PC19 High DG - WECC Study Results July 23, 2015 W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 2 Overview Production Cost Model Assumptions Results Scope • E3 Assumptions • Geographic Variations • Capacity Added for Study • Scope • Key Questions W E S T E R N E L E C T R I C I T Y C O O R • Generation Change • Dump Energy • Path Flows D I N A T I N G C O U N C I L 3 PC19 High DG WECC • Study Requestor: SPSC • Changes from 2024CC: – Increased DG generation throughout all of the Western Interconnection. Noting impacts on west-wide energy dispatch and indicators of stress on the supply system; Increase in capacity by 22,648 MW *Note in this study analysis DG refers to small scale solar PV or “rooftop solar” for individual retail customers • Key Questions: – How does the system respond to the additional DG? (i.e. overgeneration, dump energy) – How does the DG “injection” impact transmission flow and path utilization throughout the region and on the interties? *No changes were made to transmission or load W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 4 DG Starting Point (E3)* • E3 analysis focuses on small scale solar PV installations by retail customers – Does not include “wholesale DG” that a utility might procure to meet state DG targets • Market-Driven DG Model Key Drivers: • • • • • • Solar PV capital cost Customer bill savings Federal investment tax credit State-specific incentive programs State net energy metering caps Utility system interconnection potential Affect customer decision to invest in solar PV Limit total penetration On a utility’s system *Source: E3 W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 5 DG Assumtions (E3)* • Assumption Overview: • High DG projections are developed by relaxing existing Net Energy Metering (NEM) caps and assuming achievement of aspirational solar PV cost reductions • Key Assumptions: • Assumes Net Energy Metering (NEM) caps are removed, allowing installations of DG in each utility’s service territory up to its “Interconnection Potential • No change in retail rate design – California Exception: After 2017 exports are assumed to be compensated at avoided cost • Retail rates escalate at 0.5% per year in real terms • Federal ITC sunsets in 2017 – Credit reduces to 10% of capital costs thereafter • Current state inventive programs sunset after current NEM cap is exceeded *Source: E3 W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 2024 High DG Projections Total capacity: 22,648 MW Load Area AESO APS AVA BCHA BPA CFE CHPD DOPD EPE FAR EAST GCPD IID LDWP MAGIC VLY NEVP NWMT PACE_ID PACE_UT PACE_WY PACW Distributed PV Capacity (MW) 1,548 129 394 18 13 70 34 14 74 1,032 75 747 207 49 576 141 263 Peak Load (MW) 16,370 8,512 2,571 11,603 12,023 2,753 803 500 2,346 420 1,029 1,198 5,826 884 4,937 2,324 878 5,642 1,829 4,387 Capacity (% of Peak) 0.0% 18.2% 5.0% 0.0% 3.3% 0.0% 2.3% 2.6% 3.0% 8.2% 1.4% 6.2% 17.7% 8.5% 15.1% 8.9% 5.5% 10.2% 7.7% 6.0% Load Area PG&E_BAY PG&E_VLY PGN PNM PSC PSE SCE SCL SDGE SMUD SPP SRP TEP TIDC TPWR TREAS VLY WACM WALC WAUW Distributed PV Capacity (MW) 2,234 2,813 441 490 1,645 204 4,534 57 933 495 322 1,240 434 117 19 153 821 294 19 Peak Load (MW) 12,792 12,517 4,828 3,472 7,235 5,222 23,779 2,709 4,520 3,206 3,603 8,484 4,151 603 1,137 1,924 5,529 2,460 152 Capacity (% of Peak) 17.5% 22.5% 9.1% 14.1% 22.7% 3.9% 19.1% 2.1% 20.6% 15.4% 8.9% 14.6% 10.5% 19.5% 1.7% 7.9% 14.8% 12.0% 12.2% 6 7 Generation Change Annual Generation by Category (MWh) 2024 PC1 v1.5 2024 PC19 High DG WECC Conventional Hydro Energy Storage Steam - Coal Steam - Other Nuclear Combined Cycle Combustion Turbine IC Other DG/DR/EE - Incremental Biomass RPS Geothermal Small Hydro RPS Solar Wind 0 W E S T E R N 50,000 E L E C T R 100,000 I C I T Y 150,000 C O O R D 200,000 I N A T I 250,000 N G C O 300,000 U N C I L 8 Production Cost and CO2 Category Conventional Hydro Energy Storage Steam Nuclear Combined Cycle Combustion Turbine IC DG/DR/EE - Incremental Biomass RPS Geothermal Small Hydro RPS Solar Wind == Total == 2024 PC1 15-01-19 2024 PC 19 High DG WECC 238,955,786 238,935,910 3,592,412 3,344,337 230,393,384 212,095,530 56,254,786 56,206,670 278,957,656 254,970,479 51,794,128 48,872,363 818,909 655,300 17,916,707 65,404,109 19,581,287 19,034,598 31,937,139 31,523,705 4,360,054 4,351,069 38,182,163 35,734,009 74,232,546 73,783,251 1,050,342,237 1,048,276,420 Cost (M$) CO2 Cost (M$) CO2 Amount (MMetrTn) Dump Energy (MWh) Pumping (PL+PS) (MWh) W E S T E R N E 22,843 1,730 363 357,799 15,426,008 L E C T R I C I T Y C O Difference -19,876 -248,076 -18,298,043 -48,116 -23,987,178 -2,921,765 -163,609 47,487,402 -546,689 -413,434 -8,985 -2,448,153 -449,295 -2,065,817 21,477 1,613 336 3,499,883 15,104,430 O R D I N A T I N G C (1,366) (116) (26) 3,142,084 (321,579) O U N C I L 9 Changes in Total Annual Generation Annual Energy Difference (MWh): 2024 PC1 v1.5 vs 2024 PC19 High DG WECC Conventional Hydro Energy Storage Steam - Coal Steam - Other Nuclear Combined Cycle Combustion Turbine IC Other DG/DR/EE - Incremental Biomass RPS Geothermal Small Hydro RPS Solar Wind (30,000) W E S T E R N (20,000) E L E (10,000) C T R 0 I C I T 10,000 Y C O 20,000 O R D I 30,000 N A T I 40,000 N G 50,000 C O U N 60,000 C I L 10 Generation Change By State Annual Gen Change (GWh) 2024 PC1 v1.5 vs 2024 PC19 High DG WECC 30,000 25,000 Conventional Hydro Energy Storage 20,000 Steam - Coal Steam - Other Nuclear 15,000 Combined Cycle Combustion Turbine 10,000 IGS assigned to UT 5,000 IC Other Biomass RPS DG/DR/EE - Incremental Geothermal 0 Small Hydro RPS Solar -5,000 Wind -10,000 AB W E S AZ T E BC R N CA CO E L ID E C MT T R MX I C NE I T NM Y NV C O OR O SD R D TX I N UT A T WA I N WY G C O U N C I L 11 Generation Change by Subregion Change (GWh) by Subregion - 2024 PC1 v1.5 vs. 2024 PC19 High DG WECC -10,000 -5,000 0 5,000 10,000 15,000 20,000 25,000 30,000 Alberta Conventional Hydro Energy Storage British Columbia Steam - Coal Steam - Other Nuclear Basin Combined Cycle IGS assigned to CA Combustion Turbine IC California Other Biomass RPS DG/DR/EE - Incremental Desert Southwest Geothermal Small Hydro RPS Solar Northwest Wind Rocky Mountain W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 12 Dump Energy 2500000 Biomass RPS Conventional Hydro Geothermal Other Solar unknown 2,185,696 2000000 Combined Cycle DG/DR/EE - Incremental IC Pumping Load Steam - Coal Wind Combustion Turbine Energy Storage Nuclear Small Hydro RPS Steam - Other (blank) 1500000 1000000 500000 171,852 90,328 228 0 0 0 0 0 0 0 AB AZ BC N E CA CO ID MT MX NE Y C NM NV OR SD TX UT WA WY (blank) -500000 W E S T E R L E C T R I C I T O O R D I N A T I N G C O U N C I L 13 Modeling Constraints Constraints Name Type Costs (K$) Duration (Hrs) CC Duration (Hrs) PC19 FromBusName MAGUNDEN-OMAR 230 kV line #1 Branch 26,238 5,741 4,418 MAMMOTH-BIG CRK3 230 kV line #1 Branch 8,515 106 REDBUTTE-UTAH-NEV 345 kV line #1 Branch 7,706 CAL SUB 120/120 kV transformer #1 Branch BLKGLADW 115/115 kV transformer #1 FromBusID ToBusName ToBusID MAGUNDEN 24087 OMAR 24101 1,476 MAMMOTH 24316 BIG CRK3 24303 965 2,500 REDBUTTE 66280 UTAH-NEV 67657 2,181 964 1,072 CAL SUB 64025 CAL S PS 64023 Branch 2,083 2,252 2,807 BLKGLADW 72771 BLKDPSW 72773 P60 Inyo-Control 115 kV Tie Interface 1,111 2,602 1,019 PG&E Bay 25% LocalMinGen Nomogram 0 511 1,043 LDWP 25% LocalMinGen Nomogram 0 3,859 5,079 SCE 25% LocalMinGen Nomogram 30,401 5,127 5,566 W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 14 Nomograms • Nomogram: – Constraint (inequality) enforced by GV – When “at limit”, additional thermal generation is dispatched to balance the inequality • 4 new nomograms to 2024 CC: – LDWP 25% LocalMinGen – PG&E Bay 25% LocalMinGen – SCE 25% LocalMinGen – SDGE 25% LocalMinGen W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 15 Nomogram Constraint PC19 vs CC 1000 500 0 1 1001 2001 3001 4001 5001 6001 7001 8001 -500 -1000 PG&E Bay 25% LocalMinGen PG&E Bay 25% CC LDWP 25% LocalMinGen -1500 LDWP 25% CC SCE 25% LocalMinGen -2000 SCE 25% CC -2500 -3000 -3500 -4000 W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 16 Difference in Duration (Hrs) Difference in Modeling Constraints PC19 vs CommonCase 2000 1500 Duration (Hrs) 1000 500 0 -500 -1000 -1500 Branch Branch Branch Branch Branch Interface Nomogram Nomogram Nomogram MAGUNDENOMAR 230 kV line #1 MAMMOTHBIG CRK3 230 kV line #1 REDBUTTEUTAH-NEV 345 kV line #1 CAL SUB 120/120 kV transformer #1 BLKGLADW 115/115 kV transformer #1 P60 InyoControl 115 kV Tie PG&E Bay 25% LocalMinGen LDWP 25% LocalMinGen SCE 25% LocalMinGen -1323 1370 1535 108 555 797 532 1220 439 Series1 W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 17 Results – Most Heavily Utilized Paths • Congestion vs Utilization – Some lines are designed to be congested • “Most Heavily Utilized” = A path that meets any one of the following criterion (10-year plan utilization screening): – U75 > 50% – U90 > 20% – U99 > 5% • Uxx = % of year that flow is greater than xx% of the path limit W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 18 Results – Changes in Transmission Utilization Most Heavily Utilized Paths P01 Alberta-British Columbia P83 Montana Alberta Tie Line P08 Montana to Northwest P10 West of Colstrip Most Heavily Utilized Paths P60 Inyo-Control U75 U90 U99 P10 West of Colstrip 50.50% 0% 0% P45 SDG&E-CFE 13.31% 10.70% 9.3% P83 Montana Alberta Tie Line 16.09% 8.67% 5.48% P45 SDG&E-CFE W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 19 Results Common Case Most Heavily Utilized Paths - PC1_1_5 U75 U90 Y C U99 80% 70% Percent of Hours 60% 50% 40% 30% 20% 10% 0% W E S T E R N E L E C T R I C I T O O R D I N A T I N G C O U N C I L 20 Results PC19 Most Heavily Utilized Paths - PC19 High DG - WECC U75 U90 Y C U99 60% 50% Percent of Hours 40% 30% 20% 10% 0% W E S T E R N E L E C T R I C I T O O R D I N A T I N G C O U N C I L 21 Path Flows WECC P10 West of Colstrip N -> S 3000 Megawatts 2000 1000 0 -1000 -2000 -3000 2024CC-V1.5 2024 PC19 High DG 2012 2024 Max 2024 Min 2024 Max 2024 Min WECC P45 SDG&E-CFE N -> S 600 400 Megawatts 200 0 -200 -400 -600 -800 -1000 2024CC-V1.5 W E S T E R N E L E C 2024-PC19 High DG T R I C I T Y 2012 C O O R D I N A T I N G C O U N C I L 22 Path Flows WECC P66 COI N -> S 6000 Megawatts 4000 2000 0 -2000 -4000 -6000 2024CC-V1.5 2024-PC19 High DG 2024 Max 2024 Min WECC P83 Montana Alberta Tie Line N -> S Megawatts 2012 600 500 400 300 200 100 0 -100 -200 -300 -400 2024CC-V1.5 W E S T E R N E L E C 2024 PC19 High DG T R I C I T Y 2012 C O O 2024 Max R D I N A 2024 Min T I N G C O U N C I L 23 Findings • Generation and Energy Changes: – Increased DG availability results in a reduction in Coal (steam) and Combined Cycle generation – Increased levels of dump energy (likely due to modeling constraints – nomograms, transfer capacity) • Transmission Changes: – Increased path over-utilization in Southern CA and in the North-East regions • Production Cost Changes: – Decrease in production cost – Decrease in CO2 production W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L 24 Contact Info Tyson Niemann tniemann@wecc.biz 801-819-6887 W E S T E R N E Dan Beckstead dbeckstead@wecc.biz 801-819-7657 L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L Distributed Generation Projections for High DG Case October 10, 2014 Arne Olson, Partner Nick Schlag, Sr. Consultant Background In a number of past efforts, E3 has worked with LBNL and WECC to establish input assumptions regarding distributed generation in study cycles: • In 2011-12, E3 worked with LBNL and WECC to develop estimates of DG potential for the SPSC’s 2022 and 2032 High DG/DSM cases • In 2014, E3 & LBNL developed an approach to project “market-driven” distributed generation in the WECC, which was used to inform the 2024 Common Case WECC has requested projections of distributed generation consistent with High DG futures for the Western Interconnection to use in the SPSC’s 2024 and 2034 High DG/DSM cases To develop these projections, E3 has used logic from both prior efforts to assess future DG installations 26 Defining “Distributed Generation” “Distributed” generation means different things to different people: • Behind-the-meter, e.g., customer-owned resource • Small utility or IPP owned resource that is connected at the distribution system and serves load downstream • Small resource that is connected at the distribution system and does not serve load downstream • Small resource that is connected to the sub-transmission system (i.e., low-voltage transmission) near load • Small resource that is located remote from load • Large resource that is located in load pocket and helps defer or avoid transmission investments This analysis focuses on small scale solar PV installations that individual retail customers would install to avoid purchasing electricity from an electric utility • Does not include “wholesale DG” that a utility might procure to meet state DG targets 27 Approaches to Developing High DG Assumptions 2022/2032 High DG Case assumptions developed in two steps: • Estimate interconnection potential for each state • Make state-specific adjustments to interconnection potential to reflect differences in economic drivers of DG 2024/2034 High DG Case assumptions derived by modeling customer decisions under a scenario favorable to distributed generation adoption • Use E3’s Market Driven DG Model to develop projections of adoption • Rely on estimates of interconnection potential as an upper bound 28 MODELING MARKETDRIVEN DG Background In prior transmission planning study cycles, WECC has incorporated distributed solar PV assumptions consistent with state policy goals This framework ignores the potential for market-driven DG • With low PV costs, this could become a large amount of capacity E3 and LBNL have developed a framework to incorporate market-driven DG into transmission planning studies Channels for Distributed Solar PV Adoption Program Goals (e.g. California Solar Initiative) RPS Set-Asides Policy-driven DG, modeled in past WECC studies (e.g. 30% DG set-aside in Arizona) Market-Driven Adoption New to WECC studies 30 E3’s Market Driven DG Model To provide inputs for WECC’s transmission planning studies, E3 has developed a model of DG deployment throughout the WECC footprint between present day and 2040 • Joint funding from WECC and LBNL through DOE’s ARRA grants Input assumptions capture geographic variations in PV costeffectiveness and state policy • State-specific PV costs • State-specific net metering policy • Capacity factors at a BA level • Utility-specific retail rates (and incentives where applicable) The model also captures the changing cost-effectiveness of PV: • Continued declines in PV capital costs • Expiration of incentives & tax credits (e.g. ITC in 2017) • Escalation of retail rates • Expected changes to state net metering policies (e.g. California AB 327) 31 2024 Common Case Recommendations The Market-Driven DG Model used to develop preliminary recommendations for customer-sited solar for the 2024 Common Case Market Driven DG State (MW) Arizona 1,751 California 5,742 Colorado 742 Idaho 51 Montana 35 New Mexico 170 Nevada 241 Oregon 191 Utah 106 Washington 90 Wyoming 47 Total 9,166 2024 Peak Market Load Driven DG (MW) (% of Peak) 23,227 7.5% 68,908 8.3% 11,789 6.3% 5,664 0.9% 2,483 1.4% 5,139 3.3% 9,951 2.4% 10,392 1.8% 5,537 1.9% 20,950 0.4% 3,464 1.4% 167,505 5.5% For the 2024 Common Case, TAS adjusted the recommended values (shown at left) downward by 20% 32 HIGH DG CASE RECOMMENDATIONS Key Drivers of Market Driven DG Model The main drivers of the modeled customer adoption of solar PV are: 1. Solar PV capital cost 2. Customer bill savings 3. Federal investment tax credit 4. State-specific incentive programs 5. State net energy metering caps 6. Utility system interconnection potential Affect customer decision to invest in solar PV Limit total penetration on a utility’s system Changing the assumptions for each of these parameters provides the basis for exploring alternative projections 34 Overview of Assumptions High DG projections are developed by relaxing existing NEM caps and assuming achievement of aspirational solar PV cost reductions Assumption Reference Case Current Policy Net Metering Caps • • Solar PV Cost Trends Current NEM caps remain in place California cap lifted after 2016 Moderate Reductions • Cost trajectory derived by E3 for TEPPC planning studies High DG Case NEM Caps Removed • • All NEM caps lifted Limits associated with interconnection potential enforced Aspirational Reductions • Sunshot goals achieved by 2020 35 Treatment of NEM Caps In the Reference Case, each state’s NEM cap was enforced according to current policy State Current NEM Cap Arizona n/a California Limits under current NEM rate design established by AB327 (approximately 5% of non-coincident peak); beyond 2017, alternative rate designs will be considered with no associated cap Colorado n/a Idaho n/a New Mexico n/a Nevada 3% of utility peak Oregon 0.5% of peak for munis, coops, & PUDs; no cap for IOUs Utah 0.1% of peak for munis; 20% of peak for IOUs Washington 0.5% of peak Wyoming n/a High DG case assumes current NEM caps are removed, allowing installations of DG in each utility’s service territory up to its ‘Interconnection Potential’ 36 Interconnection Potential Background To estimate interconnection potential across the WECC, E3 leveraged results from a 2012 analysis, Technical Potential for Local Distributed Photovoltaics in California 1. Rule 21 (Current Policy): sum of rated capacity of interconnections on a feeder may not exceed 15% of the feeder’s peak load 2. 30% Rule: same as (1), but with constraint relaxed to 30% 3. Max w/o Curtailment: the maximum capacity that can be installed on a feeder for which all generation will serve load on that feeder (e.g. no required backflow or curtailment) In 2012 study cycle, E3 generalized these results to the WECC BAs; the same method is used to determine limits in this study cycle 20,000 Incremental PV Potential (MW) Study produced estimates of the amount of “local” distributed PV (LDPV) potential under different interconnection standards in California: 15,336 15,000 11,668 10,000 6,638 5,000 0 Rule 21 • 30% Rule for 2024 High DG projections Residential Rooftop • Max w/o Curtailment for 2034 High DG projections Ground Mounted 30% Rule Max w/o Curtailment Commercial Rooftop 37 Capital Cost Trajectories Reference case cost reduction trajectory derived through application of learning curve approach Residential Costs (2013 $/W-dc) $8 $4.11 $2 • IEA medium-term renewable energy outlook $0 2010 Aspirational case cost reduction trajectory assumes achievement of Sunshot goals by 2020 $3.23 $4 20% learning rate on modules; 15% on BOS Adopted by TEPPC Aspirational $6 • • Reference $2.83 $1.50 2014 2018 2022 $1.50 2026 2030 2034 Commercial Costs (2013 $/W-dc) $8 Reference Aspirational $6 $4 • $1.50/W residential $2 • $1.25/W commercial $0 2010 $3.54 $2.80 $2.45 $1.25 2014 2018 2022 $1.25 2026 2030 2034 38 Other Key Assumptions No changes in retail rate design • Surplus NEM generation is compensated at full retail rate • EXCEPTION: in California, after 2017, exports are assumed to be compensated at avoided cost (see Slide 30) Retail rates escalate at 0.5% per year in real terms Federal ITC sunsets in 2017 • Credit reduces to 10% of capital costs thereafter Current state incentive programs sunset after current NEM cap is exceeded • e.g. Washington & Oregon (see Slide 31) 39 2024 Projections Reference Case projections WECC-US 2012 - 2024 20,000 15,000 10,000 Incremental Additions 5,000 Installed Capacity (MW) 25,000 0 2012 2014 2016 2018 2020 2022 2024 Market Driven DG State (MW) Arizona 1,751 California 5,742 Colorado 742 Idaho 51 Montana 35 New Mexico 170 Nevada 241 Oregon 191 Utah 106 Washington 90 Wyoming 47 Total 9,166 2024 Peak Market Load Driven DG (MW) (% of Peak) 23,227 7.5% 68,908 8.3% 11,789 6.3% 5,664 0.9% 2,483 1.4% 5,139 3.3% 9,951 2.4% 10,392 1.8% 5,537 1.9% 20,950 0.4% 3,464 1.4% 167,505 5.5% Market Driven DG State (MW) Arizona 3,533 California 12,305 Colorado 2,301 Idaho 351 Montana 249 New Mexico 613 Nevada 1,023 Oregon 812 Utah 574 Washington 639 Wyoming 248 Total 22,648 2024 Peak Market Load Driven DG (MW) (% of Peak) 23,227 15.2% 68,908 17.9% 11,789 19.5% 5,664 6.2% 2,483 10.0% 5,139 11.9% 9,951 10.3% 10,392 7.8% 5,537 10.4% 20,950 3.1% 3,464 7.2% 167,505 13.5% High DG Case projections WECC-US 2012 - 2024 20,000 15,000 Incremental Additions 10,000 5,000 0 2012 2014 2016 2018 2020 2022 2024 Installed Capacity (MW) 25,000 40 Comparison to 2022 High DG Recommendations 2022 and 2024 High DG projections have similar quantities of distributed generation capacity, but show a regional shift • Relative increases in California, Colorado • Slight decreases in states in the Pacific Northwest State Arizona California Colorado Idaho Montana New Mexico Nevada Oregon Utah Washington Wyoming Total 2022 High DG (MW) 3,650 11,670 1,410 550 160 600 1,090 1,240 690 1,090 510 22,660 2024 High DG (MW) 3,533 12,305 2,301 351 249 613 1,023 812 574 639 248 22,648 Change (MW) (117) 635 891 (199) 89 13 (67) (428) (116) (451) (262) (12) Notable increases from 2022 Notable decreases from 2022 41 2034 Projections Reference Case projections WECC-US 2012 - 2034 30,000 25,000 20,000 15,000 10,000 5,000 Installed Capacity (MW) 35,000 0 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 Market Driven DG State (MW) Arizona 2,314 California 6,816 Colorado 1,133 Idaho 93 Montana 65 New Mexico 251 Nevada 307 Oregon 234 Utah 181 Washington 95 Wyoming 82 Total 11,570 2034 Peak Market Load Driven DG (MW) (% of Peak) 27,833 8.3% 78,325 8.7% 12,749 8.9% 6,312 1.5% 2,763 2.3% 5,954 4.2% 11,489 2.7% 11,794 2.0% 5,481 3.3% 23,560 0.4% 3,955 2.1% 190,215 6.1% Market Driven DG State (MW) Arizona 4,495 California 17,852 Colorado 3,426 Idaho 493 Montana 345 New Mexico 773 Nevada 1,274 Oregon 1,067 Utah 739 Washington 852 Wyoming 333 Total 31,650 2034 Peak Market Load Driven DG (MW) (% of Peak) 27,833 16.1% 78,325 22.8% 12,749 26.9% 6,312 7.8% 2,763 12.5% 5,954 13.0% 11,489 11.1% 11,794 9.0% 5,481 13.5% 23,560 3.6% 3,955 8.4% 190,215 16.6% High DG Case projections WECC-US 2012 - 2034 30,000 25,000 20,000 15,000 10,000 5,000 0 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 Installed Capacity (MW) 35,000 42 DETAILED PROJECTIONS BY LOAD AREA 2024 High DG Projections Total capacity: 22,648 MW Load Area AESO APS AVA BCHA BPA CFE CHPD DOPD EPE FAR EAST GCPD IID LDWP MAGIC VLY NEVP NWMT PACE_ID PACE_UT PACE_WY PACW Distributed PV Capacity (MW) 1,548 129 394 18 13 70 34 14 74 1,032 75 747 207 49 576 141 263 Peak Load (MW) 16,370 8,512 2,571 11,603 12,023 2,753 803 500 2,346 420 1,029 1,198 5,826 884 4,937 2,324 878 5,642 1,829 4,387 Capacity (% of Peak) 0.0% 18.2% 5.0% 0.0% 3.3% 0.0% 2.3% 2.6% 3.0% 8.2% 1.4% 6.2% 17.7% 8.5% 15.1% 8.9% 5.5% 10.2% 7.7% 6.0% Load Area PG&E_BAY PG&E_VLY PGN PNM PSC PSE SCE SCL SDGE SMUD SPP SRP TEP TIDC TPWR TREAS VLY WACM WALC WAUW Distributed PV Capacity (MW) 2,234 2,813 441 490 1,645 204 4,534 57 933 495 322 1,240 434 117 19 153 821 294 19 Peak Load (MW) 12,792 12,517 4,828 3,472 7,235 5,222 23,779 2,709 4,520 3,206 3,603 8,484 4,151 603 1,137 1,924 5,529 2,460 152 Capacity (% of Peak) 17.5% 22.5% 9.1% 14.1% 22.7% 3.9% 19.1% 2.1% 20.6% 15.4% 8.9% 14.6% 10.5% 19.5% 1.7% 7.9% 14.8% 12.0% 12.2% 44 2034 High DG Projections Total capacity: 31,650 MW Load Area AESO APS AVA BCHA BPA CFE CHPD DOPD EPE FAR EAST GCPD IID LDWP MAGIC VLY NEVP NWMT PACE_ID PACE_UT PACE_WY PACW Distributed PV Capacity (MW) 1,990 177 553 27 18 87 49 20 91 1,327 103 925 282 67 740 181 347 Peak Load (MW) 22,683 9,715 2,920 12,948 13,930 3,513 990 638 2,891 500 1,199 1,449 6,550 889 5,548 2,541 988 5,523 1,891 4,633 Capacity (% of Peak) 0.0% 20.5% 6.1% 0.0% 4.0% 0.0% 2.7% 2.8% 3.0% 9.7% 1.6% 6.3% 20.3% 11.6% 16.7% 11.1% 6.8% 13.4% 9.5% 7.5% Load Area PG&E_BAY PG&E_VLY PGN PNM PSC PSE SCE SCL SDGE SMUD SPP SRP TEP TIDC TPWR TREAS VLY WACM WALC WAUW Distributed PV Capacity (MW) 3,237 4,247 571 607 1,965 262 6,605 75 1,437 620 422 1,509 513 174 26 206 1,108 470 26 Peak Load (MW) 14,225 14,478 5,644 3,679 7,105 5,602 26,716 2,852 5,331 3,480 4,487 10,321 4,693 710 1,252 2,171 7,136 3,910 172 Capacity (% of Peak) 22.8% 29.3% 10.1% 16.5% 27.7% 4.7% 24.7% 2.6% 27.0% 17.8% 9.4% 14.6% 10.9% 24.5% 2.1% 9.5% 15.5% 12.0% 15.4% 45 Thank You! Energy and Environmental Economics, Inc. (E3) 101 Montgomery Street, Suite 1600 San Francisco, CA 94104 Tel 415-391-5100 Web http://www.ethree.com MARKET-DRIVEN DG: METHODOLOGY AND ASSUMPTIONS General Model Logic E3’s Market-Driven DG model combines a customer decision model with policy targets and NEM caps to provide a comprehensive assessment of behindthe-meter solar PV in the Western Interconnect Modeling steps: 1. Assess potential size of distributed solar PV market based on economics 2. Adjust forecast upward to meet any policy targets 3. Limit total installations based on state net metering caps 48 Step 1: Market-Driven Adoption Cumulative Net Cost ($) $4,000 $3,000 $2,000 Payback $1,000 $0 -$1,000 0 5 10 15 -$2,000 -$3,000 100% 80% 60% 40% 20% 7% 0% 0 -$4,000 Years Since Installation 5 10 15 20 Technical potenial 7% 6% 5% t t-1 3% 30 35 4. Apply to technical potential 8% 4% 25 Payback Period 3. Fit logistic curve Market Penetration (%) Maximum Market Share (%) 2. Determine max market share 1. Determine payback period MW x Market penetration at t % = Installed capacity at t MW 2% 1% 0% 0 5 10 15 20 25 Years 49 Calculating the Payback Period The payback period is the first year in which a customer who choose to install solar PV will have a net positive cash flow To determine the payback period, E3 considers: • System capital costs: costs of purchasing & installing a PV system • Operating & maintenance costs: costs of year-to-year maintenance, including inverter replacement • Federal tax credits: investment tax credit (30% until 2017; 10% thereafter) • State & local incentives: up-front & performance-based incentives, vary by utility & state • Bill savings: reductions monthly energy bills, vary by utility • Green premium: a non-financial value that a customer derives from having invested in solar PV (assumed to be 1 cent/kWh) 50 Solar PV Capital Costs by Installation Vintage Installed PV cost assumptions based on draft recommendations for PV capital costs developed by E3 • Presented to TAS on December 19 Future cost reductions primarily reflect lower balanceof-systems costs $10 $9 Installed Cost (2014 $/W-dc) Residential Historical Commercial $8 $7 $6 $4.8 $5 $4.0 $4 $3.6 $3.0 $3 $2 $1 $0 2010 2012 2014 2016 2018 2020 2022 2024 51 Solar PV Costs by State System average costs are adjusted for each state to capture regional variations in costs • Regional adjustments based on LBNL’s Tracking the Sun VI 2013 Installed Costs (2014 $/W-dc) $6 Residential $5.1 $4.8 $5 $4.2 $4 Commercial $4.8 $4.0 $4.6 $3.9 $4.6 $3.9 $4.6 $3.8 $4.6 $3.8 $4.5 $3.8 $4.3 $3.7 $4.3 $3.6 $3.6 $3.7 $3.5 $3.1 $3 $2.9 $2 $1 $0 CA NM WA OR MT ID UT WY NV AZ CO TX Where Tracking the Sun VI did not report PV costs, costs were interpolated based on the Army Corps of Engineer’s Construction Works Cost Index 52 Avoided Energy Cost All WECC states currently allow net metering, under which a customer is compensated for PV output based on its retail rate • This is the primary economic benefit to a customer who chooses to install distributed PV Market adoption model includes utility-specific rate information for 30 large utilities in the West (a subset are shown below) 2013 Residential Retail Rate ($/kWh) • For other smaller utilities, a state-specific average retail rate is used California: IOUs’ high tiered rates provide strong incentive to customers $0.35 $0.30 Southwest Rocky Mountains Northwest: Low-cost hydropower keeps rates low General trend in retail rates $0.25 $0.20 $0.15 $0.10 $0.05 $0.00 53 Changes to Avoided Energy Cost over Time E3 assumes that utilities continue to compensate customers at their full retail rate throughout the analysis horizon with one exception • Real escalation of 0.5% per year is assumed California’s AB 327 directs the CPUC to implement a standard NEM tariff beginning in July 2017 As this tariff has not yet been defined, E3 has chosen to model it in the following manner: • All generation consumed on-site is compensated at the customer’s retail rate • 50% for residential systems, 70% for commercial systems (based on CPUC NEM study) • All generation exported to the grid is compensated at the utility’s long-run avoided cost (based on a CCGT) 54 State-Specific Incentives Payback period is also heavily influenced by state incentive programs E3’s model captures the impact of two large incentive programs: • Renewable Energy Cost Recovery Program (WA) • Performance-based incentive capped at $5,000 per year • Program ends in 2020 • Residential Energy Tax Credit (OR) • Incentive of $2.1/W-dc, capped at $6,000 • Program ends in 2018 Note: incentives linked to specific policy targets (e.g. setasides, program goals) are not modeled explicitly and are instead accounted for by adjusting market-driven forecast upward to meet policy goals 55 Sample Payback Period Results, 2013 Residential Systems Payback periods vary widely across the WECC geography as a function of: • System costs • Retail rates • Incentives • Capacity factors Cost ($/W-ac) ITC (%) Incentive ($/W-ac) Incentive ($/kWh) Retail Rate ($/kWh) Capacity Factor (%) Payback (yrs) Utility State Arizona Public Service Co AZ $ 5.06 30% $ - $ - $ 0.13 22% 12 Pacific Gas & Electric Co CA $ 6.02 30% $ - $ - $ 0.31 20% 7 Public Service Co of Colorado CO $ 4.39 30% $ - $ - $ 0.12 20% 13 Idaho Power Co ID $ 5.39 30% $ - $ - $ 0.09 19% 20 NorthWestern Energy LLC - (MT) MT $ 5.43 30% $ - $ - $ 0.11 17% 19 Public Service Co of NM NM $ 5.66 30% $ - $ - $ 0.13 23% 13 Nevada Power Co NV $ 5.06 30% $ - $ - $ 0.12 22% 13 Portland General Electric Co OR $ 5.46 30% $ 1.25 $ - $ 0.10 15% 17 PacifiCorp UT $ 5.39 30% $ - $ - $ 0.11 19% 17 Puget Sound Energy Inc WA $ 5.60 30% $ - $ 0.15 $ 0.10 14% 11 56 Modeling Solar PV Adoption NREL’s Solar Deployment System (SolarDS) model provides one of the more transparent forecasts of PV adoption: • “…a geospatially rich, bottom-up, market-penetration model that simulates the potential adoption of photovoltaics (PV) on residential and commercial rooftops in the continental United States through 2030” Much of the logic used in the Adoption Module has been adapted from SolarDS: • Maximum market share as a function of payback period • Logistic curves for adoption Documentation for SolarDS model: http://www.nrel.gov/docs/fy10osti/45832.pdf (Figures taken from this document) 57 Assumed Payback Curves Payback curves are based on functional forms documented in SolarDS model Maximum Market Share (% of technical potential) 100% Res Existing 90% Res New 80% Maximum Market Share (%) Payback (yrs) Com Existing Utility State Com New Arizona Public Service Co AZ 12 2.7% 60% Pacific Gas & Electric Co CA 7 12.2% 50% Public Service Co of Colorado CO 13 2.0% 40% Idaho Power Co ID 20 0.2% NorthWestern Energy LLC - (MT) MT 19 0.3% Public Service Co of NM NM 13 2.0% Nevada Power Co NV 13 2.0% Portland General Electric Co OR 15 1.1% PacifiCorp UT 17 0.6% Puget Sound Energy Inc WA 11 3.7% 70% 30% 20% 10% 0% 0 5 10 15 Payback Period 20 25 30 58 Assumed Technical Potential E3 calculates technical potential by specifying: 1. The percentage of total customers that could feasibly install solar PV (50% for residential and commercial) 2. The representative system size for a typical install (4 kW for residential; 50 kW for commercial) Rooftop PV Technical Potential (GW) Resulting assumed technical potential aligns well with NREL’s assessment of rooftop PV technical potential on a state level: 80 E3 Assumed Technical Potential 70 NREL Modeled Technical Potential Source: U.S. Renewable Energy Technical Potentials: A GISBased Analysis (NREL) 60 50 40 30 20 10 0 AZ CA CO ID MT NM NV OR UT WA WY Total technical potential is approximately 150 GW in 2010 59 Step 2: Policy Adjustments A large number of states have enacted policies to encourage the deployment of distributed solar PV In cases where the market-based adoption forecast falls short of state policy targets, upward adjustments are made to reflect achievement of current policy • Assumes utilities will fund programs to reach targets State Policy Arizona RPS DG Set-Aside (4.5% of IOU/coop retail sales by 2025) California California Solar Initiative (2,300 MW for IOUs; 700 MW for publics) Colorado RPS DG set-aside (3% of IOU 2020 retail sales; 1% of public utility 2020 retail sales) New Mexico RPS DG set-aside (0.6% of 2020 retail sales) Nevada Nevada Solar Incentives Program (36 MW among NVE and SPP) Oregon Energy Trust (124 MW among PGE and PacifiCorp) Solar Volumetric Incentive and Payments Program (27.5 MW among PGE, PacifiCorp, and IPC) 60 Policy Adjustments For each utility, initial market-driven DG forecast is adjusted upward in each year it is short of policy targets Illustrative example shown for APS 900 Market-Driven DG Policy Target Installed Capacity (MW) 800 700 600 500 400 300 200 100 0 2010 2012 2014 2016 2018 2020 2022 2024 61 Step 3: Adjust for Net Metering Policy Common Case projections assume all current NEM caps remain in place • Arizona, Colorado, Montana, New Mexico, Wyoming: no cap • Oregon & Washington: 0.5% of utility peak • Idaho: 0.1% of utility peak • Nevada: 3% of utility peak • California: 5% of noncoincident peak (currently) Common Case projections assume these caps remain in place throughout the analysis • Exception: California’s AB 327 lifts the existing NEM cap beginning in 2017 with the implementation of a standard NEM tariff 62 NEM Adjustments For each utility whose installed capacity would be constrained by a NEM cap, installation forecast is adjusted downward to the limit Illustrative example shown for Puget Sound Installed Capacity (MW) 300 Market-Driven DG Policy Target 250 200 150 100 50 0 2010 2012 2014 2016 2018 2020 2022 2024 63