Task

advertisement
Defining the Activities
Documents
 Goal Statement


defines why
helps manage expectations
 Statement of Work


what gets delivered
defines scope
 Software Project Management Plan


how will the project be run
organizes the team(s)
 Work Breakdown Structure


what are our tasks
organizing document
SOW
SPMP
WBS
Tasks
> SOW
SPMP
WBS
Tasks
Statement of Work

Written by the Customer
Similar to a Call for Proposals (CFP)

Purpose




“A SOW should specify in clear, understandable terms the
work to be done in developing or producing the goods to be
delivered or services to be performed by a contractor.
A SOW defines all non-specification requirements for
contractor effort.
Specifications are typically referenced in the SOW but the
specific qualitative or quantitative technical requirements shall
not be spelled out in the SOW. “
-- U.S. Government
> SOW
SPMP
WBS
Tasks
SOW Format – example 1
STATEMENT OF WORK
1.
2.
3.
4.
5.
6.
GENERAL. The Bureau of Reclamation has a requirement for …
BACKGROUND.
WORK TO BE PERFORMED BY CONTRACTOR.
GOVERNMENT-FURNISHED MATERIALS/SERVICES.
SUMMARY OF DELIVERABLE.
PROJECT COMPLETION/DELIVERY SCHEDULE
6.1 REVIEW OF DELIVERABLES.
6.2 ACCEPTANCE OF DELIVERABLES.
7. CONTRACTOR PAYMENT SCHEDULE
8. TECHNICAL COORDINATION
9. ADDRESS FOR DELIVERABLES
> SOW
SPMP
WBS
Tasks
SOW Format – example 2
DOD-type SOW
1.
2.
3.
4.
Scope – what is in this SOW
Background
Related Documents
Deliverables




Sub-Tasks
Reports
place of work
review timetable
Software Project Management Plan
Contents

Goal Statement

Process Model

management and technical

Organizational Chart

Timetable and Deliverables



Work Breakdown – next topic tonight
Schedule – in two weeks
Budget

costs estimates - next week
SOW
> SPMP
WBS
Tasks
SOW
> SPMP
WBS
Tasks
IEEE 1058 Standard for SPMP
1. Introduction
1.1 Project overview
1.2 Project deliverables
1.3 Evolution of the SPMP
1.4 Reference materials
1.5 Definitions and acronyms
2. Project organization
2.1 Process model
2.2 Organizational structure
2.3 Organizational boundaries and interfaces
2.4 Project responsibilities
3. Managerial process
3.1 Managerial objectives & priorities
3.2 Assumptions, dependencies & constraints
3.3 Risk management
3.4 Monitoring & controlling mechanisms
3.5 Staffing plan
4. Technical process
4.1 Methods, tools & techniques
4.2 Software documentation
4.3 Project support functions
5. Work packages, schedule &
budget
5.1 Work packages
5.2 Dependencies
5.3 Resource requirements
5.4 Budget & resource allocation
5.5 Schedule
Jargon Alert!
Work Breakdown Structure

“Simply stated, a WBS is a hierarchical
list of the work activities to complete a
project.”
Jargon Alert!

Activity – A major unit of work to be completed
in achieving the objectives of a software project.
An activity has precise starting and ending dates,
incorporates a set of tasks to be completed,
consumes resources and results in work products.
An activity may include other activities in a
hierarchical manner.
IEEE Std 1058 – Standard for Software Project Management Plans
Jargon Alert!

Task – The smallest unit of work subject to
management accountability. A task is a well
defined work assignment for one or more project
members. The specification of work to be
accomplished in completing a task is documented
in a work package. Related tasks are
usually grouped to form activities.
IEEE Std 1058 – Standard for Software Project Management Plans
Jargon Alert!

Work Package – A specification for the work to
be accomplished in completing an activity or task.
A work package defines the work product(s), the
staffing requirements, the expected duration, the
resources to be used, the acceptance criteria for
the work products, the name of the responsible
individual, and any special considerations for the
work.
IEEE Std 1058 – Standard for Software Project Management Plans
Jargon Alert!

Project Function – An activity that spans the
entire duration of a software project. Examples
of project functions include project management,
configuration management, quality assurance,
and verification and validation.
IEEE Std 1058 – Standard for Software Project Management Plans
Jargon Summary

A SPMP contains the WBS.

The WBS is made up of a list of Activities.

Activities are made up of Tasks.
SOW
SPMP
> WBS
Tasks
WBS Definition - MIL-HDBK-881
A product-oriented family tree composed of hardware, software,
services, data, and facilities. The family tree results from systems
engineering efforts during the acquisition of a defense materiel item.
A WBS displays and defines the product, or products, to be
developed and/or produced. It relates the elements of work to be
accomplished to each other and to the end product.
A WBS can be expressed down to any level of interest. However the
top three levels are as far as any program or contract need go
unless the items identified are high cost or high risk. Then, and only
then, is it important to take the work breakdown structure to a lower
level of definition.
SOW
SPMP
> WBS
Tasks
Primary uses of WBS

Determining Budget

Creating a Schedule

Insuring that we didn’t forget anything

Matching staff skills to tasks

Communicating the big picture
SOW
SPMP
> WBS
Tasks
WBS Formats

Tree


Useful at early stages for big picture
Indented List


Most popular format
Easy to create and edit (eg Excel)
SOW
SPMP
> WBS
Tasks
Example WBS
#
Task Description
Who
Resources
M&S
1
Get to Work
Eat Breakfast
Shower
Get Dressed
Goto Office
SD, WD
SD
SD
SD
bread, coffee
soap
existing clothes
vehicle
$1
$.10
1.1
1.2
1.3
1.4
2
Daily Communication
2.1 Check Email
$.75
Start
Stop
SOW
SPMP
> WBS
Tasks
Example WBS
http://www.hyperthot.com/pm_wbs.htm
SOW
SPMP
> WBS
Tasks
Example WBS
SOW
SPMP
> WBS
Tasks
WBS Rules

Avoid too much detail

break down until a group can do the activity in a week
or month - a work package

Only specify what you can manage

Limit depth of indention to manageable level
SOW
SPMP
> WBS
Tasks
WBS Rules
a. Show all software project work at a level that can be used for
software project tracking and reporting. The WBS must provide the
information that allows the project manager to extract progress
measurement (technical, cost, and schedule) for the project's required
status reporting.
b. Include products, events (e.g., reviews and audits), and processes
(e.g., software qualification) that will show visibility into software
development, testing, deployment, training, and life cycle support (as
required).
c. Assign WBS elements so that they can support risk assessment,
engineering change proposal evaluation, contract change evaluation,
interface management, data management, and configuration control.
d. Provide the ability to extract costs for separate types of software work
effort (e.g., prototype, full scale development, maintenance).
e. Ensure that the WBS is compatible with the available project resources
(e.g., staff) and organization (e.g., independent qualification testing).
http://www.stsc.hill.af.mil/resources/tech_docs/process_plan/prplp104.html
SOW
SPMP
WBS
> Tasks
Identifying Tasks



SOW
Experience / Other WBSs
Standards Documents

such as IEEE 1074
SOW
SPMP
WBS
> Tasks
IEEE 1074
"IEEE Standard for Developing
Software Process Life Cycles"

contains a good checklist of activities
SOW
SPMP
WBS
> Tasks
IEEE 1074 Activity Groups

Software Life Cycle Model Planning

Project Management

Predevelopment

Development

Post-Development

Integral
- detailed next
- detailed next
IEEE 1074
•
•
•
•
•
•
Software Life Cycle Model Planning
Project Management
Predevelopment
Development
Post-Development
Integral
Predevelopment
5. Concept Exploration
6. System Allocation
Development
7. Requirements – detailed next
8. Design
9. Implementation – detailed next
IEEE 1074
•
•
•
•
•
•
Software Life Cycle Model Planning
Project Management
Predevelopment
Development
Post-Development
Integral
Development
7. Requirements
24. Define and Development Software Requirements
25. Define Interface Requirements
26. Prioritize and Integrate Software Requirements
9. Implementation
32.
33.
34.
35.
36.
37.
Create Test Data
Create Source Code
Generate Object Code
Create Operating Documentation
Plan Integration
Perform Integration
Next …
Before we can build a schedule, we need
to know how much time everything will
take, how many people we will need, how
much money…
In other words, estimating
Download