LIEF Project Plan

advertisement

LIEF Project Plan

Jeremy Mould & Jon Lawrence

Agenda KISS Kickoff Meeting 12/3

0900

0930

1000

Break

JM/LW

XY

Meeting overview / Skype

Science requirements ETC

Telescope & optical design

1100

1200

Lunch

JL

MCBA

Optical/cryostat/thermal/system

1400

1500

JL

LW

1600 or Friday JM

Control system/interfaces

System/data pipeline

Deployment/logistics

Project management

Kunlun

Infrared

Sky Survey

Document Scope

• project definition plan for AST3-NIR Antarctic instrument project,

– funded via a successful ARC LIEF grant

• includes instrument high level aims & objectives,

– key project personnel,

– the proposed concept,

– budget, and schedule,

– assessment of key risks at initialisation phase

Project Aims

Primary aims of this project are to:

• conduct a deep high-cadence wide-field K dark infrared sky survey (KISS) from Antarctica;

• enhance Australia/China/US collaboration in

Antarctic astronomy;

• gain knowledge on operation of & procurement for IR detector arrays to be used in Antarctica.

Project Objectives

• Design & build a wide-field K-band imager for AST3-

NIR telescope

– AST3-NIR telescope is designed & built by NAOIT;

• Integrate & interface imager with AST3-NIR telescope

– location for integration to be determined,

– possibly U Tas in Hobart per John Dickey & Andrew Cole

• Support commissioning activities (in-person and/or remotely) for the AST3-NIR telescope + instrument in

Antarctica

– at Dome A, South Pole, or Dome C.

KISS LIEF proposal Investigators

• Jeremy Mould (SUT) as Lead Investigator

• Karl Glazebrook (SUT) as Chief Investigator

• Michael Ashley (UNSW) as Chief Investigator

• Michael Burton (UNSW) as Chief Investigator

• Lifan Wang (TAMU) as Partner Investigator

• Ji Yang (PMO) as Partner Investigator

• Anna Moore (Caltech) as Partner Investigator

• Jon Lawrence (AAO) as Partner Investigator

• Peter Tuthill (USyd) as Chief Investigator

• Mike Ireland (ANU) as Chief Investigator.

Key instrument project roles

• Jeremy Mould (SUT) as Lead Investigator

• Jon Lawrence (AAO) as Project Leader

• Julia Tims (AAO) as Project Manager

• Jessica Zheng (AAO) as Instrument Scientist

• Nic Bingham (AAO) as Control System Engineer

• Michael Ashley (UNSW) as Control System Lead

• Xiangyan Yuan (NIAOT) as Telescope Lead Scientist

Ownership

• “The instrument developed and all materials procured for the instrument project will be owned by Swinburne and made available onloan to the project team for the duration of the project”

– i.e. to the end of the KISS survey phase

• this is of no consequence for the science

– and doesn’t apply to the telescope or its other attachments, such as the data system

Science case

Science case (more detail in LIEF text) includes:

• supernovae,

• exo-planets,

• variable stars,

• AGN reverberation mapping,

• gamma-ray-bursts,

• young stellar objects,

• young massive stars,

• cosmic infrared background.

Concept

Baseline instrument concept consists of

• 2.5

 m cut-off HgCdTe detector array,

• mounted in a cryostat with internal baffling,

• K dark filter and optically powered window

• camera mounts to flange on telescope providing focal control.

• Narcissus mirrors mounted on telescope structure are used to reduce thermal emission

– rather than a cold stop within the cryostat.

• instrument includes control system

– interfaces with AST3 telescope & PLATO Supervisor computer.

Detector Array & Cryo System

• Supplier of detector array

• Baseline is Teledyne;

• Also to be explored is Selex ES, a European company who may be offer an alternative without ITAR restrictions.

• Array size and configuration

• Baseline and preferred option is science grade H2RG (2k x 2k);

• De-scope options include engineering grade H2RG (with contiguous 1k x 1k region), and science grade H1RG (1k x 1k array).

• Detector and cryo system supplier

• Baseline is Teledyne+GL Scientific to supply detector with detector mounting plate and SIDECAR ASIC focal plane electronics

– AAO to design cryostat body, cooling & vacuum system, baffling, window mount,

& filter holder

– Alternative #1 is Teledyne+GL Scientific to supply complete winterised detector/cryo/controller system

– Other alternatives to be explored.

Telescope Interface

Telescope configuration

• AST3-3 is a clone of the AST3-2 telescope but with a folded Nasmyth focus

– this telescope is currently in the construction phase;

• AST3-4 Cassegrain-focus infrared-optimised telescope with the same mirror diameter as AST3-2

(i.e. 0.68 m).

– likely to have superior performance for AST3-NIR camera

– currently unfunded with a longer lead time. A preliminary optical design exists for this telescope

• A larger telescope with 1 m diameter (unfunded).

Telescope

Telescope mount

Alt-Azimuth or

Equatorial

Telescope location

• Preferred option is Chinese Kunlun station at Dome A;

– Alternatives (due to ITAR restrictions) are US Amundsen-Scott

South Pole station or French-Italian Dome C station.

• Telescope/instrument integration

• Preferred option would be to integrate & test instrument with telescope in China, but this is unlikely due to ITAR

• Camera integration may be at Swinburne (pending lab space)

• Camera/telescope integration may be at U Tas in Hobart (lab space available)

Outside Scope

Following activities not within scope of project but are essential :

AST3-NIR telescope & telescope control system: To be provided by NIAOT.

Deployment & logistics to & in Antarctica: To be provided by PRIC or NSF OPP.

PLATO power supply: existing PLATO-A power supply module does not provide sufficient power for AST3-1, AST3-2, and AST3-NIR & instrumentation.

– new module is required – likely dedicated to AST3-NIR+instrument.

– this is currently not funded.

Operations: Observatory and telescope operations are not included within project scope. To be provided by NAIOT+UNSW.

Survey program: Development and management of science cases & observing program to be provided by science team(s) coordinated by Lead Investigator.

– See preliminary KISS plan for M.Burton, M.Ashley and team roles

Data pipeline: Under this project a functioning software/control system will be provided with limited capability to transfer data or for image analysis.

• A more sophisticated on-site data reduction pipeline is not currently assigned or funded. Capability to create source catalogs on site is required.

• Data archive is allocated to ANU according to the LIEF.

Project subsystems (WBS)

Systems & Management: Project management, systems engineering and instrument requirements management

Interfaces: Development of interface specifications and drawings for telescope, detector, and electronics/control systems

Detector & Controller: Design & procurement for detector & detector controller

Cryostat System: Design & procurement for cryostat body and cryo-controller;

Control System: Design, procurement, & assembly for instrument controller.

Software: Development and testing of low level control software and high level instrument control and interface software;

AIT: Camera sub-system integration & testing, and integration of camera with telescope to occur within Australia.

– If integration in China is allowed, additional travel funding will be required.

Anticipated Scheduled Milestones

ID Milestone Completion

0 Preliminary discussions with DoS re: ITAR

1 Project Kick-off (Meeting at HKU)

2 Requirements Review

3 Detector & Interface Specification

4 RFQ Teledyne

5 Contract Negotiation (Detector)

6 Purchase Order (Detector)

7 PDR (De-Scope Option)

8 SAIL Readiness Review at SUT

9 Procurement Lead-time (Detector)

10 Float Procurement Lead-time (Detector)

11 AIT

12 Camera Pre Delivery Review

13 Shipping to Antarctica

14 Commissioning

15 Science Survey commences

Due Date

January 2015

Feb.– Mar. 2015

June 2015

July 2015

August 2015

September 2015

October 2015

December 2015

July 2016

November 2016

January 2017

Feb. – June 2017

Late 2017

Nov. 2017

Jan. 2018

Feb. 2018

Management

• AAO’s Project Leader and Project Manager will manage the camera project.

• Lead Investigator’s role will be to provide signoff on the Instrument Requirements and take responsibility for all high-level decisions

– e.g. design trade-offs.

• Lead Investigator will have responsibility for developing science teams & survey program.

Project Reviews

• Consistent with similar sized instrument projects at AAO, there will be no formal external reviews.

• There will be a series of internal reviews

– as given in the scheduled milestones:

• Requirements Review,

• Final Design Review,

• SAIL Readiness Review,

• Camera Pre-Delivery Review.

• These reviews will involve a subset of:

– LIEF team

– AAO/SUT/UNSW project team

– representatives from the NIAOT telescope team.

Work Distribution Option A

• In this model, AAO will be responsible for overall management and systems engineering of project and for the design and procurement of all components.

• AAO will be responsible for assembly and testing of instrument control electronics and software

– some fraction possibly subcontracted to UNSW

• SUT will be responsible for AIT of detector and cryostat subsystem, & overall instrument system integration & test

– These tasks will occur at SUT laboratories

– employment of a new SUT detector engineer.

• AAO and SUT will both contribute to the telescope integration and commissioning support activities

Work Distribution Option B

• In this model, all available funds ($1,175k) will be transferred to the AAO

– responsible for all aspects of camera project, including management, systems engineering, design and procurement, & assembly & testing.

– NB: Some fraction of the control system may be sub-contracted to UNSW.

Contracts

• MIA will distribute all project funds to SUT.

• After MIA signed, subcontract will be prepared to arrange for transfer of funds between SUT & AAO

• subcontract specifies detailed Statement of Work

– based on an AAO template

– previously used with other Australian unis for LIEF

Preliminary Risk Assessment (in order)

• US export license for Dome A denied  move to South Pole

• Aust. export license for Dome A denied  move project to SP

• US export license for South Pole denied  re-evaluate

• Australian export license for South Pole denied  re-evaluate

• US export license for China denied  integration in Australia

• No funds to fill funding shortfall  de-scope to H1RG

• Project estimate too low  de-scope to H1RG

• No SUT funding for lab  camera AIT at AAO, SUT engineer to AAO for assembly;

• No SUT detector engineer  camera AIT at AAO using AAO personnel

• SUT detector engineer not well qualified  camera AIT at AAO

• No SUT detector engineer overlap with detector delivery  SUT to extend position;

• Detectors (long lead item) are delayed  project is delayed;

• Partners do not contribute full amount  de-scope to H1RG;

• Scope creep  de-scope to H1RG;

• Power module not funded  replace AST3-1 and AST3-2 or deploy to South Pole;

• Deployment (Dome A) not approved by PRIC  project delayed;

• Deployment (South Pole) not approved by US NSF  project delayed

Team plan

Dec 2014

Feb 2015

March

SRO

AAO

J. Mould

Send out MIA to partners

Ordering H2RG: contact ITAR

Advertise with SPIE for Engineer

Project kickoff meeting

SUT Development Find donor to equip SAIL

All partners Sign MIA and return it to SRO

SRO Invoice TAMU, Sydney, ANU, UNSW

AAO Put $80k in escrow for design work at AAO

M. Burton Form KISS Science Team, study impact of descope options 1,2

M. Ashley Form KIS Survey Management Team

Team plan 2

April

June

July

AAO

A. Moore

Commence detailed design

Organize PDR at AAO

AAO Pay itself $80k & invoice SUT for $20k

M. Burton Science Team report

August

October

D. Hicks

AAO

November AAO

Organize CDRs at AAO and NIAOT

Place purchase order for detector

If CDR satisfactory, invoice SUT for up to $100k design work

AAO & SRO Procure all material against $773k budget*

2016 Mould & Wang If ITAR OK, discard SPole descope option 1

July A. Moore SAIL Readiness Review at SUT

Mould & Lawrence If review successful, discard 1K array descope option 2

Team plan 3

September SUT VC

December D. Hicks

Feb 2017

March

SAIL

A. Moore

April

May

June

July

August

Open Swinburne Astro Instrument Lab

Supervise project handover AAO to SAIL

Ass-Integrate-Test camera subsystems

Survey & System Software Review at SUT

M. Ashley Survey Management Team report

M. Ireland Data Management Review

SAIL

UNSW

D. Hicks

AIT camera system

Survey power review

Camera Pre Delivery Review

September Xiangyan Yuan

November SAIL

AIT telescope

Ship camera to Hobart for integration with telescope

Feb 2018 M. Ashley & PMO Commissioning

Kickoff Meeting Summary 12/3/15

Jeremy Mould

Lifan Wang

Nick Suntzeff

Shihai Yang

Haiping Li

Haikun Wen

Xiaoyan Li

Xiangyan Yuan

Vlad Churilov

Jon Lawrence

Michael Ashley

Jessica Zheng

Swinburne Co Lead Investigator (Camera)

TAMU Co lead investigator (System)

TAMU

NIAOT

Visitor

Control system engineer

NIAOT

NIAOT

NIAOT

NIAOT

AAO

AAO

UNSW

AAO

Optics

Mechanical design

Control software & remote ops

Optical design & telescope mngmt

Mechanical and system engineer

Lead camera project

Control systems and power

Instrument scientist

Michael Burton

Peter Tuthill

Michael Ireland

Julia Tims

By phone

UNSW

Sydney

ANU

AAO

Science Team Chair

Chief Investigator

Chief Investigator, Data archive

Project Manager

Management

• Jeremy Mould will make an org chart

• Jessica Zheng will make an ETC

• Michael Burton will create and maintain a set of science requirements

• Jeremy & Lifan will consider the composition of an External Advisory Committee

Telescope

• We agreed that the baseline plan is to design mods to

AST3-3 to meet the science reqs, not to propose AST3-4.

• Jessica & Haiping will work on baffle design to meet the science requirements.

– This is preferred to changing the speed of the telescope beam, or changing the bent Cassegrain design.

– They will also specify the mirror coatings (gold or …..).

Environment control

• Jon, Michael, Xiangyan, Vlad will develop a thermal model of telescope.

• Some of the resources to maintain optical transmission & thermal equilibrium are CaH absorber, ITO, waste heat.

• AST3 only monitors temp of encoder not tube but some

Mohe data exist.

System requirements

• Science = Jessica

• Transport = PRIC

• Operation, includes telescope, services, ops, environment, work.

• Sunpower cryocooler will be used.

• To handle outgassing of plastics, getter will be used.

• Vlad, Xiangyan and Haikun will study the focus mechanism to avoid duplication if possible.

• Jon, Xiangyan and Jessica will study other optics issues, such as the edge treatment of the fold mirror.

Control system

• Michael talked about power system redundancy, power down modes, transients (ESD & EOS), testing manufacturers’ specs, maximizing software control.

Detector

• ANU currently has most Teledyne experience.

• Cognizant engineer to visit AAO

• Jeremy Mould and Nick Suntzeff will develop a calibration strategy. (Is a shutter required?)

Computers

• Can we develop hardware and software standards for the project? Shihai Yang , Xiaoyan Li and Michael will review the computer architecture of AST3-2. Can it be improved? Should we use new low power processors and He filled disks?

Interface Control Document

• TBD

• Xiangyan will develop a schedule for the NIAOT work and compare with the schedule for AAO work. Jeremy will add a software review to the team plan. When is the science project complete?

Backup deployment plans

Lifan will write an NSF OPP proposal.

– Jeremy will develop an iPeV proposal.

Data Management

• Michael Ireland will develop a technical data management plan.

This does not include any changes to the AST3 collaboration’s data access policies. There will be data releases to the community.

Filter

• Peter Tuthill will study the impact of changing Kdark’s

Delta lambda from 0.18 um.

• There is no filter wheel in the baseline design.

Enabling data

• Jeremy will list our needs

New policies

• Lifan will consider a policy to support instrument builders.

Next meetings

• SCAR AAA Hawaii August

• Nanjing Meeting 2015 end

Download