Project Plan Presentation P0842X – LED Lighting Technologies COURTNEY WALSH (ME) IAN FRANK (ME) MATT BENEDICT (ME) SHAWN RUSSELL (ME) WIN MAUNG (ME) NARESH POTOPSINGH (ME) Why LEDs? RIT spends approximately $6 million on electricity every year Half goes towards lighting (~$3 million) LED Reduce energy consumption Longer lifetime Lower maintenance costs Less waste Environmentally friendly LED Information Efficacy Light output divided by power input LED 30 lumen/watt Future LEDs 150-200 lumen/watt Fluorescent Light 85 lumen/watt Incandescent bulb 16 lumen/watt HPS ~ 125 lumen/watt Color Rendering Indices (CRI) CRI measures fidelity of the colors of objects reflecting the emitted light LED Vary from 62-91 Incandescent bulb 100 Metal Halide ~85 HPS 22 http://lighting.sandia.gov/XlightingoverviewFAQ.htm Color Temperature Degree warmth or coolness of a light source LED 5000-7500 (cool white) Metal Halide 3000 K (very yellow) to 20000 K (very blue) HPS 2700 K Lifetime LED 100,000 hours Incandescent 1000 hours Fluorescent 10,000 hours Efficiency Comparisons http://www.iolighting.com/efficacy.htm Project Breakdown Comparison Outdoor HPS: Shawn Metal Halide: Courtney Indoor T8 Tube: Naresh CPL Replacement: Win Developing Nations Ian Power Module Matt Start Term: 2007-2 for MSD1 Start Term: 2008-2 for MSD1 End Term: 2007-3 for MSD2 End Term: 2008-3 for MSD2 Preliminary Work Breakdown Structure Person All Week 0 - 1 (03 Dec 07) Establish team values and norms Three Week Project Plan Week 1 - 2 (10 Dec 07) Understand customer needs Week 2 - 3 (17 Dec 07) Present individual "research" to group Review and understand the project Meet with customers to establish any additional needs Participate in brainstorming session Meet with faculty guide and consultants (or Brainstorm any additional needs) Team building exercises/ice breakers Participate in benchmarking session Identify and gather any additional benchmarking materials Introduce project to team Help team get up to speed Arrange the necessary meetings ME 1 Schedule a meeting with all team leads to coordinate projects Review CAD package tutorials ME 2 EE 1 EE 2 Review Fatigue analysis package for deformation, stress, and thermal (heat transfer) analysis (Or lead needs brainstorming session) Lead benchmarking session Focus on human interface portion of benchmarking session Record and publish results from benchmarking and needs evaluation Focus on materials and mechanical analysis portion of benchmarking session - Look into possible interface options and prepare report Lead brainstorming Help others when/where needed Look into possible materials and prepare report - Review EE analysis programs Focus on power supply portion of benchmarking session Look into power supply options and prepare report Review chosen control language Focus on power storage and light emitting portions of benchmarking session - Look into storage and lighting options - prepare report - Review EE analysis programs Review MATLAB ISE 1 Arrange meeting with customers Determine product target specifications - Review CAD tutorials Review sustainability guidelines Focus on manufacturing, sustainability, and environmental Look into sustainability and DFM options - prepare concern portions of benchmarking session report - - Preliminary Work Breakdown Structure Diagram Representation Team Values and Norms Punctual Each team member will arrive on time and will notify fellow team members of any expected absences. It is important that the team member ensures that at least one member of the team confirms the notification Thorough Each team member is expected to do their assigned work in a manner such that it does not have to be redone by another, and if they feel that they have been assigned too much work to do that they seek out help from other team members or faculty consultants Accurate Each team member will accurately complete and document their work Professional and Ethical Each team member will credit work and information to the proper sources and will be trustworthy in all of their dealings. Demonstrates the core RIT values of SPIRIT. Each team member will remember that they are representing RIT and as such the reputation of RIT and the SD program are reflected in their work. Committed Each team member will contribute an equal share to the success of the project and commit to the challenge set before them with the understanding that the SD process should a fun and informative Grading and Assessment Preliminary Grading Scheme Grade Level Senior Design I Senior Design II D Have completed concept development for Have multiple concepts in the works with at least two of the original concepts and a semi-clear plan for executing at least have a project production plan for one of one of them the concepts C Have a concept singled out and in the process of being completed B Have a working concept nearly developed Have finished the bulk of product A Have finished concept development and are ready to proceed with fabrication Have finished concept development and begun working on the final project Have a completed working product Issues and Risks Economic Funding Secure from FMS and EE Department Environmental Protection Agency P3 Grant Cost return Lifetime cost comparison to current systems Technical Light distribution Design lens/reflector system Longevity Design for extreme conditions Use proven materials Social Group dynamics Team building activities Safety Health hazards Consult Underwriters Laboratory and IEEE standards Outdoor Projects Mission Statement Walkway Metal Halide Replacement This specific project will focus on developing a replacement for the Metal Halide walkway fixtures that are located around campus. These metal halide fixtures aim provide a good return on the investment as well as an efficient light source. The LED fixture needs to be energy efficient, cost effective, and easy to maintain. Parking lot High Pressure Sodium Replacement This product is a LED replacement kit to convert conventional lighting fixtures to accept LED lights. This kit will be design specifically for RIT and will prove to have a positive economical impact. Final Project Plan Project Name LED Lighting Technologies for a Sustainable Entrepreneurial Venture Project Number P08428 Project Family Sustainable Products, Systems, and Technologies Track Track Sustainable Technologies for the RIT Campus Start Term 2007-2 for Senior Design I End Term 2007-3 for Senior Design II Potential Faculty Guide Dr. Robert Stevens (ME) Confirmed Faculty Consultant Dr. Vincent Amuso (EE) Choice Primary Customer RIT Facilities Management Metal Halide Replacement Replacement Primary use on campus is for walkway lighting Can be seen on quarter mile Metal Halide High-intensity discharge lamp High light output for their size Operate under high pressure and temperature Color Rendering Index Color Temperature 85 3,000 K (very yellow) to 20,000 K (very blue) Life Expectancy 10,000 to 12,000 hours Phase 0: Planning Staffing Requirements Mechanical Engineers Industrial and Systems Engineers 3 Mechanical Engineer 1 Team Lead Assign tasks to rest of the team Keep in contact with team leads from other projects Prepare deliverables Contribute to mechanical design Mechanical Engineer 2 Primary mechanical engineer Develop casing for LED light Integrate parts together Develop CAD package Mechanical Engineer Develop light fixture Integrate parts together Develop CAD package 3 Electrical Engineers 1 Electrical Engineer 1 Primary electrical engineer Determine power source Develop interface to power source LED integration Any computer programming 2 Industrial Engineer 1 Primary industrial engineer Develop fixture for LED light Communicate with other LED teams Industrial Engineer 2 Create a sustainable system Help to optimize the system Make system manfactureable Business Majors Consultant Business Major 1 Aid with the manufacturing process a potential business plan to manufacture product Create Customer Needs Target Specifications Metric Importance (Stars) Units Target Value Production Cost 4 US $ ~$400 Usable Temperature Range 5 Degrees (F or C) -10-100 F, (-25-40 C) Water-Proof 4 Binary Yes Heat/Cold Resistant 4 Binary Yes Vandal Resistant 4 Binary Yes Lifetime 5 Hours 100,000 CRI Level 1 No units 85 Energy Efficient 5 lumen/watt 85 Standardized 4 Binary Yes Weight of Light (Mass) 3 Lbs (kg) ~10 Future Plans Await PRP approval High Pressure Sodium Lamp Replacement This is a low pressure sodium lamp This is a spectrum of a high pressure sodium lamp A Basic design of a high pressure sodium lamp Phase 0: Planning Staffing Requirements Mechanical Engineers Industrial and Systems Engineers 3 Mechanical Engineer 1 Team Lead Assign tasks to rest of the team Keep in contact with team leads from other projects Prepare deliverables Contribute to mechanical design Mechanical Engineer 2 Develop light dispersing lens Conduct Heat Transfer analysis Develop FEA package Mechanical Engineer Develop light fixture Integrate parts together Develop CAD package 3 Electrical Engineers 1 Electrical Engineer 1 Primary electrical engineer Determine power source Develop interface to power source LED integration 1 Industrial Systems Engineer 1 Integration of the Design and Manufacturing process Implement Lean Manufacturing processes Observe ergonomic issues 1 Business Majors Business Major 1 Marketing Campaign Budget Web page Customer Needs Target Specifications Metric Material Properties Lifetime Inexpensive materials Simple design Minimum output Ballast efficiency Color Temperature CRI UL codes and IEEE standards Light fixture mounting Manufacturability Low maintenance Electrical connections Efficiency LED’s are powerful Accepts AC and DC inputs Bending Strength Availability of parts Importance (Stars) 2 2 1 2 2 2 1 1 Units Binary years US$ Subj. Ft-Candles % K None Target Value Yes 30 700 Yes 1 95 2700 22 1 Binary Yes 1 2 1 1 2 2 3 1 2 Subj. Minutes Subj. Minutes Lumens/Watt Ft-Candles Binary kN Subj. Good 30 Yes 2 150-200 1 Yes NA Readily available Future Plans Await PRP approval Indoor Projects Mission Statement Compact Fluorescent Lamp Replacement This project will focus on developing a replacement for Compact Fluorescent Lamp fixtures that are located on RIT campus. These CFL fixtures aim provide a good return on the investment of LED lamp as well as an efficient light resources. The LED fixture needs to be low cost, high energy efficiency, last long life, and easy to maintain. T-8 Replacement Administrative Information Project Name LED Lighting Technologies Project Number P08426 Project Family Sustainable Entrepreneurial Venture Track Sustainable Products, Systems, and Technologies Track Start Term 2007-2 for MSD1 End Term 2007-3 for MSD2 Faculty Guide Dr. Vincent Amuso (EE) Faculty Consultant Dr. Robert Stevens (ME) Graduate Teaching Assistant Jeff Webb (ME) Primary Customer Mr. Dave Harris Customer contact information RIT Institute of Technology facility Manager 47@mail.rit.edu Compact Fluorescent Lamp Replacement Commonly used in www.botany.uwc.ac.za classroom, dorm, lab replacement by LED lamp Uses 110 V or 277V Research fixture Save energy cost Interview with customer for more detailed needs Phase 0: Planning Staffing Requirements Mechanical Engineers 3 Mechanical Engineer 1 Team Lead Assign tasks to rest of the team Keep in contact with team leads from other projects Prepare deliverables Contribute to mechanical design Mechanical Engineer 2 Develop light dispersing lens Conduct Heat Transfer analysis Develop FEA package Mechanical Engineer 3 Develop light fixture Integrate parts together Develop CAD package Electrical Engineers 1 Electrical Engineer 1 Primary electrical engineer Determine power source Develop interface to power source LED integration Industrial and Systems Engineers 1 Industrial Systems Engineer 1 Integration of the Design and Manufacturing process Implement Lean Manufacturing processes Observe ergonomic issues 1 Business Majors Business Major 1 Marketing Campaign Budget Web page Establish the Importance of the Customer Needs Need The Product Needs to Importance 1. LED reduces RIT power demand/consumption 5 2. LED minimizes energy lost to heat 3 3. LED performs aesthetics 3 4. LED is interchangeable with existing technologies 5 5. LED performs as better than current systems 4 6. LED can be safety to use 4 7. LED reliability in tamper-resistant 3 8. LED has cheaper price for consumer 3 9. LED is easy to maintain/ replace 3 10. LED is recyclable 4 11. LED does not generate excess heat 3 12. LED is adaptable on natural energy resources 5 Establish Target Specifications Metric No. Metric Importance 1. Efficiency 5 2. Weight 1 3. Lens Hardness 4 4. Charge Time 4 5. Lifetime 5 6. Light distribution drop height 4 7. Rechargeable 5 8. Production Cost 5 9. Intensity of Light 3 10. Recyclable Components 5 11. Storage Capacity 5 12. Power Supply 5 13. Power Drop Cycles 4 14. Light Distribution 3 Units hrs/charge kg Mohs hrs hrs m cycles US $ Lux Binary mAh Binary cycles delta lux/delta m Future Plans Finish conducting interviews with the sponsor Further review old Senior Design project Develop a more complete draft of the needs assessment based on a particular direction (changing CFL to LED lighting) Reserve desired workspaces and equipment before the completion of DPM course Refine P08426 project for SD I Sponsor: www.rit.edu Estimated Budget: $2,500.00 Questions? T8 Replacement T8 is most common lamp used 80,000 to 100,000 in use now Approximately 25,000 are replaced all over campus annually Uses 115V~120V Very low wattage ~ 40W Already Very efficient Phase 0: Planning Staffing Requirements Mechanical Engineers Industrial and Systems Engineers 3 Mechanical Engineer 1 Team Lead Assign tasks to rest of the team Keep in contact with team leads from other projects Prepare deliverables Contribute to mechanical design Mechanical Engineer 2 Develop light dispersing lens Conduct Heat Transfer analysis Develop FEA package Mechanical Engineer Develop light fixture Integrate parts together Develop CAD package 3 Electrical Engineers 1 Electrical Engineer 1 Primary electrical engineer Determine power source Develop interface to power source LED integration 1 Industrial Systems Engineer 1 Integration of the Design and Manufacturing process Implement Lean Manufacturing processes Observe ergonomic issues 1 Business Majors Business Major 1 Marketing Campaign Budget Web page Future Plans Build a lamp which uses even lower wattage than the T-8 Use a strip of LED’s for efficiency Use a reflector to scatter the light for a greater lighting Use brighter LED’s Protect fixture for durability Design Concept – Intelligent Power Module 277 VAC Modular Enclosure 208 VAC 110 VAC Power Conversion & Conditioning 12 VDC Power Controller/Switch 12 VDC 12 VDC 12 VDC Power Storage 24 VDC P0842X Demand Response Demand Response - any action taken in response to an emergency signal that temporarily limits electric demand. Demand Response is a great way to guard New Yorkers against grid events, reduce dependence on oil, lower peak electric prices, and increase revenue. Incentives for Reductions in Peak Electric Demand Permanent Demand Reduction (PDR) Con Edison Rest of State $600/kW $300/kW Demand Response Load Curtailment & Shifting Distributed Interval Meters (LC/S) Generation (DG) (IM) Con Edison Rest of State Con Edison Everywhere $200/kW $50/kW $150/kW $1,500/meter http://www.nyserda.org/programs/peakload/default.asp What’s in it for RIT? RIT has a peak demand for the year of about 15 Megawatts! The associated demand charge is around $11/kW. ~65% of this is due to lighting If this peak demand is reduced to 14 MW, RIT saves $11,000 in one month! Note: •Monthly Demand charge is dictated by highest ½ hour of demand during the week. http://www.nyiso.com/public/webdocs/company/about_us/annual_report/nyiso_areport2006final.pdf LED Project Philosophy Reduce lighting costs by reducing demand Reduce demand by reducing energy consumption Reduce consumption using more efficient technologies Make technologies more efficient by making them more intelligent… Phase 0: Planning Staffing Requirements Mechanical Engineers Industrial and Systems Engineers 3 Mechanical Engineer 1 Team Lead Assign tasks to rest of the team Keep in contact with team leads from other projects Prepare deliverables Contribute to mechanical design Mechanical Engineer 2 Develop light dispersing lens Conduct Heat Transfer analysis Develop FEA package Mechanical Engineer Develop light fixture Integrate parts together Develop CAD package 3 Electrical Engineers 1 Electrical Engineer 1 Primary electrical engineer Determine power source Develop interface to power source LED integration 1 Industrial Systems Engineer 1 Integration of the Design and Manufacturing process Implement Lean Manufacturing processes Observe ergonomic issues 1 Business Majors Business Major 1 Marketing Campaign Budget Web page Opportunities & Options for SDI • Refine project scope: • Inputs/Outputs dependent (somewhat) on other projects within the family • Possibility for applications outside LED realm • Detailed cost savings and government incentives analysis, with recommendations Future Plans Continue through list of potential faculty guides Conduct thorough patent search Refine project scope and determine design options and expectations http://www.nyiso.com/public/webdocs/company/about_us/annual_report/nyiso_areport2006final.pdf Applications for Developing Nations Faculty Guide Dr. Robert Stevens (ME) Currently two billion people live without clean, healthy, reliable lighting or power. Many of these people use gas and oil lamps, which produce a great deal of soot and carbon dioxide in addition to consuming vast amounts of fuel to produce relatively little usable lighting. The average income is very low in these nations, so it will be necessary for these products to be extremely inexpensive The climate in these nations will necessitate that the product be, among other things, water-proof and able to withstand extreme weather conditions This project seeks to provide a clean, reliable, inexpensive, and nonpower-dependent source of light for developing nations. Staffing Requirements Mechanical Engineers Industrial and Systems Engineers 2 Mechanical Engineer 1 Team Lead Assign tasks to rest of the team Keep Team on Track for April 2009 Delivery Prepare deliverables Contribute to mechanical design (human interfacing) Mechanical Engineer CAD Work Mechanical Testing Mechanical Analysis 2 Electrical Engineers 2 Electrical Engineer 1 Power Supply Design Power Supply Integration Controls Electrical Engineer 2 Power Storage Selection/Design Power Supply Integration Light Emission Sub-System 1 Industrial Systems Engineer 1 Design for Manufacture Sustainability Aspects Environmental Concerns Implement Lean Manufacturing processes Observe ergonomic issues Industrial Designers 1 Industrial Designer 1 Design of Exterior Shell Light Distribution Aesthetics Business Majors Consultant Roll Entrepreneurial Aspects and Feasibility Economic Efficiency Customer Need – Engineering Metrics Matrix Preliminary Metrics # Metric Units Importance (Stars) Potential Value 1 Production Cost U.S. $ ***** 50 2 Has On-Board Power Supply Binary ***** Yes 3 Usable Temperature Range °F or °C *** (30-120)°F or (0-50)°C 4 Water-Proof Binary *** Yes 5 Heat/Sand-Proof (Air Tight) Binary *** Yes 6 Storage Capacity mAh **** 6000 7 Recharge-ability Cycles ***** 500 8 Lifetime hrs ***** 100,000 9 Distribution of Light (Δ Lux)/(Δ m) ** 10 Intensity of Light Lux ** 11 Functional Drop Height m *** 3 12 Drop Cycles Lens Hardness (Resists 13 Scratching) Cycles Mohs Hardness *** 50+ *** 6+ 14 Efficiency Lumens/Watt ***** 15 Efficiency hrs/charge ***** 60 16 Charge Time hrs *** ≤4 17 Recyclable Parts Binary * Yes 18 Environmentally Friendly Binary * Yes 19 Aesthetically Pleasing Subjective * Yes 20 Weight (Mass) lb (kg) ** <10lb (<4.5kg) ~0 Future Plans 2007 12 November – 20 December Write P3 Grant Proposal with Dr. Steven 2008 1 January – End of Summer Quarter Project Promotion (find interested students) Secure Additional Funding if Necessary Fall Quarter Gear-Up for Senior Design December (Winter Quarter) Senior Design I 2009 Spring Quarter Senior Design II April National P3 Expo on the National Mall in Washington D.C. Questions?