LESSON 15 INVENTORY MODELS (DETERMINISTIC) EOQ MODEL FOR PRODUCTION PLANNING Outline • EOQ Model for Production Planning – The multi-product inventory control model with a finite production rate – An example showing the problem with separate EPQ computation – The procedure – An example 1 EOQ Model for Production Planning • This model is an extension of the EPQ model • Consider the problem of producing many products in a single facility. The facility may produce only one product at a time. • In each production cycle there is only one setup for each product, and the products are produced in the same sequence in each production cycle. This assumption is called the rotation cycle policy. • For example, if there are three products A, B and C, then a production sequence under the rotation cycle policy is A, B, C, A, B, C, …. 2 EOQ Model for Production Planning • The goal is to determine the optimal production quantities of various products produced in each cycle and the optimal length of the cycle. • Finding optimal production quantity of each product separately using the EPQ formula Qj * 2K j j hj ' may not give a good solution because a production quantity may not be large enough to meet the demand between two production runs of the product. 3 EOQ Model for Production Planning • For example, suppose that there are three products A, B and C, then a production sequence under the rotation cycle policy is A, B, C, A, B, C, …. • The production quantity of product A obtained from the EPQ formula may not be large enough to meet the demand during the production run of products B and C. • The next example elaborates on the problem of using EPQ formula separately for each product. 4 Optional Example Problem with Separate EPQ Computation Example 6: Tomlinson Furniture has a single lathe for turning the wood for various furniture pieces including bedposts, rounded table legs, and other items. Two products and some relevant information appear below: Annual Setup Time Unit Annual Piece Demand (hours) Cost Production J-55R 18,000 1.2 $20 33,600 H-223 24,000 0.8 35 52,800 Worker time for setup is valued at $85 per hour, and holding costs are based on a 20 percent annual interest charge. Assume 8 hours per day and 240 days per year. 5 Optional Example Problem with Separate EPQ Computation Find the optimal production quantities separately for each product and show that production quantity of H-223 is not large enough to meet the demand between two production runs of H-223. Product J - 55R : K set - up time worker time 1.2 85 $102 h Ic 0.20 20 $4/unit/year 18,000 0.5357 P 33,600 h' h1 41 0.5357 $1.8571/unit/year P 6 Product J - 55R (continued from the previous slide) : Optional 2 K 2 102 18,000 Q EPQ 1,406.1404 units h' 1.8571 * Max Inventory, H Q 1 1,406.141 0.5357 652.85 units P * Q* 1,406.1404 Uptime, T1 240 10.0439 days P 33,600 Minimum downtime (days), required Uptime for H - 223 setup time of H - 223 4.2027 days (see the next slide) 0.8 hr/ 8 hr per day 4.3027 days H 652.8509 240 18,0001 8.7047 days 4.3027 days (downtime demand met) Maximum inventory lasts for (days) 7 Product H - 223 : Optional K set - up time worker time 0.8 85 $68 h Ic 0.20 35 $7 /unit/year 24,000 0.4545 P 52,800 h' h1 71 0.4545 $3.8182 /unit/year P 2 68 24,000 2 K 924.5848 units Q EPQ 3.8182 h' * Max Inventory, H Q 1 924.581 0.4545 504.32 units P * Q* 924.5848 240 4.2027 days Uptime, T1 52,800 P 8 Product H - 223 (continued from the previous slide) : Optional Minimum downtime (days), required Uptime for J - 55R setup time of J - 55R 10.0439 days 1.2 hr/ 8 hr per day 10.1939 days Maximum inventory lasts for (days) H 504.3190 240 24,000 5.0432 days 10.1939 days (downtime demand cannot be met) Conclusion : If EPQ quantities are produced, demand for Product H - 223 cannot be met when product J - 55R is produced. 9 Annual production rate (units/year) Annual Demand rate (units/year) Setup time (hour) K, Setup cost, $ Unit cost, $ h, Holding cost/unit/year demand/production h' Separate EPQ solution Q* Maximum inventory Uptime (days) Minimum downtime (days) Maximum inventory lasts for (days) J-55R 33600 18000 1.2 Optional H-223 52800 24000 0.8 20 35 10 Annual production rate (units/year) Annual Demand rate (units/year) Setup time (hour) K, Setup cost, $ Unit cost, $ h, Holding cost/unit/year demand/production h' Separate EPQ solution Q* Maximum inventory Uptime (days) Minimum downtime (days) Maximum inventory lasts for (days) J-55R 33600 18000 1.2 102 20 4 0.5357 1.8571 Optional H-223 52800 24000 0.8 68 35 7 0.4545 3.8182 1406.1404 924.5848 652.8509 504.3190 10.0439 4.2027 4.3027 10.1939 8.7047 5.0432 11 EOQ Model for Production Planning • The previous example shows that if production quantities of different products are computed separately, then demand of every product may not be met. • Therefore, all the products must be considered at the same time. • To solve the integrated problem, first, the cycle time T is computed. For each product j, the production quantity Q j is the demand of the product during the cycle time. If j is the annual demand of product j Q j jT 12 EOQ Model for Production Planning • Let T be the cycle time and Tj be the production time of product j Q j jT PjT j Tj T j Pj • Let sj be the setup time of product j and n be the number of products T s1 T1 s2 T2 sn Tn Idle time 13 EOQ Model for Production Planning T s1 T1 s2 T2 sn Tn Idle time sn Tn s1 T1 s2 T2 1 T T T T T T n s n T n n 1 j j j 1 s j 1 T j 1 j 1 T j 1 T j 1 Pj n T s j 1 n 1 j 1 j j Pj 14 EOQ Model for Production Planning • Two rules for T* n T * Cycle1 s j 1 n 1 j 1 n j j Pj T * Cycle2 2 K j j 1 n h' j 1 j j • T* is the maximum of the two. T* = max (Cycle1, Cycle2) 15 Example EOQ Model for Production Planning Example 7: Tomlinson Furniture has a single lathe for turning the wood for various furniture pieces including bedposts, rounded table legs, and other items. Two products and some relevant information appear below: Annual Setup Time Unit Annual Piece Demand (hours) Cost Production J-55R 18,000 1.2 $20 33,600 H-223 24,000 0.8 35 52,800 Worker time for setup is valued at $85 per hour, and holding costs are based on a 20 percent annual interest charge. Assume 8 hours per day and 240 days per year. Find the 16 optimal production quantities. 2 n s s j 1 j j 1 s1 s2 j 2 n K K j j 1 n j j 1 2 j P P j 1 j j 1 K1 K 2 j 1 P1 2 P2 2 n h' j 1 j j j h' j j j 1 h'1 1 h'2 2 17 n Cycle1 s j 1 n 1 j 1 j j Pj n Cycle2 2 K j j 1 n h' j 1 j j T * max Cycle1, Cycle2 18 Product J - 55R : Q * T * Max Inventory, H Q* 1 P Q* Uptime, T1 P Downtime T * Uptime Maximum inventory lasts for (days) H downtime of J - 55R (uptime setup time) of H - 223 (check) 19 Product H - 223 : Q * T * Max Inventory, H Q* 1 P Q* Uptime, T1 P Downtime T * Uptime Maximum inventory lasts for (days) H downtime of H - 223 (uptime setup time) of J - 55R (check) 20 K, Setup cost, $ h, Holding cost/unit/year demand/production h' h'(demand) J-55R H-223 Total 102 68 170 4 7 0.5357 0.4545 0.9903 1.8571 3.8182 EOQ Model for Production Planning Cycle1 in days Cycle2 in days Cycle time=max(cycle1, cycle2) in days Q* = cycle time demand Maximum inventory Uptime (days) Downtime (days) Maximum inventory lasts for (days) 21 READING AND EXERCISES Lesson 15 Reading: Section 4.9 , pp. 226-229 (4th Ed.), pp. 215-220 (5th Ed.) Exercise: 29, 30 pp. 230-231(4th Ed.), pp. 219-220 (5th Ed.) 22