Jeremy Mould & Jon Lawrence
0900
0930
1000
Break
JM/LW
XY
Meeting overview / Skype
Science requirements ETC
Telescope & optical design
1100
1200
Lunch
JL
MCBA
Optical/cryostat/thermal/system
1400
1500
JL
LW
1600 or Friday JM
Control system/interfaces
System/data pipeline
Deployment/logistics
Project management
• project definition plan for AST3-NIR Antarctic instrument project,
– funded via a successful ARC LIEF grant
• includes instrument high level aims & objectives,
– key project personnel,
– the proposed concept,
– budget, and schedule,
– assessment of key risks at initialisation phase
Primary aims of this project are to:
• conduct a deep high-cadence wide-field K dark infrared sky survey (KISS) from Antarctica;
• enhance Australia/China/US collaboration in
Antarctic astronomy;
• gain knowledge on operation of & procurement for IR detector arrays to be used in Antarctica.
• Design & build a wide-field K-band imager for AST3-
NIR telescope
– AST3-NIR telescope is designed & built by NAOIT;
• Integrate & interface imager with AST3-NIR telescope
– location for integration to be determined,
– possibly U Tas in Hobart per John Dickey & Andrew Cole
• Support commissioning activities (in-person and/or remotely) for the AST3-NIR telescope + instrument in
Antarctica
– at Dome A, South Pole, or Dome C.
• Jeremy Mould (SUT) as Lead Investigator
• Karl Glazebrook (SUT) as Chief Investigator
• Michael Ashley (UNSW) as Chief Investigator
• Michael Burton (UNSW) as Chief Investigator
• Lifan Wang (TAMU) as Partner Investigator
• Ji Yang (PMO) as Partner Investigator
• Anna Moore (Caltech) as Partner Investigator
• Jon Lawrence (AAO) as Partner Investigator
• Peter Tuthill (USyd) as Chief Investigator
• Mike Ireland (ANU) as Chief Investigator.
• Jeremy Mould (SUT) as Lead Investigator
• Jon Lawrence (AAO) as Project Leader
• Julia Tims (AAO) as Project Manager
• Jessica Zheng (AAO) as Instrument Scientist
• Nic Bingham (AAO) as Control System Engineer
• Michael Ashley (UNSW) as Control System Lead
• Xiangyan Yuan (NIAOT) as Telescope Lead Scientist
• “The instrument developed and all materials procured for the instrument project will be owned by Swinburne and made available onloan to the project team for the duration of the project”
– i.e. to the end of the KISS survey phase
• this is of no consequence for the science
– and doesn’t apply to the telescope or its other attachments, such as the data system
Science case (more detail in LIEF text) includes:
• supernovae,
• exo-planets,
• variable stars,
• AGN reverberation mapping,
• gamma-ray-bursts,
• young stellar objects,
• young massive stars,
• cosmic infrared background.
• 2.5
m cut-off HgCdTe detector array,
• mounted in a cryostat with internal baffling,
• K dark filter and optically powered window
• camera mounts to flange on telescope providing focal control.
• Narcissus mirrors mounted on telescope structure are used to reduce thermal emission
– rather than a cold stop within the cryostat.
• instrument includes control system
– interfaces with AST3 telescope & PLATO Supervisor computer.
• Supplier of detector array
• Baseline is Teledyne;
• Also to be explored is Selex ES, a European company who may be offer an alternative without ITAR restrictions.
• Array size and configuration
• Baseline and preferred option is science grade H2RG (2k x 2k);
• De-scope options include engineering grade H2RG (with contiguous 1k x 1k region), and science grade H1RG (1k x 1k array).
• Detector and cryo system supplier
• Baseline is Teledyne+GL Scientific to supply detector with detector mounting plate and SIDECAR ASIC focal plane electronics
– AAO to design cryostat body, cooling & vacuum system, baffling, window mount,
& filter holder
– Alternative #1 is Teledyne+GL Scientific to supply complete winterised detector/cryo/controller system
– Other alternatives to be explored.
• AST3-3 is a clone of the AST3-2 telescope but with a folded Nasmyth focus
– this telescope is currently in the construction phase;
• AST3-4 Cassegrain-focus infrared-optimised telescope with the same mirror diameter as AST3-2
(i.e. 0.68 m).
– likely to have superior performance for AST3-NIR camera
– currently unfunded with a longer lead time. A preliminary optical design exists for this telescope
• A larger telescope with 1 m diameter (unfunded).
Telescope mount
Alt-Azimuth or
Equatorial
Telescope location
• Preferred option is Chinese Kunlun station at Dome A;
– Alternatives (due to ITAR restrictions) are US Amundsen-Scott
South Pole station or French-Italian Dome C station.
• Telescope/instrument integration
• Preferred option would be to integrate & test instrument with telescope in China, but this is unlikely due to ITAR
• Camera integration may be at Swinburne (pending lab space)
• Camera/telescope integration may be at U Tas in Hobart (lab space available)
Following activities not within scope of project but are essential :
• AST3-NIR telescope & telescope control system: To be provided by NIAOT.
• Deployment & logistics to & in Antarctica: To be provided by PRIC or NSF OPP.
• PLATO power supply: existing PLATO-A power supply module does not provide sufficient power for AST3-1, AST3-2, and AST3-NIR & instrumentation.
– new module is required – likely dedicated to AST3-NIR+instrument.
– this is currently not funded.
• Operations: Observatory and telescope operations are not included within project scope. To be provided by NAIOT+UNSW.
• Survey program: Development and management of science cases & observing program to be provided by science team(s) coordinated by Lead Investigator.
– See preliminary KISS plan for M.Burton, M.Ashley and team roles
• Data pipeline: Under this project a functioning software/control system will be provided with limited capability to transfer data or for image analysis.
• A more sophisticated on-site data reduction pipeline is not currently assigned or funded. Capability to create source catalogs on site is required.
• Data archive is allocated to ANU according to the LIEF.
• Systems & Management: Project management, systems engineering and instrument requirements management
• Interfaces: Development of interface specifications and drawings for telescope, detector, and electronics/control systems
• Detector & Controller: Design & procurement for detector & detector controller
• Cryostat System: Design & procurement for cryostat body and cryo-controller;
• Control System: Design, procurement, & assembly for instrument controller.
• Software: Development and testing of low level control software and high level instrument control and interface software;
• AIT: Camera sub-system integration & testing, and integration of camera with telescope to occur within Australia.
– If integration in China is allowed, additional travel funding will be required.
ID Milestone Completion
0 Preliminary discussions with DoS re: ITAR
1 Project Kick-off (Meeting at HKU)
2 Requirements Review
3 Detector & Interface Specification
4 RFQ Teledyne
5 Contract Negotiation (Detector)
6 Purchase Order (Detector)
7 PDR (De-Scope Option)
8 SAIL Readiness Review at SUT
9 Procurement Lead-time (Detector)
10 Float Procurement Lead-time (Detector)
11 AIT
12 Camera Pre Delivery Review
13 Shipping to Antarctica
14 Commissioning
15 Science Survey commences
Due Date
January 2015
Feb.– Mar. 2015
June 2015
July 2015
August 2015
September 2015
October 2015
December 2015
July 2016
November 2016
January 2017
Feb. – June 2017
Late 2017
Nov. 2017
Jan. 2018
Feb. 2018
• AAO’s Project Leader and Project Manager will manage the camera project.
• Lead Investigator’s role will be to provide signoff on the Instrument Requirements and take responsibility for all high-level decisions
– e.g. design trade-offs.
• Lead Investigator will have responsibility for developing science teams & survey program.
• Consistent with similar sized instrument projects at AAO, there will be no formal external reviews.
• There will be a series of internal reviews
– as given in the scheduled milestones:
• Requirements Review,
• Final Design Review,
• SAIL Readiness Review,
• Camera Pre-Delivery Review.
• These reviews will involve a subset of:
– LIEF team
– AAO/SUT/UNSW project team
– representatives from the NIAOT telescope team.
• In this model, AAO will be responsible for overall management and systems engineering of project and for the design and procurement of all components.
• AAO will be responsible for assembly and testing of instrument control electronics and software
– some fraction possibly subcontracted to UNSW
• SUT will be responsible for AIT of detector and cryostat subsystem, & overall instrument system integration & test
– These tasks will occur at SUT laboratories
– employment of a new SUT detector engineer.
• AAO and SUT will both contribute to the telescope integration and commissioning support activities
• In this model, all available funds ($1,175k) will be transferred to the AAO
– responsible for all aspects of camera project, including management, systems engineering, design and procurement, & assembly & testing.
– NB: Some fraction of the control system may be sub-contracted to UNSW.
• MIA will distribute all project funds to SUT.
• After MIA signed, subcontract will be prepared to arrange for transfer of funds between SUT & AAO
• subcontract specifies detailed Statement of Work
– based on an AAO template
– previously used with other Australian unis for LIEF
• US export license for Dome A denied move to South Pole
• Aust. export license for Dome A denied move project to SP
• US export license for South Pole denied re-evaluate
• Australian export license for South Pole denied re-evaluate
• US export license for China denied integration in Australia
• No funds to fill funding shortfall de-scope to H1RG
• Project estimate too low de-scope to H1RG
• No SUT funding for lab camera AIT at AAO, SUT engineer to AAO for assembly;
• No SUT detector engineer camera AIT at AAO using AAO personnel
• SUT detector engineer not well qualified camera AIT at AAO
• No SUT detector engineer overlap with detector delivery SUT to extend position;
• Detectors (long lead item) are delayed project is delayed;
• Partners do not contribute full amount de-scope to H1RG;
• Scope creep de-scope to H1RG;
• Power module not funded replace AST3-1 and AST3-2 or deploy to South Pole;
• Deployment (Dome A) not approved by PRIC project delayed;
• Deployment (South Pole) not approved by US NSF project delayed
Dec 2014
Feb 2015
March
SRO
AAO
J. Mould
Send out MIA to partners
Ordering H2RG: contact ITAR
Advertise with SPIE for Engineer
Project kickoff meeting
SUT Development Find donor to equip SAIL
All partners Sign MIA and return it to SRO
SRO Invoice TAMU, Sydney, ANU, UNSW
AAO Put $80k in escrow for design work at AAO
M. Burton Form KISS Science Team, study impact of descope options 1,2
M. Ashley Form KIS Survey Management Team
April
June
July
AAO
A. Moore
Commence detailed design
Organize PDR at AAO
AAO Pay itself $80k & invoice SUT for $20k
M. Burton Science Team report
August
October
D. Hicks
AAO
November AAO
Organize CDRs at AAO and NIAOT
Place purchase order for detector
If CDR satisfactory, invoice SUT for up to $100k design work
AAO & SRO Procure all material against $773k budget*
2016 Mould & Wang If ITAR OK, discard SPole descope option 1
July A. Moore SAIL Readiness Review at SUT
Mould & Lawrence If review successful, discard 1K array descope option 2
September SUT VC
December D. Hicks
Feb 2017
March
SAIL
A. Moore
April
May
June
July
August
Open Swinburne Astro Instrument Lab
Supervise project handover AAO to SAIL
Ass-Integrate-Test camera subsystems
Survey & System Software Review at SUT
M. Ashley Survey Management Team report
M. Ireland Data Management Review
SAIL
UNSW
D. Hicks
AIT camera system
Survey power review
Camera Pre Delivery Review
September Xiangyan Yuan
November SAIL
AIT telescope
Ship camera to Hobart for integration with telescope
Feb 2018 M. Ashley & PMO Commissioning
Jeremy Mould
Lifan Wang
Nick Suntzeff
Shihai Yang
Haiping Li
Haikun Wen
Xiaoyan Li
Xiangyan Yuan
Vlad Churilov
Jon Lawrence
Michael Ashley
Jessica Zheng
Swinburne Co Lead Investigator (Camera)
TAMU Co lead investigator (System)
TAMU
NIAOT
Visitor
Control system engineer
NIAOT
NIAOT
NIAOT
NIAOT
AAO
AAO
UNSW
AAO
Optics
Mechanical design
Control software & remote ops
Optical design & telescope mngmt
Mechanical and system engineer
Lead camera project
Control systems and power
Instrument scientist
Michael Burton
Peter Tuthill
Michael Ireland
Julia Tims
UNSW
Sydney
ANU
AAO
Science Team Chair
Chief Investigator
Chief Investigator, Data archive
Project Manager
• Jeremy Mould will make an org chart
• Jessica Zheng will make an ETC
• Michael Burton will create and maintain a set of science requirements
• Jeremy & Lifan will consider the composition of an External Advisory Committee
• We agreed that the baseline plan is to design mods to
AST3-3 to meet the science reqs, not to propose AST3-4.
• Jessica & Haiping will work on baffle design to meet the science requirements.
– This is preferred to changing the speed of the telescope beam, or changing the bent Cassegrain design.
– They will also specify the mirror coatings (gold or …..).
Environment control
• Jon, Michael, Xiangyan, Vlad will develop a thermal model of telescope.
• Some of the resources to maintain optical transmission & thermal equilibrium are CaH absorber, ITO, waste heat.
• AST3 only monitors temp of encoder not tube but some
Mohe data exist.
• Science = Jessica
• Transport = PRIC
• Operation, includes telescope, services, ops, environment, work.
• Sunpower cryocooler will be used.
• To handle outgassing of plastics, getter will be used.
• Vlad, Xiangyan and Haikun will study the focus mechanism to avoid duplication if possible.
• Jon, Xiangyan and Jessica will study other optics issues, such as the edge treatment of the fold mirror.
Control system
• Michael talked about power system redundancy, power down modes, transients (ESD & EOS), testing manufacturers’ specs, maximizing software control.
• ANU currently has most Teledyne experience.
• Cognizant engineer to visit AAO
• Jeremy Mould and Nick Suntzeff will develop a calibration strategy. (Is a shutter required?)
Computers
• Can we develop hardware and software standards for the project? Shihai Yang , Xiaoyan Li and Michael will review the computer architecture of AST3-2. Can it be improved? Should we use new low power processors and He filled disks?
• TBD
• Xiangyan will develop a schedule for the NIAOT work and compare with the schedule for AAO work. Jeremy will add a software review to the team plan. When is the science project complete?
•
Backup deployment plans
Lifan will write an NSF OPP proposal.
– Jeremy will develop an iPeV proposal.
Data Management
• Michael Ireland will develop a technical data management plan.
This does not include any changes to the AST3 collaboration’s data access policies. There will be data releases to the community.
• Peter Tuthill will study the impact of changing Kdark’s
Delta lambda from 0.18 um.
• There is no filter wheel in the baseline design.
Enabling data
• Jeremy will list our needs
New policies
• Lifan will consider a policy to support instrument builders.
Next meetings
• SCAR AAA Hawaii August
• Nanjing Meeting 2015 end