SOP CHECK SHEET: MAINTENANCE SCHEDULE AND CHECKS/TESTS OF TRANSMISSION LINES Description of Inspection and Maintenance Work 1. Visual inspection (A walk around visual inspection from ground level and keeping in view the safe limits of approach to live and moving parts to check apparent condition, abnormal noise, rust on body of the equipment and component parts, etc.) 2. Foot Patrolling Inspection (Mechanical Defects such as missing/loose braces, Condition of Jumper Terminal Pad, Missing Split Pins, and Other Problem Areas such as Cultivated and Jungle Growth, Effects of Polluted Areas/Deserts,) 3. Climbing Inspection (General Problems, Evaluation of Condition of Line). Dead Line or Live Line 4. Conductor Condition (Loose Strands, Broken Strands, Dislocated Spacers, Vibration Dampers, etc.) 5. Overhead Shield Wire/Earthing Conductor (Loose Strands, Broken Strands, Dead end/suspension clamps, OPGW Splicing Box Condition, etc.) 6. Structure Marking (Faded and Obsolete Signs: Numbering, Danger Plates, Phase Marking, etc.) 7. Insulator Testing (Insulator String) (Mandatory Before Live Specified Time Period D/W M3/6 Y1 Y5/10 Yes - Remarks/Criteria/Standard/Safety Precautions Wear PPE and carry basic line man tools, earth resistance test set, binocular, etc. Make entries of the observations in check sheets/note book. - Yes - - Should be OK and no defects (foot patrolling should be done twice a year on all lines) - - Yes - Should be OK and no defect (Climbing inspection should be done once a year on all towers) Should be OK, intact and secured Should be OK, intact and secured - Yes - - Should be OK intact as per design (Replace or repair as required) - Yes - - Should be OK and intact (Replace failed insulator) 1 Line Work) 8. Insulator Washing and Greasing (before Foggy Season Yes - - Should be OK and no defects (insulator washing should be done twice a year on all lines in polluted areas) Should be OK and no hotspot/s (thermovision survey should be done twice a year on all lines) Should be OK and no defect (Vibration studies should be done twice a year on all lines) 9. Thermovision Survey - - Yes - 10. Vibration Studies - - - Yes Yes - - - Should be OK and intact and secured Yes - - - Should be OK and intact and secured - Yes - - Should be OK and intact and secured - Yes - - - - Yes - Should be OK and intact and secured Should be OK and no damage - - Yes - Should be OK and no damage and no missing hardware Yes - - - - - - Yes - - - Yes Should be OK and intact, no damage and no missing hardware Should be OK and intact, no damage, and no missing hardware Should be OK and intact Yes - - - Should be OK and intact TOWER 11. Footings Soil: Eroded, Back filling, De-watering of saline/rainy area, etc. 12. Footings Concrete: Chipped, Cracked, Broken, etc. 13. Base Structure: Loose/Missing Braces and Missing Nut/Bolts, etc. 14. Counter Poise 15. Steel Braces/Joint Plates: Bent, Rusted, Broken, etc. 16. Tower Members: Twisted, Broken, Rusted, Pitted 17. Step Pins/Bolts: Loose, Missing, Rusted, etc. 18. Bolts: Loose, Missing, Rusted 19. Galvanizing/Paint: Peeled, Pitted, etc. 20. Danger Plates/ Phase Plates/Signs: Worn, Damaged, Missing, etc. 2 8. TRANSMISSION LINE TECHNICAL DIRECTIVE Basic Maintenance Program of Transmission Lines SCOPE This directive provides for the basic minimum requirements to keep lines in an acceptable and reliable condition. Maintenance is discussed under the following headings: 1) Foot Patrol 2) Climbing Inspection/Maintenance 3) Structure marking 4) Insulator Testing 5) Insulator Washing & Greasing 6) Thermovision Survey 7) Vibration Studies 8) Commissioning 9) Condition Survey 1) FOOT PATROL Foot Patrol should be done twice a year on all transmission lines. This should identify most mechanical defects and point out problem areas that require further attention. A report from the field on Form LMS- 1 & LMS-2 (copy attached) is required by TSG for evaluation. 2) CLIMBING INSPECTION/MAINTENANCE 2.1) This program is used to evaluate the condition of a line. A report from the field on Form LMS-3 & 4 is required by TSG for evaluation. It should identify general problems, if any, which would lead to a rehabilitation program if cost justified. 2.2) A ten year cycle is required for all transmission lines. 10% of each line will be inspected each year. If many serious defects are found on a line a more frequent cycle for those lines should be discussed with TSG (N5P0015). 2.3) Climbing maintenance should be scheduled as follows: Divide the line into several sections (each section may contain 10 towers) and then arrange to inspect 10% of each section every year. This will then sample the whole line every year. 2.4) Minor defects should be repaired during the inspection. Spare Material should 3 be available on the job. site for these repairs. 2.5) Climbing maintenance can be performed deadline or live line depending on circuit availability. 3) STRUCTURE MARKING Faded and obsolete marking signs shall be replaced / repainted as required. 4) INSULATOR TESTING 4.1) It is required to test insulators on a string prior to performing live line work on or near an insulator string.*(N5P008 & N5P0013) 4.2) Testing insulators on 10 to 20% of a line will point out manufacturer defects as well as electrical in service defects. This program should be considered if a variety of insulator failures occur on a line. 5) INSULATOR WASHING/GREASING In locations where there is a buildup of atmospheric pollutants, insulators shall be washed or greased at a frequency such that flashovers are prevented. The frequency will be determined by experience and/or testing of samples *(Old No. TSG/TL-008) 6) THERMOVISION SURVEY 6.1) T his program identifies potential connection failures such as hot sleeves, pads and bolted connections which may burn-down the conductors. 6.2) Thermovision can be done from the air or the ground. For transmission lines a helicopter is highly desirable. At terminal towers or in built up areas a truck may he required. 6.3) Normally, the thermovision is done at the time when there is maximum load on line and each line is completed on a yearly cycle. (Thermovision check Form LMS-6) 7) VIBRATION STUDIES 7.1) Vibration studies on transmission lines should be done using the following order of preference. a) Lines having broken strands at suspension clamps. 4 b) Lines with no dampers. c) Lines that have wire dampers. d) Lines that have one damper per span e) Lines that have two dampers per span. 7.2) GS0 should identify the lines that should be studied and set up a program in consultation with TSG. 8) COMMISSIONING 8.1) Commissioning of lines should start when construction forces begins to erect structures on new lines. On rehabilitation work, start the commissioning when the field work begins. 8.2) Commissioning is required to insure that the line is constructed to specifications and to acceptable standards. 8.3) For lines 100km in length one man can usually do most of the work except for tower bolt checking and verification. 8.4) Sag checks must be made separately from GSC, at the time of sagging the conductors. 8.5) Check 20% of the towers and all dead-end towers for proper bolt torque. 20% of tower bolts on these towers should be verified for tightness, using a torque wrench. 8.6) Suspension clamp, dampers and dead-end conductor hardware are to be checked on the towers identified for commissioning. 9) CONDITION SURVEY 9.1) Condition survey is done on as and when as required basis. 9.2) Normally a survey is required to verify conductor to ground clearances as well, as for allowable heights of proposed under builds such as distribution facilities. This may also be used to determine maximum loading due to sags on the transmission line. 5 9. REFERENCE DATA FOR COMPARISON WITH THE TEST RESULTS Reference data and previous record is one of the important pre-requisite for an effective operation and maintenance program. For evaluation of different test results and to take decisions on the bases of these test results one must need some reference values and the permissible limits. Such reference data may be the factory test results or commissioning test results or the accepted test results of similar make/type/model equipment or the recommendations of certain reputed standards/specification. In this section, the most commonly applicable data has been compiled as a ready reference for the user of this SOP. This data has been collected from all the possible sources, however supply of new or more data along with feedback comments will be welcomed. 6 Table-9a: CHARACTERISTICS OF UNUSED UNINHIBITED MINERAL INSULATING OIL: IEC 296 (Old Specifications) CHARACTERISTICS OF UNUSED UNINHIBITED MINERAL INSULATING OIL: IEC 296 (Old Specifications) Sr. Property Permissible Values for Measured No. Characteristics Class-I Class-II Class-III 1 Appearance Clear, free Clear, free Clear, free from sediments from sediments from sediments and suspended and suspended and suspended matter matter matter 3 2 Density kg/dm at 20 ≤0.895 ≤0.895 ≤0.895 °C (old Specific Gravity) 3 Interfacial ≥40 ≥40 ≥40 Tension/Surface Tension at 25 °C (mN/m) or (N/m x 10-3) 4a Kinematic Viscosity ≤ 16.5 ≤ 11 ≤ 3.5 2 mm /s at 40 °C (Centistokes) 4b Kinematic Viscosity ≤ 40 ≤ 25 ≤6 2 mm /s at 20 °C (Centistokes) 4c Kinematic Viscosity ≤ 800 2 mm /s at -15 °C (Centistokes) 4d Kinematic Viscosity ≤ 1800 2 mm /s at -30 °C (Centistokes) 4e Kinematic Viscosity ≤ 150 2 mm /s at -40 °C (Centistokes) 5 Pour Point °C ≤ -30 ≤ -45 ≤ -60 6 Flash Point °C ≥ 140 ≥ 130 ≥ 95 7 Neutralization Value/ ≤ 0.03 ≤ 0.03 ≤ 0.03 Acidity (mg KOH/g) 7 8 9 3 11 12 13 14 Water Content mg/kg Max. 30ppm (ppm) (mg/kg) for bulk supply or 40ppm (mg/kg) for delivery in drums and IBC Break Down DES(kV ≥ 30 as at 2.5 mm gap) delivered and ≥ 50 after treatment Tan δ / Dielectric ≤0.005 Dissipation FactorDDF (at 40 to 60 Hz & 90 °C) Oxidation Stability ≤0.40 Neutralization * see note Value(mg KOH/g) Oxidation Stability ≤0.10 Sludge % by mass * see note Corrosive Sulfur Non corrosive Anti-oxidant Not detectable Additives Max. 30ppm (mg/kg) for bulk supply or 40ppm (mg/kg) for delivery in drums and IBC ≥ 30 as delivered and ≥ 50 after treatment ≤0.005 Max. 30ppm (mg/kg) for bulk supply or 40ppm (mg/kg) for delivery in drums and IBC ≥ 30 as delivered and ≥ 50 after treatment ≤0.005 ≤0.40 * see note ≤0.40 * see note ≤0.10 * see note Non corrosive Not detectable ≤0.10 * see note Non corrosive Not detectable * Note. The determinations on the oxidized oil are limited to the neutralization value and to the sludge however, in certain countries it is usual to determine also the DDF. In this case the maximum value of DDF will be established by agreement between purchaser and supplier. 8 Table-9b: CHARACTERISTICS OF UNUSED INSULATING OIL: IEC 296 (Old Specifications) INHIBITED MINERAL CHARACTERISTICS OF UNUSED INHIBITED MINERAL INSULATING OIL: IEC 296 (Old Specifications) Sr. Property Permissible Limiting Values for Measured No. Characteristics Class-IA Class-IIA Class-IIIA 1 Appearance Clear, free Clear, free from Clear, free from sediments sediments and from sediments and suspended suspended and suspended matter matter matter 3 2 Density kg/dm at ≤0.895 ≤0.895 ≤0.895 20 °C (old Specific Gravity) 3 Interfacial ≥40 ≥40 ≥40 Tension/Surface Tension at 25 °C (mN/m) or (N/m x 10-3) 4a Kinematic Viscosity ≤ 16.5 ≤ 11 ≤ 3.5 2 mm /s at 40 °C (Centistokes) 4b Kinematic Viscosity ≤ 40 ≤ 25 ≤6 2 mm /s at 20 °C (Centistokes) 4c Kinematic Viscosity ≤ 800 2 mm /s at -15 °C (Centistokes) 4d Kinematic Viscosity ≤ 1800 2 mm /s at -30 °C (Centistokes) 4e Kinematic Viscosity ≤ 150 2 mm /s at -40 °C (Centistokes) 5 Pour Point °C ≤ -30 ≤ -45 ≤ -60 6 Flash Point °C ≥ 140 ≥ 130 ≥ 95 9 7 8 9 10 11 12 13 Neutralization ≤ 0.03 Value/ Acidity (mg KOH/g) Water Content Max. 30ppm mg/kg (ppm) (mg/kg) for bulk supply or 40ppm (mg/kg) for delivery in drums and IBC Break Down ≥ 30 as DES(kV at 2.5 mm delivered and ≥ gap) 50 after treatment Tan δ / Dielectric ≤0.005 Dissipation FactorDDF (at 40 to 60 Hz & 90 °C) Oxidation Stability * see note Corrosive Sulfur Non corrosive Anti-oxidant As agreed Additives: Contents between at least 0.15% by purchaser and mass, but not more supplier than 0.40% by mass of (DBPC: 2.6-ditert-butylparacresole) or (DBP: 2.6-di-tertbutyl-phenol) ≤ 0.03 ≤ 0.03 Max. 30ppm (mg/kg) for bulk supply or 40ppm (mg/kg) for delivery in drums and IBC ≥ 30 as delivered and ≥ 50 after treatment ≤0.005 Max. 30ppm (mg/kg) for bulk supply or 40ppm (mg/kg) for delivery in drums and IBC ≥ 30 as delivered and ≥ 50 after treatment ≤0.005 * see note Non corrosive As agreed between purchaser and supplier * see note Non corrosive As agreed between purchaser and supplier * Note. In the case of inhibited oils only the induction period is determined however in certain countries it is usual to determine also the DDF. In this case the maximum value of DDF will be established by agreement between purchaser and supplier. No limit for oxidation stability is specified. For guidance only. Oils known to give satisfactory performance in transformers in service typically have induction period in excess of 120 hours. 10 Table-9c: CHARACTERISTICS OF UNUSED MINERAL INSULATING OILS FILLED IN NEW TRANSFORMERS: IEC 60422 CHARACTERISTICS OF UNUSED MINERAL INSULATING OILS FILLED IN NEW TRANSFORMERS: IEC 60422 Sr. Property Highest Voltage for Equipment No. <72.5Kv 170kV >170Kv 1 Appearance Clear, free Clear, free Clear, free from from from sediments and sediments and sediments and suspended suspended suspended matter matter matter 2 Colour Max 20 Max 20 Max 20 3 3 Density kg/dm at 20 °C ≤0.895 ≤0.895 ≤0.895 (old Specific Gravity) 4 Interfacial ≥35 ≥35 ≥35 Tension/Surface Tension (mN/m at 25 °C) 5a Kinematic Viscosity ≤ 16.5 ≤ 11 ≤ 3.5 2 mm /s at 40 °C (Centistokes) 5b Kinematic Viscosity ≤ 40 ≤ 25 ≤6 2 mm /s at 20 °C (Centistokes) 5c Kinematic Viscosity ≤ 800 2 mm /s at -15 °C (Centistokes) 5d Kinematic Viscosity ≤ 1800 2 mm /s at -30 °C (Centistokes) 5e Kinematic Viscosity ≤ 150 2 mm /s at -40 °C (Centistokes) 6 Pour Point °C ≤ -30 ≤ -45 ≤ -60 7 Flash Point °C ≥ 140 ≥ 130 ≥ 95 8 Neutralization Value/ ≤ 0.03 ≤ 0.03 ≤ 0.03 Acidity (mg KOH/g) 9 Water Content mg/kg ≤ 20 ≤ 15 ≤ 10 (ppm) 11 10 Break Down DES(kV at 2.5 mm gap) 11 Resistivity at 90 °C (GΩm) 12 Tan δ / Dielectric Dissipation Factor-DDF (at 40 to 60 Hz & 90 °C) 13 Oxidation Stability for Uninhibited OilNeutralization Value(mg KOH/g) 13a Oxidation Stability for Uninhibited OilSludge % by mass 14 Oxidation Stability for Inhibited Oil- Induction period (hours) ≥ 40 ≥ 50 ≥ 60 min 60 min 60 min 60 ≤0.15 * see note ≤0.15 * see note ≤0.010 * see note ≤0.40 ≤0.40 ≤0.40 ≤0.10 ≤0.10 ≤0.10 Similar value Similar value Similar value as before as before as before filling filling filling *Note. Higher DDF value may indicate excessive contamination or the misapplication of solid insulation used in manufacturing and should be investigated. 12 Table-9d: CHARACTERISTICS OF UNSUED MINERAL INSULATING OILS FOR TRANSFORMERS AND SWITCHGEAR IEC 60296 (New specifications) CHARACTERISTICS OF UNSUED MINERAL INSULATING OILS FOR TRANSFORMERS AND SWITCHGEAR IEC 60296 Sr. Property Unused Mineral Low No. Insulating Oil Temperature IEC 60296 Switchgear Oil Function 1 Viscosity at 40 °C Max. 12mm2 /s Max. 3.5mm2 /s 2 Viscosity at -30 °C *see note Max. 1800mm2 /s 3 Viscosity at -40 °C*see note Max. 400mm2 /s 4 Pour Point*see note Max. -40 °C Max. -60 °C 5 Water Content Max. 30ppm Max. 30ppm (mg/kg) for bulk (mg/kg) for bulk supply or 40ppm supply or 40ppm (mg/kg) for (mg/kg) for delivery in drums delivery in drums and IBC and IBC 6 Breakdown Voltage or DES at 2.5 Min. 30 kV before Min. 30 kV before mm Gap dehydration or 70 dehydration or 70 kV after kV after dehydration dehydration 7 Density at 20 °C (old S.G) Max. 0.895 g/ml Max. 0.895 g/ml 8 DDF at 90 °C (old Tan δ or DF) Max. 0.005 (0.5%) Max. 0.005 (0.5%) Refining/Stability 1 Appearance Clear, free from Clear, free from sediments and sediments and suspended matter suspended matter 2 Acidity Max. 0.01mg Max. 0.01mg KOH/g KOH/g 3 Interfacial Tension (IFT) Min. 40 mN/m Min. 40 mN/m 4 Total Sulfur Content No general No general requirement requirement 5 Corrosive Sulfur No general No general requirement requirement 13 6 Antioxidant Additive 7 Furfural Content **see note Performance 1 Oxidation Stability 2 Total Acidity Uninhibited oil (U): Not detectable Trace inhibited oil (T): Max. 0.08% Inhibited oil (I): 0.08 – 0.40% Max. 0.1 mg/kg Uninhibited oil (U): Not detectable Trace inhibited oil (T): Max. 0.08% Inhibited oil (I): 0.08 – 0.40% Max. 0.1 mg/kg Max. 1.2mg Max. 1.2mg KOH/g KOH/g 3 Sludge Max. 0.8% Max. 0.8% 4 DDF at 90 °C (Dielectric Max. 0.500 Max. 0.500 Dissipation Factor) (Tan δ) 5 Gassing No general No general requirement requirement 6 Electrostatic Charging Tendency Special (ECT) ***see note requirement Health, Safety and Environment (HSE) 1 Flash Point Min. 135 °C Min. 100 °C 2 PCA Content (Polycyclic Max. 3% Max. 3% aromatics) 3 PCB Content (Polychlorinated Not detectable Not detectable biphenyls) * Note. This is the standard LCSET (Lowest Cold Start Energizing Temperature) for transformer oil and can be modified depending upon the climatic condition of each country. Pour point should be minimum 10K below LCSET. ** Note. Furfural and related compounds (2-FAL) in unused mineral insulating oils can result either from improper re-distillation after solvent extraction during refining or from contamination with used oil. Unused insulating oils should have a low level of 2-FAL and related compounds (IEC 1198). *** Note. Electrostatic Charging Tendency (ECT) of oil is an important property for certain designs of HV and EHV transformers which have oil pumping rates that can give rise to the build-up of electrostatic charge. This charge can result in energy discharge causing transformer failure. A method to measure ECT is proposed by CIGRE SC 12. 14 Table-9e: CONCENTRATION OF DISSOLVED GASES (DGA) IN OIL (IEC 60567 &60599) CONCENTRATION OF DISSOLVED GASES (DGA) IN OIL (IEC 60567 &60599) Sr. Gas Description Limiting Value Limiting Values No. (ppm v/v) PTESU Standard (ppm) 1 Hydrogen (H2) <200 <150 2 Methane (CH4) <50 <25 3 Ethane(C2H6) <15 <10 4 Acetylene (C2H2) <15 <15 5 Ethylene (C2H4) <60 <20 6 Carbon Mono oxide (CO) <1000 <500 7 Carbon Dioxide (CO2) <11000 <10000 8 Oxygen (O2) 2000-35000 9 Nitrogen (N2) 10000-100000 General criteria for interpretation on the bases of flame colour of combustible gases detected in Buchholz Relay is as: - If flame colour is Blue, it indicates decomposition of oil. - If flame colour is Yellow, it indicates deterioration of solid insulation. 15 Table-9f: TREATMENT OF INSULATING OIL IN TRANSFORMERS TREATMENT OF INSULATING OIL IN TRANSFORMERS RECOMMENDED REMEDIAL MEASURES Characteristic Recommended Measures Description Lower DES Value Dehydration and Filtration High Water/Moisture Dehydration and Filtration under Vacuum Contents High DDF (Tan δ) Dehydration and Filtration under Vacuum OR Regeneration/Reclamation/Replacement Neutralization Value Regeneration/Reclamation/Replacement Interfacial Tension Regeneration/Reclamation/Replacement Essential Functions of Oil - Dielectric Insulation - Heat Transfer Principal Causes of adverse changes in dielectric properties of Oil - Oxygen and Humidity: Main source is the breathing system and oil leak points. The desiccating material should be regenerated or renewed as soon as 1/3 rd of its quantity has been moisturized (colour changed from blue to pink). Attend oil leakages without intentional delays. - High Temperatures - External pollution - Electrical phenomena - Partial discharges - Corona 16 Table- 9g: CHARACTERISTICS OF SULPHUR HEXAFLOURIDE GAS (S) IEC 60376 CHARACTERISTICS OF SULPHUR HEXAFLOURIDE GAS (SF6) IEC 60376 Sr. Description Limiting Value Limiting Value No. (New/Unused Gas) (Gas in CB) 1 Purity (concentration of SF6 > 99.9% > 95% verses Nitrogen) 2 Dew Point (-°C) -50°C -10°C 3 Impurities 3a CF4 (Carbon Tetra-fluoride) < 0.05% (m/m) 3b Oxygen + Nitrogen, air < 0.05% (m/m) 3c Water < 15ppm (m/m) 3d Acidity expressed as HF < 0.03ppm (m/m) (Hydrofluoric acid) 3e Hydrolysable fluoride < 1.0ppm (m/m) expressed as HF 3f Oil content < 10ppm (m/m) Properties -Sulphur Hexafluoride is a compound having the formula SF6 -At normal room temperatures and pressures it is gaseous - It has density of 6.16g/l at 20 °C and 760 torr (about five times the density of air) - Its critical temperature 45.6 °C, it can be liquefied by compression and is normally transported as a liquid in cylinders - Inert - Colourless - Odourless - Nontoxic - Nonflammable - Good dielectric medium - Electro-negative (tends to attract the free electrons), good arc quenching medium) - High DES value, (about 3 times of the air at atmospheric pressure) - Heat transfer capability 2-5 times of air - Pressure increases with temperature by about 0.025 bar per °C - Leakage detection possible with halogen gases leakage detectors 17 Preferred sizes of cylinders -The standard sizes of cylinders, expressed in liters (l) for SF6 are: 3, 5, 10, 20, 40, 80, 150 and 500. 10 liter and 40 liter are the preferred size for use. The filling ratio of cylinders in temperate countries is 1.04kg/l and in tropical countries is 0.75kg/l. 18 Table-9h: 500KV CIRCUIT RESISTANCE DATA BREAKERS TIMING AND CONTACT 500KV CIRCUIT BREAKERS TIMING AND CONTACT RESISTANCE VALUES (H: Hydraulic, S: Motor Spring, P: Pneumatic Operating Mechanisms) Sr. Make Type Closing Opening Contact No. Time (ms) Time (ms) Resistance (Maximum) (Maximum) micro Ω per Pole (Maximum) 1 SIEMENS (H) SF6 3AT5 (4 90±10 18±3 240 Breaks per Pole) 2 SIEMENS (H) SF6 3AT4 (4 90±10 18±3 240 Breaks per Pole) 3 SIEMENS (H) SF6 3AT3E1 (2 80±6 18±2 75±5 Breaks per Pole) 4 SIEMENS (H) SF6 3AT2E1 (2 80±6 18±2 75±5 Breaks per Pole) 5 SIEMENS (H) SF6 8DQ14 (2 80±6 18±2 75±5 (GIS) Breaks per Pole) 6 MERLIN GERIN FA4 (4 42±4 19±4 250 (H) SF6 Breaks per Pole) 7 MERLIN GERIN FA4R (4 42±4 19±4 250 (H) SF6 Breaks per Pole) 8 MERLIN GERIN GFA2R (4 42±4 19±4 250 (H) SF6 Breaks per Pole) 9 MERLIN GERIN GFA4R (4 42±4 19±4 250 (H) SF6 Breaks per Pole) 10 TOSHIBA (H) SF6 GSR100 18 100 19 11 12 13 14 15 16 17 18 19 20 500R2 TOSHIBA (H) SF6 GSR100 500R2C HITACHI (H) SF6 OFTB 500/40L GEC ALSTHOM FX32D (H) SF6 GEC ALSTHOM FX22Z (H) SF6 MITSUBISHI (P) 500 SF6 SFMT/50B ABB (S) SF6 HPL 550 65 B2 (4 Breaks per Pole) AEG (P) SF6 S4M-550P 100 AREVA(S) SF6 GL317D (FK3-4) ASEA (S) SF6 HPL 550/ 4004LT DELLE PK6C ALSTHOM (ABCB) 18 100 19±3 80 25 200 450 20 Table-9i: 220KV CIRCUIT RESISTANCE DATA BREAKERS TIMING AND CONTACT 220KV CIRCUIT BREAKERS TIMING AND CONTACT RESISTANCE VALUE (H: Hydraulic, S: Motor Spring, P: Pneumatic Operating Mechanisms) Sr. Make Type Closing Opening Contact No. Time (ms) Time (ms) Resistance (Maximum) (Maximum) micro Ω per Pole (Maximum) 1 SIEMENS (H) SF6 3AQ1E1 (1 95±5 39±3 60 Break per Pole) 2 SIEMENS (S) SF6 3AP2F1 (2 63±6 18±2 54±5 Breaks per Pole) 3 SIEMENS (S) SF6 3APF1 (1 62±6 37±4 40 Break per Pole) 4 SPRECHER HGF150 28 50 ENERGIE (S) SF6 100/1A (1 Break per Pole) FKF 1-2 5 MERLIN GERIN FA2 (2 100 30 170 (H) SF6 Breaks per Pole) 6 MERLIN GERIN FA2R (2 100 30 170 (H) SF6 Breaks per Pole) 7 MERLIN GERIN FA1 (1 100 30 170 (H) SF6 Break per Pole) 8 CHINA (H) OCB SW6-245 200 40 400 (2 Breaks per Pole) 9 NMG (P) SF6 245-MHM- 100 30 50 e-1P (1 21 10 11 12 13 14 15 16 17 18 19 Break per Pole) BBC (P) SF6 ELVF-245 nc2at (2 Breaks per Pole) ABB (H) SF6 ELF SP4-1 (1 Break per Pole) ABB (S) SF6 LTB245E1 (2 Breaks per Pole) ABB (S) SF6 HPL 245/31B1 (2 Breaks per Pole) ABB (S) SF6 HPL 245/3152 (2 Breaks per Pole) AEG (S) SF6 S1-245/F3 (2 Breaks per Pole) AEG (P) SF6 S1-245 (1 Break per Pole) ALSTHOM (S) GL-314 (1 SF6 Break per Pole) FK31 NMG/VATECH SB6m-245 (S) SF6 (1 Break per Pole) CHEM China (S) OFPI-252SF6 50L, FAR (1 Break per Pole) 110 20 100 55 18 60 63±6 18±2 54±5 63±6 18±2 54±5 63±6 18±2 54±5 63±6 18±2 54±5 63±6 18±2 54±5 82-102 16-26 50 75±5 30±3 40±5 ≤ 80 ≤ 30 ≤ 30 22 Table-9j: 132KV CIRCUIT RESISTANCE DATA BREAKERS TIMING AND CONTACT 132KV CIRCUIT BREAKERS TIMING AND CONTACT RESISTANCE VALUE (H: Hydraulic, S: Motor Spring, P: Pneumatic Operating Mechanisms) Sr. Make Type Closing Opening Contact No. Time (ms) Time (ms) Resistance (Maximum (Maximum micro Ω ) ) per Pole (Maximum ) 1 SIEMENS (H) 3ARI (1 100±5 50±5 60 SF6 Break per Pole) 2 SIEMENS (H) 3AQI (1 95±5 39±3 60 SF6 Break per Pole) 3 SIEMENS (S) 3API FG (1 57±6 31±3 40 SF6 Break per Pole) 4 ENERGOINVES SFE-13 (1 130 35 60 T (P) SF6 Break per Pole) 5 S&S (S) SF6 HGF-112/1C 140 25 60 (1 Break per Pole) FKF2-6 6 AEG (P) SF6 S1-145 (1 100 40 60 Break per Pole) 7 AEG (S) SF6 S1-145 100 40 60 F1/3131/SE (1 Break per Pole) CRR-5 8 AEG (S) SF6 S1-145 100 40 60 F1/4031/SE (1 Break per Pole) CRR-5 9 ASEA (S) SF6 HPL-145/25 90 21±2 50 23 10 11 12 13 14 15 16 17 18 20 21 A1 (1 Break per Pole) BLG 1002 ABB (S) SF6 HPL-145/25 A1 (1 Break per Pole) BLG 1002 ABB (S) SF6 HPL-145/25 A1 (1 Break per Pole) BLG 1002A NMG (S) SF6 1M-MHD145 (1 Break per Pole) MITSUBISHI (S) SFM-145 (1 SF6 Break per Pole) BBC (H) OCB TR-145 (1 Break per Pole) BBC (H) OCB TR-170 (1 Break per Pole) LKNES (H) OCB MULB-150 (1 Break per Pole) ASEA (S) OCB HLD145/1250b (1 Break per Pole) CHINA (H) OCB SW6-145 (2 Break per Pole) BBC (P) SF6 ELF-145n1 (1 Break per Pole) ABB (H) SF6 SL 2-1 (1 Break per Pole) 90 21±2 50 90 21±2 50 80 250 60 130 28 100 75±10 35±10 150 75±10 35±10 150 130 50 150 90 46 150 200 40 180 110 20 50 55 18 60 24 22 22 23 24 25 ABB (S) SF6 LTB145D1/B (1 Break per Pole) ABB (S) SF6 LTB145D1/B (1 Break per Pole) CAPACITO R BANK ALATOM (S) GL-212 (1 SF6 Break per Pole) FKPIN DING SHAN LW 35-145 CHINA (S) SF6 (1 Break per Pole) TENAGA (S) SF6 LW9-145 (1 Break per Pole) 42 22±4 40 A/B/C: 45/40/40 22±4 40 100±5 50±5 60 100±20 28 +2 -4 45 150 30 45 ≤ 30 ≤ 30 CHEM China (S) OFPI-145≤ 100 SF6 40L, FAR3 (1 Break per Pole) 25 Table-9k: 66KV CIRCUIT RESISTANCE DATA BREAKERS TIMING AND CONTACT 66KV CIRCUIT BREAKERS TIMING AND CONTACT RESISTANCE VALUE (H: Hydraulic, S: Motor Spring, P: Pneumatic Operating Mechanisms) Sr. Make Type Closing Opening Contact No. Time (ms) Time (ms) Resistance (Maximum) (Maximum) micro Ω per Pole (Maximum) 1 ENERGOINVEST SFE-9 (1 130 35 60 (P) SF6 Break per Pole) 2 ABB (S) SF6 LTB-72.5 42 22±4 40 D1/B (1 Break per Pole) 3 CHINA (H) OCB SW6-72.5 200 40 180 (2 Break per Pole) 26 Table-9l: LEAD ACID DC BATTERIES OPERATION AND MAINTENANCE DATA Sr. No. Battery Make Battery Type Rated Capacity (AH) Float Charge VPC (V) Boost Charge VPC (V) Sp. Gravity at 25°C End of Discharge Voltage at 10 hours rate (V) 1 YUASA (Japan) YUASA (Japan) ROCKET (Korea) ROCKET (Korea) VARTA (Germany) VARTA (Germany) CS-170 150 2.12 2.33 1.180± 0.1C/1.80 Average Impedance Per Cell (mΩ) (Empirical Values0 1.44 CS-400 300 2.12 2.33 1.180± 0.1C/1.80 0.640 PS-170 150 2.15 2.40 1.180 0.1C/1.80 1.22 PS-400 300 2.15 2.40 1.180 0.1C/1.80 0.658 OPZS 150 2.23 2.40 1.180 0.1C/1.80 1.44 OPZS 600 2.23 2.40 1.180 0.1C/1.80 0.407 TUDOR (Italy) TUDOR (Sweden) NAMBANG (Korea) HOPPECKE (Germany) CHLORIDE (England) CHLORIDE (England) DUROS (Denmark) BERGA (Germany) FIAMM (Italy) FIAMM (Italy) CHLORIDE (Pakistan) EXIDE (Pakistan) EXIDE (Pakistan) 6TF GR200/ 3GR200 PS 150 300 2.22 2.17 2.40 2.40 1.180 1.180 0.1C/1.80 0.1C/1.83 1.30 0.731 150 2.17 2.40 1.180 0.1C/1.80 0.731 2.23 2.40 1.220 0.1C/1.80 0.731 150 2.21 2.35 1.203 0.1C/1.85 0.641 300 2.21 2.35 1.203 0.1C/1.85 0.378 150 2.20 2.40 1.240 0.1C/1.80 0.731 Gro 475 2.23 2.40 1.220 0.1C/1.80 0.315 SM4 SM4 1XMP 150 300 150 2.18 2.18 2.18 2.40 2.40 2.40 1.180 1.180 1.180 0.1C/1.80 0.1C/1.80 0.1C/1.80 0.471 0.238 0.471 1XMP19 1XMP33 150 2.20 2.40 1.180 0.1C/1.80 0.725 150 2.20 2.40 1.180 0.1C/1.80 0.352 1 2 2 3 3 4 4 5 6 7 7 8 9 10 10 11 12 12 Gro E25 YCP25/AE YCP13/AF Note-1. Correction of Specific Gravity at temperature 25 °C: S25 = St + 0.0007 (t – 25) S25 = Corrected Specific Gravity at temperature 25 °C St = Measured Specific Gravity at temperature t °C of electrolyte t = Temperature of electrolyte (°C) as measured at site Where 27 Note-2. Open Circuit Voltage Per Cell = Specific Gravity + 0.84 Volts Note-3. End of Discharge Specific Gravity = 1.415 Note-4. Average Impedance of Strap/Inter-cell Connector = 0.24 mΩ 28 Table-9m: CAPACITANCE AND DISSIPATION FACTOR VALUES OF 132/11KV POWER TRANSFORMERS Sr. No. TR Make TR Type 1 SHENYANG (China) SFZ726000 2 2 2 3 4 4 5 6 7 TR Ratings 20/26 MVA 132/11KV SHENYANG SFZ720/26 (China) * 13000 MVA 132/11KV TOSHIBA HC/OPTL 20/26 (Japan) R-D MVA 132/11KV TOSHIBA HC/OPTL 10/13 (Japan) * R-D MVA 132/11KV MINEL TPv20/26 (Yugoslavia) 7105-26 MVA 132/11KV ELTA TNARC- 20/26 (Poland) 26000/13 MVA 2 PT 132/11KV ELTA TNARC- 10/13 (Poland) * 13000/13 MVA 2 PT 132/11KV HYUNDAI TL-068 20/26 (Korea) MVA 132/11KV OTE (Italy) BERGA 10/13 MA MVA 132/11KV ELECTROPU 20/26 TRE MVA (Romania) * 132/11KV Winding Tested C Value (PF) (Empiric al Value) H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G 4270 3379 7636 4270 3379 7636 4063 3297 8170 4063 3297 8170 4113 3364 8448 5400 2949 13110 5400 2949 13110 5400 3480 9386 3882 3007 6456 4270 3379 7636 %DF Value at 20 °C (Empiri cal Value) 0.615 0.528 0.578 0.615 0.528 0.578 0.138 0.125 0.29 0.138 0.125 0.29 0.295 1.309 0.705 0.2 0.3 0.3 0.2 0.3 0.3 0.249 0.23 0.26 0.375 0.324 0.504 0.615 0.528 0.578 29 8 9 ELECTROPU TRE (Chec Republic) SIEMENS (Pakistan) * 10 SIEMENS (Pakistan) * 12 SIEMENS (Pakistan) * 13 HEC (Pakistan) * 14 PEL (Pakistan) * 15 PEL (Pakistan) * 16 PEL (Pakistan) * 17 IRANTRAFO (Iran) * 4 MEIDENSHA (Japan) * 4 MEIDENSHA (Japan) * 4 ELPROM (Bulgaria) * 4 ``` 10/13 MVA 132/11KV 40 MVA 132/11KV H-L H-G L-G H-L H-G L-G 20/26 H-L MVA H-G 132/11KV L-G 20/26 H-L MVA H-G 132/11KV L-G 20/26 H-L MVA H-G 132/11KV L-G 40 MVA H-L 132/11KV H-G L-G 20/26 H-L MVA H-G 132/11KV L-G 10/13 H-L MVA H-G 132/11KV L-G 20/26 H-L MVA H-G 132/11KV L-G 20/26 H-L MVA H-G 132/11KV L-G 10/13 H-L MVA H-G 132/11KV L-G 20/26 H-L MVA H-G 132/11KV L-G 20/26 ` MVA 132/11KV 4296 2477 7845 4270 3379 7636 4270 3379 7636 4270 3379 7636 4270 3379 7636 4270 3379 7636 4270 3379 7636 4270 3379 7636 4270 3379 7636 5400 2949 13110 5400 2949 13110 5400 2949 13110 ```````````` ``````````` 0.46 0.75 0.35 0.615 0.528 0.578 0.615 0.528 0.578 0.615 0.528 0.578 0.615 0.528 0.578 0.615 0.528 0.578 0.615 0.528 0.578 0.615 0.528 0.578 0.615 0.528 0.578 0.2 0.3 0.3 0.2 0.3 0.3 0.2 0.3 0.3 ` 30 4 GANZ (Hungary) * `````` 4 PAUWELS (Belgium) * DRF130/275 (3-WDG) 20/26 MVA 132/11KV 37.5 MVA 132/66/11 KV H-L H-G L-G H-L H-G L-T L-G H-T T-G 5400 2949 13110 5994 4413 7078 2041 40 15860 0.2 0.3 0.3 0.478 0.53 0.478 0.52 0.688 31 Table-9n: CAPACITANCE AND DISSIPATION FACTOR VALUES OF 220/132/11KV AUTO TRANSFORMERS Sr. No. TR Make TR Type TR Ratings Windin g Tested C Value (PF) (Empirica l Value) 1 CEM (France) AOTR. CV 2 SHENYAN G (China) 3 HAWKER SIDDELY (UK) ALSTHOM (France) OSFPS7160000 HSPT/T TT85 160 MVA 220/132/11K V 160 MVA 220/132/11K V 160 MVA 220/132/11K V 160 MVA 220/132/11K V 160 MVA 220/132/11K V 160 MVA 220/132/11K V 160 MVA 220/132/11K V 250 MVA 220/132/11K V 160 MVA 220/132/11K V 160 MVA 220/132/11K V 160 MVA HL-T HL-G T-G HL-T HL-G T-G HL-T HL-G T-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G H-L 4732 6374 10530 5778 7428 14496 14303 27637 24973 10400 7800 11600 8500 6700 13800 5600 5700 13200 4270 3379 7636 4270 3379 7636 4270 3379 7636 4270 3379 7636 4270 4 AUTO 5 AEG (Turkey) MRSN8254 6 BBC (Germany) AUTO 7 TBEA (China) * 8 TBEA (China) * 9 HOUPING (China) * 10 SHENBIAN (China) * 11 ABB (Spain) %DF Value at 20 °C (Empirica l Value) 0.74 0.95 0.88 1.61 0.65 1.60 0.345 0.358 0.360 0.202 0.328 0.38 0.358 0.386 0.775 0.319 0.324 0.312 0.615 0.528 0.578 0.615 0.528 0.578 0.615 0.528 0.578 0.615 0.528 0.578 0.615 32 * 12 HYUNDAI (Korea) * 13 SIEMENS (Pakistan) * 14 ABB (Germany) * 15 MEIDENSH FBORS A (Japan) DL 16 ABB (Germany) MANGLA TPFD 66 000 220/132/11K V 160 MVA 220/132/11K V 160 MVA 220/132/11K V 160 MVA 220/132/11K V 160 MVA 220/132/11K V 138 MVA 220/132/11K V H-G L-G H-L H-G L-G H-L H-G L-G H-L H-G L-G HL-T HL-G T-G HL-T (3 HL-G (5 T-G (4) 3379 7636 4270 3379 7636 4270 3379 7636 4270 3379 7636 6832 7460 14846 6289 5864 12158 0.528 0.578 0.615 0.528 0.578 0.615 0.528 0.578 0.615 0.528 0.578 0.3 0.165 0.66 1.085 0.87 0.98 33 Table-9o: CAPACITANCE AND DISSIPATION FACTOR VALUES OF 500/220/22KV AUTO TRANSFORMERS Sr. No. TR Make 1 TRAFOUNIO NRPN 600 (200x3) N (Germany) -8157 MVA 500/220/22 KV JEMOUNT AUTO 450 (150x3) SCHENIDER MVA (France) 500/220/22 KV TBEA 450 (150x3) (China) * MVA 500/220/22 KV SIEMENS NRPN 600 (200x3) (Brazil) * -8157 MVA 500/220/22 KV SIEMENS NRPN 600 (200x3) (Germany) * -8157 MVA 500/220/22 KV TBEA 200 (200x3) (China) * MVA 500/220/22 KV ELIN 450 (150x3) (Austria) * MVA 500/220/22 KV 2 3 4 5 6 7 TR Type TR Ratings Windin C Value g Tested (PF) (Empirica l Value) HL-T HL-G T-G 4196 4173 9722 %DF Value at 20 °C (Empirica l Value) 0.133 0.131 0.255 HL-T HL-G T-G 7200 5700 10800 0.32 0.205 0.531 HL-T HL-G T-G 4270 3379 7636 0.615 0.528 0.578 HL-T HL-G T-G 4196 4173 9722 0.133 0.131 0.255 HL-T HL-G T-G 4196 4173 9722 0.133 0.131 0.255 HL-T HL-G T-G 4270 3379 7636 0.615 0.528 0.578 HL-T HL-G T-G 4270 3379 7636 0.615 0.528 0.578 34 Table-9p: CAPACITANCE AND DISSIPATION FACTOR VALUES OF CONDENSER TYPE BUSHINGS OF TRANSFORMERS Sr. No. Bushing Make Type Rated Voltage Insulati on Tested C Value (PF) (Empirica l Value) 1 HAFELY (Swiss) HAFELY (Swiss) F&G (Germany) F&G (Germany) PASSONI&V ILLA (Italy) PASSONI&V ILLA (Italy) * ABB (Sweden) ABB (Sweden) ABB (Sweden) BRUSH (UK) MICAFIL (Swiss) NGK (Japan) COT-245 220KV COT-145 145KV OTF1550/525 OTF1050/245 PNE145/400A PNE245/400A GOM-1050 500KV GOB-650 132KV GOB-380 100KV OV-1451000 132KV H-L H-G H-L H-G H-L H-G H-L H-G H-L H-G H-L H-G H-L H-G H-L H-G H-L H-G H-L H-G H-L H-G 405 10840 335 11115 414.5 7828 427 7828 235.95 235.95 483.25 309.55 353.1 375.8 405 10840 2 3 4 5 6 7 8 9 10 11 12 220KV 145KV 145KV 220KV 220KV %DF Value at 20 °C (Empirica l Value) 0.68 1.94 0.58 1.26 0.03 0.36 0.065 0.355 0.79 0.79 0.774 0.687 0.687 0.25 0.68 1.94 132 KV 35 Table-9q: CAPACITANCE AND DISSIPATION FACTOR VALUES OF CURRENT TRANSFORMERS (C.T) Sr. No. CT Make Type Rated Voltage Insulatio C Value n Tested (PF) (Empiric al Value) 1 MESSWAND LER (Germany) EMEK (Turkey) EMEK (Turkey) SITW (China) AT-145 132KV H-G 500 %DF Value at 20 °C (Empirica l Value) 0.2 AT4-145 132KV H-G 307.5 0.29 (<1) AT4-245 245KV H-G 206.6 0.02 (<1) LCWB6145 FGCH-200 132KV H-G 900 0.8 (<2) 900 0.2 (<1) 634 0.6 800 22000 800 13000 1000 170 500 (<1) (<1) (<1) (<1) (<1) 350 0.2 2 3* 4 5 NISSIN 220KV H-G (Japan) 6 GALILEO TAE-245/G 220KV H-G (Italy) 7 ** ASEA IMBD-145 132KV C1 (H-L) (Sweden) C2 (H-G) 8 ** ASEA IMBD-72 66KV C1 (H-L) (Sweden) C2 (H-G) 9 HAEFELY ISOK-245 220KV H-G *** (Swiss) CA 10 LK-NES A8z61/A9z 132KV H-G (Denmark) 61 11 MESSWAND JOS-72.5 66KV H-G LER (Germany) 12 NIROU TRANS (Iran) Note. *: Top and Bottom units should be tested separately. Note. **: Use capacitance tap for test. Note. ***: CA means the bushing capacitance. 0.2 36 Table-9r: CAPACITANCE AND DISSIPATION FACTOR VALUES OF CAPACITOR VOLTAGE TRANSFORMERS (CVT) Sr. No. CVT Make Type Rated Insulati C Value (PF) %DF Voltage on (Empirical Value Tested Value) at 20 °C (Empir ical Value) 1 TRENCH ELECTRIC (Canada) GALILEO (Italy) TEHM-500 500KV TCS-245G 220KV 3 NMG (Italy) CPTa-245/4 220KV 4 HAEFLY (Swiss) CVE-245 220KV 5 TRENCH ELECTRIC (Canada) MAGRINI GALILEO (Italy) PASSONI &VILLA (Italy) HAEFLY (Swiss) TEM-L3OS 220KV CPT-245/8 220KV CVE-550 500KV 9 EMEK (Turkey) KGT-245 10 EMEK (Turkey) KGT-145 12 NIROU TRANS (Iran) * 2 6 7 8 CN(H-G) C1 C2 CN(H-G) C1 C2 CN(H-G) C1 C2 CN(H-G) C1 C2 CN(H-G) C1 C2 CN(H-G) 5000 5300 133900 8000 0.24 4000 4400 44000 4500 +10% -5% 4790 +10% -5% 74455+10% -5% 3000 (<1) 8000 ±10% (<1) 7000 +10% -5% (<1) 6900 +10% -5% 7033 +10% -5% 27176 +10% -5% 4598 (<1) 220KV CN(H-G) C1 C2 CN(H-G) C1 C2 CN(H-G) 132KV CN(H-G) 5950 (<1) 500KV (<1) (<1) (<1) (<1) 220KV 37 12 NIROU TRANS (Iran) * 132KV 38 Table-9s: LEAKAGE CURRENT MONITORING (LCM) ARRESTERS/LIGHTNING ARRESTERS OF SURGE Sr. Make No. Type Rated Mfr. MCOV Total Resistive Voltage Rated Leakage Leakage Voltage Current Current 1 ZLAX25C ZLAX15C XAA 220KV 198KV 154KV < 800µA < 200µA 132KV 120KV 90KV < 350µA < 200µA 132KV 116KV 90KV - < 200µA ZSE-C1Z 220KV 198KV 154KV < 490µA < 200µA ZSE-C1Z 132KV 120KV 90KV < 390µA < 200µA 1MB-120 132KV 120KV 90KV - < 200µA 9LXBH60 220KV 198KV 160KV - < 200µA EXLIMQ 220KV 198KV 160KV < 1000µA < 200µA Y10W120/295 YHO 10W12/38 132KV 120KV 90KV - < 200µA 12KV -KV -KV - < 200µA 2 3 4 5 6 7 8 9 10 HITACHI (Japan) HITACHI (Japan) ASEA (Sweden) MEIDENSHA (Japan) MEIDENSHA (Japan) BOWTHORP (England) GE/TRANQUELL (USA) ABB (Sweden) WENZHOU YIKUN (China) WENZHOU YIKUN (China) 39 Table-9t: CRITERIA FOR REPLACEMENT OF VACUUM INTERRUPTER IN 11KV VACUUM CIRCUIT BREAKERS (VCB) Sr. VCB Make No. Type No. of Description (to be checked Operations in CB closed position) 1 MEIDENSHA (Japan) MEIDENSHA (Japan) SIEMENS (Pakistan) HITACHI (Japan) AEG (Pakistan) TOSHIBA (Japan) VFT-12 (O/G) 10,000 VE-14 (I/C) 10,000 3AF 30,000 V 10,000 VA 30,000 VK 30,000 7 J&P (Japan) BK 10,000 8 HYUNDAI (Japan) PELKA/PEL (Turkey/Pak) PELKA/PEL (Turkey/Pak) 2 3 4 5 6 9 10 When limit of contact wipe reaches to 1mm (normal 4mm) When wear standard line coincide with the flange face When white check mark becomes invisible When distance between the reference lines exceeds 1mm When burn-off indicator becomes invisible When limit of red-painted limit of contact wipe decreases to less than 3mm When contact wear reaches 3mm/Gap reduces to 1mm (to be checked by measuring the snatch gap) 10,000 PDB5-25-8W (O/G) PDB5-25-25W (I/C) 11 A vacuum interrupter (vacuum bottle) of 11kV VCB should be replaced when any one of the following criteria is met with: - The prescribed number of total operations have been completed (operation counter reading) - Failed in vacuum degree check/test (tested with proper test set VIDAR or when tested with Hipot set). - Limit of contact wipe reached (abnormal wear of contacts). Note. Vacuum degree test / Limit of contact wipe should be checked yearly or after 1000 operations whichever comes first. 40 10. OPERATION A view of 220/132kV Control Room of 220kv G/S NKLP Lahore 41 10.1 INTRODUCTION The grid stations in grid system of NTDCL&DISCOs are designed and constructed for operation, supervision and control by the staff round the clock, unlike the grid system of many developed countries where the grid stations are remote operated, supervised and controlled at central control centers. The operation staff at control rooms of grid stations comprises shift engineers, operators, attendants, etc. and perform duty in three shifts i.e. morning shift, evening shift and night shift. The operation staff supervises and controls the grid station in accordance with the provisions made in the design and construction of the equipment and transmission lines and in compliance of the instructions of the system operator, i.e. NPCC & RCC. The operation staff records hourly loading data (Amperes), voltage data (kV), temperature, and other parameters, etc. of the transformers and transmission line in the station log sheet and onward passes to NPCC and/or RCC. They also maintain the record of all the normal and abnormal events of the local system and record of telephonic instruction of all the stakeholders of the system for reference. They coordinate with NPCC and/or RCC and manage the scheduled and non-scheduled shut-downs on the grid station equipment and transmission lines, for maintenance and other purposes. They perform switching operations of the switchgear as desired under instructions of NPCC and/or RCC. 42 10.2 General Provisions Generally operations mean all types and categories of work to be done by the employees of NTDCL&DISCOs assigned to them as a duty. These operations include technical, administrative, finance, etc. duties with the ultimate goal to build, operate and maintain the power system for transmission and dispatch of electricity to the distribution companies and down to the consumers. Generally the operations are planned but it may include unplanned work activities as desired by NTDCL&DISCOs. All the operation in-charges should give proper attention for safety of the NTDCL&DISCOs employees during operations at NTDCL&DISCOs premises. The operations in NTDCL&DISCOs are integrated as under: a) Operation of power system for generation, transmission and dispatch of electricity to the Distribution Companies (DISCOs) is a planned action by NTDCL. National Power Control Center (NPCC) Islamabad (including Regional Control Centers (RCC) North & South is the authorized System Operator on behalf of NTDCL. b) NPCC/RCC shall be responsible for the safe, secure, openly-accessible, equitable, environmentally acceptable, reliable and adequate operation and development of the power system. The Operation Codes of NEPRA Grid Code and Distribution Code outlines the necessary rules for operation of the NTDCL&DISCOs power system which should be followed as and where applicable. c) It is the primary responsibility of each employee of the NTDCL&DISCOs to keep the NTDCL&DISCOs system and its component apparatus/equipment in safe operating condition within their design parameters. d) No employee shall operate any apparatus or equipment without having authority/permission or instructions from the competent authority. e) In the existing set up of NTDCL&DISCOs, NPCC is the System Operator of the entire Grid System. In addition to the specific and general instruction of the NPCC whether written or oral, the guidelines given here under shall be followed by all NTDCL&DISCOs employees engaged in operation and maintenance work at different levels of GSO NTDCL&DISCOs such as; - Dealing operation of the HV equipment, - Issuing operating orders and messages, - Dealing with authority to work, Permit-to-Work and Hold-OFF orders, - Dealing with office work and record of operations, etc. - Recording data in the grid station daily log sheets, etc. 43 f) The employees of NTDCL&DISCOs and public should clearly understand the application and significance of operating voltage levels of different equipment or apparatus as given below with regards to their own safety as well as of the apparatus/equipment. - Control and Auxiliary Services Voltages: 24VDC, 48VDC, 110VDC and 220V DC; 110VAC, 230VAC, 400VAC, 50 Hz; - Three-phase four-wire 400VAC and 230VAC, 50 Hz are the domestic and commercial supply voltage levels in Pakistan. - Medium Voltages (MV) for transmission and distribution: 11kV, 22kV (tertiary voltage of EHV transformers) and 33kVAC, 50Hz; - High Voltages (HV) for transmission: 66kV and132kV AC, 50 Hz; - Extra High Voltages (EHV) for transmission: 220kV and 500kV AC, 50 Hz. g) Switching operations: The operation in-charge is responsible to ensure safety of the employees as well of the NTDCL&DISCOs equipment during their normal as well as emergency operations. Similarly, the operation staff on duty besides to look after the normal operations of the grid station equipment have to do switching operation. To deal with switching operations of the HV equipment safely the operation in-charge or the shift in-charge will follow as under before, during and after switching operations: - He will ensure for the approval of the desired operations of the equipment from NPCC/ RPCC. - He will inform and discuss with the NPCC/RPCC any abnormal local condition of the equipment to be operated. - He will identify the nature of operations and safety precautions required. - He will identity the operations during which workers are/or can be exposed to hazards. - He will ensure for the clear operation instructions. 44 - He will follow the prescribed procedure and instructions given in the PTW (Permit to Work) for its issuance and cancellation. - In case of maintenance work oriented operations, he will get complete information about the work to be done from the concerned supervisor and make sure that the equipment to be work upon is fully isolated from all possible sources of supply. He will issue PTW to the authorized supervisor for execution of the work in question indicating all the hazards known to him and not eliminated or covered by the PTW and also discus with the supervisor. - During the switching operations, he will continuously keep contact with NPCC/RPCC and make sure that all the operations are carried out in the approved sequence. - Satisfactory operations will be brought to the notice of NPCC/RCC regularly and abnormal situation if any will also be brought to the notice of NPCC/RCC immediately. - He will make sure that no equipment in the system gets over loaded beyond their rating as a result of operations under execution. - After satisfactory completion of the switching operations to be carried out he will inform to the NPCC/RPCC about the post operation system condition. - He will make entries of the switching operations in the substation order book for reference and record and place Caution Notice/Tag on the control switches of all equipment which may energize the point of work. - After completion of the work and obtaining clearance from the PTW holder he will cancel the PTW following the prescribed procedure and instruction and inform the NPCC/RPCC for further instruction to normalize the system. h) As the operations include technical, administrative, finance, etc. duties, therefore while working in NTDCL&DISCOs offices the office in-charges are responsible to manage for a neat, clean, safe and comfortable atmosphere. Do not use the broken furniture and office tools, etc. Do not hold paper pins, clips, etc. in the mouth and also do not use them as tooth-picks or for cleaning ears. While working on old damped record files take care of insects, dust/dirt, etc. Do not smoke and use open flames in the record rooms. 45 10.3 NPCC SOP FOR SYSTEM RELIABILITY AND SECURITY (issued by NPCC Islamabad in September 2006) Following criteria must be followed by the Dispatcher/System Operators for reliability and Security of the system to avoid blackout/major collapse. 1. While allowing shutdown especially on 500kV transmission lines it must be ascertained that even after the outage, n-1 contingency criteria is not violated, either directly or through cross trip schemes. 2. While allowing shutdown on any 500kV auto transformers, n-1 contingency criteria may not be violated. 3. Before permitting shutdown, the load-shedding may be implemented so that the loading of the system remains within the safety criteria all the time. 4. The system frequency control must be with hydel stations i.e. Mangla/Tarbela in all seasons for effective control. It may be achieved even at the cost of water spillage/hydel energy. 5. Spinning must be made available at all times so the system can have some reserve to meet with eventualities. The spinning must be as per the standard rule of being equal to the largest unit on bar i.e. about 400MW is required round the clock. Spinning should be on units that have a high pick up. 6. Frequency of the system should be maintained within the specified limit i.e. ±1% 7. Cross-trip schemes must be revised and implemented according to seasonal load flow pattern. 8. Economic consideration must not supersede the reliability, safety and security standards. 9. The system voltages should not be allowed to drop below 5% allowable limit in normal circumstances and to meet the criteria, extra generation be taken on bar or load shedding implemented, if other measures to boost the voltage have exhausted. 10. In case of 500kV transformers, the loading should be kept within 100% normally, as outage of transformers at any big station cab also result in blackout on the system, however, short time overloading as per approved criteria may be allowed keeping in view oil/winding temperature. 46 10.4 CONTINGENCY PLAN FOR BLACK START OF TARBELA POWER STATION (issued by NPCC Islamabad in October 2006) This plan is useful in restoration of station auxiliary supply and helps prompt restoration of the system as well. 1. Don’t panic please. 2. Open 220kV circuit breaker D7Q1, D7Q2 and D7Q3 to isolate 220kv and 500V system at Tarbela. 3. Open 220kV lines circuit breaker for all the lines, if they are in closed position. 4. Start Diesel Generation No: 1 & 2 5. Open all 11kV station supply circuit breakers EXCEPT 11kV BREAKER No. 1 & 28 on 11kV flank A & B respectively. 6. Close 11kV circuit breakers of Diesel Generator No. 1 & 2, Power Supply for Unit auxiliaries will appear on respective RPDC for Units (1-4). 7. Isolate both the 220kV bus bars. 8. Start any of the Unit 1-4 on “Manual Mode” and build up rated voltage after ensuring that NO INDICATION PERSISTS IN Control Room. 9. Close the relevant circuit breaker Q2 of the unit to connect it with 220kV Bus Bar No. 2. Now Bus Bar No. 2 is energized. 10. Open 11kV incoming circuit breaker for both the Diesel Generator sets. 11. Close 220kV circuit breaker D6Q2, SPT No. 1 will be energized. Now station normal supply is restored. 12. Close all the 11kV circuit breaker to restore the complete station Auxiliary power supply. 13. Ensure availability of power supply to compressors at Switchyard before any further operation of circuit breakers. 47 14. Reset 50V & 230V Battery Chargers at Switchyard and Power House and ensure that load shifted from batteries to chargers. 15. Start 2nd Unit on 220kV side after ensuring that NO INDICATION PERSISTS in Control Room. 16. Connect the 2nd Unit to 220kV Islamabad line, if so desired by NPCC by closing D4Q3 in case Unit No. 3 has been started. Make sure that 220kV circuit breaker D4Q2 & D4Q1 are open. 17. Close 220kV circuit breaker D4Q1 220kV, Bus Bar No.1 is energized now. 18. Close 220kV circuit breaker D5Q1, SPT-2 is energized now. 19. Ensure that 11kV station supply buses flank A and flank B are energized with TIE circuit breaker open. 20. Open 220kV circuit breaker DQ2 of the first started unit. The first started unit is on SNL with voltage built up, keep it running on SNL. Station supply will be available from SPT-2. 21. Ensure that all 500kV circuit breakers are open except Bay 8. 22. Complete Bay 7 on 220kV side to energize 500kV Bus Bars 1&2. Now both 500kV Bus Bars are energized. 23. For further restoration proceed as desired by NPCC. 48 10.5 PARALLEL OPERATION OF TRANSFORMERS IN THREE-PHASE SYSTEMS Transformers are in parallel operation if they are connected in parallel on at least two sides or Parallel operation means direct terminal-to-terminal connection between transformers in the same installations. A distinction should be made between bus bar interconnection and network interconnection. Only two-winding transformers are considered. The logic is also applicable to banks of three single-phase transformers. The following four conditions must be satisfied in order to avoid dangerous transient currents and for economical load sharing and successful parallel operation of two or more transformers: a) The same vector group (winding connections/phase-angle relation/clock-hour number) b) The same ratio with some tolerance and similar tapping range c) The same percentage impedance voltage with some tolerance (± 10%) (same relative short-circuit impedance This also means that the variation of relative impedance across the tapping range should be similar for the two transformers. When operating transformers in parallel, their relative impedances will determine how they share the load. Transformers will divide load in inverse proportion to their impedance (the transformer having less impedance will tend to carry more load and vice versa). Note that the impedances of two transformers should not be more than 10% apart for economical load sharing. d) The same power rating It is not advisable to combine transformers of widely different power rating (say, more than 1:2). The natural relative impedance for optimal designs varies with the size of the transformer. Rated power capacity ratio should be smaller than 3:1. In practice, a mismatch of relative loading of no more than about 10 % between two transformers of non-identical designs should be regarded as reasonable. 49 10.6 LOADING OF TRANSFORMERS – GUIDE FOR SHORT DURATION EMERGENCY AND CYCLIC OVER-LOADING OF POWER TRANSFORMERS (REFERENCE IEC 60354 LOADING GUIDE FOR OILIMMERSED POWER TRANSFORMERS AND IEC60905 LOADING GUIDE FOR DRY-TYPE POWER TRANSFORMERS) (THE SAME GUIDELINES ARE ALSO RECOMMENDED AND ISSUED BY THE DESIGN T&G DEPARTMENT VIDE # CED/NTDC/DSR/4675-84 DATED 17.20.2001) During normal operation of a transformer, in addition to its rated power for continuous loading, it can be temporarily over loaded within the permissible limits. The bushings, tap changers and other auxiliary equipment shall not to restrict the loading capabilities of the transformer. The power transformers in WAPDA system generally conform to IEC-60076 which can be overloaded to certain extent depending upon ambient air temperature and previous average loading condition of the transformers. In this regard details are given in IEC-60354 “Loading guide” for oil immersed transformers which may be gone through for more knowledge on the subject. However, convenience the salient points/instructions abstracted from the said IEC guide are given below for ready reference and knowledge of operational staff for implementation: 1. In normal cyclic duty (once in every 24 hours) the transformers can be overloaded up to 150% of its rated power in accordance with Table-1 to X. In these tables K1 indicates the average percentage load on transformer before over-loading. K2 indicates percentage load during the period of over loading and t indicates time in hours. 2. These tables are based on ambient air temperature of 0ºC, 10ºC, 20ºC, 30ºC and 40ºC. For operation at 50ºC ambient air temperature special consideration has to be made. 3. In emergency conditions (once in a few months) the transformer can be over loaded for short duration to the extent given in Table-1 to X below, provided that the winding hot spot temperature and top oil temperature do not exceed 140ºC and 115ºC respectively. The figure of 115ºC for top oil temperature is tentative in actual practice this value has to be limited to the temperature at which the conservator is completely full of oil. 4. The transformer is expected to work for its normal life span if operated continuously at a load such that winding hot spot temperature does not exceed 98 ºC. 50 For each 6 ºC rise in temperature above 98 ºC the transformer’s life is reduced to 50%. It means that a transformer expected to give service for 30 years if operated at 98 ºC winding temperature would run only for 15 years if operated continuously at 104 ºC. 5. As winding temperature and top oil temperature determine the effect of over loading on determination of the insulation and the resultant reduction of transformer’s life, utmost efforts should be made to keep the temperature gauges and the thermal protective devices in proper working order. TABLE –I ONAN and ONAF Transformers Ambient Air Temperature = 0ºC Values of K2 for given values on K1 and t t=0.5 t=1 t=2 t=4 t=6 t=8 t=12 t=24 K1=25 >200 200 178 151 138 132 125 116 K1=50 >200 200 173 148 137 131 125 116 K1=70 >200 194 167 145 135 130 124 116 K1=80 200 138 163 143 134 129 124 116 K1=90 200 181 158 140 132 128 123 116 K1=100 193 172 152 136 130 126 122 116 TABLE –II ONAN and ONAF Transformers Ambient Air Temperature = 10ºC Values of K2 for given values on K1 and t t=0.5 t=1 t=2 t=4 t=6 t=8 t=12 t=24 K1=25 >200 200 169 142 131 124 117 108 K1=50 >200 192 163 139 129 123 117 108 K1=70 >200 182 157 136 127 122 116 108 K1=80 199 176 152 133 125 121 116 108 K1=90 188 167 147 130 123 119 115 108 K1=100 173 154 137 124 119 115 112 108 51 TABLE –III ONAN and ONAF Transformers Ambient Air Temperature = 20ºC Values of K2 for given values on K1 and t t=0.5 t=1 t=2 t=4 t=6 t=8 t=12 t=24 K1=25 >200 189 159 134 123 116 110 100 K1=50 >200 180 153 131 121 115 109 100 K1=70 193 170 146 127 118 113 108 100 K1=80 183 162 141 124 116 112 107 100 K1=90 169 150 132 118 112 109 105 100 K1=100 100 100 100 100 100 100 100 100 TABLE –IV ONAN and ONAF Transformers Ambient Air Temperature = 30ºC Values of K2 for given values on K1 and t t=0.5 t=1 t=2 t=4 t=6 t=8 t=12 t=24 K1=25 >200 176 149 124 114 108 101 91 K1=50 192 168 142 121 111 106 100 91 K1=70 178 155 134 116 108 104 99 91 K1=80 164 145 126 111 104 101 97 91 K1=90 126 110 99 95 93 93 92 91 K1=100 - 52 TABLE –V ONAN and ONAF Transformers Ambient Air Temperature = 40ºC Values of K2 for given values on K1 and t t=0.5 t=1 t=2 t=4 t=6 t=8 t=12 t=24 K1=25 190 164 137 115 104 98 92 82 K1=50 177 154 130 110 101 96 91 82 K1=70 158 137 118 103 96 92 88 82 K1=80 118 104 95 88 86 84 83 82 K1=90 - K1=100 - TABLE –VI OFAF and ONWF Transformers Ambient Air Temperature = 0ºC Values of K2 for given values on K1 and t t=0.5 t=1 t=2 t=4 t=6 t=8 t=12 t=24 K1=25 177 163 147 133 127 123 119 114 K1=50 173 161 145 132 126 123 119 141 K1=70 168 155 142 131 126 122 119 114 K1=80 164 152 141 130 125 122 119 114 K1=90 160 149 138 129 124 122 118 114 K1=100 155 145 136 127 123 121 118 114 53 TABLE –VII OFAF and ONWF Transformers Ambient Air Temperature = 10ºC Values of K2 for given values on K1 and t t=0.5 t=1 t=2 t=4 t=6 t=8 t=12 t=24 K1=25 170 157 141 127 121 117 113 107 K1=50 165 153 138 126 120 117 113 107 K1=70 160 148 136 124 119 116 112 107 K1=80 156 145 134 123 119 115 112 107 K1=90 152 142 131 122 118 115 112 107 K1=100 145 135 126 119 115 113 110 107 TABLE –VIII OFAF and ONWF Transformers Ambient Air Temperature = 20ºC Values of K2 for given values on K1 and t t=0.5 t=1 t=2 t=4 t=6 t=8 t=12 t=24 K1=25 161 148 133 119 113 110 106 100 K1=50 157 144 130 118 112 109 105 100 K1=70 151 139 127 116 111 108 105 100 K1=80 146 136 125 115 110 108 105 100 K1=90 141 131 121 113 109 106 104 100 K1=100 100 100 100 100 100 100 100 100 54 TABLE –IX OFAF and ONWF Transformers Ambient Air Temperature = 30ºC Values of K2 for given values on K1 and t t=0.5 t=1 t=2 t=4 t=6 t=8 t=12 t=24 K1=25 153 140 125 113 107 103 99 92 K1=50 149 136 123 111 106 102 98 92 K1=70 142 131 119 109 104 101 98 92 K1=80 136 126 116 107 103 100 97 92 K1=90 120 111 104 99 96 95 94 92 K1=100 - TABLE –X OFAF and ONWF Transformers Ambient Air Temperature = 40ºC Values of K2 for given values on K1 and t t=0.5 t=1 t=2 t=4 t=6 t=8 t=12 t=24 K1=25 144 131 117 105 98 95 91 84 K1=50 139 127 114 103 97 94 90 84 K1=70 131 120 110 100 95 93 89 84 K1=80 119 109 100 94 90 89 86 84 K1=90 - K1=100 - 55