COMP 3513 Assignment #2 [Total mark is out of 45] 7. A project has been defined to contain the following list of activities along with their required times for completion. Activity No. 1 2 3 4 5 6 7 8 9 10 Activity Collect requirements Analyze processes Analyze data Design processes Design data Design screens Design reports Program Test and Document Install Time (weeks ) 3 2 2 6 3 2 4 5 7 2 Immediate Predecess ors 1 2 2 3 3,4 4,5 6,7 7 8,9 a. Draw a Network diagram for the activities. [Max mark: 10; 1 point for each node correctly placed in network] b. Calculate the earliest expected completion time. [Max mark: 5; either 5 or 0] 24 weeks. c. Show the critical path [Max mark: 5; 1 point for each correct node beyond node #1] d. What would happen if activity 6 were revised to take 6 weeks instead of 2 weeks? [Max mark: 5; either 5 or 0] The critical path would change to include activity 6 as well as activity 7. The overall duration of the project will remain 24 weeks. 8. Construct a Gantt chart for the project defined in Problem and Exercise 7. The following Gantt chart was created with Microsoft Project. The students may use project management software, a graphics package, or draw by hand to produce their chart. The Gantt chart for problem 8 is taken from Microsoft Project. [Max mark: 20; 2 points for each task planned correctly on the chart]