1 GOVERNMENT OF KHYBER PAKHTUNKHWA ENERGY & POWER DEPARTMENT Presentation to Energy Task Force Khyber Pakhtunkhwa 13th April 2012 2 Aim The entire country is facing acute Energy shortage which is likely to increase during summer. National Energy Conference was held in Lahore on 9-04-2012, hosted by Punjab Government chaired by the Prime Minister of Pakistan to address the issue. The Conference made certain recommendations which are to be shared with the stake holders and to enable implementation. For this the Provincial Government has notified an Energy Task Force.(ETF) 3 COMPOSITION OF ENERGY TASK FORCE 1. Senior Minister for P & D/ E & P Chairman 2. Senior Minister, Local Govt:, Election & Rural Develop 3. Minister for Information & Public Relations IPC & Transport Member 4. Minister for Industries, Commerce, Mineral Develop 5. Minister for Health 6. Minister for Law Parliamentary Affairs & Human Rights 7. Minister for Labour Member Member Member Member Member 4 ROLE OF ENERGY TASK FORCE IN KHYBER PAKHTUNKHWA The Task Force is assigned the work for engaging in a consultative process with the stakeholders for successful implementation of recommendations of the Energy Conference. The Task Force shall also periodically review the progress on implementation. 5 Sequence of presentation: a) Present situation and extent of problems b) Recommendations of Energy Conference c) Way forward 6 Present situation and extent of problems 7 Pakistan Energy Sector Overview Summer and Winter Fuel Mix - Summer Nuclear 3% Thermal - Gas 14% Hydel 35% Supply- Demand Gap Summer Projected (Peak) 3500 to 4500 MW 7 - 9 hrs load shedding Thermal - RFO 26% GENCOs 22% Fuel Mix - Winter Nuclear 8% Thermal - Gas 15% Supply- Demand Gap Winter (Peak) 3500 to 6000 MW 8-16 hrs load shedding Hydel 18% GENCOs 16% Thermal - RFO 43% 8 Historical Supply & Demand 25000 20000 15000 10000 5000 2011-12 2010-11 2009-10 2008-09 2007-08 2006-07 2005-06 -5000 2004-05 0 -10000 Computed Peak Demand Corresponding Supply Surplus/ Shortfall 9 Power Sector – Generation Addition Fuel Mix - Capacity Additions (MW) 9,000 8,000 7,000 6,000 5,000 4,000 3,000 2,000 1,000 2002 2003 2004 Hydro-Wapda 2005 2006 Thermal-Genco 2007 IPP-Hydro 2008 2009 IPP-Thermal 2010 2011 PAEC Power Sector – Generation Addition (2008-2011) Malakand - III 81 Nishat Power 200 Hubco Khan Khawar 72 Nishat Chunian 200 Foundation Power Attock Gen 163 Sapphire Power 225 Halmore Power Atlas Power 219 Techno Power (R) 60 Chashnup-II Engro Power 227 Liberty Tech 200 Karkey - Rental (R ) Saif Power 225 Gulf – Rental (R) 62 Walter Naudero (R) Orient Power 225 (Excluding Rentals of 405 MW = 2995 MW) Total 225 202 225 300 232 51 3,400 10 Generation Additions (2008-2012) Sector Description Capacity (MW) A. Gas/RFO/HSD 3237 B. Hydel Projects 153 C. Wind Power Projects 312 D. GENCO Rehabilitation 636 Total (A+B+C+D) 4338 11 25 25,000 20 20,000 15 15,000 10 10,000 5 5,000 Consumers 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003 - 2002 - Demand (MW) Millions Power Sector – Load Growth Demand (MW) Demand Increase per year = 7.31% Actual number of consumer increase 2002 – 2011 •Total = 5.38% (average per year growth) 12 Key reasons for shortfalls 1. Liquidity crunch resulting in under-utilization of installed capacity 2. Diminishing gas supply 3. Low priority to conservation and efficiency 4. Stalled progress on reforms 13 Key reasons for shortfalls – Liquidity Crunch 1. Tariff Differential – (Rs 9.56/unit average cost vs Rs 7.84 /units sale price = Rs 1.72/unit) 2. Fuel Price Adjustment Rs. 101 b unrecovered a) 1- 350 units court stay in Punjab and Sindh and all FPA collection stopped in KPK b) Late NEPRA determination from fuel consumed from Sept 2011 to Jan 2012 3. Equalization surcharge (no raise in tariff in FY12) Court Stay – Rs 80 b 4 5 6 7 8 Low recoveries from DISCOs (83%) of current bills Higher than NEPRA allowed system losses – Rs 24 b Total Receivables Rs 354 b (Private 169 b, KESC 54 b, Provincial 85 b, Federal 6 b) AJ&K tariff Rs 14 b AGRI TUBEWELL • GOP SHARE @ 40% IN BALOCHISTAN = 5 B Rs • Support in Payment of PUNJAB SHARE @ 12.5% = 6 B Rs • Support in Payment of BALOCHISTAN SHARE @ 30% = 7 B Rs 14 AVERAGE GAS REQUIREMENT VS. ACTUAL GAS SUPPLIED TO GENCOS (MMCFD) POWER STATIONS Required Gas DESCRIPTION • Gas Available Gap Required Gas Gas Available Gap Total Gap Availability (%age) (GENCOs) (GENCOs) (GENCOs) (IPPs) (IPPs) (IPPs) (GENCOs + IPPs) 2005-06 750 583 167 671 524 147 314 78% 2006-07 750 451 299 671 523 148 447 69% 2007-08 750 438 312 671 491 180 492 65% 2008-09 750 405 345 671 408 263 608 57% 2009-10 750 361 389 671 391 280 669 53% 2010-11 750 267 483 671 358 313 796 44% 2011-12 750 265 485 955 466 489 974 43% KESC supply (182 MMCFD) not included IPPS GENCOS PRESENT REQUIREMENT PRESENT ALLOCATION PRESENT REQUIREMENT PRESENT ALLOCATION 750 265 955 466 15 Projected Demand & Supply Position April to August 2012 Supplied Breakup (MW) Months Supplied (MW) Hydel Nuclear Gas RFO/HSD Computed Demand (MW) Shortfall (MW) April 12,992 2,305 615 2,761 7,311 16,492 -3,500 May 14,660 5,019 615 2,761 6,265 18,383 -3,723 June 15,451 5,036 615 2,761 7,039 19,564 -4,113 July 15,200 5,854 615 2,761 7,023 19,300 -4,100 August 15,210 5,992 615 2,761 7,021 19,322 -4,112 16 RECOMMENDATIONS OF ENERGY CONFERENCE 17 GENERATION – Immediate Sr. # 1. Measures Reallocation of gas to power sector Allocation of gas to: • • • 4 IPPS (@38MMCFD PER PLANT = 152 MMCFD) KAPCO 55 MMCFD Ideally 310 MINIMUM 207 MMCFD giving 1000MW 2 Release of receivables and subsidies 3 The borrowing limits of Provinces to be set by NEC 4 Directive to NEPRA for early determination of upfront tariff 5 Once stay on FPA vacated, power prices will jump to reflect correct cost of power. Provinces’ understanding required. 18 2- …CONTD Release of Receivables and Subsidies Description GOP SHARE @ 40% IN AGRI. BALOCH RECEIVABLES Bln. Rs. Bln. Rs. 5.08 5.08 PROVINCIAL GOVT. DEPTT/AGENCIES 9.24 a) PUNJAB 49.13 c) SINDH 6.83 d) BALOCHISTAN 65.21 PROVINCIAL GOVT. AGRI. T/WELL SUBSIDY a) PUNJAB (12.5%) 5.00 e) BALOCHISTAN (30%) 7.00 KESC Payable by KPK Consumers for delayed tariff increase due to Court Case Sub Total 12.00 49.66 18.10 150.05 19 GENERATION – Medium Term Sr. # Measures 1. Rehabilitation of public sector power plants USAID = 636 MW ADB = 800MW 2. Out sourcing management, O&M, rehabilitation and conversion of public sector power plants onto cheaper fuels Status Contracts for three plants by December 2012 20 DISTRIBUTION – Immediate Sr. # Measures 1. Introduction of Pre-paid meters 2. Revision of Electricity Act 1910: Provinces to expedite endorsement for presentation to CCI 3. To create deterrence regarding electricity theft, Provinces to help in registration of FIRs, designating special magistrates and nominating focal persons e.g. home secretary at provincial and DCO at district level for expeditious disposal of cases. 21 DISTRIBUTION – Medium Term Sr. # 1. Measures To bring in predictability and end unscheduled load shedding in the system automation of SCADA system in DISCOs 22 CONSERVATION – Short Term Sr. # Measures Action Effects 1. Commercial establishments to close by 8 pm or power supply to be cut Same decision in 2010. Provinces to implement 250 MW at Peak 2. Street Lighting Conservation: •Alternate lights •Replacement with efficient lights Provinces to implement 250 MW 3. Five days week for government departments and affiliated institutions Provinces to implement 700 MW 4. Installation of Solar Geysers in government housing Federal and provincial governments 5. Easy financing for installation of solar water heater, solar water pumping, solar lighting Directive to SBP for interest free financing 23 CONSERVATION – Short Term Sr. # Measures Action Effects Legal cover for implementation of energy conservation measures 6. Enactment of Energy Conservation Bill Pakistan Energy Efficiency & Conservation Bill is being finalized in consultation with Provincial Governments 7. Mass Awareness Campaigns Provision of Rs 50 m to ENERCON for launching of awareness campaign for promotion of energy efficiency culture 8. Launching of Pilot Projects EAD to approach donors on Energy Efficiency & for provision of funds for Capacity Building under pilot projects Public –Private Partnership 24 CONSERVATION – Medium Term Sr. # Measures 1. Mandatory Energy Audits 2. Cell Tower conversion to solar 3. Mandatory Vehicle Tune ups 4. Non-supply of power to billboards and neon signs 5. Target •Private Steel Mill E.E. •Pulp & Paper •Textile Industry For energy efficiency improvements 6. Phasing out of manufacturing and import of Incandescent bulbs in two years Status After Energy Efficiency Bill Announcement. Also replacements by CFLs and LEDs 2800 MW 25 THE WAY FORWARD 26 WAY FORWARD: Action by Provincial Government (GENERATION /DISTRIBUTION) Sr.# Measures Actions/way forward 1. Re-allocation of additional gas to power sector •4 IPPS (@38MMCFD PER PLANT = 152 MMCFD) •KAPCO 55 MMCFD •Ideally 300 MINIMUM 207 MMCFD giving 1000MW Ministry of Oil & Gas 2. Upfront tariff for all types of fuels by NEPRA NEPRA 3. Revision of Electricity Act 1910: Provinces to expedite Ministry of Water & Power /Energy & Power Department 4. Expedite conversion of steam based Independent Power Ministry of Water & Plants/GENCOs to coal. Power 5. Provinces to help in prompt registration of FIRs, designating Home Department to special magistrates and nominating focal persons e.g. home devise the mechanism secretary at provincial and DCO at district level for expeditious disposal of electricity theft cases. 6. Release of receivables and subsidies. Possibility of at source Ministry of Finance/ deduction Finance Department 27 WAY FORWARD: Action by Provincial Government ( TARIFF & INSTITUTIONAL REFORMS) Sr.# Measures Actions/way forward 1. Implement the tariff increase of 12% Ministry of Finance / Ministry of Water & Power/ NEPRA/FD 2. Uniform tariff & Revised Tariff Differential Mechanism to be implemented NEPRA/ FD 3. Increase the lifeline slab to 100 . Balance to pay NEPRA Determined Tariff in full Ministry of Finance / Ministry of Water & Power/ FD 4. Strengthening of NEPRA Ministry of Water & Power/ E&P Department 5. Fully empowered institutional mechanism for Reconciliation & settlement of all power sector disputes , billing etc. Finance Department /EMC 6. Installation of Pre-paid meters for all federal and provincial government connections Ministry of Water & Power/ Finance Department /PESCO 7. Ensure equitable load shedding in the country Ministry of Water & Power 8. KESC to voluntarily reduce its import of power from NTDC from 650MW to 300MW. Ministry of Water & Power/KESC 28 …CONT Sr.# Measures Actions/way forward 9. Gas to be priced closer to relevant alternative fuel prices. Ministry of Finance / Ministry of Oil & Gas/Provinces/CCI 10 Sources of subsidy and magnitude to be determined by the governments. Ministry of Finance/ Finance Department 29 WAY FORWARD: Action by Provincial Government (CONSERVATION) Sr.# Measures Actions/way forward Effects 1. Street Lighting Conservation: •Alternate lights •Replacement with efficient lights Local Government Department/ Commissioners 250 MW 2. Commercial establishments to close by 8 pm. chamber, of Com & Inds: Home Department 250 MW at Peak 3. Five day week for all governments Recommendations of Energy Task Force 700 MW 4. Subsidy for Solar Agri Tubewells Agriculture Department/IFI’s 5. Daylight savings from April 15th, 2012 Recommendations of Energy Task Force/E & A Department 800-1200 MW 6. Non-supply of power to billboards and neon signs LG Department/PESCO 125 MW 7. Phasing out of Incandescent bulbs Industries Department 1200 MW 8. Overall Supervision of Energy Conservation & Issues Energy Task Force through EMC of Finance Department 30 31