Spring, 2007 ISE 102 Capacity Decisions Mahmut Ali GÖKÇE Industrial Systems Engineering Dept. İzmir University of Economics Week 1 Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics www.izmirekonomi.edu.tr 1 Spring, 2007 Review of Past Four Weeks Overview of Manufacturing (Service) Systems Problems and Methods Our job is (generally speaking) making the best decision i.e., optimization; Parameters of the model - acquire data Constraints – rules to be satisfied Objective function – define the best Solution Techniques – methodology to be used Forecasting – Generate data (it is a problem as well!) LP – A Simple solution technique Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 2 of 52 www.izmirekonomi.edu.tr Spring, 2007 This Week Capacity decisions Developing Alternatives - Considerations Using Cost-Volume Analysis to make decisions Make or buy decisions Decision Trees as a methodology to help making decision under uncertainty Location decisions Things to be considered Using Cost-Volume Analysis to make decisions Transportation Model Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 3 of 52 www.izmirekonomi.edu.tr Spring, 2007 Hierarchy of Decision Problems Strategic Decisions Location, capacity, new product, layout design, etc. Horizon: years Tactical Decisions Allocation, production planning, inventory, etc. Horizon: months-year Operational Decisions Scheduling, vehicle routing, assignment, etc. Minutes-hours-days Note that the “design” decisions will be an input for “operational” problems Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 4 of 52 www.izmirekonomi.edu.tr Spring, 2007 Capacity Planning Capacity can be defined as is the productive capability of a facility, usually measured as a quantity of output per unit of time Strategic capacity planning is an approach for determining the overall capacity level of capital intensive resources, including facilities, equipment, and overall labor force size. The basic questions in capacity handling are: What kind of capacity is needed? How much is needed? When is it needed? Management must review product and service choices periodically Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 5 of 52 www.izmirekonomi.edu.tr Spring, 2007 Three Levels of Capacity Planning Long-term Physical Medium-term Workforce planning Short-term detailed planning & control Our focus now is longterm . Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 6 of 52 www.izmirekonomi.edu.tr Spring, 2007 Capacity Decisions are Important • • • • • • Impacts ability to meet future demand – under capacity Affects operating costs – excess number of workers Major determinant of initial costs – fixed cost Involves long-term commitment – design decision Affects competitiveness – delivery speed Affects ease of management – over capacity Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 7 of 52 www.izmirekonomi.edu.tr Spring, 2007 Performance Measures Think of Your Typical Daily Schedule! • Design capacity – maximum obtainable output • Effective capacity – maximum capacity given product mix, scheduling difficulties, and other doses of reality. • Actual output – rate of output actually achieved--cannot exceed effective capacity Efficiency = Actual Output Effective capacity Utilization = Actual Output Design capacity Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 8 of 52 www.izmirekonomi.edu.tr Spring, 2007 Efficiency/Utilization Example Design capacity = 50 trucks/day Effective capacity = 40 trucks/day Actual output = 36 units/day Efficiency = Actual output = 36 units/day Effective capacity = 40 units/ day = 90% Utilization = Actual output = 36 units/day Design capacity = 500 units/ day = 72% Note that higher utilization is not always desired! Why? Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 9 of 52 www.izmirekonomi.edu.tr Spring, 2007 Capacity – Developing Alternatives • Before making strategic capacity decisions managers must consider; • Design flexibility into systems • Provisions for future expansions – adjacent land • Take a “big picture” approach to capacity changes • Extra rooms for the hotel requires extra parking lots • Prepare to deal with capacity “chunks” • Can’t buy buses with 35 seats; must be 48! • Attempt to smooth out capacity requirements • Complementary products – heating and AC. • Identify the optimal operating level • Economies of Scale and Diseconomies of Scale Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 10 of 52 www.izmirekonomi.edu.tr Spring, 2007 Economies & Diseconomies of Scale Average cost per unit Production units have an optimal rate of output for minimal cost. Minimum cost 0 Figure 5-3 Rate of output Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 11 of 52 www.izmirekonomi.edu.tr Spring, 2007 Economies & Diseconomies of Scale Average cost per unit Figure 5-4 Minimum cost & optimal operating rate are functions of size of production unit. 0 Small plant Medium plant Output rate Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 Large plant Q* (What about Demand?) 12 of 52 www.izmirekonomi.edu.tr Spring, 2007 Capacity – Evaluating Alternatives • One must examine different alternatives from different perspectives. Most obvious ones are economical consideration. Will it be feasible? Also one must consider public opinion. • A number of techniques are going to be discussed from an economical stand point • Cost-Volume analysis • Decision analysis • Financial analysis • Waiting line analysis. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 13 of 52 www.izmirekonomi.edu.tr Spring, 2007 Cost-Volume Analysis • Focuses on relationships between cost, revenue and the volume of the output. • The idea is to estimate the income of the company under different operating conditions and select the most appropriate one. • First step is identifying the all costs • Fixed costs (FC) : Tend to remain constant regardless of the volume of output; cost of land, heating, property tax, etc. • Variable cost (VC) : Vary directly with volume of output; raw materials, labor, etc. {VC=Q*v – where v is variable cost per unit) • Total Cost (TC) =FC+VC Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 14 of 52 www.izmirekonomi.edu.tr Spring, 2007 Cost-Volume Analysis • Revenue per unit(R) is the price of the product. • Total Revenue (TR) = R*Q • Profit (P) = TR – TC = R*Q – (FC + Q*v) • Rearranging the terms: P = Q(R-v) – FC • Q where we have no loss or no profit is known as breakeven point. • A figure worth hundred words… Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 15 of 52 www.izmirekonomi.edu.tr Spring, 2007 Cost-Volume Relationships Amount ($) Figure 5-5a Fixed cost (FC) 0 Q (volume in units) Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 16 of 52 www.izmirekonomi.edu.tr Spring, 2007 Cost-Volume Relationships Amount ($) Figure 5-5b 0 Q (volume in units) Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 17 of 52 www.izmirekonomi.edu.tr Spring, 2007 Cost-Volume Relationships Amount ($) Figure 5-5c 0 BEP units Q (volume in units) Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 18 of 52 www.izmirekonomi.edu.tr Spring, 2007 Cost-Volume Analysis • Capacity alternatives may involve step costs, e.g., a firm may have the options of purchasing one, two or three machines, with each machine fixed costs increases, perhaps not linearly. • Potential volume would depend on the number of machines purchased: implication is multiple break-even quantities. • Example: • A manager has the option of purchasing one, two or three machines. Fixed costs and potential volumes are as follows: MC# 1 2 FC Capaci $9600 ty $1500 301 0 to 0 600 300 Asst. Prof. Dr. Izmir University of Economics 3Mahmut Ali GÖKÇE, $2000 601 Week 1 0 900 Variable cost is $10 Revenue is $ 40 19 of 52 www.izmirekonomi.edu.tr Break-Even Problem with Step Fixed Costs Spring, 2007 Figure 5-6a 3 machines 2 machines 1 machine Quantity Step fixed costs and variable costs. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 20 of 52 www.izmirekonomi.edu.tr Break-Even Problem with Step Fixed Costs Spring, 2007 Figure 5-6b Number of Machines to be bought should be decided based on sales forecast. BEP $ BEP TC TC TC 3 2 1 Quantity Step fixed costs and variable costs. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 21 of 52 www.izmirekonomi.edu.tr Spring, 2007 Make or Buy? Sometimes a company requires “temporary” increase in the capacity. Such situations are handled with over time working, hiring more workers, etc. if the extra capacity needed (or constrained resource – or bottleneck resource) is labor force. Another possibility is outsourcing the production to external companies. This might be helpful particularly if extra machining hours is needed. Rather than investment on new machines it might be better to “rent” it. Cost volume analysis is helpful for these decisions. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 22 of 52 www.izmirekonomi.edu.tr Spring, 2007 Cost-Volume-Profit Analysis Example Alto, Inc. is planning to introduce a new model of student saxophone which will be sold for $500 each. If they produce it themselves, they will incur annual fixed costs of $1,000,000 and the variable cost of production will be $300 per unit. Another option is to subcontract production to Tenor, Inc. If they subcontract, then Tenor, Inc. will charge them $400 per unit. a. If Alto, Inc. decides to produce the saxophones themselves, what quantity is required for them to break even for the year? Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 23 of 52 www.izmirekonomi.edu.tr Spring, 2007 Cost-Volume-Profit Analysis Example b. What is the “indifference point” for these two options? Over what range of volumes would each option be preferred? c. If Alto, Inc. decides to produce the saxophones themselves, by how much would they have to reduce annual fixed costs in order to reduce their break-even volume to 3,000 units? Assume that revenues and variable costs remain the same. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 24 of 52 www.izmirekonomi.edu.tr Spring, 2007 Decision Making Under Uncertainty Sometimes the decision maker may not be certain about the future. The decision must be done under uncertainty For our purposes suppose that the uncertainty is in future demand and represented with certain probabilities associated with different possible scenarios. An example is as follows; Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 25 of 52 www.izmirekonomi.edu.tr Spring, 2007 Example of a Decision Tree Problem A glass factory specializing in crystal is experiencing a substantial backlog, and the firm's management is considering three courses of action: A) Arrange for subcontracting, B) Construct new facilities. C) Do nothing (no change) The correct choice depends largely upon demand, which may be low, medium, or high. By consensus, management estimates the respective demand probabilities as .10, .50, and .40. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 26 of 52 www.izmirekonomi.edu.tr Spring, 2007 Decision Trees Decision trees are methodologies that help us to handle these type of problems. One must first identify alternatives (course of actions), secondly possible sources of uncertainties (state of natures) and finally the payoffs (outcomes). Note that for each possible course of action and state of nature there will be a certain outcome. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 27 of 52 www.izmirekonomi.edu.tr Spring, 2007 Decision Trees In this problem we have three possible alternatives Arrange for subcontracting, Construct new facilities. Do nothing (no change) We have three possible states of nature Medium Demand Low Demand High Demand Suppose that each demand scenario (low, medium, high) is quantified with a number. Based on these demand values, fixed cost of new facilities, variable costs with new facilities, variable cost of subcontracting, and all other necessary data, we have already calculated a profit for each possible scenario. These profits are presented in the following “payoff table”. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 28 of 52 www.izmirekonomi.edu.tr Spring, 2007 Example of a Decision Tree Problem: Step 1. The Payoff Table The management estimates the profits when choosing from the three alternatives (A, B, and C) under the differing probable levels of demand. These costs, in thousands of dollars are presented in the table below: A B C 0.1 Low 10 -120 20 0.5 Medium 50 25 40 Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 0.4 High 90 200 60 29 of 52 www.izmirekonomi.edu.tr Spring, 2007 Decision Trees Next step is constructing the decision trees; Each decision is represented with a rectangle. Each alternative is an arc originated from this rectangle to the right side. Each chance event is represented with a circle. Each state of nature is an arc originated from this circle to the right side. All relevant data, probabilities, outcomes, etc. should be presented accordingly. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 30 of 52 www.izmirekonomi.edu.tr Spring, 2007 Step 2. Draw The Decision Tree High demand (.4) Medium demand (.5) Low demand (.1) A High demand (.4) B Medium demand (.5) Low demand (.1) $90k $50k $10k $200k $25k -$120k C High demand (.4) Medium demand (.5) Low demand (.1) Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 $60k $40k $20k 31 of 52 www.izmirekonomi.edu.tr Spring, 2007 Step 3. Calculate the Exp. Monetary Values Third step is known as rolling back the tree. For each chance event one must determine the expected monetary values that the chance event will yield For each decision node one must select the decision that yields the highest expected monetary return. In our simple example there are three chance events and after calculating expected return of these chance events there is only one decision to be made. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 32 of 52 www.izmirekonomi.edu.tr Spring, 2007 Step 2. Draw The Decision Tree High demand (.4) Medium demand (.5) $62k A B $80.5k Low demand (.1) High demand (.4) Medium demand (.5) Low demand (.1) $90k $50k $10k $200k $25k -$120k C High demand (.4) $46k Medium demand (.5) Low demand (.1) Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 $60k $40k $20k 33 of 52 www.izmirekonomi.edu.tr Spring, 2007 Step 4. Make decision High demand (.4) Medium demand (.5) $62k A B $80.5k Low demand (.1) High demand (.4) Medium demand (.5) Low demand (.1) $90k $50k $10k $200k $25k -$120k C High demand (.4) $46k Medium demand (.5) Low demand (.1) $60k $40k $20k Alternative B generates the greatest expected profit, so our choice is B or to construct a new facility. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 34 of 52 www.izmirekonomi.edu.tr Spring, 2007 Location Decisions Week 1 Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics www.izmirekonomi.edu.tr 35 Spring, 2007 Location Problem As the capacity decision, another important design parameter used as an input in operational decisions (transportationallocation, vehicle routing, inventory, etc.) is the location decisions. Some objectives; Maximize population coverage within an x-mile radius Minimize or limit the maximum travel distance for a customer (or raw materials) Minimize average transportation cost (or customer travel distance) Options include, expand existing facilities, add new facilities, move to a new location or do nothing! Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 36 of 52 www.izmirekonomi.edu.tr Spring, 2007 Location Decision Factors Regional Factors Community Considerations Site-related Factors Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 37 of 52 www.izmirekonomi.edu.tr Spring, 2007 Regional Factors Location of raw materials – perishability, transportation Canning fresh fruits, paper industry near forests, etc. Location of markets – convenience, responsiveness Retail stores, restaurants, etc. Labor factors – cost, availability High tech firms near metropolitans, Climate and taxes Nobody goes to Siberia! Foreign locations Less expensive areas, time zone differences in case of call centers! Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 38 of 52 www.izmirekonomi.edu.tr Spring, 2007 Community Considerations Desirability of the community; Quality of life Services Attitudes Taxes Environmental regulations Developer support Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 39 of 52 www.izmirekonomi.edu.tr Spring, 2007 Site Related Factors What about the construction sites? Land Transportation Environmental Legal Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 40 of 52 www.izmirekonomi.edu.tr Spring, 2007 Multiple Plant Strategies If the company has several sites may use; Product plant strategy Market area plant strategy Process plant strategy Multiple Plant Strategies Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 41 of 52 www.izmirekonomi.edu.tr Spring, 2007 Manufacturing vs. Service Considerations Manufacturing/Distribution Service/Retail Cost Focus Revenue focus Transportation modes/costs Demographics: age,income,etc Energy availability, costs Population/drawing area Labor cost/availability/skills Competition Building/leasing costs Traffic volume/patterns Customer access/parking Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 42 of 52 www.izmirekonomi.edu.tr Spring, 2007 Evaluating Locations Cost-Profit-Volume Analysis Determine fixed and variable costs for each alternative Plot total costs Determine lowest total costs Note that the fixed and variable costs includes all costs, land, labor, transportation, etc. Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 43 of 52 www.izmirekonomi.edu.tr Spring, 2007 Example 1: Cost-Volume Analysis Fixed and variable costs for four potential locations L o c a tio n A B C D F ix e d C ost $ 2 5 0 ,0 0 1 0 0 ,0 0 1 5 0 ,0 0 2 0 0 ,0 0 0 0 0 0 V a r ia b le C ost $11 30 20 35 How did you come up with these costs in the first place? Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 44 of 52 www.izmirekonomi.edu.tr Example 1: Solution for Output=10,000 Spring, 2007 Fixed Costs A B C D $250,000 100,000 150,000 200,000 Variable Costs $11(10,000) 30(10,000) 20(10,000) 35(10,000) Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 Total Costs $360,000 400,000 350,000 550,000 45 of 52 www.izmirekonomi.edu.tr Spring, 2007 Example 1: Solution $(000) 800 700 600 500 400 300 200 100 0 0 D B C A A Superior C Superior B Superior 2 4 6 8 10 12 14 16 Annual Output (000) Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 46 of 52 www.izmirekonomi.edu.tr Spring, 2007 Evaluating Locations (cont.) Transportation Model Decision based on movement costs of raw materials or finished goods Factor Rating Decision based on quantitative and qualitative inputs Center of Gravity Method Decision based on minimum distribution costs Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 47 of 52 www.izmirekonomi.edu.tr Spring, 2007 The Transportation Model While evaluating the best location alternative we use costs (fixed and variable). Particularly for multiple plant cases these costs can be identified after an allocation decision is made. That is to say we can’t calculate the cost of transportation from an alternative site to demand centers before we decide which demand centers are going to be served by which production site. This problem is known as allocation problem. The allocation problem with objective of minimizing the transportation cost is known as “transportation model”. Also after a location decision is made transportation problem must be solved to reduce the distribution costs! Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 48 of 52 www.izmirekonomi.edu.tr Spring, 2007 The Transportation Model Requirements: List of origins and each one’s capacity List of destinations and each one’s demand Unit cost of shipping Assumptions Items to be shipped are homogeneous Shipping cost per unit is the same Only one route between origin and destination Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 49 of 52 www.izmirekonomi.edu.tr Spring, 2007 The Transportation Problem: An Example D (demand) S (supply) D (demand) D (demand) S (supply) Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics Week 1 50 of 52 www.izmirekonomi.edu.tr Spring, 2007 Transportation Problem Network Representation (m = 2, n = 3) 1 d1 2 d2 3 d3 c11 s1 c12 1 c13 c21 s2 2 c22 c23 SOURCES DESTINATIONS Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics www.izmirekonomi.edu.tr Spring, 2007 Example: BBC Building Brick Company (BBC) has orders for 80 tons of bricks at three suburban locations as follows: Northwood -- 25 tons, Westwood -- 45 tons, and Eastwood -- 10 tons. BBC has two plants, each of which can produce 50 tons per week. How should end of week shipments be made to fill the above orders given the following delivery cost per ton: Plant 1 Plant 2 Northwood 24 30 Westwood 30 40 Eastwood 40 42 Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics www.izmirekonomi.edu.tr Spring, 2007 Example: BBC LP Formulation Decision Variables Defined xij = amount shipped from plant i to suburb j where i = 1 (Plant 1) and 2 (Plant 2) j = 1 (Northwood), 2 (Westwood), and 3 (Eastwood) Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics www.izmirekonomi.edu.tr Spring, 2007 Example: BBC LP Formulation Objective Function Minimize total shipping cost per week: Min 24x11 + 30x12 + 40x13 + 30x21 + 40x22 + 42x23 Constraints s.t. x11 + x12 + x13 < 50 (Plant 1 capacity) x21 + x22 + x23 < 50 (Plant 2 capacity) x11 + x21 = 25 (Northwood demand) x12 + x22 = 45 (Westwood demand) x13 + x23 = 10 (Eastwood demand) all xij > 0 (Non-negativity) Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics www.izmirekonomi.edu.tr Spring, 2007 Example: BBC Partial Spreadsheet Showing Optimal Solution A 10 11 Dec.Var.Values 12 13 14 15 16 17 18 19 B X11 C X12 D X13 E X21 F X22 G X23 5 45 0 20 0 10 Minimized Total Shipping Cost 2490 Constraints LHS P1.Cap. P2.Cap. N.Dem. W.Dem. E.Dem. 50 30 25 45 10 RHS <= <= = = = 50 50 25 45 10 Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics www.izmirekonomi.edu.tr Spring, 2007 Example: BBC Optimal Solution From Plant 1 Plant 1 Plant 2 Plant 2 To Amount Cost Northwood 5 120 Westwood 45 1,350 Northwood 20 600 Eastwood 10 420 Total Cost = $2,490 Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics www.izmirekonomi.edu.tr Spring, 2007 The Transportation Problem LP Formulation The linear programming formulation in terms of the amounts shipped from the origins to the destinations, xij, can be written as: Min SScijxij ij s.t. Sxij < si for each origin i j Sxij = dj for each destination j i xij > 0 for all i and j Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics www.izmirekonomi.edu.tr Spring, 2007 The Transportation Problem LP Formulation Special Cases The following special-case modifications to the linear programming formulation can be made: Minimum shipping guarantees from i to j: xij > Lij Maximum route capacity from i to j: xij < Lij Unacceptable routes: delete the variable Asst. Prof. Dr. Mahmut Ali GÖKÇE, Izmir University of Economics www.izmirekonomi.edu.tr