CIP 43 Audit Observations

advertisement
CIP 43
ReliabilityFirst Audit Observations
ReliabilityFirst CIP Webinar
Thursday, September 30, 2010
Tony Purgar, Sr. Consultant - Compliance
Topics
Background
CIP 43 Audit Observations
CIP 43 Next Steps
Questions
Background
 ReliabilityFirst has started conducting CIP 43
Audits in 2010
 A planned and coordinated approach is utilized
to execute Pre-Audit, Onsite and Post-Audit
activities
• ReliabilityFirst continuously evaluates auditing
practices for improvements to help streamline the
audit process for the auditors and the registered entity
Background
 Scope:
• 2010: ReliabilityFirst is evaluating CIP compliance for the review
period covering the previous full calendar year up through the
end of audit date (based on Data Retention defined in the CIP Standards)
 2010 audits cover 1/1/09 through end of audit
• 2011: ReliabilityFirst is evaluating CIP compliance for the review
period of 10/1/10 through the end of audit date to coincide with
the release of the CIP V3 standards.
 2011 CMEP Implementation Plan and Actively Monitored List will define the
“minimum list” of CIP requirements within scope.
 Compliance is assessed against:
• CIP V1 standards from 1/1/09 to 3/31/10
• CIP V2 standards from 4/1/10 to 9/30/10
• CIP V3 standards from 10/1/10 and on………
Background
 ReliabilityFirst is sharing the following
observations for entity awareness in preparation
for an upcoming CIP 43 Audit
CIP 43 Audit Observations
 CIP 43 vs. CIP 13:
• 2 teams of 3 vs. 1 team of 3, including the Audit Team
Lead (ATL)
 Each team focused on specific CIP Standards
• CIP 43 Onsite review started ½ day earlier
 (Monday @ 1:00 pm vs. Tuesday @ 8:30 am)
• CIP 43 requires 2-3 wks of coordinated, web based
pre-audit reviews by the two audit teams
 CIP 13 usually required less with only one team
• Greater focus on final findings during pre-audit
reviews
CIP 43 Audit Observations
 Audit - completed in 1 wk onsite
• ½ days:
Monday (pm) & Friday (am)
• 8-10 hr days: Tuesday through Thursday
 Based on onsite progress, additional time would have been
scheduled to complete onsite objectives, if necessary
 While onsite, managing the hrs spent auditing allowed for
daily recap and a fresh start the next day
CIP 43 Audit Observations
 Audit team and Entity’s Primary Compliance
Contact worked closely to manage the agenda
and SME coordination between both audit teams
• Entity SMEs split their time, as needed
 Effective and timely coordination within the team
and with the entity allowed for meeting the
schedule demands
CIP 43 Audit Observations
 Onsite data requests had an assigned due date
prior to the pre-established deadline
• Due dates were agreed to by the entity and flexibility
was granted where appropriate
CIP 43 Audit Observations
 Evidence was voluminous but organized
extremely well
 Entity bookmarked all versions of policies,
procedures, processes, programs and test
results for entire audit review period
 This resulted in efficient evidentiary reviews that
supported the schedule demands
CIP 43 Audit Observations
 Daily status reports were issued to keep the
entity and audit team abreast of the overall audit
status
• The entity and audit team appreciated the value of the
daily status report
 At the end of each day, audit team met to
discuss status, results, questionable
interpretations, problem areas, expectations and
plans for the next day
CIP 43 Audit Observations
 The audit team used the following tools and
techniques to supplement evidentiary reviews:
 CIP-002:
• Entity presented its process for determining Critical
Assets and Critical Cyber Assets per its risk based
assessment methodology
• Examined the meaning of “essential to the operation”
with regard to remote cyber access
• Examined other systems that access Critical Assets
and how the risks of those systems are addressed
CIP 43 Audit Observations
 CIP-003:
• Regionally developed “Cyber Security Policy”
checklist was used to confirm the entity’s cyber
security policy addressed all CIP-002 thru CIP-009
requirements
 CIP-004:
• Regionally developed ”CIP-004” checklist was used to
evaluate training, PRA and physical / electronic
access records for a designated sample size.
– Supporting evidence for each date, activity, record was
cross-checked against the checklist
CIP 43 Audit Observations
 CIP-006:
• Conducted thorough walk thru of main control center,
backup control center and IT data centers
• Checked drop ceilings, cages, raised floors, HVAC
and maintenance penetrations
• Evaluated unauthorized access attempts (i.e. held
door).
• Evaluated physical access controls (i.e. monitoring,
logging, alarming, security personnel activities)
CIP 43 Audit Observations
 CIP-005 & CIP-007:
• Strategic (haphazard) sampling was utilized
 The audit team selected four applications representing major
processes and walked through entity procedures associated
with each requirement
• Evaluated firewall rule-sets and compared physical
ESP device connections (i.e. ports) against diagrams
and documentation
CIP 43 Audit Observations
 CIP-008 & CIP-009:
• Reviewed the meaning of “annual”; how it relates to
applicable requirements; and the audit team’s
evidentiary expectations
• Reviewed “Bookending” expectations regarding
exercising of Cyber Security Incident Response Plans
and Recovery Plans for Critical Cyber Assets
CIP 43 Next Steps
 ReliabilityFirst is preparing for the 2011 CIP Audit
Schedule
• CIP 43 and 693 audits will be conducted separately
 Regional Entities are sharing audit observations to help
develop effective practices and regional consistencies,
where practical
 ReliabilityFirst will implement audit process
improvements, as necessary, based on audit
observations
 We welcome your support and preparedness in making
your CIP 43 Audit a success!!!!!!
Questions
 Questions should be emailed to Karen Yoder
(karen.yoder@rfirst.org) Subject: “CIP
WEBINAR”
 Questions will be considered in the order they
are received
 Clarifying questions are welcome and we will do
our best to answer during the question period
 Challenges to a position should be addressed to
the presenter and will be taken offline
Download