Department of Water and Power City of Los Angeles Renewables Portfolio Standard (RPS) Master Plan Building Out Opportunities October 9, 2006 LADWP Generation Resources CASTAIC VALLEY SCATTERGOOD HAYNES HARBOR 2 LADWP RPS Master Plan On December 13, 2005 LADWP management presented to the Board on how LADWP plan to meet the RPS goal of 20% by 2010 Six general areas that make up the Master Plan – Existing resources – Consisting of Aqueduct, Hyperion digestion, Lopez microturbines, solar rooftops, landfill gas contracts, Wyoming Wind project, and purchases – Planned resources – Consisting of Pine Tree Wind Project, Powerex Small Hydro, and the ongoing solar rooftops program – 2004 LADWP RFP – Resource acquisition consisting of originally seven projects – 2005 SCPPA RFP – Resource acquisition consisting of originally seven projects and now new 2006 SCPPA RFP that closes October 16th. – LADWP Development – Resource development on LADWP owned properties. – Transmission Developments – Consisting of the Pine Tree Transmission Line, new Tehachapi Transmission System, Green Path Project, and Southern Transmission System upgrade DSM Assumptions – Use the Maximum Achievable Level 3 Location of Proposed Renewable Energy Projects and Existing Transmission Constraints From Northwest Hydro Wind Biomass Landfill Gas Waste to Energy Solar Geothermal Transmission Constraint 4 Projected Resources by Percent of Load (Sep 5, 2006) 25% Hydro Biomass Geothermal Wind 20% 20% by 2010 Goal Solar LADWP Development Renewable Generation, GWh Mix 15% 2005 SCPPA RFP 10% 2004 LADWP RFP Planned 5% Existing 0% 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 5 Planned and Developed Renewable Resources Pine Tree Wind Project (120 MW) – Completed draft RFP specification for BOP work. – A final draft RFP specification for design build of the 230 kV transmission line is complete. – Barren Ridge switching station under construction. Waste to Energy Conversion – Proposed four 25 MW (total of 100 MW) Municipal Solid Waste to energy conversion technology developments with Los Angeles Bureau of Sanitation. The projects will be located in Los Angeles and the in-service dates are projects to be 2010 through 2013. Concentrated Solar Power – Proposing two 125 MW CSPs for development by LADWP on owned lands with transmission access and tentative in-service dates of 2010. Geothermal – 50+ MW of geothermal development in the Salton Sea area on owned land with tentative in-service date of 2012. 6 MAP 1 SOLAR RESOURCE 7 BIG PINE INDEPENDENCE LONE PINE MAP 2 SOUTHERN OWENS VALLEY 8 BARREN RIDGE SWITCHING STATION (PROPOSED) KRAMER JUNCTION HARPER DRY LAKE MOJAVE MAP 3 HIGH DESERT ADELANTO SWITCHING STATION 9 LADWP PROPERTIES MAP 4 SALTON SEA 10 Inyo - Rinaldi Line Upgrade Project To Cottonwood/Inyo OWENS GORGE 9 miles SCE 1. Reconductor Barren Ridge to Rinaldi w/ 1113 ACSS. Wind 2 150+ MW 2008 COD INYO 2. New line from Barren Ridge to Castaic w/ 1113ACSS. 81 miles Barren Ridge Pine Tree 120 MW 2007 COD Pine Tree COTTONWOOD 500MW WTG 68 miles BARREN RIDGE Wind 3 100+ MW 2009 COD Wind # 3 Substation CASTAIC 76 miles 71.6 miles To Castaic OLIVE To Rinaldi SYLMAR NORTHRIDGE 234 miles RINALDI 11 Inyo - Rinaldi Line Upgrade Project Information Pine Tree Project Construction (1/2007 COD) – Barren Ridge 230 kV Substation – Pine Tree 34.5 kV Substation – Barren Ridge – Pine Tree Line (10 Miles) – Environmental Studies: Completed Wind #2 Project Construction (10/2008 COD) – Pine Tree 230 kV Bus – Wind #2 – Pine Tree 230 kV (10 miles) Wind #3 Project Construction (12/2008 COD) – Wind #3 230 kV Substation – Barren Ridge – Wind #3 230 kV Line (12 miles, 1113 ACSS conductor) – Wind #3 – Castaic 230 kV Line (72 miles, 1113 ACSS conductor) – Environmental Studies: Will be conducted by LADWP (need 2 years) Re-conductor Barren Ridge – Rinaldi 230 kV line (12/2010 COD) – 1113 ACSS conductor (76 miles) 12 Southern Transmission System (STS) 13 DC (STS) Upgrade Project Information Upgrade Project Level: – Recommended Upgrade: 480 MW (2400 MW rating) – Upgrade cost & benefit expected to be shared by existing STS owners – LADWP upgrade share: 286 MW (59.53%) Upgrade Timeline: – Project Rating Studies (12/2006) – HVDC Control and Design Studies (12/2006) – HVDC Equipment Installation (10/2008) – 2400 MW DC Rating COD (12/2008) 14 Palo Verde – Devers #2 and Green Path Project Lines Victorville Lugo Upland LADWP Transmission Project Mira Loma Century Rancho Vista Existing 500kV Line New 500kV Line Existing 230/287kV Line Serrano Rebuild/New 230/287kV CAISO Meter Point Valley Devers CALIFORNIA Mirage Palo Verde – Devers Line #2 Ramon IID Transmission Upgrades S.D. Central ARIZONA Indian Hills Coachella Valley Palo Verde Hassayampa Ave 58 Midway San Felipe Bannister Geothermal Highline North Gila Miguel ECSS U.S.A. I.V. MEXICO IID Transmission Project 15 LADWP Green Path Transmission Project Victorville Lugo Upland Mira Loma Century Rancho Vista Existing 500kV Line New 500kV Line Existing 230/287kV Line Serrano Rebuild/New 230/287kV CAISO Meter Point Valley Devers Mirage Ramon Indian Hills Coachella Valley 16 LADWP Green Path Transmission Project Project Plan-of- Service: – 500 kV, 100 mile line from a new Indian Hills Substation (IID) to a new Upland Substation (LADWP – near Rancho Cucamonga) – Expected project rating at 1200 MW (Phase 1 WECC rating process) – Ownership: LADWP 80%, others 20% – Project include upgrade about 40 miles of Victorville – Century 287 kV line 1 from Victorville to 500 kV. – Projects Provides substantial system reliability improvement to the Grid Project Timeline: – Rating Studies and Reliability Assessment: 7/2004 – 12/2006 – Environmental Studies: 10/2005 – 6/2008 – Project Construction Period: 3/2009-10/2009 – Project COD: November 2010 17