Project Time Management
Dr. Ahmet TÜMAY, PMP
Project Time Management includes the processes required to manage timely completion of the project.
The planning effort for time management is part of the Develop Project Management Plan process
(Section 4.3), which produces a schedule management plan that sets the format and establishes criteria for developing and controlling the project schedule.
• Establishes policies and procedures for planning, developing, managing, executing and controlling the Project schedule
The Activity Definition process will identify the deliverables at the lowest level in the work breakdown structure (WBS), which is called the work package.
Project work packages are planned (decomposed) into smaller components called schedule activities to provide a basis for estimating, scheduling, executing, and monitoring and controlling the project work.
• Process of identifying and documenting the specific actions to be performed to produce the Project deliverables
Decomposition; Subdividing the work packages into smaller, more manageable components, activities. This activity definition is often performed by the project team members responsible for the work package.
Rolling Wave Planning; Rolling wave planning is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail at a low level of the WBS, while work far in the future is planned for WBS components that are at a relatively high level of the WBS.
Activity List; The activity list includes the activity identifier and a scope of work description for each schedule activity in sufficient detail to ensure that project team members understand what work is required to be completed.
Activity Attributes; These attributes are used for project schedule development and for selecting, ordering, and sorting the planned schedule activities in various ways within reports.
Milestone List; Significant point or event in the project. May be mandatory or optional.
Activity sequencing involves identifying and documenting the logical relationships among project activities.
Schedule activities can be logically sequenced with proper precedence relationships, as well as leads and lags to support later development of a realistic and achievable project schedule.
.1 Precedence Diagramming Method (AON)
4 Type Dependencies FS,FF,SS,SF
.2 Dependency Determination
Mandatory Dependencies; hard logic, inherent in the nature of the work being done (a built prototype before test) or contractually required.
Discretionary Dependencies; preferred logic, or soft logic, usually established based on knowledge of best practices within a particular application area where a specific sequence is desired, even though there are other acceptable sequences.
External Dependencies; those that involve a relationship between project activities and non-project activities.
.3 Leads and Lags
Estimating schedule activity resources involves determining what resources (persons, equipment, or materiel) and what quantities of each resource will be used, and when each resource will be available to perform project activities.
The resource needs of each lower, more detailed piece of work are estimated, and these estimates are then aggregated into a total quantity for each of the schedule activity’s resources.
The process of approximating the number of work periods needed to complete individual activities with estimated resources
• Activity Resource Requirements,
• Resource Calendars,
• Project Scope Statement, constraints and assumptions
– Available skilled resources,
– Contract terms and requirements,
– Existing conditions,
– Availability of information,
– Length of the reporting periods.
• Project Risks
• Analogous Estimating; Analogous estimating uses parameters such as duration, budget, size, weight, and complexity, from a previous, similar project, as the basis for estimating the same parameter or measure for a future project. Frequently used for the early phases of project. Less costly, fast but less accurate.
• Parametric Estimating; Uses statistical relationships between historical data and other variables to calculate an estimate for activity parameters, like cost, duration
• Three Point Estimates (PERT);
• Reserve Analysis; Project teams can choose to incorporate additional time referred to as contingency reserves, time reserves or buffers, into the overall project schedule as recognition of schedule risk.
An iterative process of analysing activity sequences, durations, resource requirements and schedule contraints to create the Project schedule model. Model defines activities start and finish dates.
– Critical Path Method
– Schedule Compression
• Crashing
• Fast Tracking
– What-If-Scenario Analysis
– Resource Leveling
Schedule control is the process of monitoring the status of the project and manage changes to the schedule baseline and concerned with:
•Determining the current status of the project schedule,
•Influencing the factors that create schedule changes,
•Determining that the project schedule has changed,
•Managing the actual changes as they occur.
• Performance Reviews; measure compare and analyse schedule performance – EV (Earned Value
Analysis, Kazanılmış Değer Analizi)
• Variance Analysis
• Project Management Software