Introduction: • Project Cost Management is the knowledge use for managing costs. Processes in this area help to ensure a project is completed within the approved budget • It includes the processes involving in estimating, budgeting and controlling costs. • These processes interact with each other and with processes in the other knowledge areas as well Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 2 Estimate Costs Determine Budget Control Costs Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 3 Definitions: 1. Estimate Costs-The process of developing an approximation of the monetary resources needed to complete project activates. 2. Determining Budget-The process of aggregating the estimated costs of individual activates or work packages to establish an authorized cost baseline. 3. Control Costs: The process on monitoring the status of the project to update the project budget and managing changes to the cost baseline. Each process has specified: 1) Inputs, 2) Tools / Techniques 3) Outputs Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 4 Estimate Cost: 7.1 Estimate Cost Inputs 7.2 Determine Budget 7.3 Control Cost Tools & Techniques Out puts •Scope baseline. •Expert judgment. •Activity cost estimates. •Project schedule. •Analogous estimating. •Basis of estimates. •Human Resource plan. •Parametric estimating. •Risk register. •Bottom-Up estimating. •Project document updates. •Enterprise environmental factors. •Three –point estimates. •Organizational process assets. •Cost of quality. •Reserve analysis. •Project management estimating software. •Vendor bid analysis. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 5 Estimate Cost: Inputs Scope baseline The scope baseline is the approved project scope statement, WBS, and WBS dictionary. These collectively provide the deliverables, statements of work, constraints, and assumptions that are necessary for accurate cost estimating. Project schedule The project schedule specifies the planned start and finish date for each scheduled activity. Human resource plan The human resource plan contains details regarding the how the project will be staffed and the labor rates for estimating costs Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 6 Estimate Cost: Inputs Enterprise environmental factors Factors beyond the project’s boundaries impact costs, including marketplace conditions and the pool of available suppliers. Organizational process assets Lessons learned, project files, and historical information from the organization are crucial for good estimates. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 7 Estimate Cost: Tools & Techniques Expert judgment, relies on historical experience to assess and adjust estimates. Analogous estimating uses the costs from similar projects or activities as the basis for the current project. Parametric estimating uses mathematical formulas to derive estimates. Bottom-up estimating decomposes activities to the lowest level possible for cost estimating purposes, and then aggregates component costs back up to a summary activity level Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 8 Estimate Cost: Tools & Techniques Three-point estimates (PERT analysis), help to remove the uncertainty from estimates by providing a weighted average using the pessimistic, optimistic, and most-likely values. The Formula: (Optimistic Estimate + (4 x Most-Likely Estimate ) + Pessimistic Estimate) 6 Example: Optimistic $75 Most Likely $100 Pessimistic $150 Three-point estimate = ($75 + (4 x $100) + $150) / 6 Three-point estimate = $104.17 Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 9 Estimate Cost: Outputs Activity cost estimates , are a complete accounting of all component costs, such as labor, resources, services, fees, licenses, of a scheduled activity. Basis of estimates, is the supporting detail to the activity cost estimates including the references for cost estimate, considered assumptions, constraints, range of accuracy, and the confidence level in the estimate. Project document updates, the process of estimating costs can result in updates to several project documents, including the WBS, and the WBS dictionary. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 10 Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 11 Determine Budget: 7.1 Estimate Cost Inputs 7.2 Determine Budget Tools & Techniques •Activity cost estimates. •Cost aggregation. •Basis of estimates. •Reserve analysis. •Scope baseline. •Expert judgment. •Project schedule. •Historical relationships. •Resource calendars. •Funding limit reconciliation. •Contracts. 7.3 Control Cost Out puts •Cost performance baseline. •Project funding requirements. •Project document updates. •Organizational process assets. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 12 Determine Budget: Tools & Techniques Cost aggregation, Individual costs are aggregated in many different ways for budgeting purposes, including at the work package, deliverable, summary activity, or other classification levels. Reserve analysis , are time or cost buffers in the project schedule or budget that help the project respond to uncertainties Expert judgment, is based upon the experience and knowledge of subject matter experts. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 13 Determine Budget: Tools & Techniques Historical relationships, refers to the characteristics of the current and past projects that can be used to develop models that aid in budgeting. Funding limit reconciliation, matches the project's planned need for funding with the organization's ability to provide that funding Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 14 Determine Budget: Outputs Cost performance baseline is a time-phased budget that is used for project cost management, monitoring, and reporting. It is commonly shown as an S-curve graph. Project funding requirements, refers to the entire estimated cost of the budget, including any contingency or management reserves. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 15 Determine Budget: Cost performance baseline Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 16 Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 17 Control Costs: 7.1 Estimate Cost Inputs 7.2 Determine Budget 7.3 Control Cost Tools & Techniques Out puts •Project management plan. •Earned value management. •Work performance measurement. •Project funding requirements. •Forecasting. •Budget forecasts. •To – complete performance index. •Organizational process assets update change requests. •Work performance information. •Organizational process assets. •Performance reviews. •Variance analysis. •Project management software. •Project management plan updates project document updates. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 18 Control Costs: Inputs Project management plan , includes the cost management plan which describes how project costs will be managed, reported on, and controlled. The cost performance baseline is also part of the project management plan, and it’s used to compare actual costs to planned costs. Project funding requirements, refers to the entire estimated cost of the budget, including any contingency or management reserves. It’s used to compare actual costs to planned costs. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 19 Control Costs: Inputs Work performance information , is any data that related to the work which produces the project deliverables. Examples are schedule and progress status information, budget and cost status, quality status, estimates to complete, resource utilization information, and lessons learned. Organizational process assets , are the source of existing policies, processes, organizational data and knowledge. The organization may have cost-related policies, procedures, and reporting methods that must be followed. . Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 20 Control Costs: Tools & Techniques Earned value management, measures the performance of the project. It also provides a way to forecast future performance based on what's happened so far with the project. Forecasting, involves predicting future performance based on historical work performance information and expert judgment. To-complete performance index (TCPI), is a formula that provides the level of performance that must be achieved to meet either the budget at completion (BAC) or the estimate at completion (EAC). Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 21 Control Costs: Tools & Techniques Performance reviews, are assessments that analyze the project’s historical cost performance. It includes earned value measurements, variance analysis, and trend analysis. Variance analysis, compares expected cost performance to what is actually occurring, and determines the causes of any variance uncovered. Project management software, automated tools can help in monitoring, tracking, and reporting on earned value measurements. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 22 Control Costs: Outputs Work performance measurements includes work performance information that specifically provides mathematical measurements of performance that is communicated to stakeholders. It may also report on earned value values for WBS components or control accounts within the WBS. Budget forecasts on the project’s expected completion cost and variances is documented and provided to stakeholders throughout the project. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 23 Control Costs: Outputs Organizational process assets updates for the lessons learned, corrective actions taken and the reasons, and the causes of financial variances. Change requests to the cost baseline as required Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 24 Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 25 Control Costs Formulas: Acronym Name Formula AC Actual Cost AC = actual cost of the project up to the measurement period BAC Budget at Completion BAC = total budgeted cost of the project EV Earned Value EV = Actual % complete x BAC PV Planned Value PV = Planned % complete x BAC CV Cost Variance CV = EV - AC Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 26 Control Costs Formulas: Acronym Name Formula SV Schedule Variance SV = EV - PV CPI Cost Performance Index CPI = EV / AC SPI Schedule Performance Index SPI = EV / PV EAC Estimate at Completion EAC = BAC / CPI ETC Estimate to Complete ETC = EAC - AC VAR Variance at Completion VAR = BAC - EAC Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 27 Control Costs Formulas: Example: Planned work complete = 80% Actual work complete = 75% (BAC) = 1,000,000 4-month project M1 M2 M3 M4 •4-month project: Total budget $1,000,000 = Budget at completion (BAC) •Project cost at end of month three: $950,000 = Actual cost (AC) •Estimated work complete at end of month three: 80% •Actual work complete at end month three: 75% Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 28 Control Costs Formulas: Planned value PV = Planned % Complete x BAC PV = 80% x $1,000,000 = $800,000 Earned value EV = Actual % Complete x BAC EV = 75% x $1000,000 = $750,500 Planned Value (PV) is how much work was expected to be completed Earned Value (EV) is how much work has actually been completed Cost variance CV = EV – AC CV = $750,000 - $950,000 = -$200,000 Cost Variance (CV) is how the cost of the project is comparing to the value of work completed Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 29 Control Costs Formulas: Cost performance index CPI = EV / AC CPI = $750,500 / $950,000 = 0.79 Cost Performance Index (CPI) shows how much work is being completed for every unit of cost spent (Output/Input) For every $1 input (cost) , we are earning only $0.8 in work output Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 30 Control Costs Formulas: Schedule performance index SPI = EV / PV SPI = $750,500 / $800,000 = 0.94 Schedule Performance Index (SPI) shows how close the actual completed work compared to the schedule For every hour we planned , we are completing only 0.94 hours. Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 31 Control Costs Formulas: Estimate at completion EAC = BAC / CPI EAC = $1000,000 / 0.94 = $1,063,829 Based on current performance, the project will be completed at cost = $1,063,829. Estimate to complete ETC = EAC - AC ETC = $1,063,829 - 950,000 = $113,829 Estimate At Completion (EAC) forecasts the total cost of the project based on current project performance Estimate To Complete (ETC) forecasts how much more money will be required to finish the project Based on current performance, the project requires $113,829 to get it finished Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 32 Control Costs Formulas: Variance at completion VAR = BAC – EAC VAR = $1,000,000 - $1,063,829 = -$63,829 Based on current performance, the project will run about $63,829 over budget Variance At Completion (VAR) predicts difference between the budgeted and actual project cost at the end of the project Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 33 Thank You Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 34 Q&A: WBS Element P Q R S PV $1,000 $2,000 $1,000 $2,000 EV $1,100 $1,800 $1,200 $1,900 AC $1,150 $2,100 $1,050 $1,800 1. Using the table above, the cost performance index (CPI) for WBS Element R is: a. 0.875 b. 1.14 c. 0.952 d. 0.833 1. b CPI = EV / AC CPI = 1200 / 1050 CPI = 1.14 Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 36 Q&A: WBS Element P Q R S PV $1,000 $2,000 $1,000 $2,000 EV $1,100 $1,800 $1,200 $1,900 AC $1,150 $2,100 $1,050 $1,800 2. Using the table above, which WBS element is over budget and behind schedule? (important) a. Element P b. Element Q c. Element R d. Element S 2. b CV = EV – AC = 1800 – 2100 = -300 (over budget) SV = EV – PV = 1800 – 2000 = -200 (behind schedule) Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 37 Q&A: WBS Element P Q R S PV $1,000 $2,000 $1,000 $2,000 EV $1,100 $1,800 $1,200 $1,900 AC $1,150 $2,100 $1,050 $1,800 3. Using the table above, which WBS element has a favorable cost variance of $150? a. Element P b. Element Q c. Element R d. Element S 3. c CV = EV – AC = 1200 – 1050 = 150 favorable variance Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 38 4. The work breakdown structure, the work packages, and the company’s accounting system are tied together through the: a. Chart of accounts b. Overhead rates c. Budgeting system d. Capital budgeting process 4. a Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 39 5. Management reserves are normally defined as a percentage of the total budget. As a project goes through its life cycle phases, the project manager wants the dollar value of the management reserve to ___________, whereas the customer wants the dollar value of the management reserve to ___________. a. Increase, increase b. Increase, decrease c. Decrease, increase d. Remain the same, be returned to the customer 5. d Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 40 6. Which of the following types of cost are not relevant to making project financial decisions: a. Sunk cost b. Opportunity cost c. Material cost d. Labor cost 6. a Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 41 7. Upon completion of 75% of the project, the original schedule and cost estimate that were submitted at the inception of the project are referred to as the: a. Baseline b. Budgeted costs c. Estimates upon completion costs d. Scheduled costs 7. a Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 42 8. Which of the following would increase the accuracy of estimating the project cost? a. Pricing out the work at higher levels in the work breakdown structure b. Using historical data from a non similar project c. Talking to people who have worked on similar projects d. Intuition 8. c Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 43 Direct Labor $10.50 6374 hours $68,329 $10.72 Planned price/unit Actual units/hour Actual cost Actual price/unit Direct Material $14.77 5433 units $83,994 $15.46 9. Using the table Above, the labor rate cost variance is: a. $66,927.00 b. $68,329.00 c. $386.00 d. ($0.22) 9. d Labor Rate Cost Variance = Planned Cost (BAC) – Actual Cost (AC) Labor Rate Cost Variance = 10.50 – 10.72 Labor Rate Cost Variance = -0.22 Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 44 10. What tool have project managers come to use to identify the costs associated with a project? a. A bill of materials b. A Gantt chart c. An arrow diagram network d. A work breakdown structure 10. d Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 45 11. Cost estimating: A. Involves developing an estimate of the costs of the resources needed to complete project activities. B. Includes identifying and considering various costing alternatives. C. Involves allocating the overall estimates to individual work items. (cost budgeting) D. A and C E. A and B 11. e Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 46 12) Which type of project cost estimate is the most accurate? A) B) C) D) Preliminary Definitive Order of magnitude Conceptual 12. B Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 47 13) )Cost budgeting can be best described by which of the following? A) The process of developing the future trends along with the assessment of probabilities, uncertainties, and inflation that could occur during the project B) The process of assembling and predicting costs of a project over its life cycle C) The process of establishing budgets, standards, and a monitoring system by which the investment cost of the project can be measured and managed D) The process of gathering, accumulating, analyzing, reporting, and managing the costs on an on-going basis 13. C Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 48 14) ) Cost controls can be best described by which of the following? A) The process of developing the future trends along with the assessment of probabilities, uncertainties, and inflation that could occur during the project B) The process of assembling and predicting costs of a project over its life cycle C) The process of assembling and predicting costs of a project over its life cycle D) The process of gathering, accumulating, analyzing, reporting, and managing the costs on an on-going basis. 14. D Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 49 15) ) Three Point Statistical Estimating Formula Group. Expected Value = A) (Optimistic + (4 X Most Likely) + Pessimistic ) x 6 B) (Optimistic + (4 X Most Likely) + Pessimistic ) divided by 6 C) (Optimistic + (4 X Most Likely) x Pessimistic ) divided by 6 D) Optimistic + (4 + Most Likely) + Pessimistic ) divided by 6 15. B Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 50 16) ) Which is not a technique used for cost estimation : A) Analogous Estimating B) Bottom-up Estimating C) C) Parametric Estimating D) Vendor Bid Analysis E) Resource Leveling 16. E Khalid & Riyad, KAU, EMBA, PMP Course 30 Apr 2010 51