ITER CODAC Wolf-Dieter Klotz ITER Organization, Cadarache, France 1 F4E Industrial Colloquium Barcelona,Oct. 2008 • ITER at a glance • CODAC overall architecture • ITER procurement model • Standardization for Instrumentation & Control (I&C) 2 F4E Industrial Colloquium Barcelona,Oct. 2008 The Core of ITER Central Solenoid Nb3Sn, 6 modules 29m Cryostat 24 m high x 28 m dia. Toroidal Field Coil Nb3Sn, 18, wedged Vacuum Vessel 9 sectors Blanket 440 modules Poloidal Field Coil Nb-Ti, 6 Port Plug ~28m heating/current drive, test blankets limiters/RH diagnostics Major plasma radius 6.2 m Plasma Volume: 840 m3 Torus Cryopumps, 8 Plasma Current: 15 MA Typical Density: 1020 m-3 Divertor Typical Temperature: 20 keV 54 cassettes Fusion Power: 500 MW Machine mass: 23350 t (cryostat + VV + magnets) - shielding, divertor and manifolds: 7945 t + 1060 port plugs - magnet systems: 10150 t; cryostat: 820 t 4 F4E Industrial Colloquium Barcelona,Oct. 2008 The ITER Site Magnet power convertors buildings Cryoplant buildings Hot cell Tokamak building Tritium building • • Cooling towers Area about 60 ha Buildings up to 60m high and 200m long 6 F4E Industrial Colloquium Barcelona,Oct. 2008 ITER Site Preparation • The building construction permit was granted in April, 2008. • Building construction will begin in 2009. Courtesy AIF 7 F4E Industrial Colloquium Barcelona,Oct. 2008 International Cooperation Seven Parties are involved in ITER Construction 8 F4E Industrial Colloquium Barcelona,Oct. 2008 Construction Sharing C “Contributions in Kind” Major systems provided directly by Parties A Systems suited only to Host Party industry - Buildings - Machine assembly - System installation - Piping, wiring, etc. - Assembly/installation labour Overall cost sharing: EU 5/11, Others 6 Parties 1/11 each Overall contingency up to 10% of total. Total amount: 3577 kIUA (5079 M€-2007) Overall costs shared according to agreed evaluation of A+B+C B Residue of systems, jointly funded, purchased by ITER Project Team 10 F4E Industrial Colloquium Barcelona,Oct. 2008 What makes ITER different? • Internationally exploited experiment • “In-kind” procurement from 7 Parties • Nuclear installation – new rules • Reliability/availability higher than any previous fusion project • Continuous operation rather than pulsed • Long timescale to construct, operate, maintain 11 F4E Industrial Colloquium Barcelona,Oct. 2008 Roles & Responsibilities for Construction ITER Organization Seven Parties • Planning/Design • Integration / QA / Safety / Licensing / Schedule • Installation • Testing + Commissioning • Operation • Detailing / Designing • Procuring • Delivering • Support installation 12 F4E Industrial Colloquium Barcelona,Oct. 2008 CODAC Architecture 13 F4E Industrial Colloquium Barcelona,Oct. 2008 ITER seen by CODAC Control, Data Access and Communication • ~150 ‘one off’ industrial plant systems • delivered ‘in-kind’ with corresponding package • including •science •diagnostics •plasma control •industrial control • interconnected by dedicated networks 14 F4E Industrial Colloquium Barcelona,Oct. 2008 3 Tier Segregation CODAC PBS 4.5 Interlocks PBS 4.6 Nucl.Safety PBS 4.8 Comm. over Networks 15 F4E Industrial Colloquium Barcelona,Oct. 2008 Remote Access CODAC - 4.5 Plant Operation Zone CIS - 4.6 CSS - 4.8 16 F4E Industrial Colloquium Barcelona,Oct. 2008 A Different View 17 F4E Industrial Colloquium Barcelona,Oct. 2008 CONTROL INTERLOCK 18 SAFETY CODAC, CIS, CSS PBS 4.5, 4.6, 4.7 PLANT SYSTEMS 19 20 21 22 23 24 25 26 27 CODAC Integrates all Systems 28 F4E Industrial Colloquium Barcelona,Oct. 2008 CODAC required equipment • Control room equipment •Engineering and configuration workstations •Scientific tools •Remote control rooms management SW •Mass data storage •Configuration databases •Central supervision system •Central Alarm system •Central timing system •Plant interface systems •Fast control systems •Fast data acquisition systems •Plant monitoring systems •Slow control systems •Industrial automation and control • Process instrumentation •Various type of networks 29 Interlock & Safety required equipment • Highly reliable and available PLC systems (SIL3 and class 2) • Various type of transducers • Various type of networks: TCP/IP, Safety field buses, monitored hardwired links • Supervisory systems • Long term safe data storage • Safety operator’s desks 30 CODAC, Interlock & Safety required activities • I&C Support for plant systems • Eng. support for CODAC • Eng. support for Interlock&Safety • Technical specifications • Engineering Design • Detailed Design • Prof-of-concept with prototypes • Procurement of equipment • SW programming • HW assembly • HW and SW integration • Factory testing • Installation and Commissioning 31 ITER IO Contract Strategy 2009 Q1 Q2 Q3 2010 Q4 Q1 Q2 Q3 2011 Q4 Q1 Q2 Q3 2012 Q4 Q1 Q2 Q3 2013 Q4 Q1 Q2 Q3 2014 Q4 Q1 Q2 Q3 2015 Q4 Q1 Q2 Q3 2016 Q4 Q1 Q2 Q3 2017 Q4 Q1 Q2 Q3 2018 Q4 Q1 Q2 Q3 2019 Q4 Q1 Q2 Q3 Q4 Start Integrated commissioning Start of Tokamak assembly First Plasma I&C Support for Plant Systems Assistance Contracts CODAC Support Central Interlock and Safety Systems Support Prototypesrealization realization(x (x10) 10) Prototypes CentralInterlock InterlockSystems Systemsrealization realization(x(x (x3) 3) Central Interlock Systems realization 3) Central CentralSafety SafetySystems Systemsrealization realization(x(x(x3) 3) Central Safety Systems realization 3) Central CODAC sub-systems Development CODAC sub-systems Development CODAC sub-systems Development CODAC sub-systems realization (~x 10) Procurement Contracts I&C Plant Systems Development I&C Plant Systems Development I&C Plant Systems Development I&C Plant Systems realization (~ x100) In fund, contracts placed by ITER IO In kind, contracts placed by ITER DAs Task agreements, most probably no contracts with with Industry 32 F4E Industrial Colloquium Barcelona,Oct. 2008 ITER Procurement Model 33 F4E Industrial Colloquium Barcelona,Oct. 2008 Fund versus In-Kind Procurement IN FUND Procurement IN KIND Procurement 34 F4E Industrial Colloquium Barcelona,Oct. 2008 Procurement Allocation pg.1 35 F4E Industrial Colloquium Barcelona,Oct. 2008 Procurement Allocation pg.2 36 F4E Industrial Colloquium Barcelona,Oct. 2008 Procurement Allocation pg.3 37 F4E Industrial Colloquium Barcelona,Oct. 2008 Procurement Allocation pg.4 38 F4E Industrial Colloquium Barcelona,Oct. 2008 Plant System I&C Costs • Assume CODAC + Plant System I&C is 7% of total cost • low end of typical range • amounts to about ➟ 317M€ • CODAC (the supervisory part) + CIS + CSS is funded at ➟ 75M • needs to be verified if CSS can be included • A first (top-down) estimate of Plant System I&C inside procurement arrangements is therefore the remaining ➟ 242M€ • EU has ~32.9% of procurement, and probably a greater fraction (~42.2%) of Plant System I&C ➟ 102M€ • ~75% is dominated by engineering costs ➟ 76.8M€, rather than component costs ➟ 25.2M€ 39 F4E Industrial Colloquium Barcelona,Oct. 2008 Procurement Schedule extracted form Integrated Project Schedule IPS version 16-May-2008 • • YEAR 2008 2009 2010 2011 2012 No. of Procurements 13 32 22 11 6 Peak in preparing Procurement Arrangements: now to 2010 no new Procurement Arrangements after 2012 40 F4E Industrial Colloquium Barcelona,Oct. 2008 CODAC Boundary CODAC component Provided to supplier “Ambassador” Procurement agreement Factory-testing Site acceptance Commissioning CODAC component Provided to supplier “Ambassador” 41 F4E Industrial Colloquium Barcelona,Oct. 2008 The Procurement Chain 42 F4E Industrial Colloquium Barcelona,Oct. 2008 Integrated Project Teams in the DAs • There is need for efficient communication between CODAC and the Domestic Agency. • A model is suggested based on expert centers in the DAs. • Experts from the different DAs could spend time in Cadarache to develop a full understanding of CODAC, while at the same time contributing to the development of CODAC itself. • When in their Participant Teams, their knowledge can be passed on to the domestic industries or research institutions which, in turn, enhance the contact with the end-suppliers. 43 F4E Industrial Colloquium Barcelona,Oct. 2008 Standardization for Instrumentation & Control 44 F4E Industrial Colloquium Barcelona,Oct. 2008 Standards Requirements Procurement cannot work without Standardization Reliability, Availability and Serviceability (RAS) Open Standards Conservative Solutions Commercial off-the-shelf (COTS) Minimize New Development Very easy to use Low Risk Fast Delivery Low Total cost per channel Bottom Up and Top Down Engineering to PLC 45 F4E Industrial Colloquium Barcelona,Oct. 2008 Standards ToBeDefined’s Procurement cannot work without Standardization • • • • Plant System Controllers • PLCs • PCs/PCI • Chassis based systems: Compact PCI, PXI, ATCA, AMC, μTCA Open Software • Operating Systems (LINUX distribution) • SCADA frameworks: EPICS, TANGO • RT-OS Development Methodologies/Frameworks • PLC programming • Application IDEs: Eclipse, Control Studio, ... Network Standards based on Gbit Ethernet • Protocols over IP and TCP 46 F4E Industrial Colloquium Barcelona,Oct. 2008 Standards How To - 3 Sources Procurement cannot work without Standardization • • • Plant System Host - will be provided by CODAC • works as gateway between Plant System and CODAC • contains communication middleware • maps plant data and protocols to a universal CODAC format miniCODAC - will be provided by CODAC • works as portable system for plant design and SAT (may be FAT as well) • contains SCADA tools to set up autonomous plant control systems Plant Control Design Handbook - is provided by CODAC • is the reference for mandatory and recommended standards 47 F4E Industrial Colloquium Barcelona,Oct. 2008 The End 48 F4E Industrial Colloquium Barcelona,Oct. 2008