ladwp rps - Independent Energy Producers

advertisement
Department of Water and Power
City of Los Angeles
Renewables Portfolio Standard (RPS) Master Plan
Building Out Opportunities
October 9, 2006
LADWP Generation Resources
CASTAIC
VALLEY
SCATTERGOOD
HAYNES
HARBOR
2
LADWP RPS Master Plan

On December 13, 2005 LADWP management presented to the Board on how
LADWP plan to meet the RPS goal of 20% by 2010

Six general areas that make up the Master Plan

–
Existing resources – Consisting of Aqueduct, Hyperion digestion, Lopez
microturbines, solar rooftops, landfill gas contracts, Wyoming Wind project, and
purchases
–
Planned resources – Consisting of Pine Tree Wind Project, Powerex Small
Hydro, and the ongoing solar rooftops program
–
2004 LADWP RFP – Resource acquisition consisting of originally seven projects
–
2005 SCPPA RFP – Resource acquisition consisting of originally seven projects
and now new 2006 SCPPA RFP that closes October 16th.
–
LADWP Development – Resource development on LADWP owned properties.
–
Transmission Developments – Consisting of the Pine Tree Transmission Line,
new Tehachapi Transmission System, Green Path Project, and Southern
Transmission System upgrade
DSM Assumptions – Use the Maximum Achievable Level
3
Location of Proposed Renewable Energy Projects and
Existing Transmission Constraints
From Northwest
Hydro
Wind
Biomass
Landfill Gas
Waste to Energy
Solar
Geothermal
Transmission
Constraint
4
Projected Resources by Percent of Load (Sep 5, 2006)
25%
Hydro
Biomass
Geothermal
Wind
20%
20% by 2010 Goal
Solar
LADWP Development
Renewable Generation, GWh
Mix
15%
2005 SCPPA RFP
10%
2004 LADWP RFP
Planned
5%
Existing
0%
2006
2008
2010
2012
2014
2016
2018
2020
2022
2024
2026
5
Planned and Developed Renewable Resources

Pine Tree Wind Project (120 MW)
–
Completed draft RFP specification for BOP work.
–
A final draft RFP specification for design build of the 230 kV transmission line is
complete.
–
Barren Ridge switching station under construction.

Waste to Energy Conversion – Proposed four 25 MW (total of 100 MW) Municipal
Solid Waste to energy conversion technology developments with Los Angeles Bureau
of Sanitation. The projects will be located in Los Angeles and the in-service dates are
projects to be 2010 through 2013.

Concentrated Solar Power – Proposing two 125 MW CSPs for development by
LADWP on owned lands with transmission access and tentative in-service dates of
2010.

Geothermal – 50+ MW of geothermal development in the Salton Sea area on owned
land with tentative in-service date of 2012.
6
MAP 1
SOLAR RESOURCE
7
BIG PINE
INDEPENDENCE
LONE PINE
MAP 2
SOUTHERN OWENS VALLEY
8
BARREN RIDGE SWITCHING
STATION (PROPOSED)
KRAMER
JUNCTION
HARPER
DRY LAKE
MOJAVE
MAP 3
HIGH DESERT
ADELANTO SWITCHING STATION
9
LADWP
PROPERTIES
MAP 4
SALTON SEA
10
Inyo - Rinaldi Line Upgrade Project
To Cottonwood/Inyo
OWENS GORGE
9 miles
SCE
1. Reconductor Barren
Ridge to Rinaldi w/ 1113
ACSS.
Wind 2
150+ MW
2008 COD
INYO
2. New line from Barren
Ridge to Castaic w/
1113ACSS.
81 miles
Barren Ridge
Pine Tree
120 MW
2007 COD
Pine Tree
COTTONWOOD
500MW WTG
68 miles
BARREN RIDGE
Wind 3
100+ MW
2009 COD
Wind # 3 Substation
CASTAIC
76 miles
71.6 miles
To Castaic
OLIVE
To Rinaldi
SYLMAR
NORTHRIDGE
234 miles
RINALDI
11
Inyo - Rinaldi Line Upgrade Project Information




Pine Tree Project Construction (1/2007 COD)
–
Barren Ridge 230 kV Substation
–
Pine Tree 34.5 kV Substation
–
Barren Ridge – Pine Tree Line (10 Miles)
–
Environmental Studies: Completed
Wind #2 Project Construction (10/2008 COD)
–
Pine Tree 230 kV Bus
–
Wind #2 – Pine Tree 230 kV (10 miles)
Wind #3 Project Construction (12/2008 COD)
–
Wind #3 230 kV Substation
–
Barren Ridge – Wind #3 230 kV Line (12 miles, 1113 ACSS conductor)
–
Wind #3 – Castaic 230 kV Line (72 miles, 1113 ACSS conductor)
–
Environmental Studies: Will be conducted by LADWP (need 2 years)
Re-conductor Barren Ridge – Rinaldi 230 kV line (12/2010 COD)
–
1113 ACSS conductor (76 miles)
12
Southern Transmission System (STS)
13
DC (STS) Upgrade Project Information


Upgrade Project Level:
–
Recommended Upgrade: 480 MW (2400 MW rating)
–
Upgrade cost & benefit expected to be shared by existing STS owners
–
LADWP upgrade share: 286 MW (59.53%)
Upgrade Timeline:
–
Project Rating Studies (12/2006)
–
HVDC Control and Design Studies (12/2006)
–
HVDC Equipment Installation (10/2008)
–
2400 MW DC Rating COD (12/2008)
14
Palo Verde – Devers #2 and Green Path Project Lines
Victorville
Lugo
Upland
LADWP Transmission Project
Mira Loma
Century
Rancho Vista
Existing 500kV Line
New 500kV Line
Existing 230/287kV Line
Serrano
Rebuild/New 230/287kV
CAISO Meter Point
Valley
Devers
CALIFORNIA
Mirage
Palo Verde – Devers Line #2
Ramon
IID
Transmission
Upgrades
S.D.
Central
ARIZONA
Indian Hills
Coachella
Valley
Palo Verde
Hassayampa
Ave 58
Midway
San Felipe
Bannister
Geothermal
Highline
North Gila
Miguel
ECSS
U.S.A.
I.V.
MEXICO
IID Transmission Project
15
LADWP Green Path Transmission Project
Victorville
Lugo
Upland
Mira Loma
Century
Rancho Vista
Existing 500kV Line
New 500kV Line
Existing 230/287kV Line
Serrano
Rebuild/New 230/287kV
CAISO Meter Point
Valley
Devers
Mirage
Ramon
Indian Hills
Coachella
Valley
16
LADWP Green Path Transmission Project


Project Plan-of- Service:
–
500 kV, 100 mile line from a new Indian Hills Substation (IID) to a new Upland
Substation (LADWP – near Rancho Cucamonga)
–
Expected project rating at 1200 MW (Phase 1 WECC rating process)
–
Ownership: LADWP 80%, others 20%
–
Project include upgrade about 40 miles of Victorville – Century 287 kV line 1 from
Victorville to 500 kV.
–
Projects Provides substantial system reliability improvement to the Grid
Project Timeline:
–
Rating Studies and Reliability Assessment: 7/2004 – 12/2006
–
Environmental Studies: 10/2005 – 6/2008
–
Project Construction Period: 3/2009-10/2009
–
Project COD: November 2010
17
Download