What’s a Project?
AD642
Why the Emphasis on Project Management?
Many tasks do not fit neatly into business-as-usual
Organizations need to assign responsibility and authority
for the achievement of their goals
Copyright 2011 John Wiley & Sons, Inc.
1-2
Characteristics of Projects
Unique
Specific deliverables
Specific due date
Copyright 2011 John Wiley & Sons, Inc.
1-3
Other Common Characteristics of Projects
Multidisciplinary
Complex
Often involve conflicts
Part of programs
Copyright 2011 John Wiley & Sons, Inc.
1-4
Definition of a Project
“A project is a temporary endeavor
undertaken to create a unique
product or service.”
Project Management Institute, 2007
Definition of Project
Management
“The application of knowledge,
skills, tools, and techniques to
a broad range of activities in
order to meet the
requirements of a particular
project.”
Project Management Institute 2007
1-6
The Triple Constraint
A more realistic view
And even more so…
The Life Cycle of Projects
All organisms have a life cycle (i.e., they are born, grow,
wane, and die) … and so do projects
Some projects follow an S-shaped curve … they start
slowly, develop momentum, and then finish slowly
Other project follow a J-shaped curve … they start slowly ,
proceed slowly, and then finish rapidly
Copyright 2011 John Wiley & Sons, Inc.
1-10
PMBOK Process Groups
PMI describes the project lifecycle in five groups
Initiating
Planning
Executing
Monitoring and controlling
Closing
Initiating
Defining a new project
Developing charter
Identifying stakeholders
Obtaining authorization
Planning
Scope
Requirements analysis
Work Breakdown Structure
Define activities and milestones
Estimate resources and duration
Develop project schedule and budget
Executing
Manage the project
Perform quality assurance
Manage stakeholders
Manage team
Monitoring and Controlling
Change management
Monitor actuals and baseline
Scope
Budget
Schedule
Risk management
Closing
Obtain acceptance
Post-project audit
Document and archive
Initiating a project: SOW
Projects typically start with a Statement of Work
Describes the business need
Has fairly broad scope
Overall strategic plan
SOW is often part of the response to an RFP when a third
party is to be involved
Business case
Part of the SOW
The justification for the project
Might contain competitive analysis, high-level ROI,
opportunities for market expansion, regulatory
requirements, and more
SOW signoff
A signed SOW is the document that kicks off a project
In third-party arrangements (such as consulting) it is a
contract
Information from the SOW is used to develop the
Project Charter
Time for Meetings!
Once a SOW has been signed, the project formally
exists
If a PM hasn’t been involved yet, now is the time
Initial meetings are to help the PM understand the
project, the players, and the resources
No project plan yet
A kickoff meeting introduces all the players
Initial Project Coordination and the Project
Charter
Early meetings are used to decide on participating in
the project
Used to “flesh out” the nature of the project
Outcomes include:
Technical scope
Areas of responsibility
Delivery dates or budgets
Risk management group
Outside Clients
When it is for outside clients, specifications cannot be
changed without the client’s permission
Client may place budget constraints on the project
May be competing against other firms
Project Charter Elements
Purpose
Objectives
Overview
Schedules
Resources
Personnel
Risk management plans
Evaluation methods
Starting the Project Plan: The WBS
What is to be done
When it is to be started and finished
Who is going to do it
WBS Constraints
Some activities must be done sequentially
Some activities may be done simultaneously
Many things must happen when and how they are
supposed to happen
Each detail is uncertain and subjected to risk
Hierarchical Planning
Major tasks are listed
Each major task is broken down into detail
This continues until all the activities to be completed
are listed
Need to know which activities “depend on” other
activities
The Work Breakdown Structure (WBS)
A hierarchical planning process
Breaks tasks down into successively finer levels of
detail
Continues until all meaningful tasks or work packages
have been identified
These make tracking the work easier
Need separate budget/schedule for each task or work
package
6-27
A Visual WBS
Steps to Create a WBS
1. List the task breakdown in successive levels
2. Identify data for each work package
3. Review work package information
4. Cost the work packages
5. Schedule the work packages
6. Continually examine actual resource use
7. Continually examine schedule
Human Resources
Useful to create a table that shows staff needed to
execute WBS tasks
One approach is a organizational breakdown structure
Organizational units responsible for each WBS element
Who must approve changes of scope
Who must be notified of progress
WBS and OBS may not be identical
The Responsibility (RACI)
Matrix
Another approach is the Responsible, Accountable,
Consult, Inform (RACI) matrix
Also known as a responsibility matrix, a linear
responsibility chart, an assignment matrix, a responsibility
assignment matrix
Shows critical interfaces
Keeps track of who must approve what and who must
be notified
6-31
Sample RACI Matrix
Agile Project Planning and Management
When scope cannot be determined in advance,
traditional planning does not work
Agile project management was developed to
deal with this problem in IT
Small teams are located at a single site
Entire team collaborates
Team deals with one requirement at-a-time with
the scope frozen
Interface Coordination Through Integration
Management
Managing a project requires a great deal of
coordination
Projects typically draw from many parts of the
organization as well as outsiders
All of these must be coordinated
The RACI matrix helps the project manager accomplish
this
Bottom line
For a PM to succeed, it’s crucial for them to be involved
as early as possible in the project lifecycle
The reality is that PMs are often brought in well after
the WBS and scheduling is complete
It’s up to the PM to carefully balance the triple or quad
constraints with the expectations of the stakeholders