Planning and Managing Projects Chapter 8 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity A B C D E F G H I J K Description Immediate Predecessor(s) Select administrative and medical staff. — Select site and do site survey. — Select equipment. A Prepare final construction plans and layout. B Bring utilities to the site. B Interview applicants and fill positions in A nursing, support staff, maintenance, and security. Purchase and take delivery of equipment. C Construct the hospital. D Develop an information system. A Install the equipment. E,G,H Train nurses and support staff. F,I Responsibility Johnson Taylor Adams Taylor Burton Johnson Adams Taylor Simmons Adams Johnson To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity AON Network A B C D E F G H I J K Description I Immediate Predecessor(s) Select administrative and medical staff. — Select site and do site survey. — Select equipment. A F K A Prepare final construction plans and layout. B Bring utilities to the site. B Interview applicants and fill positions in A nursing, maintenance, Startsupport staff, C Finish G and security. Purchase and take delivery of equipment. C Construct the hospital. D D B H J A Develop an information system. Install the equipment. E,G,H Train nurses and support staff. F,I,J Responsibility Johnson Taylor Adams Taylor Burton Johnson Adams Taylor Simmons Adams Johnson E Figure 8.4 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Activity Description Completion Time A B C D E F G H I J K I 15 Immediate Predecessor(s) Select administrative and medical staff. — Select site and do site survey. — A F KA Select equipment. 12 10 Prepare final construction plans and layout. 6B Bring utilities to the site. B Interview applicants and fill positions in A C G nursing, Startsupport staff, maintenance, Finish 10 35 and security. Purchase and take delivery of equipment. C Construct the hospital. B D H JD Develop an information system. 9 10 40 4A Install the equipment. E,G,H Train nurses and support staff. F,I,J Responsibility Johnson Taylor Adams Taylor Burton Johnson Adams Taylor Simmons Adams Johnson E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Path Expected Time (wks) Activity Immediate Predecessor(s) Description I Completion Time A-F-K 28 15 A Select administrative and medical staff. A-I-K 33 B Select site and A-C-G-J 61Ado site survey. F C Select equipment. 12 10 B-D-H-J D Prepare final63 construction plans and layout. B-E-J E Bring utilities37 to the site. F G H I J K Interview applicants and fill positions in C G nursing, Startsupport staff, maintenance, 10 35 and security. Purchase and take delivery of equipment. Construct the hospital. B D H Develop an information system. 9 10 40 Install the equipment. Train nurses and support staff. — — KA 6 B B A Responsibility Johnson Taylor Adams Taylor Burton Johnson Finish C JD 4A E,G,H F,I,J Adams Taylor Simmons Adams Johnson E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Path Expected Time (wks) Activity Immediate Predecessor(s) Description I Completion Time A-F-K 28 15 A Select administrative and medical staff. A-I-K 33 B Select site and A-C-G-J 61Ado site survey. F C Select equipment. 12 10 B-D-H-J D Prepare final63 construction plans and layout. B-E-J E Bring utilities37 to the site. F G H I J K Interview applicants and fill positions in C G nursing, Startsupport staff, maintenance, 10 35 and security. Purchase and take delivery of equipment. Construct the hospital. B D H Develop an information system. 9 10 40 Install the equipment. Train nurses and support staff. — — KA 6 B B A Responsibility Johnson Taylor Adams Taylor Burton Johnson Finish C JD 4A E,G,H F,I,J Adams Taylor Simmons Adams Johnson E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital I 15 A F K 12 10 6 C G Start B 9 Earliest Start and Earliest Finish Times Finish 10 35 D H J 10 40 4 E 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest start time 12 I 27 Earliest finish time 15 0 A 12 12 12 Critical path 0 B 9 9 Earliest Start and Earliest Finish Times 27 K 33 10 12 Start F 22 C 22 6 22 10 9 D 19 10 G 57 Finish 35 19 H 59 40 59 J 63 4 9 E 33 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital 12 I 27 15 0 A 12 12 27 K 33 10 12 12 Start F 22 C 22 6 22 10 0 B 9 9 Latest Start and Latest Finish Times 9 D 19 10 G 57 Finish 35 19 H 59 40 59 J 63 4 Project finish Time = 63 9 E 33 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital 12 I 27 15 0 A 12 12 27 K 33 63 63 10 12 12 Start F 22 C 22 6 22 10 0 B 9 9 Latest Start and Latest Finish Times 9 D 19 10 9 E 33 G 57 Finish 35 19 H 59 40 Latest finish time 59 J 63 4 63 Latest finish time 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital 12 I 27 15 0 A 12 12 10 12 12 Start F 22 C 22 Latest start time 22 10 0 B 9 9 Latest Start and Latest Finish Times 9 D 19 10 9 E 33 27 K 33 57 63 6 G 57 Finish 35 19 H 59 40 Latest finish time J 59 63 59 4 63 Latest start time 24 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Earliest start time Latest start time A 0 12 2 12 14 I 12 27 42 15 57 Critical path 0 0 B 9 9 9 Latest Start and Latest Finish Times Latest finish time F 27 K 33 57 63 12 22 47 10 57 C Start Earliest finish time 12 22 14 10 24 D 9 19 9 10 19 6 G 22 57 24 35 59 H 19 59 19 40 59 Finish J 59 63 59 4 63 9 E 33 35 24 59 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital I 12 27 42 15 57 A 0 12 2 12 14 F C 12 22 14 10 24 Start 0 0 Activity Slack Analysis B 9 9 9 27 K 33 57 63 12 22 47 10 57 D 9 19 9 10 19 6 G 22 57 24 35 59 H 19 59 19 40 59 Finish J 59 63 59 4 63 9 E 33 35 24 59 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Slack Hospital St. Activity Adolf’s I 12 27 42 15 57 Slack = LS – ES or A 0 12 2 12 14 Slack = LF – EF F C 12 22 14 10 24 Start 0 0 Activity Slack Analysis B 9 9 9 27 K 33 57 63 12 22 47 10 57 D 9 19 9 10 19 6 G 22 57 24 35 59 H 19 59 19 40 59 Finish J 59 63 59 4 63 9 E 33 35 24 59 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Slack Hospital St. Activity Adolf’s I SlackK = 57 – 27 = 30 or A 0 12 2 12 14 SlackK = 63 – 33 = 30 12 27 42 15 57 F C 12 22 14 10 24 Start 0 0 Activity Slack Analysis B 9 9 9 27 K 33 57 63 12 22 47 10 57 D 9 19 9 10 19 6 G 22 57 24 35 59 H 19 59 19 40 59 Finish J 59 63 59 4 63 9 E 33 35 24 59 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Node Duration ES LS Slack St. Adolf’s Hospital A 12 0 2 2 I B C D E F G H I J K 9 10 10 24 10 35 40 15 4 6 0 12 9 9 12 22 19 12 59 27 0 14 9 35 47 24 19 42 59 57 0 2 0 26 35 2 0 30 0 30 0 0 Critical Path B 9 9 9 12 27 42 15 57 F 27 K 33 57 63 12 22 47 10 57 C 12 22 14 10 24 D 9 19 9 10 19 6 G 22 57 24 35 59 H 19 59 19 40 59 Finish J 59 63 59 4 63 9 E 33 35 24 59 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Cost-Time Relationships in Cost Analysis Direct cost (dollars) 8000 — Crash cost (CC) 7000 — Linear cost assumption 6000 — 5200 5000 — Estimated costs for a 2-week reduction, from 10 weeks to 8 weeks 4000 — 3000 — 0— Normal cost (NC) | 5 | 6 (Crash time) Figure 8.11 | 7 8 | 9 | 10 | 11 (Normal time) Time (weeks) To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital TABLE 8.1 DIRECT COST AND TIME DATA FOR THE ST. ADOLF’S HOSPITAL PROJECT Activity Normal Time (NT) Normal Cost (NC) A B C D E F G H I J K 12 9 10 10 24 10 35 40 15 4 6 $ 12,000 50,000 4,000 16,000 120,000 10,000 500,000 1,200,000 40,000 10,000 30,000 Totals $1,992,000 Crash Time (CT) 11 7 5 8 14 6 25 35 10 1 5 Crash Cost (CC) $ 13,000 64,000 7,000 20,000 200,000 16,000 530,000 1,260,000 52,500 13,000 34,000 Maximum Time Reduction (wk) 1 2 5 2 10 4 10 5 5 2 1 Cost of Crashing per Week $ 1,000 7,000 600 2,000 8,000 1,500 3,000 12,000 2,500 1,000 4,000 $2,209,000 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Modeling project schedule in Excel Forward schedule (Earliest time) ES = EF of predecessor, if only one predecessor ES = Max(EF of predecessors), if more than one EF = ES + Activity duration Backward schedule (Latest time) LF = LS of successor, if only one successor ES = Min(LS of successors), if more than one LS = LF - Activity duration To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Optimal crashing using Excel Solver Target cell = Cost or project completion time Changing cells = Crashing time Constraints = Crashing time <= MTR Options: • Non-negative • Tolerance • Estimates, derivative, search To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Pert = Project Evaluation Review Technique Finding probability for project completion time To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. Probability Probabilistic Time Estimates a m b Time Mean Figure 8.12 (a) Beta Distribution To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Probabilistic Time Estimates I A F K Mean a + 4m + b te = 6 Variance 2 = ( Start B C G D H Finish J E b–a 6 2 ) To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Probabilistic Time Estimates I A Activity B Most Optimistic Likely Pessimistic (a) (m) (b) 7 8 15 Start B F K C G D H Finish J E Example 8.6 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Probabilistic Time Estimates I A Activity B Most Optimistic Likely Pessimistic (a) (m) (b) 7 8 15 7 + 4(8) + 15 te = = 9 weeks 6 2 = ( 15 - 7 6 Start B F K C G D H Finish J E 2 ) = 1.78 Example 8.6 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Time Estimates (wk) Optimistic Activity (a) A B C D E F G H I J K 11 7 5 8 14 6 25 35 10 1 5 Likely (m) Pessimistic (b) 12 8 10 9 25 9 36 40 13 2 6 13 15 15 16 30 18 41 45 28 15 7 Activity Statistics Expected Variance Time (te ) ( 2 ) 12 9 10 10 24 10 35 40 15 4 6 0.11 1.78 2.78 1.78 7.11 4.00 7.11 2.78 9.00 5.44 0.11 Example 8.6 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital What is the probability the project will be completed in 65 days? Critical Path = B - D - H - J TE = 9 + 10 + 40 + 4 = 63 days 2 = (variances of critical path activities) 2 = 1.78 + 1.78 + 2.78 + 5.44 = 11.78 = 11.78 = 3.432 Example 8.7 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Probabilities Critical Path = B - D - H - J T = 65 days TE = 63 days = 3.432 z= T – TE = 65 – 63 3.432 = 0.58 From Normal table in page 807, for z = 0.58, the table area = 0.7190 The probability that the project will be Completed within 65 days is 71.9% Example 8.7 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Normal distribution: Mean = 63 weeks; = 3.432 weeks Length of critical path Probability of meeting the schedule is 0.7190 Probability of exceeding 65 weeks is 0.2810 63 65 Project duration (weeks) To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Expected project completion time with 98% probability Critical Path = B - D - H - J T = TE + z Normal table for 98%, z = 2.055 T = 63 + 2.055 (3.432) = 70.05 weeks To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved. St. Adolf’s Hospital Probabilities Path = A - C - G – J Find probability for T = 65 days TE = 12 + 10 + 35 + 4 = 61 days 2 = (variances of activities) 2 = 0.11 + 2.78 + 7.11 + 5.44 = 15.44 z= T – TE 2 From Appendix 2 65 – 61 z= = 1.02 Pz = .8461 15.44 Example 8.7 To Accompany Krajewski & Ritzman Operations Management: Strategy and Analysis, Seventh Edition © 2004 Prentice Hall, Inc. All rights reserved.