NETWORK AND BLOCK DIAGRAMS YUSUF OZ FATIH BOLUKBAS HUSEYIN ANIL KARABULUT What is Project Network Diagram? A project network diagram is a pictorial representation of the sequence in which the project can be done. Developed in the 1950’ to overcome the shortcoming of the Gantt Chart. Superiority over Gantt Chart: Displays detailed information on each work unit Clearly reflects the order of tasks in multiple phases Reflects the shortest path to completion Reflects the best usage of resource Helps of Network Diagrams Network diagrams help us in following way: Finds our critical / non-critical activities. Understand the types of activity dependencies and when they are used. Ideal Situations of Network Diagrams Network Diagrams are ideal for these situations: Detailed project management Implementation tracking Contingency plans Resource control Types of Network Diagram Arrow diagram (AOA – Activity on Arrow) Precedence diagram (AON – Activity on Node) AOA for Computer Institute AON for Computer Institute Dependency FS = Finish to Start SS = Start to Start FF = Finish to Finish SF = Start to Finish ARROW DIAGRAMS The arrow diagram shows the required order of tasks in a project or process The arrow diagram lets you calculate the “critical path” of the project WHEN TO USE ARROW DIAGRAMS When scheduling and monitoring tasks of a complex project with interrelated tasks and resources. When you know the steps of the project or process When project schedule is critical, with serious results for completing the project late or early ARROW DIAGRAM PROCEDURE List all the necessary tasks in the project or process Determine the correct sequence of the tasks Diagram the network of tasks Between each two tasks, draw circles for “events.” Look for three common problem situations and redraw them using “dummies” or extra events DUMMY ACTIVITY? A dummy is an arrow drawn with dotted lines used to separate tasks that would otherwise start and stop with the same events or to show logical sequence Dummy separating simultaneous tasks BLOCK DIAGRAMS The block diagram is a simple pictorial representation of a system or sub-systems to illustrate the relationships between sub-systems. IMPORTANCE OF BLOCK DIAGRAMS Identification the system Visualization the system WHEN TO USE BLOCK DIAGRAMS? Establish the boundaries of a system under consideration Outline the elements contained within the scope of a task Identify inputs and outputs for components within a system Identify relationships between systems or components Establish critical paths through systems HOW TO USE BLOCK DIAGRAMS? Construct the initial diagram using pencil and paper then transfer to the computer Space blocks far apart, leave enough space to add more blocks when needed Start at the input to the system and follow the path Requirements Interfaces – Internal & External Elements System Contributors / Other Aspects Process makes it possible, people make it happen. REFERENCES http://www.super-business.net/IT-Project- Management/172.html http://www.michelbeauregard.com/msProjectnetwo rkDiagram.pdf http://thequalityportal.com/q_block.htm THANKS…