Document

advertisement
Four-Laning of Devihalli-Hassan Section from Km. 110.000 to Km.189.500 of NH-48
including a New 2-lane with paved shoulder bypass for Channarayapatna town and
widening of existing Hassan bypass to 2-lane with paved shoulder on DBFOT basis in
the state of Karnataka under NHDP Phase IIIA
MONTHLY PROGRESS REPORT
MONTH – April 2014
Report No. 38
Client
: National Highways Authority of India
Concessionaire
: L&T Devihalli - Hassan Tollway Limited
Independent Engineer : LEA Associates South Asia Pvt. Ltd
EPC Contractor
: Larsen & Toubro Limited
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL 2014
MONTHLY PROGRESS REPORT
FOR
Four-Laning of Devihalli-Hassan Section from Km. 110.000 to Km.189.500 of NH48 including a New 2-lane with paved shoulder bypass for Channarayapatna town
and widening of existing Hassan bypass to 2-lane with paved shoulder on DBFOT
basis in the state of Karnataka under NHDP Phase IIIA
DISTRIBUTION LIST: 1) PROJECT DIRECTOR, NHAI, BANGALORE
: 2 copies
2) INDEPENDENT ENGINEER
: 1 copy
3) L&T - IDPL, IMPLEMENTATION UNIT, Chennai
: 1 copy
CONFIDENTIALITY: The reader is reminded that neither this document, nor its contents, may be copied,
transcribed or replicated in part nor in full, without the written permission of L&T Devihalli Hassan Tollway
Ltd. Channarayapatna, which permission shall be entirely at the discretion of L&T Devihalli Hassan Tollway
Ltd. Channarayapatna.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL 2014
TABLE OF CONTENTS
ITEM
CHAPTER
Page No.
1
Introduction
1
2
Executive Summary
2
3
Project Location Map
4
4
Project Layout
5
5
Project Overview
6
6
Status of Preconstruction Activities
8
7
Progress of Works
10
8
Status of Physical/ Financial Activities
15
9
S Curve
16
10
Drawings Submitted to Authority/IE up to 30.11.2013
17
11
Schedule of Plant & Machinery
18
12
Status of Applicable Permits
19
13
Progress Strip Chart
20
14
Quality Control Report
36
15
Weather Report
74
16
Organization Chart
I) CONCESSIONAIRE
75
II) OPERATIONS & MAINTENANCE
76
III) EPC
77
17
Status of NCRs
78
18
Maintenance Activity Report
79
19
Safety Report
85
20
Accident Report
88
21
Progress Photographs
94
22
Annexures
96
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Page No: 1
1. INTRODUCTION
This monthly progress report covers for the period 1st April 2014 to 30th April 2014 as per the
article 13.1 of Concession Agreement.
The project Four- Laning of Devihalli - Hassan Section from Km. 110.000 to Km.189.500 of NH48 including a New 2-lane with paved shoulder bypass for Channarayapatna town and
widening of existing Hassan bypass to 2-lane with paved shoulder on DBFOT basis in the state
of Karnataka under NHDP Phase IIIA. The zero chainage of the project road commences at Km
107+684 near Devihalli Village. The project road then traverses towards west and runs
through a few rural / urban settlements, viz., Hirisave (Km 120+379), Channarayapatna (Km
139+677), Shanthigrama (Km 164+831), and ends at Km 184+912 at Hassan. The proposed
alignment follows existing alignment to a major extent and deviates from the existing
alignment at two locations. The alignment traverses mainly through plain and rolling terrain.
The major part of the proposed alignment passes through rural areas. The land use on both
sides of existing carriageway mostly falls under the category of agriculture.
The villages & towns found along the project highway are economically prosperous due to
coconut plantation & other commercial activities. The highway besides carrying normal goods
is a major arterial route to connect important tourist places, via, Shravana belagula, Belur,
Halebedu, Dharmasthala, Subramanaya, Horanadu etc.
The main corridor from Devihalli to Hassan enrooting 2 districts states, namely Mandya and
Hassan in the state of Karnataka. Section in Mandya district starts at km 107+684 and ends at
km 118+400 and section of Hassan district starts at km. 118+400 and ends at km 184+912.
The total length of the project road is 77.228 km.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Page No: 2
2. EXECUTIVE SUMMARY
M/s. National Highways Authority of India have identified the Devihalli to Hassan Road Sector (NH: 48
revised as NH: 75) to be widened to Four Lane from Km.110.000 to Km.189.500 including a new 2- lane
with paved shoulder bypass for Channarayapatna and widening of existing Hassan bypass to 2-lane
with paved shoulder on DBFOT basis in the State of Karnataka under NHDP Phase IIIA.
Feasibility study of this project was carried out by M/s. Secon, from Km 110+000 to Km 189+500 as
per CA provision.
NHAI has awarded the Contract for Project execution to M/s. L&T Devihalli Hassan Tollway Limited
on 17.06.2010. M/s L&T Devihalli Hassan Tollway Limited has given this project to M/s. Larsen &
Toubro Limited as EPC Contractor for execution.
To provide better level of service to the Vehicular Traffic, the existing Two-lane carriageway road sector
is proposed to be widened to Four Lane dual Carriageway including new Two lane bypass at
Channarayapatna and strengthening of the existing Two-lane Hassan bypass.
Enumeration of Trees and Estimates for Tree felling, utility shifting like Electrical and Water supply
were derived and the same was sanctioned by Authority during the Development period. Respective
works were taken up and completed tree felling and shifting of electrical and water supply works are
completed and few are balance, due to land constraints that has been dealt in separate sheet. Joint
Memorandum of site inventory was prepared and signed by both parties Authority and Concessionaire
on 14.12.2010.
Details on Design, drawings, Project Quality Plan, Project Safety Plan, Traffic Management Plan and
construction program time schedule for completion of the Project in accordance with the Project
Completion Schedule as set forth in Schedule – G. Work program has been approved for Completion
targeted to 10.06.2013 i.e. 30 months starting from 14th Dec’10. Further due to Delay in handing over
of Right of way and other issues, Independent Engineer has Recommened the Extension of Time upto
31st December 2013 vide their letter No. LASA/73384/D-H/IE/MD/1824 dated 17.09.2013, for which
Extension of Time is yet to be received from the Authority/IE.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Page No: 3
Authority appointed a qualified firm M/s HAKS consultant as Safety Consultant for safety audit of the
Project Highway. M/s HAKS Safety consultant had a site inspection on 27th September 2013.In order to
prevent injury or accidents, safety signs and barricading are being arranged at working zones. Safety
patrolling teams along with vehicles carrying all safety needs, boards etc., are deployed to comply the
traffic safety plan.
2.1 PHYSICAL PROGRESS:
Out of 77.228 kms,Commercial operation has been commenced for 59.700 kms on 14th November 2013
at Ch.116+790 Toll Plaza and on 15th November 2013 (due to public protest) at Ch.165+170 Toll Plaza.
In 59.700 Km New Bypass of Chennarayapatna town has been opend for the traffic and existing road
has been handed over to the Authority.
Further, work has been fully completed in all respects in 14.652 KMS for which PCOD is applied vide
our letter DHTL/CRP/IE/2013/765 Dated 11.12.2013 which is yet to be received by the concessionaire,
Excluding the COS (VUP) Stretch of 2.876 Kms. In VUP stretch, works are in progress.
The delay in issuance of COS order & Advance as per the Article 16 of Concession Agreemet affects the
progress of the work in the COS Stretches.
2.2 Delays/Slippage
The progress has been affected due to the following reasons,
1. Stoppage of works by public for demanding vehicular underpasses in 2 locations.
2. Non availability of land due to the Forest Land, land affected due to valuation issues & Major
Law & order issues, etc. due to the hindrances in bits & pieces has affected the progress of
work.
3. Due to unseasonal Rains
4. Non-availability of Aggregates as the permission of crusher has been banned on installation
of new stone crusher by the Hon'ble High Court of Karnataka appeal no.6616/7041 of 2011,
which affected the project progress.
2.3 ENVIRONMENTAL MANAGEMENT PLAN:
The Environmental Management Plan has been submitted vide letter No: DHTL/CRP/IE/2013/696
dated 21.08.2013 for the approval and the same is being implemented at the Project site.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 4
MONTH: APRIL - 2014
3.PROJECT LOCATION MAP
/
Devihalli
Devihalli
Hassan
Start of project Road
Channarayapatna
a
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Page No: 5
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 6
MONTH: APRIL - 2014
5.PROJECT OVERVIEW
The project Four- Laning of Devihalli - Hassan Section from Km. 110.000 to Km.189.500 of NH-48 including a
New 2-lane with paved shoulder bypass for Channarayapatna town and widening of existing Hassan bypass
to 2-lane with paved shoulder
The Project has a total length of 77.228 Km
Authority
: National Highways Authority of India.
Concessionaire
: L&T Devihalli Hassan Tollway Limited.
EPC Contractor
: M/s Larsen & Toubro Limited
Independent Engineer
: M/s LEA Associates South Asia Pvt Ltd
Design Consultant
: M/s Scott Wilson India Pvt Ltd
Concession Period
: 30 Yrs. incl. Construction period.
Construction Period
: 910 Days (Nine Hundred and Ten days from 14-12-2010)
Appointed Date
: 14-12-2010
Scheduled Four / Two Laning Date
: 10-06-2013
EOT Recommended
: 31-12-2013
Estimated Project Cost as per CA
: 453 Crores
Total Length of Road work
: 77.228 Km
Carriageway
: 4-Lane/2-Lane Carriageway.
STRUCTURES:
A. Minor Bridges
: 21 Nos
B. Slab Culverts
: 14 Nos
C. Pipe Culverts
: 66 Nos
D. Grade Separators
: Nil
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
ROADS
A. Main Road Works
Total Project
Length
:77.228 Km
4 - Lane Carriageway
:58.366 Km
2 - Lane Carriageway
:18.862 Km
B. At Grade Junctions
Major Intersections
: 11 Nos
Minor Junctions
: 19 Nos
LHS
: 28 Nos
RHS
: 28 Nos
C. Bus bay
D. Truck Lay Bye
:6 Nos.
E. Drain
F. Toll Plaza
LHS
:10.534 Km
RHS
:10.534 Km
: 2 Nos
: Ch.116+790 & Ch.165+170
Page No: 7
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 8
MONTH: APRIL - 2014
6. STATUS OF PRECONSTRUCTION ACTIVITIES
Preconstruction activities concerning clearances for construction of project highway is presented under this
head.
6.1
6.2
6.3
6.4
Joint Memorandum.
Land acquisition
Tree Cutting
Utility Shifting
6.1 Joint Memorandum:Joint Memorandum was completed and the same was signed with NHAI on 14.12.2010 with the land availability
at 72.52%
6.2 Land Acquisition:The Authority has intimated vide letter no NHAI/22023/1/12/PIU-BNG/3752 dated 18th March 2013, they
have handed over the Forest land by issuing the copy of lease agreement with Forest Department and
Authority. But, while referring the Lease Agreement, it has been executed for 20 years from the date of
Government order dated 7th December 2012. Whereas the Concession Agreement has been signed for
30 years, which in shortfall of 8 years between Concession period and Forest lease.
i.
Hence, the forest land to be handed over to the Concessionaire as per the Article 10 of the Concession
Agreement.
As per site condition availability of land for construction of MCW is given below, which was prepared based on
joint visit had on 30-11-2012 along with NHAI, IE & Concessionaire representatives and the same has been
updated.
Sl
No
1
2
Particulars
Four Lane
Carriage way
Two Lane
Carriageway
Total Length
Obstructed
Length due to
Valuation
(in Km)
Obstructed
Length due to
Law & Order
(in Km)
LHS
RHS
LHS
RHS
LHS
RHS
58.332
0.060
0.340
0.010
0
0.070
0.340
18.896
0
0
0
0
77.228
0.060
0.340
0.010
0
Total
Length
(in Km)
The Details of the above table is enclosed in Annexure - A
Total Obstructed
Length (in Km)
0
0.070
Percentage of
Clearance for
construction w.r.t
Total Length (in %)
LHS
RHS
99.88%
99.42%
100.00%
0.340
99.47%
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 9
MONTH: APRIL - 2014
6.2a Land Acquisition for Toll Plaza:
Authority vide letter no. NHAI/22015/1/10/PIU-BNG/4029 dated 06th January 2014 has intimated that land has
been cleared in Toll Plaza at Ch.116+790 and Ch.165+170 by issuing the possession certificate partially. But
actually concessionaire was not able to take up the works due to heavy protest from public, one of the land
owner Mr.Guruswamy brough INJUCTION SUIT from Court and insisting to stop entire activity in the Toll Plaza .
Due to which concessionaire were unable to take up the work. Further authority is requested to handover the
toll plaza balance land as per the Article 10 of the Concession Agreement.
6.2 b The Hindrances which are obstructing the balance puch list is enclosed in Annnexure E, The most of the
hindrances are due to Law & Order issues ascends due to various public demands such as Service Road, VUPs,
median opening, pedstrain under passes, Bus Shelter,etc. in which few are against the codal provisions. In this
regard the Local Admin is also not cooperating to resovle it and few hindracnes are also due to the payment
delays.
6.2 C The Hindraces which are affecting the COS Works are enclosed in Annexure F. Further are utilities which
needs to be reshifted due
6.3 Tree Cutting:
Tree cutting works are completed between ch.107.684 and 184.912. The reimbursement claim for cost incurred
in felling of trees is submitted vide the letter DH/CRP/PD/2012/141 dated 12th April 2012 is to be processed for
the payment by Authority at the earliest.
6.4 Electrical Utility Shifting:
Shifting, Erection of Electrical Poles & Stringing works are completed at Mandya District & Channarayapatna
Taluk, except in COS, VUP areas at Hiresave and Shanthigrama village. Utility shifting has been completed 98%
in Hassan Taluk. Balance works are pending only at COS areas . The detailed status is enclosed Annexure B.
6.4a Water Pipe Line Shifting and tank bunds:
The approved Estimates received on 14.02.11. Works are completed at Mandya District and 99% works are
completed at Channarayapatna Taluk, Hassan District and balance 1% are in progress at COS areas at Hiresave
and Shanthigrama Village. The detailed Status is enclosed in Annexure C.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 10
MONTH: APRIL - 2014
7. PROGRESS OF WORKS
The following works have been carried out during the month of April – 2014.


Highway

Clearing & Grubbing

Kerb Casting & painting

Earth work excavation

Laying of BC layer

Construction of Embankment

Median Plantations

Construction of Subgrade

Fixing KM stones

Construction of GSB layer

Road markings

Laying of WMM layer

Slope protection works

Laying of DBM layer

Safety crash barriers
Structures
Pipe culverts
Works in 58 pipe culverts has been completed and 8 are in progress in which 2 nos are in
repair and Rehabilitation and 6 nos are missing locations. Among 17 additional pipe culverts
17 are completed and 1 irrigation Pipe culvert also completed under Change of Scope.
Box culverts
Works in 14 Box culverts have been completed. The 2nos of additional Box culvert has been
completed and 3 nos of Irrigation Box Culvert also completed under change of scope.
Minor Bridges
Works in 21 Minor Bridges have been completed and 1 additional Minor Bridge has been
completed up to Deck slab.

Toll Plaza
1. Toll Plaza @ Ch.116.790 - Toll Plaza works are completed in the available land and
Commercial operation started on 14.11.2013. (Detailed strip chart enclosed as
Annexure D)
 Partially Land handed over to Concessionaire on 09.10.2013 vide letter no:
NHAI/22051/1/10/PIU-BNG/2781 dated 31.10.2013, NHAI/22012/1/10/PIUBNG/3796 dated 24.12.2013 and NHAI/22012/1/10/PIU-BNG/4029 dated
06.01.2014 and work is in progress.
2. Toll Plaza @ Ch.165.170 - Toll Plaza works are completed in the available land and
Commercial operation started on 15.11.2013. (Detailed strip chart enclosed as Annexure D)

Land handed over partially to Concessionaire on 09.10.2013 vide letter no:
NHAI/22051/1/10/PIU-BNG/2781 dated 31.10.2013, due to which we are unable to
take up the works.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 11
MONTH: APRIL - 2014
Due to the payment delays, valuation problems, Law & order issues, the work could not be taken up as
scheduled. The physical progress achieved so far is as follows,
Sl.
No
Unit
Total
Scope
Completed
up to March
2014
(Linear)
Km
58.33
58.33
Km
58.33
56.9
Sub grade
Km
58.33
57.04
GSB
Km
58.33
56.84
WMM
Km
58.33
56.54
DBM
Km
58.33
56.24
BC
Km
58.33
55.80
Kerb
Km
53.47
52.50
Description
of the Work
A. 4 Lane Carriage way
1
Clearing&
Grubbing
2
Earth work
3
4
5
6
7
8
During this
Month April
2014
-
Completed
up to April
2014
58.33
56.9
57.04
% of Work
Completed
100.00%
97.55%
97.79%
56.84
97.45%
56.54
96.93%
56.24
96.42%
55.80
95.66 %
-
52.50
98.19 %
During this
Month April
2014
Completed
up to April
2014
% of Work
Completed
-
B. 2 Lane Carriageway in widening & strengthening/Hassan Bypass
S.No
Description
Unit
Total
Scope
Completed
up to March
2014
(Linear)
1
Clearing&
Grubbing
Km
9.749
9.749
-
9.749
100%
2
Earth Work
Km
9.749
9.749
-
9.749
100%
3
Sub grade
Km
9.749
9.749
-
9.749
100%
4
GSB
Km
9.749
9.749
-
9.749
100%
5
WMM
Km
9.749
9.749
-
9.749
100%
6
DBM
Km
9.749
9.749
-
9.749
100%
7
BC
Km
9.749
9.749
-
9.749
100%
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 12
MONTH: APRIL - 2014
S.No
Description
Unit
Total
Scope
Completed
up to March
2014
During this
Month April
2014
Completed
up to April
2014
% of Work
Completed
(Linear)
C. 2 Lane Carriageway in New Construction/ Channarayapatna Bypass
1
Clearing&
Grubbing
Km
9.147
9.147
-
9.147
100.00%
2
Earth Work
Km
9.147
9.147
-
9.147
100.00%
3
Sub grade
Km
9.147
9.147
-
9.147
100.00%
4
GSB
Km
9.147
9.147
-
9.147
100.00%
5
WMM
Km
9.147
9.147
-
9.147
100.00%
6
DBM
Km
9.147
9.147
-
9.147
100.00%
7
BC
Km
9.147
9.147
-
9.147
100.00%
D. Summary of Work Status of Pipe Culverts
Sl.
Location/
Total
No.
No
Road
No
Taken
Status of Completed Work Progress
Excavation
PCC
Cradle
Pipe
concrete laying
Head
Remarks
Wall
2 No’s are in
1
Four Laning
44
42
42
42
42
42
42
COS area &
Work in
progress
2
3
CR Patna
Bypass
Hassan
Bypass
Total
03
03
03
03
03
03
03
19
13
13
13
13
13
13
66
58
58
58
58
58
58
6 no’s only
Rehabilitation
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 13
MONTH: APRIL - 2014
E. Summary of Work Status of Box Culverts
Status of Completed Work Progress
Sl.No
Location/ Road
Total No No.Taken
Remarks
Foundation
Sub
Deck Slab
Structure
1
Four Laning
14
14
14
14
14
2
CR Patna Bypass
-
-
-
-
-
3
Hassan Bypass
-
-
-
-
-
14
14
14
14
14
Total
F. Summary of Work Status of Minor Bridges
Sl.No
Location/
Total
Road
No
Status of Completed Work Progress
No.Taken
Remarks
Foundation
Sub
Deck Slab
Structure
1
Four Laning
17
17
17
17
17
2
CR-Patna Bypass
04
04
04
04
04
3
Hassan Bypass
-
-
-
-
-
21
21
21
21
21
Total
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 14
MONTH: APRIL - 2014
G. Additional Structures:
Status of Completed Work Progress
Sl.No
1
Particulars
Total No No.Taken
Pipe Culverts
Excavation
PCC
Cradle
concrete
Pipe
laying
Head
Wall
Remarks
17
17
17
17
17
2 No’s only
Rehabilitation
17
17
No.
Status of Completed Work Progress
Foundation Sub Structure Deck Slab
Sl.No
Particulars
Total No
2
Box Culverts
2
2
2
2
2
3
3
3
3
3
Minor Bridge
1
1
1
1
1
Sr.
No.
Type of Structure
Scope
1
VUP
1
Hirisave Ch: 122.300
2
VUP - MDR
crossing
1
Bagur Road Ch : 145.220
3
VUP
1
Shanthigrama Ch : 166.450
Taken
3
Irrigation box
culverts
4
Sr.
No.
1
Type of Structure
Location
Scope
Service Road @ Udaypura
1
Remarks
Status of work
Retaining Wall Works under Progress
Completed
Retaining Wall Works under Progress
Total length
Completed length
Remarks
250mts - LHS
---
250mts - RHS
---
Land not
Handed over
by NHAI
1. DHTL/CRP/IE/2012/ 514 dated 31.12.2012,
2. DHTL/CRP/IE/2013/ 516 dated 02.01.2013,
3. DHTL/CRP/IE/2013/ 594 dated 26.03.2013,
4. DH/CRP/PD/2013/ 246 dated 31.01.2013.
5. DHTL/CRP/IE/2013/601 dated 05.04.2013
Further the Advance payment has been requested to Authority/IE through above letters. Which is to be
expedited and these factors are affecting progress of COS structures of 2No’s VUP due to huge financial
implication.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 15
MONTH: APRIL - 2014
Progress of Retaining wall for VUP @ Ch. 121+840
Sl No
Particualars
Unit
Total Scope
LHS
1)
2)
3
RHS
Completed on
LHS
April-14
RHS
Cumulative
Completed
LHS
RHS
Bangalore Side (Ch.121.740 to Ch.121.834)
Excavation
M
94
64
PCC
M
94
64
81.750
51.700
Raft
M
94
64
62
51.750
Wall
M
94
64
62
51.750
Hassan Side ( Ch.121.846 to Ch.121.920)
Excavation
M
74
74
PCC
M
74
74
61.750
61.750
Raft
M
74
74
62
61.750
Wall
M
74
74
62
61.750
Approaches - MCW (Other than VUP Approaches)
Bangalore Side (Ch.121.300 to Ch.121.770) & Hassan Side (Ch.122.700 to Ch.121.920)
Embankment
M
1250
90
180
SG
M
1250
90
480.000
GSB
M
1250
0
440.000
WMM
M
1250
0
760
DBM
M
1250
0
340
BC
M
1250
0
0
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 16
MONTH: APRIL - 2014
Progress of Service Road for VUP @ Ch. 121+840
Sl No
Particualars
Unit
Total Scope
LHS
RHS
Completed on
LHS
April-14
Cumulative
Completed
RHS
LHS
RHS
Service Road (Ch.121+380 to Ch.122+320) including taper portion
1
Clearing & Grubbing
M
940
940
0
0
150
520
2
Earth Work
Excavation
M
940
940
0
520
320
700
3
Earth Work
Embankment
M
940
940
80
290
580
590
4
Sub Grade
M
940
940
150
-200
570
500
5
GSB
M
940
940
100
13
280
490
6
WMM
M
940
940
0
-395
270
430
7
DBM
M
940
940
0
-10
0
430
8
SDBC
M
940
940
0
0
0
0
Progress of Retaining wall for VUP @ Ch. 166+432
Sl No
Particualars
Unit
Total Scope
LHS
1)
RHS
Completed on
April-14
Cumulative
Completed
LHS
RHS
LHS
RHS
Bangalore Side (Ch.166.200 to Ch.166.426)
Excavation
M
226
236
PCC
M
226
236
0.6
11.8
166.6
221.8
Raft
M
226
236
0
10
0
180
Wall
M
226
236
0
150
0
250
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 17
MONTH: APRIL - 2014
Sl No
Particualars
Unit
Total Scope
LHS
2)
RHS
Completed Aprilon
14
LHS
RHS
Cumulative Completed
LHS
RHS
Hassan Side ( Ch.166.438 to Ch.166.447)
Excavation
M
9
9
PCC
M
9
9
Raft
M
9
9
Wall
M
9
9
Approaches - MCW (Other than VUP Approaches)
Bangalore Side (Ch.165.700 to Ch.166.200) & Hassan Side (Ch.166.447 to Ch.167.176)
Embankment
M
1229
0
0
0
120
SG
M
1229
0
40
0
40
GSB
M
1229
0
0
0
0
WMM
M
1229
0
0
0
0
DBM
M
1229
0
0
0
0
BC
M
1229
0
0
0
0
Service Road (Ch.165+835 to Ch.166+800) including taper portion
1
Clearing & Grubbing
M
965
965
2
Earth Work Excavation
M
965
965
3
Earth Work Embankment
M
965
965
4
Sub Grade
M
965
965
5
GSB
M
965
965
6
WMM
M
965
965
7
DBM
M
965
965
8
SDBC
M
965
965
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.`
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 19
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
8.Status of Physical/ Financial Activities
Sl
No
Description
Scope
Cost (in
Wt(%)
Lakhs)
Planned Wt
(%)
Up to March’14
Achieved Wt
Cost (in Lakhs)
(%)
Planned Wt
(%)
This Month April’14
Achieved Wt
(%)
Cost (in
Lakhs)
Planned Wt
(%)
Up to April’14
Achieved Wt
(%)
Cost (in
Lakhs)
1.PRELIMINARIES-A
1.1
Survey, Design & Investigation
2.00
906.17
2.00
2
906.17
2.00
2.00
906.33
2.Construction Works
2.1
Site Clearance
2.2
Earthwork
2.3
Subgrade
0.33
8.69
3.50
150.77
3937.37
1583.58
0.33
8.68
3.41
0.33
8.68
3.41
150.77
3932.8391
1542.8594
0.33
8.69
3.50
0.33
8.68
3.41
149.41
3934.12
1544.77
7.84
8.54
1.23
21.14
12.10
3549.46
3869.16
554.96
9575.53
5480.28
7.42
8.04
1.07
19.830
11.30
7.42
8.04
1.07
19.83
11.3
3359.3104
3642.6284
482.77008
8982.1552
5117.9474
7.84
8.54
1.23
21.14
12.10
7.42
8.04
1.07
19.830
11.30
3363.03
3641.77
485.95
8984.46
5117.60
3.28
1486.98
2.60
2.6
1178.7037
3.28
2.60
1177.97
4.56
3.74
0.52
2066.03
1692.97
233.60
3.79
3.72
0.52
3.79
3.72
0.52
1717.1609
1683.9167
233.6
4.56
3.74
0.52
3.79
3.79
0.52
3958.53
1715.603
233.42
3
3.Pavement works
3.1
GSB
3.2
WMM
3.3
Kerb
3.4
DBM/PCC
3.5
BC
4.Drainage & Protection Works
4.1
Drain works & Turfing
5.Road Furniture
5.1
Road furniture
5.2
Exit/Entry Ramps & Intersections
5.3
Plantation
6.CD WORKS
6.1
Box culvert
6.2
Pipe culvert
7.Structural Works
7.1
Minor Bridge
8.Project Facilities
8.1
Truck layby
8.2
Bus bay
9.Toll Plaza
9.1
Toll Plaza
10.Miscellaneous
10.1 Bridge Rehabilitation
10.2 Maintenance
10.3 Video Recording, MPRs, Maintenance of
Vehicles, Laboratory
10.4
Mobilization of Plant & Machinery, Base
camp, Office set-up, Remuneration for staffs
Total
0.07
31.687
0.73
1.05
330.31
477.10
0.73
1.05
0.73
1.05
330.31
477.1
0.73
1.05
0.73
1.05
330.24
477.16
5.34
2417.33
5.34
5.34
2417.33
5.34
5.34
2417.32
0.88
1.78
397.28
805.90
0.88
0.88
0.88
1.78
397.28
1.78
397.28
805.9
0.88
1.78
1.78
805.89
3.33
1508.23
3.25
3.25
1471.9962
3.33
3.25
1474.12
0.88
1.32
3.31
400.00
600.00
1500.00
0.88
1.32
3.31
0.88
1.32
3.31
400
600
1500
0.88
1.33
3.31
0.88
1.32
3.31
400.00
599.51
1499.96
3.92
1777.11
3.92
3.92
1777.11
3.92
3.92
1777.12
100.00
45300.12
100.00
95.17
43107.857
100.00
95.24
43139.54
4
0.07
31.687
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.`
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
9. S – CURVE:
Page No: 19
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 20
MONTH: APRIL - 2014
10. DRAWINGS SUBMITTED TO AUTHORITY/IE
DESCRIPTION
UNIT
SCOPE
SUBMITTED
TO IE
DETAILS
SUBMITTED
APPROVED
BY IE
GFC
REMARKS
1
ROADS
kms
77.228
77.228
Plan &
profile
77.228
77.228
Approved on 20th
September 2012
2
PAVEMENT
DESIGN
kms
1
1
Pavement
Design
3
MINOR
BRIDGE
Nos
21
21
4
BOX
CULVERT
Nos
14
14
5
PIPE
CULVERT
Nos
66
66
6
TOLL PLAZA
Nos
2
2
7
TRUCK LAY
BYE
Nos
6
6
8
BUS LAY
BYE
Nos
56
9
Major
Junctions
Nos
10
Minor
Junctions
11
S.NO.
Approved on
25thJan 2012
1
1
21
21
Approved on 19th
March 2012
Design &
Drawings
14
14
Approved on 19th
March 2012
Design &
Drawings
66
66
GFC issued
2
2
Approved on
29.04.2013
Plan & Cross
Section
6
6
Approved
56
Working
Drawings
56
56
Approved
11
11
Working
Drawings
11
11
Approved
Nos
19
19
Working
Drawings
19
19
Approved on 22nd
August 2013
Drain
Km
21.068
21.068
TCS
21.068
12
VUP
Nos
3
3
Design&
Drawings
3
3
Approved
13
Alternate
Pavement
Design for
7Km
7
Alternate
Pavement
Design
7
7
Approved.
Km
7
21.068 Approved
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 21
MONTH: APRIL - 2014
11. STATUS OF MAJOR PLANT & MACHINERY
S.NO
TYPE OF MACHINERTY
1
Excavators
2
CAPACITY
1.1 cum
MODEL
TOTAL
PC 200 L&T Komatsu,JCB 210
5
Graders
GD 511A L&T Komatsu
5
3
Dozer
D41E L&T,CAT
1
4
Soil Compactors
Trench Compactor
L&T1107D, BW 212AD,EC 5250
PD 120 AD
BW
4
5
6
Tandam Rollers
IR IDD 90
3
7
Pneumatic Tyre Roller(PTR)
IR220
1
8
Pavers
400 TPH
BITELLI ,APOLLO
2
9
Bitumen Tanker
5 KL
Comet Leyland
2
10
Water Tankers
20 KL,15 KL, KL
2516 Leyland,Hmt Tractor
7
11
Taurus
10 m3
Leyland 2516
20
12
Tipper
4 m3
Leyland comet
5
13
Tractors
2 m3
HMT,MAHENDRA
2
14
Wheel Loaders
3 m3(5 T)
Changlin ZL50H
4
15
Hydra crane
12 T,10T
ACT 12 XW,
2
16
Truck Mounted Crane
10T - 50T
XCMG QY50 K
1
17
RMC Batching Plant
30 cum/hr
CP30 ,Stetter
2
18
WMM Plants
100 TPH,250 TPH
APPOLLO
2
19
Hot Mix Plants
200 TPH
BF 2500 ,DMI Corporation
1
20
Crusher Plants
400 TPH,200TPH
Swedela,PUJULONA
3
21
Gensets
500 kva,400
kva,380kva,62.5kva,50kva,15
kva,10 kva,5 kva
18
22
Compressors
165 PSI
IR HP 400,Tractor compressor
1
23
Kerb Machine
KP 40
KP 40, Appollo
1
24
Light Vehicles
Bolero,sumo,tavera,omini,indica
6
25
Motor Bikes
HeroHonda,TVS
11
26
Hydraulic boomer
27
Transit Mixers
6 CUM
2516 Leyland,
5
28
Trailer
40 Tons
LEYLAND
2
29
Hindustan Dumpers
40 Tons
Hindustan
2
30
Crawler
Atlascopco
1
31
JCB
32
Mobile Diesel Tanker
33
Bolero Camper
34
Weigh Bridge
35
Rig
1
1
3
8 KL
2
3
100T,80T,60T
2
1
REMARKS
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 22
MONTH: APRIL - 2014
12.STATUS OF APPLICABLE PERMITS
Sl No
Statutory Requirement
Status
1
Permission of State Government for extraction of Obtained from the Mining department.
boulders from quarry
2
Permission of Village Panchayat and Pollution Obtained for the CFE (Concent For Establishment) 0n
Control Board for installation of crushers
10.02.2012 & CFO (Concent For Operation) yet to be
receive.
3
License for the use of explosives
Available.(Planning for usage from licensed vendor)
4
Permission of the State Government for drawing
of water from river/reservoir
Water not planned to draw from river or reservior
5
License from Inspector of factories or other
competent authority for setting up Batching Plant
Not Applicable as there is no commercial sale of
concrete from batching plant.
6
Clearance of Pollution Control Board for setting up
Batching Plant
Obtained for the operation
7
Clearance of Village Panchayat and Pollution
Control Board for Asphalt Plant
Obtained concern from KSPCB for HMP & WMM
Plant establishment at km.162 vide letter
no.16/KSPCB/EO(HSN)/AEO/SR/2012-13/547 dated
10.07.12, CFO obtained on 10.07.2012,
8
Clearance of Village Panchayats and State
Government for borrow earth
Mining permits obtained from mining department,
Karnataka.
9
Permission of State Government for cutting of
trees
Obtained for the Entire Project
10
Any other permits or clearances required under
Applicable Laws
Labour license obtained
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
DEVIHALLI HASSAN TOLLWAY LIMITED (DBFOT PROJECT)
PROGRESS CHART
Page No: 23
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
DEVIHALLI HASSAN TOLLWAY LIMITED (DBFOT PROJECT)
PROGRESS CHART
Page No: 24
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
DEVIHALLI HASSAN TOLLWAY LIMITED (DBFOT PROJECT)
PROGRESS CHART
Page No: 25
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
DEVIHALLI HASSAN TOLLWAY LIMITED (DBFOT PROJECT)
PROGRESS CHART
Page No: 26
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
PROGRESS OF BOX CULVERTS as on 30.04.2014
MONTH: OCTOBER -2012
Page No: 27
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
PROGRESS OF BOX CULVERTS as on 30.04.2014
MONTH: OCTOBER -2012
Page No: 28
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
PROGRESS OF BOX CULVERTS as on 30.04.2014
MONTH: OCTOBER -2012
Page No: 29
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 30
MONTH: APRIL - 2014
PROGRESS OF IRRIGATION BOX CULVERTS as on 30.04.2014
MONTH: OCTOBER -2012
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
PROGRESS OF PIPE CULVERTS as on 30.04.2014
MONTH: OCTOBER -2012
Page No: 31
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
PROGRESS OF PIPE CULVERTS as on 30.04.2014
MONTH: OCTOBER -2012
Page No: 32
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
PROGRESS OF PIPE CULVERTS as on 30.04.2014
MONTH: OCTOBER -2012
Page No: 33
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 34
MONTH: APRIL - 2014
PROGRESS OF ADDITIONAL PIPE CULVERTS as on 30.04.2014
MONTH: OCTOBER -2012
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
PROGRESS OF MINOR BRIDGES as on 30.04.2014
MONTH: OCTOBER -2012
Page No: 35
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
PROGRESS OF MINOR BRIDGES as on 30.04.2014
MONTH: OCTOBER -2012
Page No: 36
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
MONTH: OCTOBER -2012
Page No: 37
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 38
MONTH: APRIL - 2014
Progress of VUPs at Ch.121+840
LHS Side
MONTH: OCTOBER -2012
Hassan Side
Bangalore Side
62 m Final Lift
Completed
62 m 1st Lift Completed
62 m Raft Completed
62 m PCC Completed
11 m
20
80 m PCC Completed
62 M
80 M
RHS Side
Bangalore Side
51 m Wall Final Lift Compleed
51 m Wall 1st Lift Completed
51 m Raft Completed
51 m PCC Completed
64 M
Hassan Side
60 m Wall Final Lift Completed
60 m Wall 1st Lift Completed
60 m Raft Completed
60 m PCC Completed
62M
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 39
MONTH: APRIL - 2014
Progress of VUPs at Ch.166+432
Bangalore Side
226 M
MONTH: OCTOBER -2012
Hassan Side
9M
RHS Side
Bangalore Side
2
0
m
Hassan Side
20m
Final Lift
20 2nd
Lift
F
i
210 m PCC Completed
236 M
9M
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 40
MONTH: APRIL - 2014
QUALITY CONTROL REPORT
Objective: The objective is to establish a well-equipped QC laboratory and Technically Organized personnel in
MONTH: OCTOBER -2012
the Quality Control and Quality assurance, Quality system in works. It is to Create Working Procedures and
Technical Procedures in implementation and Documentation in accordance to the Project Contract Specification.
Produce and Create a Qualitative Construction Materials In Terms Of Design Mix and Methodology so as to
achieve the above Objectives. Identify the source / preparation of Design Mixes before commencing the
Construction of Work and periodically reviewing when changes in Source and Design Mixes during Construction
so as does not delay the projected completion of the Project. By creating a report on the QC Test and Frequency
on Lab and Field and a statistical report on the Field Test on a monthly basis.
Quality Assurance:
A detailed Project Quality Plan has been prepared with detailed construction activities
methodology and Quality Assurance Plan with Acceptance Criteria. Necessary mix design and job mix formula
has been prepared for GSB, WMM, DBM, BC and concrete works. As per IRC SP 57:2000 and IRC SP 47: 1998 has
been followed for Quality assurance of Q3 standards. Pertaining to IRC SP 84: 2009 of CA, QAM covering Quality
System and QAP has been implemented in the project work.
MATERIALS: All borrow materials source like soil, water, aggregate, sand, cement, steel; Bitumen, Emulsion
admixture and Hume pipes have been identified. Source of locations are shown in project Key plan.
Borrow soil: Borrow soil locations are identified for the construction of embankment and subgrade in the project
stretch. All relevant test as per specifications have been conducted.
The status of Borrow soil is tabulated below:
Sl No
Borrow locations
identified
Submitted for IE
Approval
Borrow area
approved
1
45
36
36
A summary of all borrow soil locations, Quantities are also tabulated below:
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 41
MONTH: APRIL - 2014
Qty Used
As on
date Jan
2014
Balance
Qty
Status
S.No
Borrow area
Chainage
MONTH:
OCTOBER
Lead
From -2012
Qty as per
Side
NH -48
Drawing
1
B.A. 01
115+510
RHS
1.0 km
32000
12460
19540
Approved
2
B.A. 02
119+435
RHS
200 m
30000
0
30000
3
B.A. 03
126+500
RHS
3.6 Km
60000
8628
51372
Approved
Approved
4
B.A. 04
116+625
RHS
0.6 Km
20000
4627
15373
Approved
5
B.A. 05
116+800
LHS
300 m
22500
22226
274
Approved
6
B.A. 06
133+100
LHS
2.0 Km
60000
42304.9
17695.1
Approved
7
B.A. 07
127+660
RHS
1.0 + 0.2 Km
15000
15000
0
Approved
8
B.A. 10
148+000
LHS
0.5Km
13500
0
13500
Approved
9
B.A. 11
151+900
LHS
200 m
22500
22500
0
Approved
10
B.A. 13
153+085
LHS
3.0 Km
18000
18000
0
Approved
11
B.A. 14
116+860
LHS
0.3 Km
15000
5820
9180
Approved
12
B.A. 15
136+330
RHS
0.3 Km
13500
13500
0
Approved
13
B.A. 16
111+230
LHS
0.3 Km
14400
8137
6263
Approved
14
B.A.17
144+240
RHS
4.0 Km
24750
24750
0
Approved
15
B.A.18
137+300
RHS
3.0 Km
28125
28125
0
Approved
16
B.A.19
158+000
RHS
250 m
60000
44472
15528
Approved
17
B.A.20
141+430
RHS
3.5 + 0.5 Km
24000
17436
6564
Approved
18
B.A.21
127+660
RHS
1.5 Km
30000
26026
3974
Approved
19
B.A.22
127+660
RHS
1 Km
22500
1047
21453
Approved
20
B.A.23
143+500
BHS
3 Km
24000
3182
20818
Approved
21
B.A.24
146+600
RHS
2.6 km
15000
6191
8809
Approved
22
B.A.25
145+200
RHS
3 Km
72600
57999.5
14601
Approved
23
B.A.26
122+980
RHS
3 Km
15000
10526
4474
Approved
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 42
MONTH: APRIL - 2014
24
B.A.27
170+500
RHS
20 Km
18300
MONTH: OCTOBER -2012
17883
417
Approved
25
B.A.32
169+540
RHS
2.2 km
30000
30000
0
Approved
26
B.A.32.A
169+540
RHS
2.2 km
20000
10823
9177
Approved
27
B.A.33
157+360
LHS
0.6 km
13500
13500
0
Approved
28
B.A.34
162.030
RHS
2.9 km
9600
9600
0
Approved
29
B.A.37
122+260
RHS
2.0 km
45000
0
45000
Approved
30
B.A.39
166+000
RHS
4.0 Km
33750
33750
0
Approved
31
B.A.39 A
166+000
RHS
4.0 Km
30000
30000
0
Extended
32
B.A.40
109+100
RHS
0.05 km
24750
8853
15897
Approved
33
B.A.41
136+000
LHS
2.0 km
60000
5630.1
54370
Approved
34
B.A.43
116+620
RHS
1.1 km
12113
0
12113
35
B.A.44
169+520
RHS
1.8 km
33750
18844
14906
Approved
36
B.A.45
168+840
RHS
0.8 km
16875
9381
7494
Approved
Approved
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 43
MONTH: APRIL - 2014
Concrete Mix Designs: Concrete mix design as per IS 10262 -2009 has been carried out for various concrete
MONTH: OCTOBER -2012
grades. The batching plant of 2 No’s of 30 m3/Hour has been established at 129/00 RHS camp and 162/00 RHS
camp site. The detailed concrete mix design details are given below:
Sl.
No
Grade
Cement
20 mm
10 mm
Sand
In Kg
In Kg
In kg
In Kg
W/C
ratio
Admixture
Remarks
1
M15
260
784
522
771
0.50
-
Birla super /penna
power
2
M20
290
758
505
746
0.50
0.60
Birla super /penna
power
M20 Kerb
320
711
474
761
0.50
-
Penna power
4
M20RCC
320
841
560
717
0.45
0.90
Penna Power
5
M25
340
745
496
702
0.45
0.85
Birla super /penna
power
6
M30
360
741
494
699
0.42
0.80
Birla super /penna
power
7
M35
390
694
463
743
0.40
-
Birla super /penna
power
8
M40
420
801
534
654
0.38
0.65
Birla super
9
DLC
150
624
468
858
-
-
Birla super
10
PQC
425
781
521
646
0.30
1.0
Birla super
3
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 44
MONTH: APRIL - 2014
MIX DESIGNS:
S.NO
MIX DESIGNS
IE APPROVED LETTERS NUMBERS
MONTH: OCTOBER -2012
APPROVAL DATE
1
GSB
136 & 162 CAMP LASA/73384/DH/IE/TL/152
19.09.2011
2
GSB ( RAM)
136 & 162 CAMP LASA/73384/DH/IE/TL/426
26.07.2012
3
WMM
136 CAMP LASA/73384/D-H/IE/TL/272 &
162 CAMP LASA/73384/D-H/IE/TL/193
25.02.2012 & 0 7.12.2012
4
DBM GRADE I
LASA/73384/D-H/IE/TL/273
25.02.2012
5
DBM GRADE II
LASA/73384/D-H/IE/TL/298
24.03.2012
6
DBM GRADE II
WITH RAP
LASA/73384/D-H/IE/TL/463
18.09.2012
7
BC GRADE II
Oriental LASA/73384/D-H/IE/TL/563
28.01.2013
8
BC GRADE II
136 Crusher LASA/73384/D-H/IE/TL/564
28.01.2013
9
BC GRADE II
136 Crusher LASA/73384/D-H/IE/TL/616
18.03.2013
Materials:
Source of material of cement, aggregate, sand, water, steel, admixture, Hume pipes etc, have been
identified and tested for the properties and third party test for conformation also done.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 45
MONTH: APRIL - 2014
Details of all sources of materials are tabulated below:
Sl No
Material
Used for
Identified
Approval
submission
Approval
granted
Remarks
MONTH: OCTOBER -2012
1
Borrow soil
Emb/SG
45
34
34
45No’S
2
Water
Concrete
5
5
4
129+000RHS,
158+000RHS,
166+000RHS,
158+150RHS.
3
Sand
Concrete
1
1
1
Hemavathi river
4
Aggregate
Road works&
Concrete
4
4
4
5
Steel
Concrete
5
5
3
159+350LHS,133+100LHS,
Balaji crusher,
Oriental granite.
Vizag, TATA,SAIL
6
Cement
Concrete
6
6
6
7
Admixture
Concrete
3
3
2
8
Hume pipe
Pipe culvert
3
3
2
9
Curing
Compound
BitumenVG30,CRMB
Emulsion
Kerb
2
2
1
Hemavathy Spun pipe, BSCPL
136 CAMP
Sika India
Bituminous
works
Prime/tack
2
2
2
MRPL,HPCL
3
3
3
Hincol,, M/S
Muthoots.BSCPL IL
Above the
MinOr Bridges
1
1
1
Tikitar
13
Mastic
asphalt Sheet
Road Marking
Safety
2
2
2
14
Road signages
Safety
1
1
1
15
W beam
crash barrier
Wire rope
Safety Fence
Safety
1
1
1
M/S Kataline Infrastructure
Pvt ltd, M/S Auto mark
industries
ltd India Pvt
M/S
TradePvt
vision
ltd.
M/S V K Industries
Safety
1
1
1
Brifen (Hill & Smith IPI)
10
11
12
16
Birla, Penna, Dalmia, Ramco
,Zuari & Chettinad
BASF,SWC
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 46
MONTH: APRIL - 2014
Third Party Test:
All the Source of Materials has been tested at External Agency Lab for Confirmatory. The
Summary of Tests Conducted by External Agencies – Up to April 2014 has been tabulated vide Table1.
MONTH: OCTOBER -2012
Calibration:
Calibration for all the equipment has been carried out. The details of up to date calibration status of
all equipment’s are summarized in Table-II.
Quality Control:
Based on Quality Assurance Plan and IRC SP 57: 2000, the materials are tested as per specification.
Detailed monthly Quality Control & Quality Assurance statistics tests have been prepared and
enumerated as summary.
Quality Audit:
Project site on 10.9.11 detailed Quality Audit has been carried out by GM, Manager - QC, NHAI HQ,
New Delhi.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 47
MONTH: APRIL - 2014
S. No.
Description
1.0 Tests on OGL
1.1 Gradation
1.2 Atterberg Limits
1.3 Procter
1.4 CBR Test
1.5 Free Swell index
2.0 Tests on Borrow areas
2.1
2.2
2.3
2.4
2.5
Gradation
Attenberg Limits
Procter
CBR Test
Free Swell index
3.0 Embankment (BA, Cut soil)
IS Specification
Clause
Frequency of
Tests
Quantity
Executed
during
MAR 2014
Total Tests upto previous
month
Tested
Tests conducted during
current month
Total Tests up to
FEB 2014
Passed Failed Tested Passed Failed Tested Passed
Failed
IS:2720 (Part4)
IS:2720 (Part5)
IS:2720 (Part8)
IS:2720 (Part16)
IS:2720 (Part40)
As required
As required
As required
As required
As required
605
605
603
440
604
603
602
601
345
597
2
3
2
95
7
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
605
605
603
440
604
603
602
601
345
597
2
3
2
95
7
MORT&H 305
IS:2720 (Part4)
IS:2720 (Part5)
IS:2720 (Part8)
IS:2720 (Part16)
IS:2720 (Part40)
As required
As required
As required
As required
As required
233
233
233
227
233
233
233
233
219
233
0
0
0
8
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
233
233
233
227
233
233
233
233
219
233
0
0
0
8
0
12584 M3
MORT&H 305
3.1 Gradation
IS:2720 (Part4)
1 test /1500 m3
611
611
0
2
2
0
613
613
0
3.2 Attenberg Limits
IS:2720 (Part5)
1 test /1500 m3
611
611
0
2
2
0
613
613
0
3.3 Procter
IS:2720 (Part8)
611
611
0
2
2
0
613
613
0
3.4 Field Density
IS:2720 (Part28)
5034
4991
43
108
108
0
5142
5099
43
3.5 Free Swell index
IS:2720 (Part40)
1 test /1500 m3
1 set Test per
1000Sqm
As required
611
611
0
2
2
0
613
613
0
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 48
MONTH: APRIL - 2014
S. No.
Description
4.0 Sub grade (BA, Cut soil)
IS Specification
Clause
Frequency of Tests
Quantity Total Tests upto previous
Executed
month
during APRIL
Tested Passed Failed
2014
Tests conducted during
current month
Tested
Passed
Total Tests up to
APRIL 2014
Failed Tested
Passed
Failed
39 M 3
MORT&H 305
IS:2720 (Part4)
1 test /1500 m3
585
585
0
1
1
0
586
586
0
4.2 Atterberg Limits
IS:2720 (Part5)
1 test /1500 m
3
585
585
0
1
1
0
586
586
0
4.3 Procter
IS:2720 (Part8)
1 test /1500 m
3
585
585
0
1
1
0
586
586
0
3
387
8412
585
372
8348
585
15
64
0
1
6
1
1
6
1
0
0
0
388
8418
586
373
8354
586
15
64
0
76
76
0
2
2
0
78
78
0
2376
2259
50
17
24
2815
2321
2254
50
17
23
2748
55
5
0
0
1
67
1
1
0
0
0
6
1
1
0
0
0
6
0
0
0
0
0
0
2377
2260
50
17
24
2821
2322
2255
50
17
23
2754
55
5
0
0
1
67
3718
2195
2210
3571
9
28
1
3910
3704
2194
2205
3570
9
28
1
3879
14
1
5
1
0
0
0
31
1
1
1
1
0
0
0
12
1
1
1
1
0
0
0
12
0
0
0
0
0
0
0
0
3719
2196
2211
3572
9
28
1
3922
3705
2195
2206
3571
9
28
1
3891
14
1
5
1
0
0
0
31
4.1 Gradation
4.4 CBR Test
4.5 Field Density
4.6 Free Swell index
5.0 Filter Media & Back filling
5.1 Gradation
6.0 GSB Mix Design
6.1 Gradation
6.2 Atterberg Limits
6.3 Procter
6.4 CBR Test
6.5 TFV
6.6 Field Density
7.0 WMM Mix Design
7.1 Combined Gradation
7.2 Aggregate Impact Value
7.3 Flakiness & Elagation index
7.4 Atterberg Limits
7.5 Water absorbtion
7.6 Procter
7.7 CBR Test
7.8 Field Density
IS:2720 (Part16)
IS:2720 (Part28)
IS:2720 (Part40)
MORT&H 2500
1 test /3000 m
1set Test per 500 Sqm
As required
MORT&H 401
IS:2720 (Part5)
IS:2720 (Part8)
IS:2720 (Part16)
BS:812
IS:2720 (Part28)
MORT&H 406
IS:2386 Part1
IS:2386 Part4
IS:2386 Part1
IS:2720 (Part5)
IS:2386 Part2
IS:2720 (Part8)
IS:2720 (Part16)
IS:2720 (Part28)
72 M
3
1 test/200m3
1 test/200m3
As required
As required
As required
1 set Test per 500Sqm
82 M 3
1 test/100m3
As required
As required
1 test/100m3
As required
As required
As required
1 set Test per 500Sqm
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 49
MONTH: APRIL - 2014
S. No.
Description
IS Specification
Clause
8.0 PAVING BITUMEN VG-30 (60/70) S65 TYPE-1/CRMB
8.1 Penetration at 25 0C
0
8.2 Softening point C
8.3 Ductility at 27 0C
8.4 Specific gravity at 27 0C
8.5 Absulte Visocity
8.6 Elastic Recovery
8.7 Separation test
9.0 DENSE BITUMINOUS MACADAM (DESIGN) MORT&H 500
9.1 Gradation(Individual, Dry mix)
IS:2386 Part1
9.2 Aggregate Impact Value Test
IS:2386 Part4
9.3 Flakiness and Elongation Index
IS:2386 Part1
9.6 Binder Content
9.7 Grading of mix after extraction
IS:2386 Part1
9.8 Marshall Stability test
ASTM D 1559
9.10 Core Density
ASTM D 1559
Frequency of Tests
Quantity Total Tests upto previous
Executed
month
during APRIL
Tested Passed Failed
2014
Tests conducted during
current month
Tested
Passed
Total Tests up to
APRIL 2014
Failed Tested
Passed
Failed
For Every New Lot
997
997
0
0
0
0
997
997
0
For Every New Lot
997
997
0
0
0
0
997
997
0
For Every New Lot
13
13
0
0
0
0
13
13
0
For Every New Lot
For Every New Lot
For Every New Lot
For Every New Lot
15
122
7
1
15
122
7
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
15
122
7
1
15
122
7
1
0
0
0
0
1583
1583
0
3
3
0
1586
1586
0
1815
1815
0
2
2
0
1817
1817
0
1815
1815
0
2
2
0
1817
1817
0
859
859
0
2
2
0
861
861
0
859
859
0
2
2
0
861
861
0
1277
1277
0
1
1
0
1278
1278
0
5677
5677
0
0
0
0
5677
5677
0
35.52 M 3
1 test per 400 T of mix or
2 tests per day
1 test per 50 m3 of
Aggregates
1 test per 50 m3 of
Aggregates
1 test per 400 T of mix or
2 tests per day
1 test per 400 T of mix or
2 tests per day
1 test per 400 T of mix or
2 tests per day
1 core per 250 sq-m
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 50
MONTH: APRIL - 2014
S. No.
Description
IS Specification
Clause
Frequency of Tests
Quantity
Total Tests upto previous
Executed
month
during APRIL
Tested Passed Failed
2014
Tests conducted during
current month
Tested
Passed
Total Tests up to
APRIL 2014
Failed Tested
Passed
Failed
10.0 BC
10.1 Gradation
IS:2386 Part1
10.2 Aggregate Impact Value Test
IS:2386 Part4
10.3 Flakiness and Elongation Index
IS:2386 Part1
10.4 Extraction
IS:2386 Part1
10.5 Mould Casting
ASTM D 1559
10.6 Core Cutting
ASTM D 1559
11.0 Fine Aggregate
11.1 Gradation /Sieve analysys
11.2 Specific gravity
11.3 Water absorbtion
12.0 Coarse Aggregate
12.1 Gradation
12.2 Specific gravity
12.3 Aggregate Impact Value
12.4 Flakiness index
12.5 Water absorbtion
13.0 Cement
13.1 Fineness
13.2 Consistancy
13.3 Initial,Final setting time
13.4 Compressive Strength-set
13.5 Soundness of Cement
MORT&H 1008
IS:2386 (Part1)
IS:2386 (Part2)
IS:2386 (Part2)
MORT&H 1007
IS:2386 (Part2)
IS:2386 (Part3)
IS:2386 (Part4)
IS:2386 (Part1)
IS:2386 (Part3)
MORT&H 1006
IS:4031 (Part1)
IS:4031 (Part4)
IS:4031 (Part5)
IS:4031 (Part6)
IS:4031 (Part6)
1 test per 400 T of mix or
2 tests per day
1 test per 50 m3 of
Aggregates
1 test per 50 m3 of
Aggregates
1 test per 400 T of mix or
2 tests per day
1 test per 400 T of mix or
2 tests per day
539
539
0
0
0
0
539
539
0
1013
1013
0
0
0
0
1013
1013
0
1013
1013
0
0
0
0
1013
1013
0
356
356
0
0
0
0
356
356
0
600
600
0
0
0
0
600
600
0
3666
3666
0
0
0
0
3666
3666
0
1 test / 15 days
As required
As required
1351
6
6
1351
6
6
0
0
0
21
0
0
21
0
0
0
0
0
1372
6
6
1372
6
6
0
0
0
1 test / 15 days
As required
1 test / 15 days
1 test / 15 days
As required
1552
12
294
285
10
1552
12
294
285
10
0
0
0
0
0
21
0
3
3
0
21
0
3
3
0
0
0
0
0
0
1573
12
297
288
10
1573
12
297
288
10
0
0
0
0
0
Every batch
Every batch
Every batch
Every batch
Every batch
148
148
148
349
109
148
148
148
349
109
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
148
148
148
349
109
148
148
148
349
109
0
0
0
0
0
1 core per 250 sq-m
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 51
MONTH: APRIL - 2014
S. No.
Description
14.0 Concrete-cube
14.1 Cube test mix trials-set
14.2 Cube test-work(set)
14.3 Cube test-work(set)DLC
14.4 Field Density (DLC)
14.5 Beams test-works PQC
IS Specification
Clause
MORT&H 1700
MOST Sec. 1700
MOST Sec. 1700
MOST Sec. 903.5.1.1
MOST Sec. 903.5.1.1
MOST Sec. 903.5.2.1
Frequency of Tests
Quantity Total Tests upto previous
Executed
month
during APRIL
Tested Passed Failed
2014
Tests conducted during
current month
Tested
Passed
0
332
0
0
0
0
332
0
0
0
Total Tests up to
APRIL 2014
Failed Tested
Passed
Failed
680
15924
99
32
295
3
1
0
0
0
695.9 M3
MOST Sec1700
MOST Sec. 1700
1 Set Test /1000 Sq m
2 Cubes, 2beams / 150 m3
683
15593
99
32
295
680
15592
99
32
295
3
1
0
0
0
0
0
0
0
0
683
15925
99
32
295
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 52
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
S.No
1
Date of
Sample
Sending
28.02.2011
Sample
Description
Water at
129+000 RHS,
158+500 RHS
Size
129 CAMP,
136 CAMP &
162 CAMP
Details of Tests
Test Results
Limits
1. Organic & Inorganic, 2.Sulphates 3.
Suspended matter 4.PH value 5.Chlorides
7.80,7.72
6.0 - 8.0
6.Alkaline limit by titration as per specified
value
(max 10 ml of 0.1 normal Hcl to neutralize
200ml of
water)
CL 100 mg/l,60 mg/l
500 mg/l
Inorganic 360 mg/l
3000 mg/l
Name of Agency
Remarks
Bangalore
University
Within
Limit
Civil-Aid Techno
clinic Pvt. Ltd.
Bangalore
Within
Limit
Inorganic 396 mg/l
7.Acidity limit by titration as per specified
value
(max 10 ml of 0.1 normal NaOH to
neutralize 200ml of water
1.1
01.08.2011
Water
1. Organic & Inorganic, 2.Sulphates 3.
Suspended matter 4.PH value 5.Chlorides
728 mg/l 634 mg/l, 104.33
mg/l, 35.0 mg/l, 7.76, 198.55
mg/l, 0.90 ml, 51.0 ml,
150+580 LHS
6.Alkaline limit by titration as per specified
value
(max 10 ml of 0.1 normal Hcl to neutralize
200ml of
water)
7.Acidity limit by titration as per specified
value (max 10 ml of 0.1 normal NaOH to
neutralize 200ml of water
404 mg/l 599 mg/l, 59.72 mg/l,
32.0 mg/l, 7.74, 198.55 mg/l,
0.80 ml, 35.50 ml,
137+060 RHS
116+890 LHS
322 mg/l 229 mg/l, 28.66 mg/l,
39.0 mg/l, 7.80, 28.36 mg/l,
0.60 ml, 31.0 ml
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 53
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No.
Sample
Size
Details of Tests
Description
Sending
1.2
05.09.2011
1. Organic & Inorganic, 2.Sulphates 3.
Suspended matter 4.PH value
5.Chlorides
Water
6.Alkaline limit by titration as per
specified value
(max 10 ml of 0.1 normal Hcl to
neutralize 200ml of
water)
7.Acidity limit by titration as per
specified value
(max 10 ml of 0.1 normal NaOH to
neutralize 200ml of water)
166 Camp
136 Camp
125+500 RHS
1.3
16.09.2011
Water
129+00
0 RHS
1.Organic & Inorganic,2.Sulphates 3.
Suspended matter 4.PH value
5.Chlorides 6.To neutralize 200 ml of
water using phenolphthalein and
methyl as an indicator
Test Results
Limits
Name of
Agency
Remarks
134 mg/l 5.0 mg/l, 1.89
mg/l, 34.0 mg/l, 7.05,
22.69 mg/l, 0.30 ml, 1.0
ml,
196 mg/l 245.0 mg/l,
13.04 mg/l,, 44.0 mg/l,
7.75, 39.71 mg/l, 0.60
ml, 20.0 ml,
Civil-Aid Techno
clinic Pvt. Ltd.
Bangalore
196 mg/l 195.0 mg/l,
12.53 mg/l, 31.0 mg/l,
8.04, 42.55 mg/l, 0.40
ml, 21.0 ml,
7.43,Nil,290 mg/l,44
mg/l,92 mg/l, Nil, Nil, 2
ml
Bangalore
University
Within
Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 54
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No.
Sample
Size
Details of Tests
Description
Sending
1.Organic & Inorganic,2.Sulphates 3.
Suspended matter 4.PH value
150+150
1.4
16.09.2011
Water
5.Chlorides 6.To neutralize 200 ml of
RHS
water using phenolphthalein and
methyl as an indicator
1.Organic & Inorganic,2.Sulphates 3.
Suspended matter 4.PH value
164+040
5.Chlorides 6.To neutralize 200 ml of
1.5
04.04.2012
Water
RHS
water using phenolphthalein and
methyl as an indicator
1.6
1.7
17.09.2012
17.09.2012
Water
Water
125+500
RHS
129+200
RHS
1.Organic & Inorganic,2.Sulphates 3.
Suspended matter 4.PH value
5.Chlorides
6.Alkaline limit by titration as per
specified value (max 10 ml of 0.1
normal Hcl to neutralize 200ml of
water)
Test Results
Limits
Name of Agency
7.60,Nil,410 mg/l,62
mg/l,104 mg/l, Nil, Nil, 2
ml
Bangalore
University
6.50,Nil,414 mg/l,46
mg/l,150 mg/l, Nil, Nil, 2
ml
Bangalore
University
62 mg/l 336.0 mg/l, 13.40
mg/l,, 4 mg/l, 7.23, 28.83
mg/l, 0.78ml, 88.99 ml,
87 mg/l 323 mg/l, 18.50
mg/l,, 0.42 mg/l, 7.74,
28.83 mg/l, 27.63ml,
60.99 ml,
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 55
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
S.No.
Date of
Sample
Sending
Sample
Description
Size
Details of Tests
Test Results
7.Acidity limit by titration as per
specified value (max 10 ml of 0.1
normal NaOH to neutralize 200ml of
water
7.Acidity limit by titration as per
specified value (max 10 ml of 0.1
normal NaOH to neutralize 200ml of
water
7.Acidity limit by titration as per
specified value (max 10 ml of 0.1
NaOH to neutralize 200ml of water)
13 mg/l 39 mg/l, 0.17 mg/l,,
8.0 mg/l, 7.67, 16.0 mg/l,
2.20ml, 0.25 ml,
1.8
17.09.2012
Water
136+000
LHS
1.9
17.09.2012
Water
137+060
RHS
1.10
17.09.2012
Water
150+150
RHS
1.11
17.09.2012
Water
164+04
RHS
7.Acidity limit by titration as per
specified value (max 10 ml of 0.1
NaOH to neutralize 200ml of water)
50.0 mg/l 295 mg/l, 24.02
mg/l,, 15.00 mg/l, 7.21,
83.99mg/l, 13.50ml,1.15ml,
Water
158+500
RHS
7.Acidity limit by titration as per
specified value (max 10 ml of 0.1
normal NaOH to neutralize 200ml of
water
77.0 mg/l 268 mg/l, 26.25
mg/l,, 15.00 mg/l, 7.41,
85.99 mg/l, 13.20 ml, 0.64
ml,
1.12
17.09.2012
Limits
Name of Agency
132.0 mg/l 272 mg/l, 24.02
mg/l,, 5.0 mg/l, 7.44, 72.99
mg/l, 15.70ml, 0.75 ml,
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
111.0 mg/l 335 mg/l, 29.69
mg/l,, 16.00mg/l, 7.48,
53.99mg/l, 24.80ml,0.93ml,
Provingring
2
28.02.2011 50KN -0394
50KN -0104
25 KN - 701
Proving
ring
1.Calibration
Remarks
5.94 kgs , 7.05 kgs, 3.64 kgs
OK
Bangalore
University
28.02.12,
16.07.12,
28.02.12.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 56
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
S.No
2.1
Date of
Sample
Sending
Sample
Description
11.04.2012
4,46,51,89,1
1,21,92,260
21.03.2011
19,22,61,04,
465
12.10.2011
189112
Coarse
Aggregate
3
11.03.2011
3.1
15.06.2011
Balaji
Crusher
Coarse
Aggregate
Coarse
Aggregate
(Oriental
Granite)
CH:166+400
LHS
Size
Details of Tests
Test Results
Limits
0-25
mm
Name of
Agency
Remarks
Pooja Orecision
Instruments
1. Calibration
OK
OK
Bangalore
University
Bangalore
University
1.Soundness 2.Deleterious Content
3.Alkali aggregate,4.organic material
5.total sulphate& chloride 6.Petro
graphic Examination
Deleterious - Nil
Soundness - 1.18% &
1.36%,Petrographic
Quartz,Feldspar
minerals,Alkali-Non
reactive, Organic
Material - Nil
Max 3%
Max 12% & 18 %
Bangalore
University
1.Soundness 2.Deleterious Content
3.Alkali aggregate,4.organic material
5.total sulphate& chloride 6.Petro
graphic Examination
Deleterious - Nil
Soundness - 1.22% &
1.40%,Petrographic
Quartz,Feldspar
minerals,Alkali-Non
reactive
Max 3%
Max 12% & 18 %
Bangalore
University
With in
Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 57
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
S.No
3.2
Date of
Sample
Sending
15.06.2011
Sample
Description
Coarse
Aggregate
Reddy
Verranna
3.3
05.09.2011
CH:175+200
LHS
Quarry
Aggregate
136 Camp
3.4
14.12.2011
Size
Details of Tests
Test Results
Limits
Name of
Agency
1.Soundness 2.Deleterious Content
3.Alkali aggregate,4.organic material
5.total sulphate& chloride 6.Petro
graphic Examination
1.10 % with sodium
sulphate, 1.14 % with
magnesium sulphate,
Bangalore
University
1.Soundness 2.Deleterious Content
3.Alkali aggregate,4.organic material
5.total sulphate& chloride 6.Petro
graphic Examination 7.Aggregate
Impact Value 8.Specific gravity and
water absorption
1.10 % with sodium
sulphate, 1.14 % with
magnesium sulphate, Nil,
Nonreactive,Nil,Quartz,Pl
agioclase Feldspar,20.40
%,2.64 & 0.42 %
Bangalore
University
1.Clay Reading ,2.Sand Reading
3.Mean Sand Equivalent Value
48.5,36.3,75
Bangalore
University
(Oriental
Granite)
CH:166+400
LHS
Fine
Aggregate
Coarse
Aggregate
1,Stripping Value (Coating Retained)
96%
MIM - 95 %
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 58
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No
Sample
Size
Details of Tests
Description
Sending
3.5
11.03.2011
Test Results
Limits
Name of Agency
Remarks
BSCPL Quarry
CH:159+350 LHS
1.Clay Reading ,2.Sand Reading
NIL,NIL,0.25%
3.Mean Sand Equivalent Value
Bangalore
University
Fine Aggregate
3.6
03.10.2011
Coarse
Aggregate
1.Soundness 2.Deleterious Content
3.Alkali aggregate,4.organic material
5.total sulphate& chloride 6.Petro
graphic Examination 7.Aggregate
Impact Value 8.Specific gravity and
water absorption
3.7
30.09.2011
GSB 136 Camp
Crusher
1. TFV (10% Fine value) 2.
Deleterious Content
166 Camp
Crusher
1. TFV (10% Fine value) 2.
Deleterious Content
1.Soundness 2.Deleterious Content
3.Alkali aggregate,4.organic material
5.total sulphate& chloride 6.Petro
graphic Examination 7.Aggregate
Impact Value 8.Specific gravity and
water absorption
3.8
03.10.2011
Quarry
Aggregate
159+350 LHS
1.34 % with sodium
sulphate, 1.22 % with
magnesium sulphate, Nil,
Non reactive, Nil, Nil,
Quartz,Plagioclase
Feldspar,23.30 %,2.58 &
0.51 %
14.4 %,
10.2 %,
1.34 % with sodium
sulphate,1.22 % with
magnesium
sulphate,
Nil,Non
reactive,Nil,
Nil,Quartz,Feldspar,23.30
%,2.58 & 0.51 %
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
Bangalore
University
With in
Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 59
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No
Sample
Size
Details of Tests
Description
Sending
3.9
10.04.2011 Stone Polish
1.Before Polishing
Value
BSCPL IL
2.After Polishing
Pvt.Ltd.
3.PSV Control Specimen ( C )
4.PSV = ( S+52.5-C )
Test Results
Limits
Name of
Agency
Remarks
63.5
57.2
50
Length of Slide 15+/-0.5 mm
BMS Collage of
Engineering
59.7
The Aggregate Satisfying
MORT&H Specification
0.25
1.Soundness 2.Deleterious Content Deleterious
Max 3%
3.Alkali aggregate,4.organic material Soundness - 0.72% &
0.90%,Chlorides,Organic - Max 10% & 15 %
5.total sulphate& chloride
Nil,Alkali-Non reactive
5.Remarks
4
11.03.2011
Fine
Aggregate
Steel
5
5.04.2011
Steel (RINL
Vizag)
8 , 10,
12,16 &
20mm
1.Yield Stress 2.Elongation 3.tensile
Strength 4. Bend & Rebend test
523 N/mm2 ,22.5 %,630
N/mm2
529
N/mm2 ,26 %,661 N/mm2
544 N/mm2 ,23.3 %,659
N/mm2
557 N/mm2 ,27.5 %,668
N/mm2
521
N/mm2 ,25.0 %,631 N/mm2
Min 485 N/m2
(8mm),elongation
min 14.5%
Min 545 N/m2
(10mm,12mm),elo
ngation min 12%
Min 565 N/m2
(16mm),elongation
min 16%
Bangalore
University
With in
Limit
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalo
re
With in
Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 60
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No
Sample
Size
Details of Tests
Description
Sending
Sectional Weight,UTS N/mm2, %
5.1
13.05.2011 Steel (Vizag)
age elongation
5.2
5.4
15.06.2011
05.09.2011
Sail Fe - 500
8,
12,16
&20m
m
Sail, Vizag
10mm,
1.Yield Stress 2.Elongation 3.tensile
25mm,
Strength 4. Bend & Rebend test
25mm
1.Yield Stress 2.Elongation 3.tensile
Strength 4. Bend & Rebend test
5.5
16.09.2011
Steel (TMT) Fe
500 D
10mm, 1.Yield Stress 2.Elongation 3.tensile
12mm Strength 4. Bend & Rebend test
5.6
21.09.2011
Steel TATA
Tiscon (Fe 500)
16 mm
1.Yield Stress 2.Elongation 3.tensile
Strength 4. Bend & Rebend test
Test Results
(7mm MS) UTS 424 N/mm2
elongation 34%
558 N/mm2 ,16.2 %,618
N/mm2
542
N/mm2 ,19.5 %,598 N/mm2
554 N/mm2 ,18.0 %,612
N/mm2
564 N/mm2 ,15.0 %,633
N/mm2
577 N/mm2 ,20 %,707
N/mm2 (Sail)
533 N/mm2 ,24 %,664
N/mm2 (Sail)
543 N/mm2 ,23.2 %,674
N/mm2 (Vizag)
Limits
Min 410 N/mm2
UTS elongation
min 23%
Name of
Agency
Shri Ram
Institute
Remarks
With in
Limit
Bangalore
University
Min 545 N/mm2
UTS elongation
min 12%
Civil-Aid Techno
clinic Pvt. Ltd.
With in
Limit
Bangalore
558 N/mm2 ,17.6 %,630
N/mm2
550 N/mm2 ,19.2 %,606
N/mm2
Min 500 N/mm2
UTS elongation
min 12%
Bangalore
University
With in
Limit
550 N/mm2 ,22.5 %,661
N/mm2
Min 545 N/mm2
UTS elongation
min 12%
Civil-Aid Techno
clinic Pvt. Ltd.
Bangalore.
With in
Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 61
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No
Sample
Size
Details of Tests
Description
Sending
5.7
5.8
5.9
5.10
5.11
14.12.11
16.09.2011
15.02.2012
13.07.2012
17.09.2012
Test Results
Civil-Aid Techno
clinic Pvt. Ltd.
Bangalore
With in
Limit
N/mm2, OK
558
N/mm2 ,17.60 %,630 N/mm2, OK
Min 545 N/mm2 UTS
elongation min 12%
Bangalore
University
With in
Limit
Min 545 N/mm2 UTS
elongation min 12%
Bangalore
University
With in
Limit
Bangalore
University
With in
Limit
Civil-Aid Techno
clinic Pvt. Ltd.
Bangalore
With in
Limit
10,12,1
6,20,32
Steel TATA
12mm,1
0mm
1.Yield Stress 2.Elongation
3.tensile Strength 4. Bend
& Rebend test
12mm,1
0mm
1.Yield Stress 2.Elongation
3.tensile Strength 4. Bend
& Rebend test
552 N/mm2 ,20.60 %,608
N/mm2, OK
555
N/mm2 ,19.40 %,612 N/mm2, OK
12mm
1.Yield Stress 2.Elongation
3.tensile Strength 4. Bend
& Rebend test
556 N/mm2 ,21.30 %,608
N/mm2, OK
Steel SAIL
8mm,12
mm,16
mm
1.Yield Stress 2.Elongation
3.tensile Strength 4. Bend
& Rebend test
Remarks
Min 545 N/mm2 UTS
elongation min 12%
Steel SAIL (Fe
500)
Steel SAIL
Name of Agency
554 N/mm2 ,28.0 %,682 N/mm2
564 N/mm21.7, %,686 N/mm2
518 N/mm,23.8 %,625 N/mm2
527 N/mm,27.0 %,643 N/mm2
578
%,715
N/mm2
550 N/mm,18.8
N/mm2 ,19.20
%,606
1.Yield Stress 2.Elongation
3.tensile Strength 4. Bend
& Rebend test
Steel SAIL
Limits
487 N/mm2 ,25.0 %, 574
N/mm2, OK
525
N/mm2 ,20.0 % ,629 N/mm2, OK
541 N/mm2 ,19.40 %,644
N/mm2, OK
Min 485 N/m2
(8mm),elongation
min 14.5%
Min 545 N/m2
(10mm,12mm),elong
ation min 12%
Min 565 N/m2
(16mm),elongation
min 16%
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 62
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No
Sample
Size
Details of Tests
Description
Sending
1.Ratio of % of lime to %
Cement
of silica,alumina and Iron
oxide
6
5.04.2011
Cement
Penna
PowerOPC
53
Test Results
Limits
Chloride 0.014%
Max 0.05%
2.Ratio of alumina to that
of Iron oxide
Sulphur 1.59%
Max 2.5%
3.Insoluble residue
Magnesia 1.82%
Max 6%
4.Magnesia
Insoluble residue 0.68%
Max 3%
Civil-Aid Techno
clinic Pvt. Ltd.
Bangalore
Within
Limit
Bangalore
University
Within
Limit
5.Sulphuric anhydride
7.Chloride
15.06.2011
Remarks
Loss on ignition 0.94
6.Loss on ignition
6.1
Name of Agency
0.88 % of silica,alumina and Iron oxide, 1.05 % Ratio of alumina to
that of Iron oxide
Ultra
Tech(Birla
Super)
1.Ratio of % of lime to %
of silica,alumina and Iron
oxide
Chloride 0.0094%
OPC 53
2.Ratio of alumina to that of
Iron oxide
Sulphur 1.70%
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 63
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No
Sample
Size
Details of Tests
Description
Sending
6.1
15.06.2011
Test Results
Limits
3.Insoluble residue
Magnesia 1.30%
Max 6%
4.Magnesia
Insoluble residue 2.40%
Max 3%
5.Sulphuric anhydride
Loss on ignition 1.90
6.Loss on ignition
7.Chloride
6.2
15.06.2011
Dalmia
Cement
OPC 53
1.Ratio of % of lime to %
of silica,alumina and Iron
oxide
2.Ratio of alumina to that
of Iron oxide
Name of
Agency
Remarks
Bangalore
University
Within
Limit
0.85 % of silica, alumina and Iron oxide, 1.22 % Ratio of
alumina to that of Iron oxide
Chloride 0.0096%
Max 0.05%
Sulphur 1.92%
Max 2.5%
3.Insoluble residue
Magnesia 1.18%
Max 6%
4.Magnesia
Insoluble residue 2.30%
Max 3%
Bangalore
University
Within
Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 64
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No
Sample
Size
Details of Tests
Description
Sending
5.Sulphuric anhydride
6.Loss on ignition
7.Chloride
7
7.1
14.10.2011
17.09.201
2
Test Results
Limits
Name of Agency
Remarks
Loss on ignition 2.10
0.84 % of silica,alumina and Iron oxide, 1.28 %
Ratio of alumina to that of Iron oxide
Admixture
1.Relative Density
Ash content 1.78%
0.95 - 1.05 T
BASF
Cons.Chemicals.
2.Dry material content
Dry material 17.62%
17± -5 %
Pvt.Ltd.
3.Ash content
Chloride .0082%
Max 2%
Batch No. 07611
4.Chloride content
pH 6.10%
Min 6 %
5.PH Value
Relative Density 1.59
Admixture
1.Relative Density
Ash content 2.18%
0.95 - 1.05 T
BASF
Cons.Chemical
s.
2.Dry material content
Dry material 39.43%
17± -5 %
Bangalore
University
With in
Limit
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
With in
Limit
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
With in
Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 65
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No
Sample
Size
Details of Tests
Description
Sending
7.2
5.04.2011
Test Results
Limits
Name of Agency
Remarks
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
With in Limit
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
With in Limit
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
With in Limit
Pvt.Ltd.
3.Ash content
Chloride .0042%
Max 2%
Batch No.
MD52512
Admixture
4.Chloride content
pH 6.45%
Min 6 %
1.Specific gravity
Ash content 2.30%
0.95 - 1.05 T
Rheoplus 71 (EI)
2.Dry material content
Dry material 16.82%
17± -5 %
BASF
Cons.Chemicals.
3.Ash content
Chloride .0084%
Max 2%
Pvt.Ltd.
4.Chloride content
pH 6.82%
Min 6 %
Relative Density 1.055
8
10.04.2011
Curing
Compound
Sika
1.Specific Gravity
1.011
Pvt.Ltd.
Batch No.
GB020112
2.Soild Content ( % )by Weight
16.02
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 66
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No.
Size
Details of Tests
Sample
Description
Sending
9
23.02.2012
Test Results
Limits
Name of
Agency
Remarks
91.20%
Not Less than
80.0 %
Bangalore
University
With in Limit
1. Presence of Calcium Carbonate
(CaCo3 ) Content in lime powder
95.02%
Not Less than
80.0 %
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalo
re
With in Limit
1.Specific Gravity,2.Flash Point,3.Softing
Point,4.Penetration,5.RTFOT
Ductility,6.Matter soluble in
trichloroethylene,7.Kinematic Viscosity
1.03,266,56.5,51,100+,99.99
,779#
Min - ( -,220,47,5070,40,99,350 )
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
With in Limit
1.Penetration,2.Softing Point,3.Flash
Point,4.Solubility in
tyrichloroethylene,5.Viscosity,6.Kinematic
Viscosity,7.RTFOT
53,50,296,99.91,2550#,432#
,1.2#,100+
Min - ( 5070,47,220,99,24
00,350,4.0,40 )
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
With in Limit
LIME POWDER
Wipro
Enterprises
1. Presence of Calcium Carbonate (CaCo3 )
Content in lime powder
Kurnool
9.1
17.09.2012
LIME POWDER
Sree Ganesh
Minaral
Industries
10
14.12.11
BITUMEN
M.R.P.L
Manglore
VG - 30
10.1
19.07.2012
BITUMEN
M.R.P.L
Manglore
VG - 30
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 67
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
S.No
Sample
Sending
10.2 19.07.2012
Sample
Description
BITUMEN
M.R.P.L
Manglore
CRMB - 60
11 23.04.2012
Emulsion
BSCPL IL
RS-1,SS-1
11.1 19.07.2012
Emulsion
BSCPL IL
RS-1,SS-1
Size
Details of Tests
Test Results
Limits
1.Penetration,2.Softing Point,3.Elastic
Recovery,4.Flash Point.
42,61.4,65,>300
Requirement
(<50,60,50,220 )
0.022,28.0,62.20,85.0,82.0,9
8.70,NIL,Positive,No
Congratulation.
Requirement as
per
MORT&H(0.05,20
-100,,60-80150,50cm,98.00,
NIL, Positive,NO
Coagulation. )
1.Residue on 600Micron,2.Viscosity,3.Residue
Percent,4.Penetration,5.Ductility,6.Solubi
lity in trichloro ethylene,7.Coagulation of
emulsion at low tempreture,8.Paticle
charge of emulsion,9.water content
1.Residue on 600Micron,2.Viscosity,3.Residue
Percent,4.Penetration,5.Ductility,6.Solubi
lity in trichloro ethylene,7.Coagulation of
emulsion at low tempreture,8.Paticle
charge of emulsion,9.water content
10.Distillation in percent by
volume
1.190o C
0.020,62.0,53.80,232.0,64.0,
99.40,NIL,15
Requirement as
per
MORT&H(0.05,20
-100,50.0,60350,50cm,98.00,
NIL, 20% )
Weak Positive
Positive
44
22-55
2.225 C
56
30-75
3.260o C
51
40-90
92
60-100
o
o
4.315 C
Name of
Agency
Remarks
With in Limit
Bangalore
University
With in Limit
Bangalore
University
With in Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 68
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No.
Sample
Size
Details of Tests
Description
Sending
1.Softing Point,2.Penetration,3.Cold
Flexibility
Breaking Load Of membrane,N/5cm
Tiki Tar
Width at RT
12 04.05.2012
Asphalt
BSCPL IL
3 mm Thick
ness
13
03.05.2012
1.One Direction, Probably Longitudnal
2.Perpendicular to one Direction,
probably Transverse
Elongation of Break,Percent at RT
1.One Direction, Probably Longitudnal
2.Perpendicular to one Direction, probably
Transverse
Test Results
Limits
Name of
Agency
Remarks
National Test
House
With in Limit
National Test
House
With in Limit
150,18,No cracking
observed
847
465
68.24
84
Elastomeric
Bearing
Observed Dimenctioned,
BSCPL IL
Length
452
Width
252
Thickness
61
Elastic Modulus,Shear Modulus,
Ultimate Compressive Strength
166.67,0.859,65
Requirement
(450+6mm,250+
6mm,60mm +/5% Max,149.69
to 224.53 ,0.80
to 1.20,No Less
than 60MPA
Bangalore
University
With in Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 69
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No.
Sample
Size
Details of Tests
Description
Sending
Test Results
Limits
Name of Agency
Remarks
0.5%
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
With in Limit
Shri Ram
With in Limit
BORROW
AREAS
14
5.04.2011
11.05.2011
14.1
14.2
15.06.2011
14.3
01.08.2011
B.A-1
@115+510
RHS
B.A-2
@119+435
B.A-3
RHS
@126+500
RHS
B.A-5
@116+800
B.A-6
LHS
@133+100
B.A-11
LHS
@151+900
B.A07@127+660
B.A-13
RHS
@153+085
B.A-16
LHS
@111+230
B.A-17
LHS
@145+240
RHS
1.Total soluble sulphate content 2.
Deleterious Content
0.026
0.025
0.027
1.Total soluble sulphate content 2.
Deleterious Content
1.Total soluble sulphate content 2.
Deleterious Content
Sulphate 0.01,0.01%
Max 1.9%
Deleterious 1.1% & 2%
Max 3%
0.04 % , Nil
Bangalore
University
0.020
1.Total soluble sulphate content 2.
Deleterious Content
0.018
0.014
0.019
Civil-Aid
Technoclinic
Pvt.Ltd.Bangalore
With in Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 70
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No.
Sample
Size
Details of Tests
Description
Sending
14.4
14.5
05.04.2011
21.09.2011
B.A-18
@137+300
RHSRHS
B.A-20
@141+430
B.A-21
RHSRHS
@127+660
B.A-19
RHSRHS
@158+000
Test Results
Limits
Name of Agency
0.5%
Civil-Aid Technoclinic
Pvt.Ltd. Bangalore
0.5%
Civil-Aid Technoclinic
Pvt.Ltd Bangalore
0.019
1.Total soluble sulphate content 2.
Deleterious Content
0.018
0.046
1.Total soluble content(SO3)
0.019
1. C - Ø Values
C-0.08,0.07-- Ø-34,35
2.Total soluble content(SO3)
0.019%
RHS
21.09.2011
14.6
14.7
14.10.2011
B.A-14
@116+860
B.A-06
LHS
@133+100
B.A-22
LHS
@127+660
B.A-23
RHS
@143+500
B.A-25
BHS
@145+200
RHS
B.A-26
@122+980
RHS
Remarks
0.02%
Civil-Aid Technoclinic
Pvt.Ltd Bangalore
0.018% , 0.022%
1.Total soluble sulphate content SO
3
0.019% , 0.023%
0.014% , 0.016%
2.Total soluble sulphate content SO
4
0.043% , 0.051%
Civil-Aid Technoclinic
Pvt.Ltd Bangalore
With in
Limit
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 71
MONTH: APRIL - 2014
SUMMARY OF TESTS CONDUCTED BY EXTERNAL AGENCIES – TABLE 1
Date of
Sample
S.No.
Sample
Size
Details of Tests
Description
Sending
B/A-14
116+860 LHS
B/A-15
136+330 RHS
B/A-27
170+500 RHS
14.8
17.09.2012
Limits
Name of Agency
0.007% , 0.023%
0.008% , 0.014%
1.Chlorides**
B/A-32
169+540 RHS
B/A-33
157+360 LHS
B/A-34
162+030 RHS
B/A-39 166
CAMP
CRUSHER
Test Results
0.007% , 0.019%
0.007% , 0.012%
0.006% , 0.022%
0.006% , 0.015%
2.Total soluble sulphate content SO3
0.008% , 0.025%
B/A-40
109+100 RHS
0.007% , 0.017%
B/A-41 136
CAMP
CRUSHER
0.008% , 0.021%
Civil-Aid Technoclinic
Pvt.Ltd Bangalore
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 72
MONTH: APRIL - 2014
SUMMARY OF CALIBRATION REPORT
TABLE - II
S.No
Instrument
Ref. No.
Type of Equipment
Calibration
Interval
Date of Calibration
Calibration Due on
3 Months
3 Months
04.02.2014
10.12.2013
04.05.2014
11.03.2014
Working
Working
1 Month
1 Month
12.04.14
05.04.14
11.05.14
04.05.14
Working
Working
1 Year
17.08.2013
17.08.2014
Remarks
A. In House Calibration
1 Rapid Moisture Meter
1
1
RMD - 3
RMD - 8
2 Sand Pouring Cylinder
1
SPC – 7
1
SPC-8
3 Compression Testing Machine (CTM)
(CTM) 2000,1000,500
162 Camp
2
KN
4 Batching Plant
136 Camp
1
6 Months
22.4.2014
21.10.2014
162 Camp
1
6 Months
29.10.2013
28.04.2014
1
6 Months
02.02.14
01.08.14
5 WMM Plant
WMM Plant
136 Camp
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 73
MONTH: APRIL - 2014
SUMMARY OF CALIBRATION REPORT
TABLE - II
S.No
Instrument
Ref. No.
Type of Equipment
Calibration
Interval
Date of Calibration
Calibration Due on
WMM Plant
162 Camp
1
6 Months
16.02.14
15.08.14
6 DBM plants
DMI Plant 162
Camp
1
6 Months
30.01.14
30.07.14
06.02.13
26.02.15
06.02.13
26..02.15
Remarks
Out Side Calibration
7 Proving Ring
1
701
Proving Ring (25 KN)
1 Year
2
394
Proving Ring (50 KN)
1 Year
1
9 Weighing Balances
565
Dial gauge
SL.NO
1 Year
04.01.2014
04.01.2015
Bangalore University
21112114, 2118018
1 Year
17.01.14
16.01.15
APT Engg Corporation
7240
1 Year
17.01.14
16.01.15
APT Engg Corporation
Bangalore University
Bangalore University
8
2)
50 Kg - 2
No's
35 kg - 1 No
3)
30 kg - 1 No
1105 - 3612088
1 Year
17.01.14
16.01.15
Indian Scale Services Hassan
4)
6 Kg - 4 No's
600 g - 2
No's
1004, 3685, 1152, 1131
1 Year
17.01.14
16.01.15
APT Engg Corporation
11015331, 8520581358
1 Year
17.01.14
16.01.15
APT Engg Corporation
1)
5)
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 74
MONTH: APRIL - 2014
SUMMARY OF CALIBRATION REPORT
TABLE – II
Instrument
Ref. No.
10 Standard Weights
S.No
Type of Equipment
Calibration
Interval
1)
20 Kg - 1 No
Weights
1 Year
2)
10 Kg - 3
No's
Weights
1 Year
3)
5 Kg - 3 No's
Weights
1 Year
4)
2 Kg - 7 No's
Weights
1 Year
5)
1 Kg - 7 No's
Weights
1 Year
6)
500 g - 3
No's
Weights
1 Year
7)
200 g - 1 No
Weights
1 Year
8)
100 g - 2
No's
Weights
1 Year
9)
10 g - 3 No's
Weights
1 Year
10)
5 g - 4 No's
Weights
1 Year
Date of Calibration
Calibration Due on
19.04.14
18.04.15
19.04.14
18.04.15
19.04.14
18.04.15
19.04.14
18.04.15
19.04.14
18.04.15
19.04.14
18.04.15
19.04.14
18.04.15
19.04.14
18.04.15
19.04.14
18.04.15
19.04.14
18.04.15
Remarks
Indian Scale Services Hassan
Indian Scale Services Hassan
Indian Scale Services Hassan
Indian Scale Services Hassan
Indian Scale Services Hassan
Indian Scale Services Hassan
Indian Scale Services Hassan
Indian Scale Services Hassan
Indian Scale Services Hassan
Indian Scale Services Hassan
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 75
MONTH: APRIL - 2014
Test to be conducted as per Schedule - I
Test No as
Name of test/Audit
Status
per CA
21
Visual & Physical Test
Completed up to 170.260
2.2
Test Drive
Completed up to 170.260
2.3
Riding Quality Test
Completed up to 170.260
2.4
Pavement Composition Test
Completed up to 170+260.
2.5
Cross- Section Test
2.6
Structural Test
2.7
Other Tests
2.8
Environmental Audit
2.9
Safety Audit
Highway
Structures
NDT
Completed up to 170+260.
Load tests
Completed & Report submitted to IE.
Completed & Report submitted to IE.
Completed and report submitted to IE
Safety audit conducted by HAKS consultatns on 29th & 30th July 2013 and report submitted to IE
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 76
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
WEATHER RECORD FOR SECTION-I
Date
Temperature ( 0c )
Humidity
Rainfall
Weather
1-Apr-14
Min.
⁰c
24.3
Max.
⁰c
31.7
Min.
%
29
Max.
%
34
-
Sunny
2-Apr-14
24.5
31.9
26
30
-
Cloudy
3-Apr-14
24.7
31.5
47
54
-
Sunny
4-Apr-14
24.6
31.0
65
72
-
Sunny
5-Apr-14
22.4
30.7
69
76
-
Sunny
6-Apr-14
22.7
30.5
70
82
-
Sunny
7-Apr-14
21.7
31.6
34
69
-
Sunny
8-Apr-14
22.3
31.9
40
80
-
Cloudy
9-Apr-14
23.1
32.0
41
62
3.3
Rainy
10-Apr-14
19.9
31.6
43
70
-
Cloudy
11-Apr-14
21.2
31.8
40
80
-
Cloudy
12-Apr-14
23.0
32.0
38
63
-
Cloudy
13-Apr-14
23.3
31.6
43
68
_
Cloudy
14-Apr-14
22.7
31.8
40
78
6.8
Rainy
15-Apr-14
21.4
31.6
43
71
-
Cloudy
16-Apr-14
21.2
32.5
35
78
-
Drizzling
17-Apr-14
21.9
32.2
40
82
-
Cloudy
18-Apr-14
22.1
32.4
39
79
-
Cloudy
19-Apr-14
22.3
32.7
45
71
-
Sunny
20-Apr-14
22.5
32.9
47
69
-
Sunny
21-Apr-14
22.7
33.1
42
67
-
Sunny
22-Apr-14
22.8
33.3
44
65
-
Sunny
23-Apr-14
23.3
33.5
39
62
-
Sunny
Remarks
mm
SUNDAY
SUNDAY
SUNDAY
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 77
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
24-Apr-14
23.5
33.7
43
70
-
Cloudy
25-Apr-14
23.1
33.1
44
73
-
Drizzling
26-Apr-14
23.3
30.0
41
79
10.1
Rainy
27-Apr-14
22.7
33.4
38
73
-
Cloudy
28-Apr-14
23.2
33.5
39
68
-
Cloudy
29-Apr-14
23.4
33.7
41
72
8.7
Rainy
30-Apr-14
23.8
33.4
42
65
-
Drizzling
SUNDAY
WEATHER RECORD FOR SECTION-II
Date
Temperature ( 0c )
Humidity
Rainfall
Weather
1-Apr-14
Min.
⁰c
24.1
Max.
⁰c
31.5
Min.
%
30
Max.
%
39
-
Sunny
2-Apr-14
24.3
31.7
28
32
-
Cloudy
3-Apr-14
24.6
31.3
50
56
-
Sunny
4-Apr-14
24.4
30.8
67
71
-
Sunny
5-Apr-14
22.1
30.6
70
78
-
Sunny
6-Apr-14
21.9
30.4
72
84
-
Sunny
7-Apr-14
21.3
31.4
36
71
-
Sunny
8-Apr-14
22.2
31.7
44
82
-
Cloudy
9-Apr-14
22.9
31.9
42
66
3.9
Rainy
10-Apr-14
19.3
31.2
46
72
-
Cloudy
11-Apr-14
21.0
31.6
41
83
-
Cloudy
12-Apr-14
22.8
31.8
39
66
-
Cloudy
13-Apr-14
23.1
31.4
42
70
-
Cloudy
Remarks
mm
SUNDAY
SUNDAY
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 78
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
14-Apr-14
22.4
31.7
44
81
-
Drizzling
15-Apr-14
21.1
31.2
46
74
-
Cloudy
16-Apr-14
20.9
32.3
38
80
-
Cloudy
17-Apr-14
21.7
31.9
42
85
-
Drizzling
18-Apr-14
21.9
32.0
40
82
-
Cloudy
19-Apr-14
22.2
32.2
44
72
-
Sunny
20-Apr-14
22.4
32.4
42
68
-
Sunny
21-Apr-14
22.6
32.6
44
64
-
Sunny
22-Apr-14
22.8
32.8
40
60
-
Sunny
23-Apr-14
23.1
33.0
42
68
-
Sunny
24-Apr-14
23.3
33.2
46
74
-
Cloudy
25-Apr-14
22.9
32.9
45
77
-
Drizzling
26-Apr-14
23.1
32.8
43
82
13.4
Rainy
27-Apr-14
22.1
33.1
41
78
-
Sunny
28-Apr-14
23.0
33.3
44
70
-
Cloudy
29-Apr-14
23.1
33.5
39
76
4.7
Rainy
30-Apr-14
23.7
33.1
38
67
-
Drizzling
SUNDAY
SUNDAY
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 79
MONTH: APRIL - 2014
16. I) ORGANIZATION CHART - CONCESSIONAIRE
P Ravindranath
Project Manager
RGR & SB– Finance
& Accounts at HQ
S.Manikandan
Dy.Manager
Planning/MIS
Ms.Neetha Shree
Secretary
Manager QS at
Cluster Office
Sri Harsha Project
Acct-admin
Bhaskar matsagar
Section – 2 Head
Sec2
Alok
Project Engineer
LA & Utilities
Ganga Prasad
- GCT
Anjaneya Reddy
Project Acct-admin
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 80
MONTH: APRIL - 2014
16. II) ORGANIZATION CHART – OPERATION & MAINTENANCE
Ms. Sheetal Shanbhag Gopalkrishna
Project Head
Operations
Equipments
Maintenance
Nakkina Kiran Kumar,
Maintenance Manager
Anant Kumar Rout,
Equipment Manager
Raju.Lingappa,
Manager – TP II
Manager – TP I
D. Suresh,
Electrical Engineer
1.
2.
3.
4.
Shift in Charge
Krishnadas.K.V
Vedamurthy
Manjunath
Vinay Sagar Patil
Cashier
1. Prakash.K
2.Dattatraya Naik
3.Chetan Kumar
4.Nagaraj.C
Shift in Charge
1. Neeraj
2.Balakrishna Reddy
3.Pavithresh
4.Jayrama Gowda
Cashier
1. Manjanna
2.Sameer
3.Sridhar
4. Girish
T.N. Sakthivel,
Equipment Engineer
C.Gopinath,
Engineer Maintanance
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
16.III) ORGANIZATION CHART – EPC CONTRACTOR
Page No: 81
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 82
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
17.Status of NCRs
Total
Closed
Balance yet
to be closed
For Proper Safety/ Traffic compliances
52
52
0
Quality issues in Highways
10
9
1
Quality issues in Structures
4
4
0
DBM top level issues
7
6
1
DBM core cutting issues
1
1
0
GSB
3
3
0
Kerb casting
1
1
0
S.NO.
1
2
3
4
5
6
7
Particulars
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 83
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
18.Maintanence Activity Report - Patch work Repairs
Existing Road Maintenance is being carried out and detailed statement as below
Sl. No.
RFI No.
Description
From
To
Length
Side
Date
Status
1
L&T DHTL/NH48/HW/3799
Patch work repairs
116.000
118.000
2.000
BHS
26.08.11
Approved
2
L&T DHTL/NH48/HW/3834
Patch work repairs
117.000
119.000
2.000
BHS
27.08.11
Approved
3
L&T DHTL/NH48/HW/3875
Patch work repairs
118.000
119.000
1.000
BHS
28.08.11
Approved
4
L&T DHTL/NH48/HW/4134
Patch work repairs
119.000
121.000
2.000
BHS
05.09.11
Approved
5
L&T DHTL/NH48/HW/4170
Patch work repairs
121.000
122.000
1.000
BHS
06.09.11
Approved
6
L&T DHTL/NH48/HW/4766
Patch work repairs
126.000
127.000
1.000
BHS
24.09.11
Approved
7
L&T DHTL/NH48/HW/4871
Patch work repairs
130.000
131.000
1.000
BHS
27.09.11
Approved
8
L&T DHTL/NH48/HW/5284
Patch work repairs
125.000
126.000
1.000
BHS
15.10.11
Approved
9
L&T DHTL/NH48/HW/5316
Patch work repairs
133.900
134.100
0.200
BHS
16.10.11
Approved
10
L&T DHTL/NH48/HW/5344
Patch work repairs
109.000
110.000
1.000
BHS
18.10.11
Approved
11
L&T DHTL/NH48/HW/5363
Patch work repairs
107.660
109.000
1.340
BHS
19.10.11
Approved
12
L&T DHTL/NH48/HW/5408
Patch work repairs
110.000
111.000
1.000
BHS
21.10.11
Approved
13
L&T DHTL/NH48/HW/5434
Patch work repairs
111.000
112.000
1.000
BHS
22.10.11
Approved
14
L&T DHTL/NH48/HW/5781
Patch work repairs
123.000
124.000
1.000
BHS
14.11.11
Approved
15
L&T DHTL/NH48/HW/5808
Patch work repairs
112.000
113.000
1.000
BHS
15.11.11
Approved
16
L&T DHTL/NH48/HW/5869
Patch work repairs
113.000
114.000
1.000
BHS
18.11.11
Approved
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 84
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
18.Maintanence Activity Report - Patch work Repairs
Existing Road Maintanence is being carried out and detailed statement as below
Sl. No.
RFI No.
Description
From
To
Length
Side
Date
Status
17
L&T DHTL/NH48/HW/5982
Patch work repairs
113.000
114.000
1.000
BHS
24.11.11
Approved
18
L&T DHTL/NH48/HW/6403
Patch work repairs
122.000
123.000
1.000
-
13.12.11
Approved
19
L&T DHTL/NH48/HW/7441
Patch work repairs
127.000
128.000
1.000
-
21.01.12
Approved
20
L&T DHTL/NH48/HW/7756
Patch work repairs
128.000
129.000
1.000
-
06.02.12
Approved
21
L&T DHTL/NH48/HW/11357
Patch work repairing
124.000
125.000
1.000
BHS
18.05.12
Approved
22
L&T DHTL/NH48/HW/11363
Patch work repairing
134.000
139.700
5.700
BHS
18.05.12
Approved
23
L&T DHTL/NH48/HW/11395
Patch work repairing
114.000
116.000
2.000
BHS
19.05.12
Approved
24
L&T DHTL/NH48/HW/11465
Patch work repairing
110.000
114.000
4.000
BHS
21.05.12
Approved
25
L&T DHTL/NH48/HW/13802
Patch work repairing
126.000
127.500
1.500
BHS
17.07.12
Approved
26
L&T DHTL/NH48/HW/13833
Patch work repairing
124.000
126.000
2.000
BHS
18.07.12
Approved
27
L&T DHTL/NH48/HW/14585
Patch work repairing work
134.000
135.000
1.000
BHS
02.08.12
Approved
28
L&T DHTL/NH48/HW/15282
Patch repairing work
178.000
184.912
6.912
BHS
14.08.12
Approved
29
L&T DHTL/NH48/HW/15679
Patch repairing work
178.000
184.912
6.912
BHS
22.08.12
Approved
30
L&T DHTL/NH48/HW/15741
Patch work repairing work
134.000
139.610
5.610
BHS
24.08.12
Approved
31
L&T DHTL/NH48/HW/15869
Patch work repairing work
134.000
139.610
5.610
BHS
27.08.12
Approved
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 85
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
18.Maintanence Activity Report - Patch work Repairs
Existing Road Maintenance is being carried out and detailed statement as below
Sl. No.
RFI No.
32
L&T DHTL/NH48/HW/15893
33
Description
From
To
Length
Side
Date
Status
Patch work repairing work
134.000
139.610
5.610
BHS
28.08.12
Approved
L&T DHTL/NH48/HW/15963
Patch work repairing work
107.684
110.000
2.316
BHS
30.08.12
Approved
34
L&T DHTL/NH48/HW/15966
Patch work repairing work
110.000
113.000
3.000
BHS
30.08.12
Approved
35
L&T DHTL/NH48/HW/15968
Patch work repairing work
113.000
116.000
3.000
BHS
30.08.12
Approved
36
L&T DHTL/NH48/HW/15971
Patch work repairing work
116.000
117.500
1.500
BHS
30.08.12
Approved
37
L&T DHTL/NH48/HW/15984
Patch work repairing work
121.000
123.500
2.500
BHS
30.08.12
Approved
38
L&T DHTL/NH48/HW/16029
Patch work repairing work
121.000
122.000
1.000
BHS
31.08.12
Approved
L&T DHTL/NH48/HW/16768
13.09.12
Approved
40
L&T DHTL/NH48/HW/17803
Patch work repairing work (
Channaraya panta Town Existing
Patch
road ) work repairing work
41
L&T DHTL/NH48/HW/17805
Patch work repairing work
110.000
113.000
3.000
BHS
29.09.12
Approved
42
L&T DHTL/NH48/HW/19868
Patch work repairing work
112.000
114.000
2.000
BHS
30.10.12
Approved
43
L&T DHTL/NH48/HW/19873
Patch work repairing work
114.000
116.000
2.000
BHS
30.10.12
Approved
44
L&T DHTL/NH48/HW/19940
Patch work repairing work
116.000
117.750
1.750
BHS
31.10.12
Approved
45
L&T DHTL/NH48/HW/19946
Patch work repairing work
121.000
123.000
2.000
BHS
31.10.12
Approved
39
C.R patna
Town
107.684
110.000
2.316
BHS
29.09.12
Approved
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 86
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
18.Maintanence Activity Report - Patch work Repairs
Existing Road Maintenance is being carried out and detailed statement as below
Sl. No.
RFI No.
46
L&T DHTL/NH48/HW/21692
47
Description
From
To
Length
Side
Date
Status
Patch work repairing work
115.000
117.500
2.500
BHS
30.11.12
Approved
L&T DHTL/NH48/HW/21694
Patch work repairing work
125.180
127.500
2.320
BHS
30.11.12
Approved
48
L&T DHTL/NH48/HW/23746
Patch work repairing work
114.000
115.000
1.000
BHS
31.12.12
Approved
49
L&T DHTL/NH48/HW/39766
Premeasurement & Repairing of
patch work
121.35
121.55
0.200
BHS
02.09.13
Approved
50
L&T DHTL/NH48/HW/40361
Premeasument & Patch repairing
work ( C.R. Patna town )
145.000
147.000
2.000
BHS
26.09.13
Approved
51
L&T DHTL/NH48/HW/40382
Premeasurement & repairing of
patch work ( C.R Patna town )
144.000
145.000
1.000
BHS
27.09.13
Approved
52
L&T DHTL/NH48/HW/40990
Premeasurement & repairing of
patch work
121.400
122.000
0.600
BHS
26.10.13
Approved
53
L&T DHTL/NH48/HW/40991
Premeasurement & repairing of
patch work
122.000
122.650
0.650
BHS
26.10.13
Approved
54
L&T DHTL/NH48/HW/41130
Premeasurement & repairing of
patch work
166.500
167.000
0.500
BHS
31.10.13
Approved
Total
107.546
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 87
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Existing Road Maintenance - Filling of Pot Holes
Existing Road Maintenance is being carried out and detailed statement as below
Sl. No.
RFI No.
1
L&T DHTL/NH48/HW/3270
2
Description
From
To
Length
Side
Date
Status
Filling of Pot holes work
107.684
110.000
2.316
BHS
10.08.11
Approved
L&T DHTL/NH48/HW/3530
Filling of Pot holes work
109.000
111.000
2.000
BHS
18.08.11
Approved
3
L&T DHTL/NH48/HW/3564
Filling of Pot holes work
110.000
111.000
1.000
BHS
19.08.11
Approved
4
L&T DHTL/NH48/HW/3597
Filling of Pot holes work
111.000
112.000
1.000
BHS
20.08.11
Approved
5
L&T DHTL/NH48/HW/3662
Filling of Pot holes work
111.000
113.000
2.000
BHS
22.08.11
Approved
6
L&T DHTL/NH48/HW/3730
Filling of Pot holes work
114.000
116.000
2.000
BHS
24.08.11
Approved
7
L&T DHTL/NH48/HW/4240
Filling of Pot holes work
123.000
124.000
1.000
BHS
08.09.11
Approved
8
L&T DHTL/NH48/HW/4271
Filling of Pot holes work
126.000
129.000
3.000
BHS
09.09.11
Approved
9
L&T DHTL/NH48/HW/4705
Filling of Pot holes work
128.000
129.000
1.000
BHS
22.09.11
Approved
10
L&T DHTL/NH48/HW/4740
Filling of Pot holes work
129.000
130.000
1.000
BHS
23.09.11
Approved
11
L&T DHTL/NH48/HW/5680
Filling of Pot holes work
131.000
136.000
5.000
BHS
09.11.11
Approved
12
L&T DHTL/NH48/HW/9948
Pre measurement for repair of Pot holes
175.000
179.000
4.000
BHS
31.03.12
Approved
13
L&T DHTL/NH48/HW/10811
Repair of Pot holes
158.000
166.000
8.000
BHS
03.05.12
Approved
14
L&T DHTL/NH48/HW/11222
Pot hole repairing work
134.000
139.700
5.700
BHS
14.05.12
Approved
15
L&T DHTL/NH48/HW/11238
Pot hole repairing work
157.880
166.500
8.620
BHS
14.05.12
Approved
16
L&T DHTL/NH48/HW/26296
Pot hole repairing work
177.000
184.000
7.000
BHS
08.02.13
Approved
17
L&T DHTL/NH48/HW/32577
Pot hole repairing work
167.000
168.000
1.000
BHS
30.04.13
Approved
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 88
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Existing Road Maintenance - Filling of Pot Holes
Existing Road Maintenance is being carried out and detailed statement as below
Sl. No.
RFI No.
18
L&T DHTL/NH48/HW/36008
Description
From
To
Length
Side
Date
Status
Pot hole repairing work
121.430
122.640
1.210
BHS
27.06.13
Approved
19
L&T DHTL/NH48/HW/41091
Over lay of BC
121.400
122.000
0.600
BHS
30.10.13
Approved
20
L&T DHTL/NH48/HW/41092
165.680
166.500
0.820
BHS
30.10.13
Approved
21
L&T DHTL/NH48/HW/41120
Over lay of BC
Over lay of BC
122.000
122.300
0.300
BHS
31.10.13
Approved
22
L&T DHTL/NH48/HW/41131
Over lay of BC
166.500
167.000
0.500
BHS
31.10.13
Approved
23
L&T DHTL/NH48/HW/41168
Over lay of BC
122.300
122.650
0.350
BHS
01.11.13
Approved
Total
59.416
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 89
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
19.SAFETY REPORT
S.No.
Description
Unit
SITE / PERSONNEL
This
Prev.
Total
Month
Cumulative
SUB-CONTRACTOR
This
Prev.
Total
Month Cumulative
TOTAL
(Staff &
Subcontractor)
Hrs.
3,40,070
1,11,70,060
1,15,10,130
0
55,38,8150
5,54,39,150
6,69,49,280
Nos.
0
1
1
0
0
0
1
Days
0
0
0
0
0
0
0
1
Man-hours Worked (Hrs.)
2
Total of Accident / Incident Reported
3
No. of Lost Workdays (LW)
4
Nos.
0
0
0
0
0
0
0
5
No. of Lost time Injury (LTI)
No. of Fatality
Noos.
0
1
1
0
0
0
1
6
No of Medical Treatment (MT)
Nos.
0
0
0
0
0
0
0
7
No. of Property Damage (Fire/Vehicle)
Nos.
0
1
1
0
0
0
1
8
No. of near Misses (NM)
No. of First Aid Cases
(minor) (FAC)
Nos.
0
0
0
0
0
0
0
Nos.
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
9
(LW x 1000000)
10
LTI Severity
=
11
LTI Frequency
=
Man-hours
worked
(LTI x 1000000)
Man hour
Worked
Workplace Target(Man hours Worked)
Actual Man hours Worked
Man hours Worked Without LTI :
Date of Last LTI Accident :
Remar
ks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 90
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Safety and Traffic Management:
Traffic and Safety has been provided in line with IRC & required specification and for the same is as below
Chainage
Sl.
No
From
To
Length
Sign
boards
1
170.300
172.500
2.200
2
172.500
175.000
3
175.000
4
Delineators
Type III
Barricade
Jercy
Crash
barrier
Required
No’s
Available
No’s
0
0
0
0
0
0
2.500
0
0
0
0
0
0
175.600
0.600
0
0
0
0
0
0
175.600
177.200
1.600
0
0
0
0
0
0
5
177.200
178.150
0.950
0
0
0
0
0
0
6
178.150
178.600
0.450
0
0
0
0
0
0
7
178.600
179.350
0.750
0
0
0
0
0
0
8
179.350
180.650
1.300
0
0
0
0
0
0
9
180.650
181.030
0.380
0
0
0
0
0
0
10
181.030
181.780
0.750
0
0
0
0
0
0
11
181.780
182.250
0.470
0
0
0
0
0
0
12
182.250
182.600
0.350
0
0
0
0
0
0
Bamboos
Remarks
Trafiic allowed on New Carriage way,
Sign Boards provided as per the
drawings
Trafic allowed on New Carriage way,
Sign Boards provided as per the
drawings
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 91
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Chainage
Sl
No
From
To
13
182.600
184.600
Length
Sign
boards
2.000
0
Delineators
Required
No’s
Available
No’s
0
0
Type III
Barricade
Jercy
Crash
barrier
Bamboos
0
0
0
14
184.600
184.720
0.120
0
0
0
0
0
0
15
184.720
184.912
0.192
0
0
0
0
0
0
Remarks
Trafic allowed on New Carriage way,
Sign Boards provided as per the
drawings
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 92
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
20.ACCIDENT REPORT
(1) Stretch: Devihalli -Hassan (NH - 48)
(2) Stretch Chainage: Devihalli - Hassan (km.110.000 to km.189.500)
(3) State:Karnataka
(4) District: Mandya , Hassan
(5) Name of Police Stations: Hirisave, C.R.Patna, Shanthigrama, Dandiganahalli & Hassan
LH
S
Rural
Head
-tail
Fatal
2
5-042014
8.40
112.00
0
RH
S
Rural
Upsi
de
Mino
r
Over
spee
d
Drive
r
negli
genc
y82
2
0
4
LCV
1
0
0
RPV, TOW
&Ambulance
Flat
Road
No
Intersecti
on
Norma
l
Car
0
0
0
RPV
Help provided by
Ambulance/patrol vehicle
Norma
l
Non-Injury
No
Intersecti
on
Vehicle responsible
Flat
Road
Remarks
No. of Animals killed if any
No. of Affected
Persons.
Minor
163.20
0
H'
Grievous
1.10
G'
Fatal
4-042014
2
0
4
F'
Weather Condition
Cause
1
E'
Intersection Type and Control
D'
Road Condition
C'
Road Feature
B'
Classification of Accident
Urban/Rural
Accident
Location
LHS/RHS
Chainage
Time of Accident (am/pm
Date/Month/ Year
Sl. No.
A'
Nature of Accident
20.ACCIDENT REPORT
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 93
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
3
06.04.2
014
20:48
PM
120.00
0KM,M
CW,
RH
S
Over
takin
g
Mino
r
4
07-042014
09:30
119.80
0
RH
S
Upsi
de
-
4
08.04.2
014
5
09.04.2
014
6
09.04.2
014
7
8
9
10
10.04.2
014
12.04.2
014
13.04.2
014
13.04.2
014
AM
05:15
PM
11:31
PM
16:37
PM
05:37
AM
16:56
PM
03:03
AM
19:10
PM
175.15
0KM,M
CW,
Mino
r&
Grev
ious
Grev
Drive
r
negli
genc
Drive
y82
r
negli
genc
Drink
y82
&driv
LH
S
Head
-tail
113.60
0KM,M
CW,
LH
S
Over
takin
g
143.10
0KM,O
TH,
LH
S
Over
spee
d
Grev
ious
Drive
r
negli
genc
Drive
yr
111.15
0KM,O
TH,
LH
S
Over
spee
d
Non
ijury
negli
genc
Drive
yr
115.10
0KM,O
TH,
RH
S
Grev
ious
123.61
0KM,M
CW,
RH
S
Illega
l
medi
an
Contr
openi
ol
ng
lost
negli
genc
Vehic
y
le
Fatal
contr
ol
Contr
lost
ol
122.40
0KM,M
CW,
RH
S
vehic
Over
le
spee
d
ious
e
lost
Grev
ious
Drive
r
negli
genc
y
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Car(Lc
v)
0
0
0
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Lcv
0
0
0
RPV,Tow
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Car&tr
actor
0
1
1
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
0
1
0
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Bus&T
wo
wheele
r
Bus&
0
1
0
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
0
0
0
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
0
1
0
RPV,Ambulan
ce
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
1
0
0
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
0
1
0
RPV
MAV
Car&T
wo
wheele
rrrrrrrrr
Car
rrrrr
Lcv
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 94
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
11
16.04.2
014
06:10
AM
140.60
0KM,M
CW,
LH
S
12
18.04.2
014
09:19
AM
117.70
0KM,M
CW,
LH
S
109.60
0KM,M
CW,
RH
S
13
19.04.2
014
20:36
PM
Left
turn
collisi
on
Head
-tail
Upsi
de
Non
ijury
Drive
r
negli
genc
Drive
yr
Non
ijury
negli
genc
Viehi
y
cle
Non
ijury
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Lcv
00
0
0
0
RPV,
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Car&L
cv
0
0
0
RPV
2
0
5
Flat
Road
No
Intersecti
on
Norma
l
Truck
0
0
0
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Truck
0
0
0
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Lcv
&Car
0
0
1
RPV
2
0
5
Flat
Road
No
Intersecti
on
Norma
l
Two
wheele
r
0
0
1
RPV
Flat
Road
No
Intersecti
on
Norma
l
0
0
RPV
2
0
5
Flat
Road
No
Intersecti
on
Norma
l
Car&T
wo
wheele
r
Two
0
d
2
0
4
wheele
r
0
0
0
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Lcv
0
0
0
RPV
contr
ol l
Drive
14
20.04.2
014
17:32
AM
153.80
0KM,M
CW,
RH
S
Upsi
de
Non
ijury
15
22.04.2
014
04:25
AM
158.60
0KM,M
CW,
LH
S
Head
-tail
Mino
r
16
23.04.2
014
06:23
131.60
0KM,O
TH,
LH
S
Mino
r
09:45
AM
113.60
0KM,M
CW,
LH
S
Sing
al
vehic
le
Head
Drive
r
negli
genc
Drive
yr
-
negli
genc
Over
y
spee
17
23.04.2
014
AM
18
24.04.2
014
02:03
PM
157.50
0KM,M
CW,
19
24.04.2
014
02:48
PM
155.85
0KM,M
CW,
-on
r
negli
RH
S
Sing
al
vehic
-
Drive
r
negli
RH
S
Upsi
de
-
Over
spee
d
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Page No: 95
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
20
26.04.2
014
08:57
PM
115.80
0KM,O
TH,
LH
S
Upsi
de
-
21
27.04.2
014
06:38
AM
141.20
0KM,O
TH,
LH
S
Upsi
de
Mino
r
Drive
r
negli
genc
Drink
y
&driv
e
22
27.04.2
014
07:40
AM
113.10
0KM,M
CW,
RH
S
Head
-tail
-
23
27.04.2
014
09:10
AM
109.10
0KM,M
CW,
RH
S
Over
spee
d
Mino
r
Drive
r
negli
genc
Drive
yr
123.20
0KM,M
CW,
LH
S
Head
-tail
-
negli
genc
Drive
yr
134.95
0KM,M
CW,
LH
S
Grev
ious
negli
genc
Vehic
y
le
162.80
0KM,M
CW,
LH
S
Grev
ious
lost
contr
Drive
ol
r
24
25
26
30.04.2
014
30.04.2
014
30.04.2
014
07:25
AM
20:30
PM
21:27
PM
Head
-tail
Head
-tail
negli
genc
y
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Two
wheele
r
0
0
0
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Car
0
0
1
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Car&C
ar
0
2
0
0
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
0
0
2
RPV
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
Truck
&Two
wheele
r
Car&C
0
0
0
RPV
2
0
5
Flat
Road
No
Intersecti
on
Norma
l
0
1
0
RPV,Police
2
0
4
Flat
Road
No
Intersecti
on
Norma
l
0
1
0
RPV
ar
Car&T
wo
wheele
r
Car&T
wo
wheele
r
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
Page No: 96
MONTH: APRIL - 2014
Note:
A: Urban/Rural and Details of Surrounding Land use
B: 1-Overturning, 2-Head on collision, 3-Rear end collision, 4- Collision Brush/Slide wipe 5-Right turn collision, 6-Skidding, 7-Right collision,
8-Others
C: 1-Fatal, 2-Grievous injury, 3-Vechicle out of control, 4-Non injury
D: 1- Drunken, 2-over speeding, 3-Vehicle out control, 4-Fault of driver of motor vehicle/driver of other
vehicle/cyclist/pedestrian/passenger, 5-Defect in mechanical condition of motor vehicle/road condition
E: 1-Single lane, 2-Two lanes, 3- Three lanes or more without central divider (median), 4-Four lanes for more with central divider
F: 1- Straight lane, 2- slight curve, 3-Sharp curve, 4- flat road, 5-Gentle incline, 6-Steep incline, 7- Hump, 8-Dip
G: 1- T- Junction, 2-y-Junction, 3-Four arm junction, 4- Staggered junction, 5-Junction with more than 4arms, 6- Roundabout junction, 7manned rail crossing, 9-Unmanned rail crossing.
H: 1-Fine, 2-Mist/Fog, 3-Cloudy, 4-Light rain, 5-Heavy rain, 6-Hall sleet, 7-Snow, 8-Strong wind, 9-Dust storm, 10-Very hot, 11-very cold,
12- Other extraordinary weather condition.
`
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - A
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
21. PROGRESS PHOTOGRAPHS
Page No: 97
`
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - A
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Page No: 98
`
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - A
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Page No: 99
`
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - A
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
Page No: 100
`
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - A
MONTHLY PROGRESS REPORT
Page No: 101
MONTH: APRIL - 2014
Joint Inspection Report For Hindrances Along With NHAI, Independent Engineer & Concessionaire (updated as on 30-04-2014)
VALUATION (RHS)
Sl.
No
Chainage
Village
From
To
Length
(kms)
Survey
Numbers
Party / Owner
Name
Type of
Obstruction
Action
Pending from
NHAI
Remarks as on Date
Hassan District
1
Heggdihalli *
125.670
125.770
0.100
2
Yeliyur
154.150
154.260
0.110
Grampanchayat
Building
166.570
166.590
0.020
Post office
166.970
167.000
0.030
School
167.200
167.280
0.080
Land
Shantigrama
3
Total
Gramathana
0.340
A) Four laning Carriageway (Ch.107+684 to Ch.139+677
& Ch.148+824 to Ch.175+163)
B) New 2 Lane Carriageway for Channarayapatna
Bypass (Ch.139+677 to Ch.148+824)
Total
0.340 Kms
0.000 Kms
0.340 Kms
Pipeline /Land
Supplementary
Award
Payment yet to
passed, payment yet to be
be released
made by SLAO.
Payment yet to land not available for COS
be released
proposal of service road
Payment yet to
be released
Payment yet to
be released
Payment yet to
be released
documents not submitted by
the party
tree payments pending
documents not submitted by
the party
`
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - A
MONTHLY PROGRESS REPORT
Page No: 102
MONTH: APRIL - 2014
Joint Inspection Report For Hindrances Along With NHAI, Independent Engineer & Concessionaire (updated as on 30-04-2014)
LAW & ORDER ISSUES (LHS)
Sl.
No
Chainage
Village
From
To
Length
(kms)
Survey
Numbers
Owner
Name
Type of
Obstruction
Problems faced
by
Concessionaire
0.010
37
Village
Panchayat
Temple
Party is not
Vacanting
Action Pending
from NHAI
Eviction Notice
yet to be issued
Remarks as on
date
Hassan District
1
Jogipura
138.350
Total
138.360
0.010
A) Four laning Carriageway (Ch.107+684 to Ch.139+677
& Ch.148+824 to Ch.175+163)
B) New 2 Lane Carriageway for Channarayapatna Bypass
(Ch.139+677 to Ch.148+824)
Total
0.010 Kms
0.000 Kms
0.010 Kms
Hindrance for
drain
`
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - A
MONTHLY PROGRESS REPORT
Page No: 103
MONTH: APRIL - 2014
Sl.
No
Joint Inspection Report For Hindrances Along With NHAI, Independent Engineer & Concessionaire on 30.11.2012(updated as on 31-01-2014)
VALUATION ISSUES (LHS)
Chainage
Length
Survey
Type of
Action Pending
Village
Owner Name
Remarks as on date
(kms)
Numbers
Obstruction
from NHAI
From
To
Mandya District
1
Nagtihalli
111.890
111.900
0.010
85,86
Balamoorthy
154.030
154.080
0.050
113/2,113/1
Ratnamma,Raith
samparka Kendra
Supplementary Award has been
submitted to P.D. NHAI for
approval
House
Hassan District
2
Yeliyur
Total
0.060
a) Four laning Carriageway (Ch.107+684 to Ch.139+677
& Ch.148+824 to Ch.175+163)
b) New 2 Lane Carriageway for Channarayapatna Bypass
(Ch.139+677 to Ch.148+824)
Total
0.060 Kms
0.000 Kms
0.060 Kms
Land
Payment yet to
be released
Supplementary Award passed,
payment yet to be made by SLAO.
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - C
Page No: 104
MONTHLY PROGRESS REPORT
MONTH : APRIL - 2014
Status of Electrical Utility shifting Works
Sl No
I
1
2
3
4
5
6
7
8
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
21
1
2
3
4
5
6
7
8
9
Estimate Details As Per Work Order-2013
Estimate for Devihalli to Kadabahalli Section of
Nagamangala Taluk
WORK ACTIVITIES
PART A-EXTENTION OF 11KV LINE
Erection of 9M RCC Poles
Horizontal X arm with HT supply
Disc insulator 45 Kn
11KV pin insulator
GUY set
Spiral Earth Electrode
Rabbit Conductor +1.5% sag
DP Set 9 Mtrs
PART-B-LAYING OF CABLE
DP Set 9 Mtrs
GOS 200AS B
Sand
Tiles
11KV class 3X95/240 Sq.mm XLPE UG Cable
Cable Termination Kit out door HS pipe
RCC Hume Pipe 2000mm long 150mm Dia
GI pipe 150mm Dia
COLAR
Cable Trench excavation
Providing 63KVA Transformer on 9Mtr pole as per S R
Shifting Transformer of existing 100KVA
Shifting Transformer of existing 25/63KVA
1.1KV pin insulator
No 8KV strain insulator
4Pin X arm
2Pin X arm
GUY set
2ACSR concuctor +1.5%sag
RCC Poles 8Mtr Long
PART C-ERRECTION/SHIFTING TRANSFORMER
Providing 63KVA Transformer on 9M pole as per S R
Shifting Transformer of Existing 25/63 KVA
Transformer
RCC Poles 8Mtrs Long
4Pin X arm
2 Pin X arm
Guy Set
No 8KV strain insulator
1.1KV Pin insulator
2ACSR Conductor +1.5% sag
Unit
Total Scope
Completed
Nos
Sets
Nos
Sets
Sets
Sets
Km
Sets
284
315
207
943
86
284
44.7
14
284.00
315.00
207.00
942.00
84.00
284.00
44.7
14.00
Set
Set
Cmt
Nos
Mtr
Set
Nos
Nos
Nos
Cmt
Set
Set
Set
set
Nos
set
set
set
km
Nos
6
6
30
300
0.75
12
30
48
30
450
6
5
1
24
12
9
0
2
0.8
2
6.00
6.00
30.00
300.00
0.75
12.00
30.00
48.00
30.00
450.00
6.00
5.00
0.00
24.00
12.00
9.00
0.00
2.00
0.80
2.00
Set
Set
3
2
3.00
2.00
Nos
set
Set
Set
Nos
Set
km
6
79
44
15
114
262
16.94
6.00
79.00
44.00
15.00
114.00
262.00
16.20
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - C
Page No: 105
MONTHLY PROGRESS REPORT
MONTH : APRIL - 2014
Status of Electrical Utility shifting Works
Sl No
1
2
3
4
5
6
7
9
1
2
3
4
5
6
II
1
2
3
4
5
6
7
8
9
1
2
3
4
5
6
7
8
1
2
Estimate Details As Per Work Order-2013
PART D-EXTENTION OF LT LINE
RCC Pole 8/9M long
4 Pin x arm
2 Pin X arm
Guy set
No 8KV starain insulator
1.1 KV pin insulator
2ACSR Conductor +1.5% sag
Electrical inspectorate Charges
PART E-DE-COMMISION LABOUR CHARGES
Releasing of 8Mtr RCC/PCC poles
Releasing of 9Mtr RCC/PCC poles
Releasing of X arms
Releasing of conductor 2/4ACSR
Releasing of conductor Rabbit
Releasing of DP set
Estimate for Kirisave gadi to Goolihomenahalli
Village in Hirisave Section
WORK ACTIVITIES
PART A-EXTENTION OF 11KV LINE
DP Structure using 9Mtr long Poles complete set
RCC Poles 9Mtr Long
PSC Pole 9 Mtr long
Spiral Earth Electrode
11KV Horizontal X arm
11KV pin insulator
Disc insulator 45KN
Guy set
Rabbit Conductor with 1.5%sag
PART-B-LAYING OF HT UG CABLE
DP structure using 9Mtr long poles
Sturt pole with fish plates,clamps(PSC 8 Mtrs)
GOS single break 200A
H frame for mounting GOS
11KV class 3X 400 Sq.mm XLPE UG cable
Outdoor pot head 400Sq.mm
GI PIPE 150mm dia
RCC hume pipe 2000mm long 150mm dia
PART C-ERRECTION/SHIFTING TRANSFORMER
Erection of 25KVA Transformer centre by 9Mtrs long
RCC pole DP Structure
Erection of 63KVA Transformer centre by 9Mtrs long
RCC pole DP Structure
Unit
Total Scope
Completed
Nos
set
set
set
Nos
set
km
26
40
35
9
54
142
6.64
26.00
40.00
35.00
9.00
53.00
141.00
6.70
Nos
Nos
Set
Km
Km
Set
47
138
203
4
21.4
5
47.00
138.00
203.00
4.00
21.00
5.00
Set
Nos
Nos
Nos
Set
Nos
Nos
Set
Km
43
218
274
492
518
1446
672
191
68.21
43.00
218.00
274.00
492.00
517.00
1445.00
670.00
191.00
68.20
Set
Set
Set
Nos
Mtrs
Nos
Mtrs
Nos
32
64
32
32
3880
64
384
960
32.00
64.00
32.00
32.00
3853.00
63.00
380.00
960.00
set
3
3.00
set
18
18.00
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - C
Page No: 106
MONTHLY PROGRESS REPORT
MONTH : APRIL - 2014
Status of Electrical Utility shifting Works
Sl No
3
1
2
3
4
5
6
7
1
2
3
4
5
6
7
8
9
10
1
2
3
1
2
3
4
5
6
7
8
Estimate Details As Per Work Order
-2013
Erection of 100KVA Transformer centre by 9Mtrs long
RCC pole DP structure
PART D-EXTENTION OF LT LINE
RCC pole 8Mtr long
PSC pole 8Mtr long
4 Pin X arm
1.1KV Pin insulator
No 8KV strain insulator
Guy set
2 ACSR with1.5% sag
PART E -PROVIDING LT ABC CABLE
1.1KV Class 3Phase ABC Cable of size 3X95 + 1X16 +
1X70 Sq.mm
Distribution box 3Phase
Piercing connector suitable for 16-95 Sq.mm AB cable
for service connection
Piercing connector suitable for 16-95 Sq.mm AB cable
for street light connection
Suspension clamp assembly
Universal hook with bolts & nuts
T Connector KZ395
Cable straight through joints
End cap
PBC insulated wire 16/25 Sqmm
PART F- SHIFTING OF EXISTING DTC's
Erection of 25KVA Transformer centre by 9Mtr long
RCC pole DP structure with all accessories(excluding
25KVA DTC) as per cost data sheet
Erection of 63KVA Transformer centre by 9Mtr long
RCC pole DP structure with all accessories(excluding
25KVA DTC) as per cost data sheet
Erection of 100KVA Transformer centre by 9Mtr long
RCC pole DP structure with all accessories(excluding
25KVA DTC) as per cost data sheet
PART G- DE-COMMISION LABOUR CHARGES
Releasing of poles 9Mtrs
Releasing of poles 8Mtrs
Releasing of X arms
Releasing of conductor Rabbit
Releasing of conductor 2/4 ACSR
Releasing of Guy set
Releasing & re erection of 100KVA DTC
Releasing & re erection of 63KVA DTC
Unit
set
Total Scope
7
Completed
7.00
Nos
Nos
set
Nos
Nos
set
Kms
41
69
231
380
540
34
23.1
41.00
69.00
231.00
380.00
538.00
34.00
23.10
Kms
2.5
Nil
Nos
set
50
150
Nil
Nil
set
63
Nil
set
set
Nos
set
Nos
Mtrs
63
40
20
13
125
1200
Nil
Nil
Nil
Nil
Nil
Nil
set
6
6.00
set
8
8.00
set
7
7.00
Nos
Nos
set
Kms
Kms
set
set
set
198
53
418
13.86
42.64
54
7
8
198.00
53.00
418.00
13.80
42.64
54.00
7.00
8.00
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - C
Page No: 107
MONTHLY PROGRESS REPORT
MONTH : APRIL - 2014
Status of Electrical Utility shifting Works
Sl No
9
10
11
12
13
14
15
III
1
2
3
4
5
6
7
8
9
10
11
1
2
3
4
5
6
7
8
1
2
3
1
2
3
4
Estimate Details As Per Work Order-2013
Releasing & re erection of25KVA DTC
Releasing 100KVA Tr. Structure
Releasing 63KVA Tr. Structure
Releasing 25KVA Tr. Structure
Releasing of DP Structure
Releasing of GOS
Releasing of H frame
Estimate for Hosakoppalu Gate to Dandiganahalli
Village in Udayapura Section
WORK ACTIVITIES
PART A-EXTENTION OF 11KV LINE
DP Structure using 9Mtr long Poles complete set
RCC Poles 9Mtr Long
PSC Pole 9 Mtr long
Spiral Earth Electrode
11KV Horizontal X arm
11KV pin insulator
Disc insulator 45KN
Guy set
Sturt pole with fish plates,clamps (PSC 8Mtrs)
Road Gaurding
Rabbit Conductor with 1.5%sag
PART-B-LAYING OF HT UG CABLE
DP structure using 9Mtr long poles
Sturt pole with fish plates,clamps(PSC 8 Mtrs)
GOS single break 200A
H frame for mounting GOS
11KV class 3X 400 Sq.mm XLPE UG cable
Out door pot head 400Sq.mm
GI PIPE 150mm dia
RCC hume pipe 2000mm long 150mm dia
PART C-ERRECTION/SHIFTING TRANSFORMER
Erection of 25KVA Transformer centre by 9Mtrs long
RCC pole DP Structure
Erection of 63KVA Transformer centre by 9Mtrs long
RCC pole DP Structure
Erection of 100KVA Transformer centre by 9Mtrs long
RCC pole DP structure
PART D-EXTENTION OF LT LINE
RCC pole 8Mtr long
PSC pole 8Mtr long
4 Pin X arm
1.1KV Pin insulator
Unit
set
set
set
set
set
set
Nos
Total Scope
6
7
8
6
5
1
1
Completed
6.00
7.00
8.00
6.00
5.00
1.00
1.00
Set
Nos
Nos
Nos
Set
Nos
Nos
Set
Set
Set
Km
10
110
382
492
580
1455
546
145
4
6
67.3
10.00
110.00
378.00
492.00
549.00
1435.00
536.00
142.00
2.00
4.00
58.00
Set
Set
Set
Nos
Mtrs
Nos
Mtrs
Nos
38
80
38
38
3640
80
480
1240
33.00
50.00
34.00
35.00
3617.00
68.00
465.00
1025.00
set
15
10.00
set
14
12.00
set
2
1.00
Nos
Nos
set
Nos
73
83
349
682
69.00
79.00
335.00
675.00
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - C
Page No: 108
MONTHLY PROGRESS REPORT
MONTH : APRIL - 2014
Status of Electrical Utility shifting Works
Sl No
5
6
7
1
2
3
4
5
6
7
1
2
3
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
IV
Estimate Details As Per Work Order-2013
No 8KV strain insulator
Guy set
2 ACSR with1.5% sag
Unit
Nos
set
Kms
Total Scope
766
113
40.2
Completed
738.00
113.00
39.40
PART E -PROVIDING LT UG CABLE
RCC pole 9Mtr long
Sturt pole with fish plates,clamps (PSC 8Mtrs)
4 Pin X arm
LT UG cable 31/2 X 120 Sq.mm
Pot Head 120 Sq.mm
GI Pipe 150mm Dia
RCC Hume pipe 2000mm long 150mm Dia
set
set
set
Mtrs
Nos
Nos
Nos
8
8
8
720
16
96
240
Nil
Nil
Nil
Nil
Nil
Nil
Nil
set
9
7.00
set
8
6.00
set
6
5.00
Nos
Nos
set
Kms
Kms
set
set
set
set
set
set
set
set
set
Nos
188
229
540
13.125
43.801
66
10
8
9
10
8
9
10
1
1
179.00
210.00
523.00
12.40
41.60
62.00
8.00
6.00
7.00
7.00
6.00
6.00
9.00
1.00
1.00
PART F- SHIFTING OF EXISTING DTC's
Erection of 25KVA Transformer centre by 9Mtr long
RCC pole DP structure with all accessories(excluding
25KVA DTC) as per cost data sheet
Erection of 63KVA Transformer centre by 9Mtr long
RCC pole DP structure with all accessories(excluding
25KVA DTC) as per cost data sheet
Erection of 100KVA Transformer centre by 9Mtr long
RCC pole DP structure with all accessories(excluding
25KVA DTC) as per cost data sheet
PART G- DE-COMMISION LABOUR CHARGES
Releasing of poles 9Mtrs
Releasing of poles 8Mtrs
Releasing of X arms
Releasing of conductor Rabbit
Releasing of conductor 2/4 ACSR
Releasing of Guy set
Releasing & re erection of 100KVA DTC
Releasing & re erection of 63KVA DTC
Releasing & re erection of25KVA DTC
Releasing 100KVA Tr. Structure
Releasing 63KVA Tr. Structure
Releasing 25KVA Tr. Structure
Releasing of DP Structure
Releasing of GOS
Releasing of H frame
Estimate for Agriculture College to Anachihalli Limits
in Hassan Taluk
WORK ACTIVITIES
PART A-EXTENTION OF 11KV LINE
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - C
Page No: 109
MONTHLY PROGRESS REPORT
MONTH : APRIL - 2014
Status of Electrical Utility shifting Works
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
Estimate Details As Per Work Order-2013
Running Single Circuit 11KV 3Phase power line on
9Mtr Supports with an average span 40Mtrs using
Rabbit ACSr Conductor as per cost data Sheet1(Location between Agriculture College to
Kasturavally Limits of S Grama section)
RCC poles 9Mtrs long
Spiral Earth electrode
Horizontal X arm with HTST support
45KN disc insulators
11KV pin insulators with GI pin
Guy Set Complete
Rabbit ACSR conductor with 1.5% sag
Coyote ACSR conductor with 1.5% sag
Stud pole using PSC 8Mtr long with accessories
4 Pin X arm for LT line crossing
1.1KV pin insulators
Special 3 Pin X arm for Dead End & Tapping Points
3 pole structure using 9Mtr RCC for Fdr terminations
2 pole structures with GOS 11KV class D/B or S/B 200
2 pole DP structure using 9Mtr RCC without GOS
PART B- LAYING OF UG CABLE
2 poles structure complete set using 9Mtr RCC poles
with 200A SB,GOS
11KV class,3*95/240/400 Sqmm XLPE UG cable 2 runs
DP to DP for road crossing
Heat shrinkable termination kit HS type suitable for
95/240/400 Sqmm cable
Straight through jointing kits HS type suitable for
95/240/400Sqmm cable
RCC Hume pipe 2000mm long & 150mm dia
Collars for RCC Hume pipe
GI pipe 150mm dia for cable raising
Cable covering tiles 250x250x40 mm
Sand for cable covering
Lighting arrester
cable trench excavation 60x0.6x1=36cmtx20 crossing
Laying of cable in a trench
Refilling & Consolidation
Covering the cable with tiles
Spreading sand & round the cable
Laying of RCC Hume pipe
PART C- ERECTION OF TRANSFORMER CENTERS
Providing 25 KVA 11KV class 3PH transformer using
9Mtr RCC poles
Unit
Total Scope
Completed
Km
26.2
Nos
Nos
set
set
set
Nos
Km
Km
Nos
Nos
Nos
Nos
Nos
set
Nos
298
298
323
248
910
97
33.3
0.81
25
15
45
20
3
35
1
275
267
295
213
657
74
29.6
Nos
40
25
Km
4
2
Nos
80
Nos
18
Nos
Nos
Mtr
Nos
Cmtr
set
Cmtr
Km
Cmtr
Km
Km
Mtr
1000
1000
240
800
150
40
720
4
667
2
2
2000
Nos
9
17
10
36
22
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - C
Page No: 110
MONTHLY PROGRESS REPORT
MONTH : APRIL - 2014
Status of Electrical Utility shifting Works
Sl No
2
3
4
5
-2013
Estimate Details As Per Work Order
Providing 25 KVA 11KV class 3PH transformer using
9Mtr RCC poles(Excluding transformer cost)
Providing 63 KVA 11KV class 3PH transformer using
9Mtr RCC poles
Providing 63 KVA 11KV class 3PH transformer using
9Mtr RCC poles(Excluding transformer cost)
Providing 100KVA 11KV class 3PH transformer using
9Mtr RCC poles(Excluding transformer cost)
Unit
Total Scope
Completed
nos
4
nos
22
16
nos
12
8
nos
4
1
2
3
4
5
6
7
8
9
PART -D EXTENSION OF LT LINES
RCC poles 9Mtrs long
Spiral earth electrode
4 Pin X arm along with bolts & nuts
1.1KV pin insulator with GI pin
No 8 Strain insulator
Guy set complete
No2 ACSR conductor with 1.5% sag
Stud pole using 8 Mt PSC pole with accessories
Road guarding cradle type
Nos
Nos
set
Nos
Nos
Nos
Km
Nos
Nos
250
250
430
872
880
102
56
30
10
123
226
298
372
544
96
44
15
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
PART E- DE-COMMISION LABOUR CHARGES
Releasing of RCC pole 9Mtr long
releasing of RCC pole 8Mtr long
Releasing of PCC pole 8Mtr long
Releasing of Rail pole 8Mtr long
Releasing of rail pole DP structure materials
Releasing of TC structure set
Releasing of Spmt TC structure
Releasing of DP structure set
Releasing of H X-arms
Releasing of 4 Pin X arms
Releasing of 2 Pin X arms
Releasing GOS S/B 200A
Releasing of 2 ACSR conductor
Releasing of 4 ACSR conductor
Releasing of 1 ACSR conductor
Releasing of 25KVA Transformer
Releasing of 63KVA Transformer
Releasing of 100KVA Transformer
Nos
Nos
Nos
Nos
set
set
set
set
Nos
Nos
Nos
set
Kms
Kms
Kms
Nos
Nos
Nos
412
142
191
30
5
19
1
26
578
138
21
4
9.37
34.12
63.21
4
12
4
328
121
147
12
2
14
14
28
13
7
2.9
55.2
2
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - C
Page No: 111
MONTHLY PROGRESS REPORT
MONTH : APRIL - 2014
Status of Water Pipe Line Shifting and tank bunds shifting Works
Sl No
1
2
-2013
Unit
Total
Scope
Completed
a) Sinking of Bore wells
b) Sinking of Bore well & Providing Hand Pump
Nos
Nos
3
8
3
8
c) Construction of 1200 mm dia. RCC Hume Pipe
Pump House
Nos
2
3
d) Construction of Hume Cistern
e) 75 mm 6Kgs/ SqM. (PVC)
e) Providing Raising Main 90mm
f) Construction of Chlorination Room
g) Construction of Cattle Tank
Nos
M
M
Nos
Nos
6
8100
2500
1
3
4
8100
2500
1
Nil
a) Sinking of Bore well 150mm dia. & 165mm dia.
b) Installation and commissioning of Hand Pump
c) Providing RCC Hume Pipe House
Nos
Nos
M
5
29
1
5
29
0
d) Erection, Electrification & Commissioning of
150mm dia 7HP/16 state submersible Motor Pump
set unit with control panel board, GI Pipes
NOs
1
0
e) Providing and laying Pipe line with 63mm dia,
4Kg/sq.cm PVC pipe
Rm
11875
11780
f) Providing & laying pipe line with 75mm dia,
4Kg/sq.cm PVC pipe
Rm
2500
2400
Rm
1030
1020
Nos
Nos
Rm
m
m
Nos
27
16
300
800
590
1
22
12
100
750
590
1
1533.6
1000
Rm
2240
2000
Rm
600
450
Description of work
Nagamangala Taluk,Mandya District (km.110.000
to km.120.000)
Channarayapatna Taluk, Hassan
District(km.120.000 to km.163.000)
g) Providing and laying pipe line with 75mm
dia,6Kg/sq.cm PVC pipe
h) Shifting of RCC precast Hume pipe Cistern
i) Providing public fountain
j)Providing & laying RCC pipe NP2
k)90mm 4Kgs
l)90mm 6kgs
l)Pump set
3
Reconstruction of water supply Schemes from KM
163+000 TO 189+500
a)Earthwork Excavation for Pipeline trenches
Cum
b)Providing and installation of PVC pipes and
refilling at sitei)75mm dia PVC 6kg/cm2
ii)63mm dia PVC pipes 6kg/cm
2
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
Annexure - C
Page No: 112
MONTHLY PROGRESS REPORT
MONTH : APRIL - 2014
Status of Water Pipe Line Shifting and tank bunds shifting Works
-2013
Sl No
Description of work
c)providing, laying & refilling of 50mm dia GI pipes
d)Providing, laying & refilling of 20mm dia GI pipes
e)providing, laying & refilling of 32mm dia GI pipes
f) Providing Public fountains
g)Providing Hand pump Bore well
h)Sinking of Bore well of 165mm dia to a depth up
to 150mm
i)Shifting of Precast Hume Pipe Pump House
j)Supplying & Providing RCC Circular Pipe Cistern
Unit
Total
Scope
Completed
Rm
80
75
Rm
69
65
Rm
30
23
Nos
Nos
10
3
3
Nos
Nos
Nos
3
3
3
3
3
1
Remarks
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
-2013
Annexure - D
Page No: 113
CONCESSIONAIRE : L&T DEVIHALLI HASSAN TOLLWAY LIMITED.
EPC CONTRACTOR : LARSEN & TOUBRO LIMITED.
MONTHLY PROGRESS REPORT
MONTH: APRIL - 2014
-2013
Annexure - D
Page No: 114
Download