Injector/BC1 Commissioning (Jan. 2, 2006 through Aug. 31, 2007) P. Emma, et al. Facilities Advisory Committee Meeting Oct. 12, 2006 LCLS http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/index.html Oct. 12, 2006 LCLS FAC 1 Paul Emma Emma@SLAC.Stanford.edu LCLS Accelerator Schematic 6 MeV z 0.83 mm 0.05 % 4.30 GeV z 0.022 mm 0.71 % Linac-1 L 9 m rf -25° ...existing linac 21-1 b,c,d DL1 L 12 m R56 0 Linac-2 L 330 m rf -41° Linac-3 L 550 m rf 0° 21-3b 24-6d 25-1a 30-8c X BC1 L 6 m R56 -39 mm Commission in Jan. 2007 BC2 L 22 m R56 -25 mm Commission in Jan. 2008 SLAC linac tunnel Oct. 12, 2006 LCLS FAC 13.6 GeV z 0.022 mm 0.01 % Linac-X L =0.6 m rf= -160 Linac-0 L =6 m rf gun 250 MeV z 0.19 mm 1.6 % 135 MeV z 0.83 mm 0.10 % 2 undulator L =130 m DL2 L =275 m R56 0 research yard Paul Emma Emma@SLAC.Stanford.edu Complete & Detailed Optics (cathode to dump) dump cathode L2 BC2 L3 LTU undulator sec-21 sec-30 Full MAD files at: http://www-ssrl.slac.stanford.edu/lcls/linac/optics/ Oct. 12, 2006 LCLS FAC 3 Paul Emma Emma@SLAC.Stanford.edu LCLS Installation and Commissioning Time-Line Drive-Laser Commissioning undulator hall ready Drive-Laser Install LTU/und. Install linac/BC2 Install First FEL Light First Spont. Light J A SOND J FMAM J J A SOND J FMAM J J 2006 2007 2008 Gun/Inj./BC1 Gun/Inj./BC1 Install Commissioning (8/21 – 1/5) Oct. 12, 2006 LCLS FAC 4 linac/BC2 FEL Comm. Commissioning LTU/undulator Commissioning Paul Emma Emma@SLAC.Stanford.edu LCLS Injector Commissioning Dates (’06 - ’07) (dates will likely slip) July 24: Sector-20 ready for laser installation Aug. 29: Laser installation complete Dec. 18: Virtual cathode fully characterized (ready to install gun) Dec. 19: RF gun installation starts (10 days) + pre-beam checkout + laser rate switched to 30 Hz (5 days) Dec. 20-Jan. 1: Holidays Jan. 2: VVS’s switched on (RF power available) Jan. 12: First laser UV-light on cathode! Jan. 12-Feb. 4: Electrons in GTL and gun-spect. (RF processing L0a,b, L1, LX) Feb. 5: Beam into L0a, L0b and down to 135-MeV spect. Feb. 20: Beam into main linac (to TD11 dump) ~June: Take beam down full linac (to SL2 stopper) http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/documents/commissioning-dates-2006-2007.ppt Oct. 12, 2006 LCLS FAC 5 Paul Emma Emma@SLAC.Stanford.edu Commissioning Definition and Strategy All components installed, aligned, connected, and initially verified by system engineer, before commissioning starts. Commissioning Sequence – Layered Approach (0-3) 0. Pre-Beam Checkout (tunnel, gallery, control room) 1. Controls/software testing, camera checks, beamline inspection, etc 2. Magnet polarities, cable connections, verify motion-control, etc 1. Beam-based Hardware and Software Checkout Establish beam transport, RF setup, MPS/BCS tests, etc Checkout of all BPMs, magnets, wires, screens, toroids, etc 2. First-Order Optics: Measurement and Correction Steering, transmission, oscillation data, feedback setup, etc Beta and dispersion matching, beam-base align key quads, etc 3. Full Beam Characterization: Measurement and Correction Measure emittance, energy spread, distributions - correct Measure beam sensitivities, optimize tuning, beam experiments No (serious) emittance measurements until all hardware/software checked out! Oct. 12, 2006 LCLS FAC 6 Paul Emma Emma@SLAC.Stanford.edu (detailed schedule available) pass-1 pass-2 pass-3 pass-1 Oct. 12, 2006 LCLS FAC pass-2 7 Paul Emma Emma@SLAC.Stanford.edu pass-3 http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/documents/2007-commissioning-plan.doc Oct. 12, 2006 LCLS FAC 8 Paul Emma Emma@SLAC.Stanford.edu LCLS Injector Commissioning Day 24-Hour Cycle (7 days/week, 1/2/07 to 8/31/07, 35 total weeks) DAY SHIFT (8:00-16:00) 1 lead physicist, 1 physicist, 1 controls eng., 1 sys. engineer, 1 LCLS operator, 1 laser operator SWING SHIFT (16:00-24:00) 1 lead physicist, 1 physicist, 1 LCLS operator, 1 laser operator OWL SHIFT (0:00-8:00) 1 LCLS operator, 1 laser operator ? Oct. 12, 2006 LCLS FAC 9 Paul Emma Emma@SLAC.Stanford.edu Personnel Available for LCLS Injector/BC1 Commissioning Shift Leaders (initially) (1 per D/S shift) 1. Dave Dowell 2. Paul Emma 3. Jim Turner 4. Bill White (laser) 5. Joe Frisch 6. Cecile Limborg LCLS Physicists (1 per D/S shift) 1. Sasha Gilevich 2. Henrik Loos 3. Heinz-Dieter Nuhn 4. John Schmerge 5. Dave Schultz 6. Jim Welch 7. Juhao Wu Laser Operators (4-5) Oct. 12, 2006 LCLS FAC Controls eng. (1 per DAY shift) 1. Stephanie Allison 2. Mike Zelazney 3. Debbie Rogind 4. Diane Fairley 5. Stephen Norem 6. Arturo Alarcon 7. Doug Murray 8. Sergei Chevtsov 9. Dayle Kotturi 10. Patrick Krejcik 11. Kristi Luchini 12. Sheng Peng 13. Stephen Schuh 14. Till Straumann Operations (1 per DAY & SWING shift and 2 per OWL) 10 Sys. Engineers (1 per DAY shift) 1. Eric Bong 2. Carl Rago 3. Leif Eriksson 4. Richard F. Boyce 5. Jose Chan 6. Tim Montagne 7. Paul Bellomo 8. Antonio de Lira 9. Dave MacNair 10. Ron Akre Accelerator, ILC, SSRL 1. Franz-Josef Decker 2. Rick Iverson 3. Doug McCormick 4. Jeff Corbett 5. James Safranek... Visitors ? Paul Emma Emma@SLAC.Stanford.edu Manpower Requirements (1/2/07 - 8/31/07) 35 weeks total (1/2/07 to 8/31/07, minus 2 weeks) 80% coverage (downtime) 14 lead-physicist shifts/week 14 physicist shifts/week 7 controls eng. shifts/week 7 sys. engineer shifts/week Average of 2-3 shifts/week for each physicist Average of 1/2 shift/week for each controls eng. Average of 1 shift/week for each sys. engineer Oct. 12, 2006 LCLS FAC 11 Paul Emma Emma@SLAC.Stanford.edu LCLS Commissioning Parameters Parameter RF rate Value Comments 10-30 Hz 10 Hz in linac with possible 30-Hz rate - 120 Hz in gun for short time to verify full rate Beam rate ≤30 Hz 30 Hz e- beam as baseline – possible short term 120Hz tests in L0-BC1 for feedback tests, etc Drive-laser rate 30 Hz 120-Hz during laser commissioning – 30 Hz during ecommissioning - shutters provide lower e- rate 200-500 pC depends on QE and diagnostics – some short spans at 10 pC – later in ’07 explore 1-nC Bunch charge Drive-laser pulse length 10 ps fwhm 10-ps fwhm startup with possibility of 6-ps at 0.2 nC Gun gradient Set as goal, although 110 MV/m is adequate in ‘07 Oct. 12, 2006 LCLS FAC 120 MV/m 12 Paul Emma Emma@SLAC.Stanford.edu LCLS FAC http://wwwssrl.slac.stanford.edu/lcls/internals/commissioning/documents/l clsinjector-commissioninggoals.doc 2007 Injector Commissioning Goals Oct. 12, 2006 13 Paul Emma Emma@SLAC.Stanford.edu Issues Controls will be mixed (SLC, Epics, Matlab) and capabilities may be limited initially (H. Shoaee) Most High-Level Applications (emittance, bunch length, feedback) done through MATLAB as temporary solution Many LCLS physicists not experienced with existing SLC controls Help from operations group is essential Oct. 12, 2006 LCLS FAC 14 Paul Emma Emma@SLAC.Stanford.edu Q 1 nC RF f 120 Hz G 120 MV/m gex,y 1 mm Dt 10 ps I 100 A E 6 MeV Photo-Cathode Gun spec. dipole e- e- UV laser solenoid YAG screens RF gun cathode Oct. 12, 2006 LCLS FAC 15 Paul Emma Emma@SLAC.Stanford.edu RF Gun EN VA CU UM TR EA TM PU TC HAM MPS BER YAG screen YAG screen LO A S NG SE B EL M BL LO Y WS SP SE O OL AL S FR OM CA TH ODE UH GA V A TE LL VAL M ET VE AL S PO H O RCU LD PI E R NE VA LVE YAG screen YAG screen trajectory (BPMs) emittance (+ slice) energy spread (+ slice) bunch length (+ dist.) charge (+ dark current) YAG screen Transverse RF deflector OTR & wire gun spectrometer Injector Diagnostics OTR & wire OTR & wire OTR & wire main SLAC Linac injector spectrometer YAG Oct. 12, 2006 LCLS FAC 16 YAG & OTR Paul Emma Emma@SLAC.Stanford.edu Injector Through BC1 RF Gun & Solenoid L0a&L0b S-Band Linacs Transverse RF Cavity Bunch-Compressor-1 (BPM, OTR, collimator) OTR & Wire Scanners Gun Spectrometer L1 S-Band Linac Wire Scanners + OTR 135 MeV 250 MeV X-Band RF Straight Ahead Spectrometer Bunch Length Diagnostics 40 m Oct. 12, 2006 LCLS FAC 17 TD-11 stopper Paul Emma Emma@SLAC.Stanford.edu Accelerator Sections Straightened Coordinate Measurement Machine (CMM) after before (De/e 30%) Four RF sections measured on CMM and straightened (L0a, L0b, L1a, L1b) Jose Chan Oct. 12, 2006 LCLS FAC 18 Paul Emma Emma@SLAC.Stanford.edu Magnet Polarities Defined and Documented DIPOLES QUADRUPOLES Oct. 12, 2006 LCLS FAC SOLENOIDS 19 Paul Emma Emma@SLAC.Stanford.edu BPMs, Wire-Scanners, etc. Polarities Defined BPMs: Wire-Scanners: q=0 q = +45º q = -45º q = +45º Oct. 12, 2006 LCLS FAC 20 Paul Emma Emma@SLAC.Stanford.edu All Magnets Measured (all steering coil ‘types’) Dipole field vs. x Current vs. integrated field FINT = 0.454 Solenoid eff. length 2 Solenoids 19 Inj. Quads 2 GTL Quads 2 BC1 Quads 3 Linac Quads 2 DL1 Dipoles 4 BC1 Dipoles 2 Spect. Bends 6 corr. types Dipole fringe field vs. z + field harmonics Oct. 12, 2006 LCLS FAC 21 Paul Emma Emma@SLAC.Stanford.edu BC1 Chicane tweaker quad 2 0-30 cm translation stage tweaker quad 1 OTR collimator BPM X-band RF Oct. 12, 2006 LCLS FAC 22 Paul Emma Emma@SLAC.Stanford.edu BC1 Dipole Fields are Marginal tracking through fields measured with stretched wire De/e0 1 to 6 % Pole nose pieces in fabrication + tweaker quadrupoles available Oct. 12, 2006 LCLS FAC 23 Paul Emma Emma@SLAC.Stanford.edu Dispersion Correction in SPPS Chicane One linear comb. of 2 tweaker quads Oct. 12, 2006 LCLS FAC 24 Paul Emma Emma@SLAC.Stanford.edu Pre-Beam Tunnel Check List etc. Oct. 12, 2006 LCLS FAC 25 Paul Emma Emma@SLAC.Stanford.edu Summary Injector commissioning starts Jan. ’07 (may slide) Main ’07 goal is to verify full functionality of gun, injector beam-line, diagnostics, and controls, not generate full beam brightness immediately Will need frequent linac access initially (8-16 hrs/week?) + 1 install-day per month (24-48 hrs?) Phase-II of commissioning comes in Jan. ’08 Information will be available at ICW site: http://www-ssrl.slac.stanford.edu/lcls/workshops/lcls_icw_oct06/index.html ...under the link: “LCLS Commissioning”. Oct. 12, 2006 LCLS FAC 26 Paul Emma Emma@SLAC.Stanford.edu