KFUPM, Department of Construction Engineering and Management Summary of AN IMPLEMENTATION MODEL FOR DESIGN-BUILD (D-B) PROJECT DELIVERY SYSTEM BY : MOHAMMAD RIAD JAWEED January 2004 Summarized by : KHALID L. ALSHAIR INTRODUCTION The Design-Build project delivery method has been enjoying increasing acceptance in recent time . In a questionnaire survey carried out in Saudi Arabia , public clients selected Design-Built as the most appropriate procurement for their objects. The basic feature of the design build method is that it entails single responsibility for the entire object . Actually, it is an expansion of the Single-Contract System to include design as well as construction . STATEMENT OF THE PROBLEM The engineering and construction industry faces formidable challenges . It suffers from low profit margin , persistent project overruns in schedule and budget , and it is plagued with claim and counter claims . Construction industry performance can be improved by use of an appropriate project delivery method . SIGNIFICANCE OF THE STUDY The study aims at developing a model for Design-Build project delivery method implementation . It includes all the phases for implementing Design-Built from project identification to contract administration . OBJECTIVES The objectives of the research are : 1- To get a greater understanding of the DesignBuild method. 2- To identify positive factors favoring the use of the Design-Build method. 3- To develop a Design-Build model. LITERATURE ANALYSIS 1- Project Delivery Method The term “project delivery method “ means the approach used to organize the project so as to manage the entire designing and building process . Following requirements fulfill the complete definition of project delivery : * For a project, its scope and requirements should be clearly stated . * Method of procedure , responsibilities and obligations should be established. * Forming and documentation of agreement . * Actual design and construction . * Handing over the project to the owner . 2- Evolution of Project Delivery Method Obtaining a project within a predefined time , cost and quality is the ultimate goal of the clients . Also the need for more need of financial planning and fewer amount of contracts has increased the possibility of looking out for new construction procurement methods . These factors together with the need for a greater degree of financial planning and a lesser amount of contract administration have brought pressure to explore new option for construction procurement . 3- Risk Assessment in Project Delivery Method Selection : * Completion Risk. * Construction Cost Risk . * Environmental Relation Risk . * Industrial Relation Risk . * Technological Risk . * Market Risk . * Political Risk . The positive factors and problems with Design – Build Method The Positive Factors favoring the use of Design-Build : Single point of Responsibility. All parties treated as professionals. Time Savings . Early knowledge of firm costs. Higher Quality. Cost-effectiveness of Design-Build. Encourages Innovation. Lower claims and litigation. Reduced Administration. Problems with Design-Build Method * Unfamiliarity with process. * Communicating owner’s needs in Design-Build is different. * Barriers in procurement and licensing laws . Development of Design Build Model The approach for model development is shown in figure. DESIGN-BUILD MODEL PHASE 1 Identify facilities for DB PHASE 2 Program Definition PHASE 3 Prequalification PHASE 4 Proposal Evaluation Project characteristics Owner Requirements Applicable Market sectors Previously constructed /Design facilities Needs Legal Limitation Financial limitation Objectives Costs Market Organization and management plan Financial Capacity Qualification of key personnel Design-Build experience Weighted Criteria Adjusted low bid Equivalent design /low bid Meets Criteria/low bid CONCLUSION The construction industry performs unsatisfactory and suffers from low profit margin and persistent project overruns in schedule and budget . The increased understanding of Design-Build project delivery will help in successful implementation of this fast growing project delivery method . The use of an appropriate project delivery method is one of the key area for the improvement of the industry. Recommendation The Design-Build method is gaining popularity as an attractive and desirable project delivery method for all types of projects . Benefits to gained are a single source of responsibility , reduced cost , reduced time, innovation, established cost , reduced claims , improved quality , improved risk management and improved productivity. THANK YOU