SMEC INTERNATIONAL Pty. Ltd. Daily Activity Report of Project Site Engineer - TPQC 1. Name of Contractor Agency : G.V.R. Infra 2. Package No :7 3. Location-Chainage 4. Date : 21st main Branch canal 52.300 to 117.007(NSLC) :14- 03- 2012 Team Present: Sl.No. 1 Irrigation Department B. Srinivasa Reddy (AE) 2 Contractor 3rdParty QC &QA Suresh (Site Engineer) V.Anantha Rama Rao (PSE) Kishore (Site Engineer) J. Srinivasa Rao (TI) 1. Description of Work:A). Earth Work, Sub-grade, Banking. B). CC Lining – Bed, Right side and Left side slopes. C). Shot creting – L/S, R/S walls. D). Structures – Foundation level, Sub-Structure, Super Structure. Parapet wall 2. Visual Observations:Constructing CC M15 for parapet wall in Km 114.170 to 113.800 L/S. Work is in progress Collected two sets of CC cubes , Cement sample collected for testing in the Laboratory. A) EARTH WORK 1). Type of Sub-grade (Soil, Rock) 2). Free of Stumps 3). Method of consolidation of Embankment NO WORK 4). Objectionable materials 5). Method of compaction and moisturing of sub-grade 6) Benching. B) CC LINING 1) Graded Filter 2) Porous Plugs 3) Profile walls NO WORK 4) Method of laying concrete 5) Under drainage provisions in the bed 6) P.V.C strips 7) Bed level etc. C)SHOT CRETING 1) Type of sub-grade. 2) Cleaning of sub-grade NO WORK 3) Filling of deep cuts 4) Proportion of concrete mix and plasticizers 5) Number of layers and their thickness 6) Reinforcement grid D) STRUCTURES 1) Verification with Approved Drawings. 2) Type of foundation strata 3) Foundation level, 4) SBC as per design drawings as per execution. 5) Dimensions of foundation as per design and mark out 6) Grade of concrete 7) Maximum size of C.A. 8) Method of Concrete Manufacturing 9) Reinforcement Verified Gravelly soils Verified YES YES CC M15 40mm CC Miller by weighing method Nil Work done Qty cc M15 in this week 80 cum No of tests to be done by agency 3. Field Tests Conducted:a) FDD/FMC Test for Earth Work b) Thickness of lining…………………........................ c) CC cubes casting d) slump test at Batching Plant and at site e) Aggregates Testing f) Bulkage g) Silt content h)Permeability (Japanese method) i) Flakiness Index k) Elongation Index 10% to be done by TPQC 1/300m³ As per 2 sets requirement 1)50mm Work done Qty As per required 80cum 4/50 m³ 1/150m³ 1/150m³ 1/150m³ 1/3m 1/150m³ 1/150m³ Tests done by TPQC 2 Sets of Samples of M15 cc cubes are collected. One sample of cement collected for testing in laboratory. 4. Deficiencies and Suggestions if any :No Deficiencies 5. Defective Work:No Defects 6. Compliance of Earlier Comments if any :Complied Rep. of I&CADD Rep.Contractor PSE / PSM TPQC