No. 3)
27
‫ختم وتوقيع املقاول‬
Construction of Water Booster Pumping Stations at Tal El-Sultan Water Storage Tank in Rafah
CONSTRUCTION OF TAL EL-SULTAN BOOSTER STATIONS
Summary:
Item
Description
1.
Total of Bill # 1
2.
Total of Bill #2
3.
Total of Bill #3
Total (US$)
Total (US$)
Vat (0%)
Grand Total (US$)
Grand Total (in letters):------------------------------------------------------------Contractor’s Name:-----------------------------------------------------------------Signature and Stamp:---------------------------------------------------------------Date:-------------------------------------------------------------------------------------