Measuring project effectiveness of cost and schedule Blue Zuma Part 4 1. Take Blue Zuma results rom Part 2B. This is leveling outside of slack. Start date is 3/2/2015; end date is 4/18/2016 duration is 290 days total cost is $1,249,200 Baseline your project (Project – Baseline) 2. Answer the questions in Part 4. Go To: View - Tables - Costs q1: $1,249,200 q2: Detailed Product Design; $317,000 q3: you can do the same as for task usage but it is cumbersome go to Report - costs - cash flow q4: July 2015; cost is $157,260; followed by Aug at $153,620 Jan 2016; cost is $2800 (go to Task Usage - click on work - select costs - unselect work in another right click select timescale - set middle tier to half year - set bottom tier to months Monthly costs are at the top Part 5 enter data from part 5 change the actual durations not the dates (go to View - Tables - Tracking) enter Actual Duration numbers from text into the ACT. Duration column on the Gantt Chart, type in 0 for any remaining also, enter 100% if no remaining time exists go back to View - Tables - entry ( some may want to go to Schedule) Duration has gone from 290 days to 264 Finish date is now 3/11/2016 cost is $1,165,000 go to Tracking Gantt you can see where the project has changed. the red lines are the critical path. ( not all of the path is highlighted because the previous tasks are complete. Qb: you can see using the tracking gantt which have gone well. you can also use the EV charts to tell which has gone well (View-Tables-More Tables - EV) you will see mostly zeros, because the program thinks you want to know how the project is doing as of 3/30. need to change the date to 9/28 (completion of Test Prototype. (Project - Status Date - type in 9/28/15 you can now see which of the tasks have done well - all but Detailed Product Design and Test Prototype and Product Design Selection Manufacturing processes has a TCPI of 0.92 Go to EV Schedule Indicators compare PV vs EV should vs has completed