RuralE.Evolution Deliverable D2.3 “Provisional Guidelines for successful application of PPP in RES Agro-energy district” RuralE.Evolution Public-Private Partnerships for RES Agro-energy districts Issued by: Aristotle University of Thessaloniki REVISED DATE: 20th September 2010 Version 2 CONTRACT N°:IEE/07/579/SI2.499063 The sole responsibility for the content of this document lies with the authors. It does not necessarily reflect the opinion of the European Communities. The European Commission is not responsible for any use that may be made of the information contained therein. Table of Contents 1 PPP UTILIZATION IN AGRO-ENERGY DISTRICTS ......................................................................... 4 1.1 1.2 1.2.1 1.2.2 1.2.3 1.2.4 1.2.5 1.2.6 1.3 1.4 1.4.1 1.4.2 1.4.3 2 INITIATIVE TO ADOPT A PPP SCHEME FOR A SPECIFIC AGRO-ENERGY DISTRICT ...... 10 2.1 2.2 2.3 3 4.6 4.7 4.8 4.9 4.10 SET UP THE PLANNING TEAM ............................................................................................................... 20 STUDY OF THE TARGET AREA’S CHARACTERISTICS ............................................................................. 21 SELECTION OF SUITABLE PARTNERS / ACHIEVEMENT OF SUCCESSFUL PARTNERSHIPS ........................ 22 IMPLEMENTATION OF A CONSENSUS BUILDING STRATEGY ................................................................ 23 SELECTION OF SUITABLE TECHNOLOGY/PRODUCTION PLAN ACCORDING TO LOCAL CHARACTERISTICS 25 INSTITUTIONAL STRUCTURES AND CAPACITY BUILDING .................................................................... 25 IDENTIFICATION OF THE SUPPLY CHAIN .............................................................................................. 26 AVAILABILITY OF THE LAND ............................................................................................................... 27 DEFINITION OF THE LOGISTIC PLAN ..................................................................................................... 28 MONITORING AND REPORTING ON RESULTS ........................................................................................ 29 BUSINESS PLAN ...................................................................................................................................... 30 5.1 5.2 5.3 5.4 5.5 6 IDENTIFICATION OF AREAS’ NEEDS ..................................................................................................... 13 ROLE OF STAKEHOLDERS.................................................................................................................... 13 MARKET TESTING ............................................................................................................................... 16 POTENTIAL BENEFITS .......................................................................................................................... 16 IDENTIFICATION OF POTENTIAL ACTORS ............................................................................................. 16 EXPLORATION OF THE AVAILABLE NATIONAL LEGAL/REGULATORY AND POLICY FRAMEWORKS ........ 17 SELECTION OF THE RIGHT PPP OPTION ............................................................................................... 17 COMMUNICATION STRATEGY TO REACH STAKEHOLDERS & THE COMMUNITY .................................... 19 PPP IMPLEMENTATION ....................................................................................................................... 20 4.1 4.2 4.3 4.4 4.5 5 TYPE OF INITIATIVE (PUBLIC OR PRIVATE?) ....................................................................................... 10 REASONS TO ADOPT A PPP ................................................................................................................. 10 NEEDS AND OBJECTIVES OF THE COOPERATION .................................................................................. 11 PPP PREPARATION ............................................................................................................................... 13 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 4 THE RATIONALE BEHIND PPPS FOR AGRO-ENERGY DISTRICTS .............................................................. 4 SUSTAINABILITY OF AGRICULTURAL & ENERGY POLICY IN EUROPE ..................................................... 4 Establish the Internal Energy Market ............................................................................................. 5 Ensure a Secure Energy Supply ...................................................................................................... 5 Reduce Greenhouse Gas Emissions ................................................................................................ 5 Develop Energy Technologies ......................................................................................................... 5 Consider the Future of Nuclear Energy .......................................................................................... 5 Implement a Common International Energy Policy ........................................................................ 6 BENEFITS FOR EUROPEAN RURAL AREAS .............................................................................................. 6 LESSONS LEARNT FROM EUROPEAN AND WORLDWIDE CASE STUDIES ................................................... 7 Conclusions on Success factors in the Implementation of PPPs ..................................................... 7 Conclusions on Weak factors in the Implementation of PPPs ........................................................ 9 Conclusions of PPP implementation in Global Cases, Including Developing Countries ............... 9 IDENTIFICATION OF THE BUSINESS MODEL ......................................................................................... 30 DEFINITION OF ECONOMIC & FINANCIAL ISSUES ................................................................................ 31 FINANCIAL IMPLICATIONS OF RISK ..................................................................................................... 35 DEFINITION OF THE STRATEGIC PLANNING .......................................................................................... 36 DEFINITION OF LEGAL & CONTRACTUAL FRAMEWORK ...................................................................... 36 REQUIREMENTS OF PARTNERSHIP CONTRACTS ...................................................................... 37 6.1 6.2 6.3 6.4 6.5 EXAMPLE: ITALY ................................................................................................................................ 39 EXAMPLE: GREECE ............................................................................................................................. 41 EXAMPLE: SPAIN ................................................................................................................................ 42 EXAMPLE: PORTUGAL......................................................................................................................... 43 EXAMPLE: HUNGARY.......................................................................................................................... 43 RuralE.Evolution - IEE/07/579/SI2.499063 Page 2 of 64 D2.3 Guidelines for PPP application 7 PPP PROCESS WITHIN RURAE-EVOLUTION PROJECT ............................................................. 47 7.1 7.2 7.3 PREPARATION AND SIGNATURE OF THE MEMORANDUM OF UNDERSTANDING (MOU) ........................ 47 CREATION OF THE PPP AND START UP OF THE COMPANY .................................................................... 48 FOLLOW-UP AND CONSTRUCTION OF THE PLANT ................................................................................ 50 8 CLOSING OF PPP .................................................................................................................................... 51 9 REFERENCES .......................................................................................................................................... 64 RuralE.Evolution - IEE/07/579/SI2.499063 Page 3 of 64 D2.3 Guidelines for PPP application 1 PPP utilization in agro-energy districts 1.1 The rationale behind PPPs for agro-energy districts Agro-energy districts represent a useful model for the achievement of important energetic and environmental goals in Europe and the world. Agro-Energy refers to the energy function of agriculture. It can make significant contributions to achieving social and environmental sustainability at local, national, regional and global levels. In fact, agricultural and livestock resources are abundant in most parts of the world, and various commercially available conversion technologies could transform current traditional and low-tech uses of these resources to modern energies. If Agro-Energy is produced efficiently and in a sustainable manner, benefits compared to fossil fuels can be achieved including food security, rural development, local self-reliance, sustainable agricultural management, biodiversity conservation and climate change mitigation, whilst offering improved energy supply and security. Unfortunately, regulatory, financial and awareness lack constraints do not allow a wide proliferation of this concept. Attention should be placed on the trade-offs of Agro-Energy systems. Main concerns include development priorities, environmental impacts, conflicts with other land uses, technological conversion efficiency, high raw material costs and the costeffectiveness of Agro-Energy technologies. In economic terms, incentives might be necessary at least to put Agro-Energy on a more equal footing with fossil fuels, for which environmental and social costs are not internalised. PPPs can provide this incentive and create this comfortable ground for the development of an energy production plant. Eventhough, there are still constraints in the application of PPPs in agro-energy districts, there is a growing tendency to take actions in the field of renewable energy making agreements between public and private enterprises. 1.2 Sustainability of agricultural & energy policy in Europe The European Union (EU) faces serious energy challenges concerning sustainability and greenhouse gas emissions as well as security of supply, import dependence and the competitiveness and effective implementation of the internal energy market.On the other hand, reforms over the past 15 years in the EU’s Common Agricultural Policy (CAP) have created crop program rules that discourage crop rotation and other sustainable practices. This is in order to maintain high base acreages, which then qualify for subsidies (EUROMED 2008; European Communities 2004). Energy accounts for 80% of all greenhouse gas (GHG) emission in the EU; it is at the root of climate change and most air pollution. The EU is committed to addressing this - by reducing EU and worldwide greenhouse gas emissions at a global level to a level that would limit the global temperature increase to 2°C compared to pre-industrial levels. However, current energy and transport policies would mean EU CO2 emissions would increase by around 5% by 2030 and global emissions would rise by 55%. The present energy policies within the EU are not sustainable. A European Energy Policy is acknowledged as the most effective response to these challenges, which are faced by all Member States. The EU intends to lead a new industrial RuralE.Evolution - IEE/07/579/SI2.499063 Page 4 of 64 D2.3 Guidelines for PPP application revolution and create a high efficiency energy economy with low CO2 emissions. To do so, it has set itself several important energy objectives. 1.2.1 Establish the Internal Energy Market An internal energy market has been developed on a Community level to ensure that consumers have the opportunity to choose a supplier, at a fair and competitive price. Nevertheless, as highlighted by the Communication on prospects for the internal energy market and the inquiry into competition in the gas and electricity sectors, there are obstacles which continue to prevent both the economy and European consumers from fully benefiting from the advantages of opening up the gas and electricity markets. Ensuring the effective implementation of the internal energy market thus remains crucial. 1.2.2 Ensure a Secure Energy Supply Minimising the EU's vulnerability concerning imports, shortfalls in supply, possible energy crises and uncertainty with respect to future supply is a clear priority. This uncertainty is all the more problematic for Member States dependent on one single gas supplier. The new energy policy emphasises the importance of measures which ensure solidarity between Member States and of the diversification of supply sources and transportation routes. Measures supporting strategic oil stocks must be reinforced and the possibilities for improving the security of gas supply must be explored. Increased security of electricity supply, which remains crucial, must also be guaranteed. 1.2.3 Reduce Greenhouse Gas Emissions Energy accounts for 80% of all greenhouse gas emissions in the EU. Determined to fight against climate change, the EU is committed to reducing its own emissions by at least 20% by 2020. It also calls for the conclusion of an international agreement which will oblige developed countries to reduce their greenhouse gas emissions by 30% by 2020. In the framework of this agreement, the EU would set itself a new objective of reducing its own emissions by 30% compared with 1990 levels. These objectives are at the heart of the EU's strategy for limiting climate change. Of course, reducing greenhouse gas emissions involves using less energy and using more clean energy. 1.2.4 Develop Energy Technologies Energy technologies play a central role in offering both competitiveness and sustainability in the energy sector while increasing security of supply. They are likewise crucial for attaining the other energy objectives. The EU, today a global leader in the renewable energy sector, intends to consolidate its position and play an equally leading role in the rapidly growing market for low carbon energy technologies. The EU must therefore develop existing energyefficient technologies as well as new technologies, in particular those devoted to energy efficiency and renewable energies. 1.2.5 Consider the Future of Nuclear Energy Faced with increasing concerns with regard to security of supply and CO2 emissions, nuclear energy has the benefit of being one of the low-carbon energy sources offering the most stable costs and supply. The decision whether or not to use nuclear energy is made by Member RuralE.Evolution - IEE/07/579/SI2.499063 Page 5 of 64 D2.3 Guidelines for PPP application States. Nevertheless, the illustrative nuclear programme emphasizes the need to have a common and coherent approach with respect to security, safety and non-proliferation as well as concerning the dismantling of installations and the management of waste. 1.2.6 Implement a Common International Energy Policy The EU is not able to achieve the objective of secure, competitive and sustainable energy alone. To do so requires the involvement and cooperation of both developed and developing countries, energy consumers and producers and countries of transit. To ensure efficiency and coherence, it is crucial that Member States and the EU are able to speak with a single voice on international energy issues. The EU will be a driving force in the development of international energy agreements, in particular by strengthening the European Energy Charter, taking the initiative in an agreement on energy efficiency and participating actively in the post-Kyoto climate change scheme. EU relations with consumer countries (such as the United States, India, Brazil or China), producer countries (Russia, Norway, OPEC countries and Algeria, for example) and countries of transit (such as the Ukraine) are of prime importance from the perspective of geopolitical security and economic stability. The EU will thus strive to develop energy partnerships with these countries which are transparent, predictable and reciprocal, in particular with its neighbouring countries. The EU also proposes a new partnership with Africa which will deal with a large variety of energy issues. The EU is committed to helping developing countries to implement decentralised energy services which are low-cost, reliable and sustainable. The EU encourages these countries, in particular Africa, to immediately invest in renewable energies and the new generation of clean energy technologies. 1.3 Benefits for European rural areas Environmental concerns are becoming a factor for selecting the PPP model. Governments are encouraged to adopt PPPs as a tool for sustainable development. Investors in PPPs too have a financial motivation for taking environmental considerations into account, because the effective use of resources and reduction of waste both in design and construction, means lowered whole life costs, and hence higher margins. Citizens too demand more attention from their governments to the social and environmental impact of projects. The objective of PPPs is to involve private partners in the implementation of projects or the provision of services, aiming not only at securing additional financial resources, but also at benefiting from their know-how, human resources, innovative approach and ability to efficiently manage complex projects for the public benefit. The main benefits of PPPs are the following: • Ability to finance more projects The Government, along with the local authorities, has to respond to the constantly increasing needs and requirements of the citizens for modern and qualitative provision of infrastructure and services. The use of private funds, complementary to the public ones, may contribute to RuralE.Evolution - IEE/07/579/SI2.499063 Page 6 of 64 D2.3 Guidelines for PPP application the faster implementation of projects and the delivery of services. PPP schemes are a new means of achieving the strategic priorities of public entities, complementary not only to the traditional public works, which by no means will be limited, but also to other forms of partnership between the public and the private sector, such as the concession agreements of the Ministry of the Environment and Public Works or the collaborations of Local Authorities with private partners, that continue to be implemented. Under PPP schemes, public entities implement and offer to citizens more works and services in a faster and more efficient manner. • Transfer of risks to the private sector The integration, depending on the structure chosen, of the design, financing, construction, and operation of a project under a PPP structure, along with the transfer of relevant risks to the private partner, creates incentives for a more diligent and efficient design and implementation of the projects. This, in effect, results in substantial reductions, if not abolishment, of cost and time overruns. Moreover, the fact that the private partner also undertakes the responsibility for maintaining the projects results in services of higher quality, with greater functionality throughout the project’s life cycle. • Enhancement of the investment environment PPP schemes mobilize more funds than those that the public sector alone could mobilize, providing, hence, the opportunity to various parties and investors of the private sector to get involved in infrastructure projects, innovate and develop new activities. The long-term nature of PPP projects results in setting up financially stable companies with predictable cash flows. These cash flows feed the market and thus promote the growth of the economy. 1.4 Lessons learnt from European and worldwide case studies A successful PPP should fulfil three conditions at a minimum: a) Benefits for private sector: generate a profitable revenue stream or expand market access. b) Benefits for the consumer: delivery of services that people want and would not have access to at the same price, in a business as usual situation, e.g. improvement of provided services c) Benefits for the government: fulfilment of a political need, social obligation, development imperative. Based on the performed case studies, interviews carried out, partner’s experience and TEGs thorough discussions during the course of the project, conclusions on the strong and weak points in the implementation of PPPs are listed below. 1.4.1 Conclusions on Success factors in the Implementation of PPPs 1. Private sector is in general a better and more experienced manager than the Public; thus, projects that provide public goods can be managed in a more efficient way through the private partner. 2. There is need for full understanding / acknowledgement of the Social Character of the PPP. 3. Private parties bring more innovation capacity in the partnerships that the public can absorb. RuralE.Evolution - IEE/07/579/SI2.499063 Page 7 of 64 D2.3 Guidelines for PPP application 4. The partnership structure is essential. Some PPP players (interviewees) consider the dedication and cooperation among the parties the most important success factor, together with the value of the concept. 5. The re-structuring of the partnership is not common but wherever detected, did not seem to create problems to the overall progress of the project. For example, in the case of the TC of middle Burgenland, after finalizing the implementation phase, the banks stepped out of the project because they had only low interest to operate the TC; so, the communities overtook a stronger role until the stabilization of the project. Then private investors will overtake the major ownership of the project with an optimized contract. 6. The replication of a PPP project, like in Burgenland, where the Technology Centre was the third to be established in the area, is definitely a success factor, especially if the same persons are involved again. There is high level of experience and also, the project concept has been already tested decreasing the risk of failure. 7. The consideration of experience and lessons learned abroad is very useful. 8. In projects where all partners were involved financially (mutual benefits shared) there is a very good chance to achieve the expected results and end up with a successful project (see example of Vatsounia in Greece). 9. For some countries, like Greece, the macroeconomic situation and EU regulations on state deficit promote PPPs. 10. In some cases, like the manure plant in Spain, a successful PPP project leads to other initiatives that are interesting for the existing consortium. In general, a development initiative among local agents in a rural environment can be a good source for new initiatives. 11. A strong insurance policy for the private actor and a risk mitigation plan is essential in order to have profit assurance for the private sector. 12. Knowledge Transfer is a common procedure in PPPs; capacity building of the public officials can potentially improve the management efficiency of the relative department in a Municipality (or other public actors) and lead to more PPP opportunities in the future. 13. A solid and simple to follow legislative framework is necessary. 14. The setting up of one or more PPP units at a central government level that provide guidance is very important because most energy PPP projects are implemented locally at a small-scale basis, where knowledge on PPPs is more limited than in national scale. 15. Community acceptance is very important, as the PPP usually directly affects the local community; in this framework media coverage and public opinion observance could offer valuable assistance. 16. In many cases, public opinion is willing to support PPP after understanding the benefits of implemented projects. 17. Political backing and political will is important, even though there are cases of small communities that managed to create a PPP without receiving essential political backing. 18. Energy PPPs make extensive use of local resources, leading to price reduction of the offered public goods, improvement of living standards and sustainable development of the areas. 19. Jobs are created for the plant management, building, maintenance, etc. 20. The relationship between investment and pricing is an important factor. 21. The level of resources available in the system and the degree of maturity and development of the actors are also important factors in the PPPs development. RuralE.Evolution - IEE/07/579/SI2.499063 Page 8 of 64 D2.3 Guidelines for PPP application 1.4.2 Conclusions on Weak factors in the Implementation of PPPs 1. 2. 3. 4. For many countries, the process of PPP implementation is long and bureaucratic. Usually there is loss of control by the public sector. There are political risks. Political preferences matter. Generally speaking, the Government's “pro-business orientation” create a much better environment for encouraging public research actors and private companies to make joint innovation efforts. 5. As far as the supply concerns (for example of animal waste or agricultural residues), there is need to ensure it in a long-term period in order to recover the investment. 6. Lack of competition might create an inefficient structure. 7. Blurriness in the partners selection procedure can jeopardise the venture; the guarantee of meritocracy and the performance evaluation during the contracting procedures is essential 8. Lack of experience in the administration of the public units; the capacity building at central level is not always accompanied by parallel actions at the local and regional level. 9. A common issue arising in public discussions on PPP in Greece and other countries is an “accusation” of disguised privatisation. 10. In many countries, the institutional framework is broadly formulated and oriented towards construction projects. Further specifications especially for energy are necessary. 11. Often partners have different expectations and understanding of their roles. 12. PPPs have been a very controversial discussion topic in the debate on the role of public and private bodies in a modern state. There are cases where PPP have been accused as “easy solutions” or a “sell-out of the country”; some projects might not be protected from political volatility. 1.4.3 Conclusions of PPP implementation in Global Cases, Including Developing Countries AUTH as WP leader has also investigated the global situation, as far as PPP in energy sector concerns. Many international organizations, like the Asian Development Bank (ADB), seek to forge strong internal PPPs in the countries in which they operate, as they have tested that such partnerships provide a valuable bridge between the two sectors. The problems in PPPs in developing countries are quite different than the ones raised in Europe. For example, many international companies are unwilling to expose themselves to capricious regulatory frameworks and changing government policies. On the other hand, in the USA, PPPs are not very common, even though energy issues seem to get PPPs moving. RuralE.Evolution - IEE/07/579/SI2.499063 Page 9 of 64 D2.3 Guidelines for PPP application 2 Initiative to adopt a PPP scheme for a specific agroenergy district 2.1 Type of Initiative (Public or Private?) During these last years, municipalities are better organizing themselves to take actions in the field of the renewable energies, making agreements with private enterprises, creating awareness to the citizens of the benefits related to renewable energies, involving town and citizen associations into common projects, cooperating with industrial associations and technology institutes for feasibility studies, trainings, and strategy decisions. Quite often a renewable energy consortium is created when there is a clear and strong policy will to proceed in Municipalities. The first step is almost always the Mayor’s decision supported by his advisers to take part into a renewable energy initiative, and implement changes and improvements into the Municipality district. Afterwards, the appropriate private companies (technology sellers, installers and maintenance) are contacted for a request for tender to next start up the project. Among different types of renewable energy, only wind energy has achieved a rather advanced relationship between public and private. This is because many times both partners (public and private) come to an agreement by which the municipality does not spend any money for the installation and moreover receive royalties according to the electricity sold, or discounts into the annual electrical bill. In relation to other types of renewable energies the market is not yet matured as much as the wind one, where the investments are also quite high. Due to the EU policy regulation, the energy prices, and the territories sensitizing to the renewable energy and environmental benefits, more and more municipalities are taking action to improve energy efficiency and competences and also trying to increase the renewable energy use and exploitation into their territories, working together with the Energy Agency and not always influenced by the private sector. 2.2 Reasons to adopt a PPP According to the EC guidelines for successful PPPs and the results of the RuralE.Evolution survey, PPP projects are able to offer a number of advantages, including: • • • Acceleration of infrastructure provision - PPPs often allow the public sector to translate upfront capital expenditure into a flow of ongoing service payments. This enables projects to proceed when the availability of public capital may be constrained (either by public spending caps or annual budgeting cycles), thus bringing forward much needed investment. Faster implementation - the allocation of design and construction responsibility to the private sector, combined with payments linked to the availability of a service, provides significant incentives for the private sector to deliver capital projects within shorter construction timeframes. Reduced whole life costs - PPP projects which require operational and maintenance service provision provide the private sector with strong incentives to minimise costs over RuralE.Evolution - IEE/07/579/SI2.499063 Page 10 of 64 D2.3 Guidelines for PPP application • • • • • the whole life of a project, something that is inherently difficult to achieve within the constraints of traditional public sector budgeting. Better risk allocation - a core principle of any PPP is the allocation of risk to the party best able to manage it at least cost. The aim is to optimise rather than maximise risk transfer, to ensure that best value is achieved. Better incentives to perform – the allocation of project risk should incentivise a private sector contractor to improve its management and performance on any given project. Under most PPP projects, full payment to the private sector contractor will only occur if the required service standards are being met on an ongoing basis. Improved quality of service -international experience suggests that the quality of service achieved under a PPP is often better than that achieved by traditional procurement. This may reflect the better integration of services with supporting assets, improved economies of scale, the introduction of innovation in service delivery, or the performance incentives and penalties typically included within a PPP contract. Generation of additional revenues – the private sector may be able to generate additional revenues from third parties, thereby reducing the cost of any public sector subvention required. Additional revenue may be generated through the use of spare capacity or the disposal of surplus assets. Enhanced public management – by transferring responsibility for providing public services government officials will act as regulators and will focus upon service planning and performance monitoring instead of the management of the day to day delivery of public services. In addition, by exposing public services to competition, PPPs enable the cost of public services to be benchmarked against market standards to ensure that the very best value for money is being achieved. 2.3 Needs and objectives of the cooperation In reviewing the potential for PPPs, the key variable is the local government’s policy as it relates to service delivery in general and PPP specifically. The policy will determine the criteria to be applied, the weighting of the various criteria and the extensiveness of the review itself. Local government will need to address specific questions: • What are the potential obstacles and constraints for these PPP opportunities? • What are the experiences of other local governments? • Would the private sector be interested in these opportunities? • Is PPP the best method to deliver these services or facilities? To determine the potential for a PPP, local government will need to address various considerations. These include: • local government policy • the legislative authority • the taxation framework • reporting and accounting • financial issues Local government policy The local government’s policy for the provision, financing and cost recovery of services will be a key factor in assessing whether PPPs are seen as an accepted approach to service delivery. The policies established by local government will be based on the values and RuralE.Evolution - IEE/07/579/SI2.499063 Page 11 of 64 D2.3 Guidelines for PPP application objectives of the community and the elected Council or Board. They will also form the basis for the local government’s plans and strategies for the provision and financing of services. If PPPs are not seen as a viable or accepted approach to service delivery based on fundamental values and policies, it is clearly not in the community’s best interest to proceed with individual PPPs. More commonly, local governments will establish policies that identify the circumstances (e.g., type of service, component of the service system) under which PPPs may be considered. In addition to local government’s servicing and financing policies, they must also consider the implications for other policies, including land use and development, human resources and economic development. Efforts should only be directed toward advancing proposals that are consistent with established local government policies. Legislative authority The legislative framework set out in the Municipal Act provides considerable flexibility for local government to enter into PPPs. There are, nevertheless, constraints and procedural requirements that will impact the ability of local governments to enter into PPPs. Local government must also adhere to other provincial and federal statutes. Taxation framework In determining whether an opportunity is suited to a PPP, the local government should recognize the interests of the possible private sector partner. One of the incentives that will attract private partners is the ability to minimize the amount of tax they are required to pay. Local government has the authority to exempt from municipal property taxes the “public use” portion of property subject to a PPP agreement. In cases where the local government provides an exemption, it can request a matching provincial property tax exemption. Reporting and accounting In addition to taxation considerations, local government should also consider accounting and financial reporting considerations that apply to PPPs. Public sector accounting standards are still evolving in the area of PPPs. The specific accounting treatment should be determined by the entity’s accountant at the time any arrangement is proposed. Financial issues Local government needs to consider a range of financing issues before proceeding with a PPP. Financial issues that should be considered prior to implementing a PPP project include: • Can private sector financing compete with public sector financing for the type of service or project being considered? • What is the effective cost of borrowing? • Can private sector companies be bonded for a project of this type and magnitude? • Are there any senior government grants available for projects of this type? • Are partnerships eligible for such grants? • Is the project financially self-sufficient or can it become self-sufficient? • What support mechanisms are the public sector prepared to make available (e.g., recourse financing, subsidies, supplies, equipment)? • Is it possible to define an equitable and appropriate rate-setting mechanism? • Is the financing structure without recourse to the local government? RuralE.Evolution - IEE/07/579/SI2.499063 Page 12 of 64 D2.3 Guidelines for PPP application 3 PPP preparation 3.1 Identification of areas’ needs The first step in preparing a PPP is the study of the area where the project will be developed in order to identify the desired coverage targets and service needs. The party that conceived the idea for an agro-energy district will have to carry out a sector analysis and define the technical specifications of the proposed PPP project. As a result of the sector analysis, the government is able to determine to what degree an enabling environment exists for PPP and what activities are required in advance of PPP to create such an environment. The diagnostic is important to: (i) identify the strengths and weaknesses of the sector and the most promising areas for efficiency increases, (ii) regularly gauge and report on the progress of reform, and (iii) tweak the reform program as needed. The sector analysis is likely to be performed with the support of a team of local and/or international engineers, lawyers, economists, financial analysts, energy and policy specialists etc. The preparation stage is the time to develop the preliminary technical specifications. Development of the final technical specifications of a project is an iterative process which builds on feedback from the market and the affordability of the project at each design stage. The technical design of a project starts with identification of desired coverage targets and service standards. From these starting points, estimating the cost of these desired services (factoring in presumed efficiency gains) and cost recovery tariffs is possible. In case of large project where high level governance is involved, there are the options of putting these cost recovery tariffs in place, subsidizing cost-recovery, or revisiting the initial targets and service standards. These preliminary specifications will ultimately be enshrined in the PPP contract dictating the technical outputs expected from the partnership. The technical preparation builds on (and refines) the analytical work that has been done in preparing the sector analysis. 3.2 Role of Stakeholders Despite the long experience with PPPs, they remain controversial among a range of stakeholders. This is partly attributable to the diverse range of stakeholders involved in the process and the difficulty in reconciling their interests and concerns. In addition, too often the stakeholders have not been properly consulted or engaged in the process. Consultation is increasingly seen as important for several reasons: • • • Inadequate consultation or communication with stakeholders increases the danger of opposition, potentially late in the process, leading to delays or even cancellation. Furthermore, the stakeholders are critical to the sustainability of a PPP. Even if the contract is awarded despite opposition, the difficulty and risk of the project increase drastically if public support is not present. Stakeholders provide valuable input to the design and practicality of an approach. Allowing stakeholders to comment on PPP strategies allows for a sense of buy-in and can lead to innovative approaches. RuralE.Evolution - IEE/07/579/SI2.499063 Page 13 of 64 D2.3 Guidelines for PPP application • • Broad public support and understanding of the reform agenda encourage politicians to stay committed. Dissemination of information leads to increased credibility of project partners. Despite these compelling reasons, some public organizations see risk in public consultation either through the danger of raising expectations that may not be met, through losing control of the flow of information, through the danger of being unable to reconcile differences, or because information might fuel opposition. These risks are easily outweighed by the benefits of communication and the crucial role it plays in building support for, and understanding of, PPP. Each role is critical, yet specific stakeholders will have different interests that influence how they approach their role. There must be a consultation process to reconcile and prioritize issues, leading to broad agreement on the objectives of PPP. Table 1lists the roles of the PPP process stakeholders and Figure 1 illustrates their interests. Table 1: Role of Different Stakeholders in the PPP Process Stakeholder Political decision makers Role Establish and prioritize goals and objectives of PPP and communicate these to the public Approve decision criteria for selecting preferred PPP option Approve recommended PPP option Approve regulatory and legal frameworks Company management and staff Identify company-specific needs and goals of PPP Provide company-specific data Assist in marketing and due diligence process Implement change Consumers Communicate ability and willingness to pay for service Express priorities for quality and level of service Identify existing strengths and weaknesses in service Investors Provide feedback on attractiveness of various PPP options Follow rules and procedures of competitive bidding process Perform thorough due diligence resulting in competitive and realistic bidding Strategic consultants Provide unbiased evaluation of options for PPP Review existing framework and propose reforms Act as facilitator for cooperation among stakeholders Source: Heather Skilling and Kathleen Booth. 2007. RuralE.Evolution - IEE/07/579/SI2.499063 Page 14 of 64 D2.3 Guidelines for PPP application EMPLOYEES Ensure fair treatment of present employees Provide career opportunities Improve productivity, efficiency, and morale GOVERNMENT Maximize revenue Provide universal access to service Ensure affordable basic service Promote fair competition Attract investors Improve public welfare Stakeholder Interests CONSUMERS Ensure fair pricing Improve quality and reliability of service Increase accountability and responsiveness INVESTORS Ensure stable, transparent regulatory process Enable organizational restructuring and asset allocations that favor efficient operations Provide trained human resources Generate more investment opportunities Figure 1: Examples of Stakeholder Interests in PPPs [1] RuralE.Evolution - IEE/07/579/SI2.499063 Page 15 of 64 D2.3 Guidelines for PPP application 3.3 Market testing Market testing must also take place as a mean to secure better value for money in provision of public services. Initial steps in the market testing process are to identify feasibility and scope of services subject to market testing, and to check whether potential value for money gains are sufficient to outweigh the costs of testing the market. The likely level of interest can be assessed through analysis of previous investments in region, country, and sector, and by assessing the market interest. the the the the As with all private sector involvement exercises, a public partner will seek to: 1) conduct market testing to discover if the private sector is willing and able to perform the required tasks; 2) give potential bidders the opportunity to provide feedback on the proposed scheme; 3) give sufficient publicity and time for potential bidders to prepare proposals; 4) provide output/outcome performance specifications that clearly identify the service requirements; 5) put in place an objective and fair bid assessment process. 3.4 Potential benefits The potential benefits of the proposed partnership must be well-defined. Properly structured, PPPs are able to deliver value for money to the public sector, acceleration of investment programs and a genuine transfer of risk to the party best able to manage it. Effective risk transfer, particularly during the construction phase, can generate significant cost savings that easily outweigh the higher funding costs of the private sector partners. FAO is striving to develop Agro-Energy for food security, rural development and climate change mitigation through the following 5 objectives: • stimulate the integration of agro energy issues into the agricultural sector; • promote the potential of agro energy in the energy market; • promote sustainable management of energy resources, of energy conversion systems and of end-uses; • enhance food security and rural development through the implementation of agro energy systems; • contribute to climate change mitigation through the implementation of agro energy systems. 3.5 Identification of potential actors The public partner wants to encourage the further development of high quality service providers in the market for public services. This requires that a competitive selection process be used which insists on quality services, socially-responsible terms and conditions, and high safety standards. If the public partner lays down reasonable expectations, abides by them over time, and provides a level playing field, quality firms will be attracted to the market. This will make it difficult for less socially responsible service providers to survive. Experience shows that it is competition that delivers the benefits from PPPs, not private provision per se. Dealing with a consortium, for most PPP projects, the following are the usual steps to select it: RuralE.Evolution - IEE/07/579/SI2.499063 Page 16 of 64 D2.3 Guidelines for PPP application conduct a market testing exercise; issue request for Expression of Interest (EoI) from the private sector; pre-qualification of private sector companies including those that have submitted an EoI; issue RFP to pre-qualified private sector companies; exclude proposals not meeting mandatory essential requirements; conduct assessment on the proposals. Negotiate with the one or two best conforming bidders to achieve improvements to bids whilst under competitive pressure; select a preferred bidder or bidders to develop detailed, fully negotiated contract documents (reserve the right to revert to alternative bidders if contract negotiations break down); request best and final offer; recommend the preferred bidder to the relevant bid evaluation committee. 3.6 Exploration of the available national legal/regulatory and policy frameworks At the moment there is no comprehensive study of the PPP market at a global level. In order to give some perspective on the topic, Table 7.2 provides details of PPP activity in 29 countries for which information is available, drawing on practitioner and other sources. 3.7 Selection of the right PPP option There are a number of common contractual structures that are considered to be PPPs these have been also presented in the chapter 4 of this deliverable (PPP classification). A typical structure for a PPP project under the DBFO (Design Build Finance and Operate) model is shown in Figure 7.3. Selecting an appropriate PPP option is based on a diagnosis of: • PPP options available (as described in chapter 4); • technical constraints and goals of the sector (as identified in the diagnostic); • legal and regulatory constraints (as identified in the diagnostic); • institutional issues (as identified in the diagnostic); • commercial, financial, and financing requirements and constraints (as identified in the diagnostic); • interest of the market (local and international as described below); • special requirements of the sector based on characteristics of the system or population. RuralE.Evolution - IEE/07/579/SI2.499063 Page 17 of 64 D2.3 Guidelines for PPP application Figure 2: Typical PPP project structure DBFO Model (Design Build Finance and Operate).[2] The list of reform objectives should be compared with the results of the diagnostic and features of each contract type, its advantages and disadvantages, likely outcomes and prerequisites. From this analysis, it is possible to determine which option is most likely to succeed at meeting the greatest number of (or the most critical) objectives. Priorities for a PPP might include increased coverage, improved services, efficiency improvements with associated reduction in government subsidy, or customer satisfaction. The government and its advisors would use cost/benefit analysis and would consult with a wide range of possible private partners (operator survey) to gain insight on the appeal, or lack of appeal, of the options under consideration. Particular PPP forms are used more widely and are more readily applied to particular sectors. For instance, BOTs (Build Operate and Transfer) are more often employed in the development of toll roads and wastewater plants while management contracts might be seen in health-care or water services. That said, no PPP option could be applied without tailoring it to the local context. The options provide a menu of contract types that can be modified to suit specific project requirements. Incorporating different components of different contract types or using several contracts in combination may be necessary. Additional modifications may be necessary to facilitate the financing of the transaction, to respond to concerns of potential partners, to improve lowincome service provision, and to address labor issues. RuralE.Evolution - IEE/07/579/SI2.499063 Page 18 of 64 D2.3 Guidelines for PPP application 3.8 Communication community strategy to reach stakeholders & the For stakeholders to play an active role in the PPP process, they must be given not only a forum for participation but also the information they need to participate effectively. The appropriate forum to communicate and build support for PPP is through an iterative dialogue with stakeholders. Each communications program must be tailored to the local context and PPP, but would include some or all the components below: • • • • opinion research: opinion research gathers data on stakeholders, their perceptions, and behaviours with respect to the issues concerning a specific PPP. The research influences the content and media of the communications program as well as the reforms themselves. The research is conducted on a relatively formal basis through questionnaires, polling, etc. stakeholder consultation: consultation is a less formal process through which themes and policies of interest are discussed within or across stakeholder groups. It is intended to gather information and build an understanding among the reformers as to current perceptions and understanding and the basis of those opinions. A key part of stakeholder consultation is to manage expectations with respect to how feedback will be incorporated into the reform process; that is, the feedback may not translate into direct change in the PPP design or process but will be one stream of influence. This might be accomplished through focus groups or stakeholder discussion groups. public awareness: public awareness efforts are aimed at a broad range of stakeholders and designed to increase general awareness of an issue. This is a proactive distribution of information that will help inform public reaction to PPP. This might be done through TV, radio, town meetings, and newspapers. public education: public education is the process of providing stakeholders with the tools and information required to increase understanding of an issue or to take on a new role. This is a more specific and detailed program than public awareness. Communication activities have to begin early in the process and continue through to closure and even during implementation. The project structure should incorporate mechanisms to ensure ongoing communication with the public and customers. The communication program associated with PPP has to occur not only at all stages of PPP, but on several levels: at the policy or key decision-makers’ level, the level of the enterprise, among the stakeholders specifically affected by a PPP, and among the public at large as needed. RuralE.Evolution - IEE/07/579/SI2.499063 Page 19 of 64 D2.3 Guidelines for PPP application 4 PPP implementation A road map to implement an agro-energy district PPP should include the main actions showed in Table 8.1 Table 2: Main action in PPP implementation 1 Set up the planning team (financial manager, technical manager, etc.) 2 Study of the target area’s characteristics 3 Selection of suitable partners / Achievement of successful partnerships (banks, public entities, etc.; competence of the Public Entity to implement the project, determine both sectors interest in this PPP) 4 Development of Business plan (a) Identification of the Business Model (how to get value from the Agro-energy District) (b) Definition of Economic & Financial issues (namely the feasibility, bankability and value for money of the project) (c) Financial Implications of Risk (e.g. Revenue Risk, Construction Risk, Political Risk, etc.) (d) Detection of the right time to enter the market (start-up of energy production plan) (e) Definition of the strategic planning (f) Definition of Legal & Contractual framework 5 Implementation of a Consensus Building Strategy 6 Selection of suitable technology/production plan according to local characteristics 7 Institutional Structures and Capacity building (PPP unit, technical assistance, etc.) 8 Identification of the supply chain (actors, environment) 9 Availability of the land (e.g. land purchase, if necessary) 10 Definition of the logistic plan 10 Monitoring and reporting on results 4.1 Set up the planning team The Planning team could be considered similar to the ‘Project Steering Committee’ (PSCom ) used in the management of multi-disciplinary projects by works departments. The role of the PSCom would be to oversee the progress of the project from start to finish, give general direction of the project and make major policy decisions. RuralE.Evolution - IEE/07/579/SI2.499063 Page 20 of 64 D2.3 Guidelines for PPP application The PSCom is not a contract administrator for the day-to-day contract administration. The PSCom will either be chaired by or report to the officer in the client department with overall authority for the project. The composition of a PSCom should be limited to an optimal size for effective operation. For example, sub-groups on different expertise fields could be formed separately and only the sub-group chairman representing the interest and concerns of the corresponding subgroup members would be members of the PSCom. The PSCom should contain the experience and expertise appropriate to its needs, and include/employ the services of an experienced Contract Manager responsible for day-to-day management and capable of ensuring adherence to the desired project timetable. In addition to members of the client department’s own staff, the PSCom might include architects, engineers with various specialisations, lawyers, and financial advisors; it may contain individuals from both within and outside the public agency; and its composition may change according to need at different stages of the project. Where advisors to the PSCom are employed from outside government, the client department will need to ensure against any conflict of interest arising. The client department should contractually prohibit advisors from later working on the same project for private sector bidders where this might risk the tailoring of advice or the use of inside information. Under the conventional procurement approach the Works Branch and works departments may serve as the works agent of the client department. Under the PPP approach, the client department is responsible for forming its own PSCom which should possess the necessary skills and knowledge to manage the contract during different stages of the project. 4.2 Study of the target area’s characteristics According to what has been presented in the deliverable D3.1, the original identification of the area was performed following: i) agricultural characteristics of the area; ii) interest expressed by local authorities to participate to the project activities; iii) connections of RuralE.Evolution partners with authorities and local entrepreneurial tissue. The identification of the original target area was accompanied by a declaration of interest by local authorities to participate to the action (enclosed to the negotiation package). Due to the particular nature of the action (for which a close relation with the above actors is required) and given some modifications occurred to the original situation (administrative elections for local authorities; modification of the Consortium composition, decadence of interest by some local authorities), some target areas were subject to modification. This kind of modification was considered predictable since the beginning of the project (being out of the direct control of the consortium) and do not affect the regular implementation of the action (some determining only a slight delay in the project activities, being occurred in the phase preliminary to the beginning of task. In a first analysis the main industrial activities of the area and the needs of energy (electricity, heat and fuels) have been considered, in particular evaluating the actual energy sources and their distribution as infrastructure. Then the agroenergy potential of the territory has been considered, evaluating the local energy services companies as potential and suitable partners to constitute a PPP. A pre-feasibility analysis of the project has been done, considering bioenergy production potential, identification of existing bioenergy production systems, prefeasibility of plant location. The regulatory framework has been considered also and so the infrastructures were analyzed. At the end of the analysis the place had proved to have strength, weaknesses and opportunities and threats, reported in a SWOT analysis. RuralE.Evolution - IEE/07/579/SI2.499063 Page 21 of 64 D2.3 Guidelines for PPP application 4.3 Selection of suitable partners / Achievement of successful partnerships Once PPP has been structured and the preparatory work is underway, the transaction manager, responsible for ensuring that the process runs smoothly, transparently, and timely, should be in place. During the transaction stages, it is important to have more formal interaction with potential bidders on the specifics of the transaction as designed. During these interactions, the public partner needs to guard against potential manipulation of the PPP design and process by the bidder to its advantage. Likewise, bidders should not enjoy any advantage (e.g., additional information) in the bidding process through such consultations. Discussions must avoid any bias toward a particular bidder and should be broadly held with sector stakeholders as well. The government may find it useful to be supported by PPP advisors in its interactions with potential bidders. Two specific points of interaction with the potential bidders are: bid conference. During the bid conference, the government presents an outline of the project and bidders are invited to react and question. However, in a formal setting surrounded by competitors, some bidders may withhold concerns, be unwilling to share good ideas, or may collude with other bidders to push for a particular change. bid document consultation. Alternatively (or in addition to a bid conference), bidders may be invited to individually comment on the draft bidding documents, including the draft contract. This approach allows the government to identify issues of concern across the range of bidders. Government should send each bidder a full set of the responses to all questions raised, thus avoiding any semblance of favoritism. A bidder will expect to have a clear understanding of the time line, the sequence of activities, the decision points, and the decision makers. This information should be given to bidders in writing and should be regularly reviewed and reconfirmed. This clarity is necessary to provide bidders with a sense of confidence in the transparency and reliability of the process. The bid package, contracts, and any marketing documents as well as protocols for communicating with the public and potential bidders need to be developed. The starting point in the actual procurement process is the public notification of the opportunity and the prequalification of bidders. Under this process, an official notification is placed in local and international print and electronic media, advising the public of an opportunity to participate in the project. The content of the advertisement depends on applicable procurement rules. Companies are invited to request a prequalification package and seek access to further information. An important aspect of information dissemination is the establishment of a data room. Prequalified bidders are invited to use this centralized repository of all information related to the PPP project, which is to be available to potential bidders. The information should be organized according to topics and as detailed, and granted equally and fairly to bidders. During a transaction, the room will be staffed by an attendant and bidders must sign and submit to data room rules (e.g., regarding access times, making photocopies, using other technical equipment, etc.). The amount of time and effort required to populate a data room should not be underestimated. Although the accuracy and completeness of the data in the data room are normally not guaranteed, the process organizers and the government nevertheless need to ensure that the data are not false or misleading. Bidders typically apply a degree of skepticism to the veracity of the data; nevertheless, they will question the seriousness of the process if very little data are available. RuralE.Evolution - IEE/07/579/SI2.499063 Page 22 of 64 D2.3 Guidelines for PPP application Prequalification ensures that only bidders with the minimum required expertise and financial strength are able to bid for the opportunity. This saves the government from the need to eliminate more rigorously from an overly large pool of bidders later in the process. It also encourages bidders that they will be included among a smaller number of equally capable competitors. The prequalification documents usually contain: • project information, such as the key characteristics of the project and the operating context (such as an information memorandum); • instructions to bidders outlining the anticipated bid process and evaluation criteria; • a list of the documents required of the prospective bidders to demonstrate their suitability for the project. In response, the prospective bidders submit information including: • legal status of bidding entity; • experience on comparable projects (including any relevant subcategories in terms of size of project, region, particular expertise); • financial status/resources of bidder; • ability to raise financing; • staff and resources to be directed toward the project. A predetermined scoring matrix should facilitate assessment of the prequalification applications. The matrix sets out each criterion to be scored, the score assigned to each, and the respective weighting. The matrix can include special criteria such as expertise in servicing low-income customers or may prioritize local bidders if desired. It is important to be realistic about the potential pool of bidders and set the threshold sufficiently high to discourage not serious or unqualified bidders, while maintaining a pool of bidders large enough for effective competition. The prequalification results in a short list of bidders invited to respond to the bidding package. Generally, a short list of between 3 and 5 companies is a manageable and competitive size. 4.4 Implementation of a Consensus Building Strategy Technically sound public-private partnerships projects can fail without a full understanding of socio-political dynamics and the value of communication in their design implementation. Today public asset divestment programs undertaken by public bodies around the world are under severe scrutiny from civil society organizations and citizens. Privatization programs can take different forms and degrees in the transfer of asset ownership and management of the service to consumers. Specifically, they can be complete sector divestments (telecom, other productive industries), private participation in infrastructure (energy, ports, railways, and roads), or public private partnerships (water services). For any of these initiatives, it is crucial to incorporate communication analysis and stakeholder engagement at the policy and program formulation stage. In this context all the privatization terminology will be used interchangeably vis-à-vis the sectors and countries profiled in the publication. It is now widely accepted that the success of PPP depends on the maturity of the institutions in the market economy, including legal frameworks on property rights, private contracts, dispute resolution mechanisms, and rules of entry and exit for business enterprises. For privatization programs to be sustainable, however, they need to be properly understood, taking into account the interests and perceptions of all stakeholders. This necessitates using RuralE.Evolution - IEE/07/579/SI2.499063 Page 23 of 64 D2.3 Guidelines for PPP application strategic communication as policy design tool, rather than something added on once a policy has already been formed. In the 1990s, many privatization programs in developing countries proceeded slowly or were aborted because of significant misconceptions and opposition among the general public. Whether opposition was voiced by political leaders, labor unions, media, specific stakeholder groups, or the public at large, these programs failed or were damaged because steps were not taken to secure the necessary political and social support. Communication activities for the range of private sector participation initiatives are more than just “public relations.” Their challenges and obstacles cannot be solved with traditional public relation tools, such as press releases, press conferences, and lobbying activities. Privatization programs require a carefully conceived and systematically applied approach to communication — one that integrates communication analysis and planning at each stage of the design and implementation. When used effectively, strategic communication can significantly increase political and social sustainability by creating space for dialog and stakeholder participation in the decisionmaking process. A strategic communication program for public private partnerships serve two broad purposes. First, it helps to avert failure by identifying current and potential sources of both support and opposition. This information is crucial not only in setting priorities for communication objectives, developing sound messages, and selecting the best possible communication channels, but also in using those channels effectively and creating new ones if needed. Communication research can raise awareness of an unsustainable status quo, uncovering existing attitudes on a range of relevant issues, such as the drain on public funds due to poor management of state-owned enterprises, political interference, clientelism, and nepotism. A well-designed communication program can explain the role of private interest in creating incentives to make society, as a whole, more prosperous. Second, a systematic approach to communication helps to achieve a well-tailored privatization and private sector participation program, serving as a two-way check and feedback mechanism at every stage, from planning through execution. Public communication programs offer managers in public institutions and state-owned enterprises tools for the privatization process that coordinate well with national economic programs and fit political and social needs. Communication programs create mechanisms for dialog with stakeholders through which expectations for privatization can be managed. Failure to use communication programs results in negative consequences found in countless development projects involving privatization. Neglect of consensus building among stakeholders for privatization weakens a project’s opportunity for success and sustainability. The consensus-building process needs to be considered at every stage, from the initial conception and strategic planning through the implementation. When preparing for privatization initiatives, a government and its advisers should make substantial efforts to engage political parties, managers of publicly owned enterprises, unions, workers, civil servants, business leaders, potential investors, national and international civil society organizations, and consumers about the program’s operations and benefits. General consensus may not be possible, but information flow and awareness raising among all stakeholders are often prerequisites for success in the range of privatization initiatives. RuralE.Evolution - IEE/07/579/SI2.499063 Page 24 of 64 D2.3 Guidelines for PPP application 4.5 Selection of suitable technology/production plan according to local characteristics The selection of suitable technology/production plan has been discussed in deliverable D3.1. In a first analysis the main industrial activities of the area and the needs of energy (electricity, heat and fuels) have been considered, in particular evaluating the actual energy sources and their distribution as infrastructure. Then the agroenergy potential of the territory has been considered, evaluating the local energy services companies as potential and suitable partners to constitute a PPP. A pre-feasibility analysis of the project has been done, considering bioenergy production potential, identification of existing bioenergy production systems, prefeasibility of plant location. The regulatory framework has been considered also and so the infrastructures were analyzed. At the end of the analysis the place, biomass and technology were individuated on the basis of a SWOT analysis. 4.6 Institutional Structures and Capacity building PPPs require a range of stakeholders within and outside public structures to assume new roles or perform existing roles in improved ways. Often, new entities are created, such as regulators or PPP units, to manage the process. Public partners must ask a series of key questions to understand the institutional requirements of the reform strategy. These questions might include: • • • • • • • are the institutional and legislative frameworks in place to support sector improvement and PPP, in particular. What are the impediments according to the public body, users, and utility; do the level of autonomy and accountability of stakeholders match their proposed obligations; are the relevant public sectors prepared to relinquish or revise their roles; are the relevant public sectors prepared to delegate some control to private partners within defined policy and regulatory parameters; does each institution have the funding, staff, training, and equipment required to discharge its functions; does each institution understand its role and know how to develop the procedures for accomplishing this role; is there a key stakeholder—i.e., a leader—with the capacity and the political will to lead and drive the reform agenda forward. These institutional roles must be clarified at the latest by the time the PPP process is complete. However, the greater the degree of uncertainty about institutional roles during the PPP process, the higher the level of perceptive risk is likely for potential investors. At the same time, there must be some flexibility to refine and update institutional roles as the sector evolves and matures. Increasingly, as decentralization takes root, public organization has the additional burden of determining at what level of government each role is best performed. In the institutional analysis, it is important not to overlook the capacity to support bidding, negotiation, and contract compliance and monitoring. Public partners may have unrealistic expectations of the ability of their own organizations in that respect. RuralE.Evolution - IEE/07/579/SI2.499063 Page 25 of 64 D2.3 Guidelines for PPP application 4.7 Identification of the supply chain Biomass can be converted into useful forms of energy using a number of different processes. Factors that influence the choice of conversion process are: the type and quantity of biomass feedstock; the desired form of the energy, i.e. end-use requirements; environmental standards; economic conditions; and project specific factors. In many situations it is the form in which the energy is required that determines the process route, followed by the available types and quantities of biomass. Biomass can be converted into three main products: two related to energy – power/heat generation and transportation fuels – and one as a chemical feedstock. Conversion of biomass to energy is undertaken using two main process technologies: thermo-chemical and biochemical/biological. Mechanical extraction (with esterification process) is the third technology for producing energy from biomass, e.g. rapeseed methyl ester (RME) bio-diesel. Within thermo-chemical conversion four process options are available: combustion, pyrolysis, gasification and liquefaction. Bio-chemical conversion encompasses two process options: digestion (production of biogas, a mixture of mainly methane and carbon dioxide) and fermentation (production of ethanol). A distinction can be made between the energy carriers produced from biomass by their ability to provide heat, electricity and engine fuels. A useful means of comparing biomass and fossil fuels is in terms of their O:C and H:C ratios, known as a Van Krevlen diagram. The lower the respective ratios the greater the energy content of the material. The major conversion technologies and processes are shown in figure 8.2. Figure 3: Biomass to energy conversion chains. [3] Understanding the full impact of Bioenergy systems on communities requires improved understanding of the nature of the complete market chains, and of the different business models, technologies, institutional arrangements and power dynamics at the various stages in the chain, which can lead to very different outcomes. RuralE.Evolution - IEE/07/579/SI2.499063 Page 26 of 64 D2.3 Guidelines for PPP application Figure 4: Actors involved in a bioenergy production chain in Tanzania [4] Figure 4 presents the actors involved in a bioenergy production chain from sisal in the coast of Tanzania. Lying on the Coast of Tanzania, bordering Kenya, Tanga Region has a population of around 1.7million, with a growth rate in population from 1998-2002 of 1.8% and a population density of 60 persons per square kilometer. The population of Tanga Region has been increasing since 1957, and as a result of high population density, forests have become endangered and wood scarce. The increasing need for income and food is not matched by increased economic development or food production. Sisal is the most important cash crop, used to produce yarns, ropes, carpets, clothing and composites, and sold to the domestic and international markets. Since 1999 Katani Ltd, a sisal growing company, has developed a system of smallholder and out-grower sisal farming, on land owned by the company and in the surrounding areas. Katani has developed the first biogas plant in the world to convert sisal biomass to biogas. This is used to run electricity generators which power production machinery, with excess electricity supplied to outgrowers/smallholders homes, schools and hospitals. 4.8 Availability of the land Land premium waiver or development rights should not be used as the major incentive for a consortium to provide the facility/service. Otherwise, the well established tender procedure/policy will be in jeopardy and projects may be criticized for bypassing the proper procedures. Land revenue will effectively be hypothecated. That said, where there are ancillary areas not needed by the required facility and the consortium identifies some commercial opportunities within the site, granting of commercial development rights may be RuralE.Evolution - IEE/07/579/SI2.499063 Page 27 of 64 D2.3 Guidelines for PPP application considered but this again, must not be the major incentive and must not undermine the normal tender procedures. The treatment of land as an asset should be dealt with on a case-by-case basis. As a matter of principle, the disposal of land should be under a fair, transparent and competitive process. Depending on the length of tenure and nature of the service involved in a PPP project, the disposal of land can be by way of a Licence; Short Term Tenancy (STT); long lease in the form of a Private Treaty Grant (PTG) or granted by public tender; or an enabling ordinance. Dealing with the problem of land acquisition contract, there are differences of opinion on whether it is best to have one unified contract, or two separate contracts that are crossreferenced to each other (one contract conferring the right to use the land/facilities and the other relating to the other PPP issues). Those in favour of a unified document argue that there is no need for a ‘separate’ service agreement, and that the private sector commonly dispenses with a service agreement. The advantage of incorporating all the rights and obligations in one document is that there should be a consistency of drafting, and less chances of inconsistencies and omissions arising. Those in favour of keeping separate documentation argue that: the land disposal document should be kept reasonably lean and simple, focusing on the development and use of government land, and conferring title. It is not an appropriate document for setting out detailed operational arrangement such as fees, entrance charges, opening times etc; the commercial arrangements in a complex PPP project can be very intricate and are best dealt with independent of the land documentation. Otherwise, preparation of the land document will take much longer and will still involve more than one drafter; under a PPP approach, many parameters and terms and conditions are determined through negotiations with the private partner. This process is not as open and competitive as the normal tendering process for land. Hence, giving up land development rights is theoretically less efficient. As the private partners are allowed to retain the incomes arising from the commercial facilities, revenues are hypothecated; modification of even minor provisions in an executed land document requires formal legal documentation, which is a lengthy, complex process that will reduce flexibility in arrangements. It may have land premium or revenue implications that may not be acceptable to the consortium; PPP issues such as profit-sharing are commercially sensitive and should not be incorporated into the land grant, which will be subject to public scrutiny through the Land Registry search facilities. It should be noted, however, that in many jurisdictions, the requirements for probity and transparency dictate that copies of the project documentation be made publicly available except for only limited commercially sensitive information. 4.9 Definition of the logistic plan Biomass is a renewable energy source which can be used as fuel in energy plants. Interest in biomass as an energy source is increasing for several reasons. The use of biomass is CO 2 neutral and therefore does not contribute to global warming. It is an alternative for fossil fuels (with limited resources) and as an energy crop it is an alternative for arable farmers. Several types of biomass can be distinguished: rest-products (like demolition wood and waste paper), agricultural by-products (like straw and tops) and energy crops (like willow, poplar and miscanthus). RuralE.Evolution - IEE/07/579/SI2.499063 Page 28 of 64 D2.3 Guidelines for PPP application The costs for biomass as a fuel are divided into three parts: the purchase prize, the logistic costs for the collection, and the costs for establishing and running the energy plant. The costs of the logistics of the biomass fuel collection may determine for a major part the feasibility of these plans, especially when the purchase prize is low as may be expected when rest-products or byproducts are used. The logistics, which include transport, storage, handling and pretreatment can be set up in many ways. Thus, it is difficult to estimate the logistical costs. The biomass fuel collection is a logistical process consisting of flows originating in source locations directed towards the energy plant. There can be direct transport or transport via collection, pre-treatment or transshipment sites. The logistics of the collection include transport, storage, handling and pre-treatment. These can be modeled by a network structure A node corresponds with a location and an arc with transport. Usually there are three transport options: road, water or rail transport. Nodes can correspond with: - a source location, where biomass becomes available; - a collection site, where biomass from several source locations is collected; - a transshipment site, needed when different kinds of transport means are used; - a pre-treatment site, included in case of more complex pre-treatments, like pelleting of waste paper; - the energy plant, the target location for all biomass. Pre-treatments, like size reduction and drying of biomass, are involved to improve transport and storage characteristics or when the biomass characteristics do not correspond with the requirements set by the energy plant. Pre-treatments are possible in every type of node, a separate pre-treatment site is included only when specialized equipment is needed that can not be placed at all locations in the logistic chain. 4.10 Monitoring and reporting on results The monitoring process in the early stages of developing the project will deal with: Oversee the design and construction phases; Monitor the project once it becomes operational; Establish and manage the day to day relationship with the consortium; Keep abreast of developments in the field covered by the project and consider the need for change; Manage the agreement of any changes during the life of the contract; Monitor the achievement of key performance indicators; Recommend and calculate payments/abatements; Report regularly to the PSCom (Project Steering Committee); Advise the PSCom (Project Steering Committee) of any serious performance failures and the need for dispute resolution measures to be initiated. Over the life of a project the individuals holding key posts will inevitably change. It is vital therefore that comprehensive records are maintained of all interactions and, wherever possible, new post holders are fully briefed by the departing incumbent. Particular care must be taken if there is a handover of responsibilities at the time of commissioning the project facilities. The Contract Manager will usually need a support team. The make-up of the support team will vary at different times, and may include both civil servants and contract staff. They may not need to work full-time on a particular project. RuralE.Evolution - IEE/07/579/SI2.499063 Page 29 of 64 D2.3 Guidelines for PPP application 5 Business plan 5.1 Identification of the Business Model As with any major public project that involves changing the way public business is done the first step is to ensure that there is a case (a business case) for proceeding. A business case addresses the issues that the proposal seeks to resolve. It will include the compelling case for change, in terms of the existing and future business needs; the options considered; the preferred option that represents the optimum balance of estimated expenditure and revenue, anticipated savings, expected benefits and the risks identified together with risk allocation and mitigation proposals; and an implementation plan to achieve the intended outcome. In the early stages it might not be clear whether a PPP or another delivery option will best resolve the issues being considered. Therefore, the development of the business case for a PPP will often be done in two stages. The stage 1 business case study involves a high level selection from among the different delivery options the one that best meets the service needs. In the stage 1 business case study, the options to be evaluated should include those of the public sector (e.g. in-house provision, contracting-in, trading fund, corporatisation, etc.) and private sector (e.g. contracting-out/outsourcing, PPP, etc.). To be considered as having a prima facie case, a PPP should meet most, if not all, of the following criteria: there is a major investment programme, requiring effective management of risks associated with construction and delivery; the private sector has the expertise to deliver the programme and there is good reason to think that it will offer value for money; the structure of the service is appropriate, allowing the public sector to define its needs as service outputs that can be adequately contracted for in a way that ensures effective, equitable and accountable delivery of public services in the long term; risk allocation between the public and private sectors can be clearly made and enforced; the value of the project is sufficiently large to ensure that procurement costs are not disproportionate; the technology and other aspects are stable and not susceptible to short-term fast paced changes; planning horizons are long term, with assets intended to be used over long periods. If this exercise provides a prima facie case for a PPP, resources would then have to be invested in the stage 2 business case study. The stage 2 business case study focuses on confirming the justifications. The stage 2 business case study should include a detailed analysis of the likely costs, benefits and risks of the PPP option to the government, baseline costs, PSC (Public Sector Comparator), critical success factors, project management and implementation plan, procurement strategy, risk management strategy, benefits realization plan, etc. It should be noted that some of the issues will be covered in both stages 1 and 2 of the business case study, e.g. evaluation of options, selection of the preferred option, etc. Stage 1 addresses the issues at a higher level and in less detail. With more information available, stage 2 will review, validate and update the assumptions and estimates made earlier and map out the way forward. For example high level cost estimates gathered from a market-testing exercise might be sufficient for comparing different options in stage 1; whereas a properly prepared PSC (Public Sector Comparator) will be required to demonstrate value for money of a PPP in stage 2. RuralE.Evolution - IEE/07/579/SI2.499063 Page 30 of 64 D2.3 Guidelines for PPP application The EU plans to issue a Government Business Case Guide in 2008 to provide more guidance on the conduct of business case studies. As with other procurement methods, the lowest priced option does not necessarily offer the best value for money. Value for money refers to the best available outcome taking account of all benefits, costs, and risks over the whole life of the procurement. Value for money is determined through a comparative analysis of the benefits, costs and risks of the available procurement alternatives. Assessing the value of these variables requires a degree of judgment and the use of both quantitative and qualitative analysis. Value for money combines economy, efficiency and effectiveness. It can manifest itself as: delivery of a service capability at a lower cost; greater certainty of an expected financial outcome due to less exposure to significant risk; increased benefits to the end user of a service due to the public sector’s focus on service delivery rather than asset procurement. Assessment of value for money is not in itself affected by the budget impact of alternative procurement methods. The assessment should also be independent of the accounting classification of a private financing arrangement i.e. whether or not any borrowing is off the government’s balance sheet. The budgetary implications of alternative procurement methods should be considered separately as part of the government resource management framework. PPP procurement inclusive of private financing should be used where it offers superior value for money compared with other procurement methods. 5.2 Definition of Economic & Financial issues A PPP deals with cash flows over long periods of time, and the value of money is affected by the time that this money is received or paid. Two interlinked types of calculation are normally used to make decision: - a discounted cash flow (DCF) calculation, which gives a value to today, or ‘net present value’ (NPV), for a future cash flow; - an internal rate of return (IRR) calculation, which determines of the overall rate of return on an investment based on its future cash flow. DCF and IRR calculation are used in a variety of different ways by the different parties to a PPP project. Dealing with the public sector a DCF calculation may be used: - when deciding whether to proceed with the procurement of a project an Economic Rate of Return calculation (a form of IRR) may also be used in this case; - in a Public Sector Compartor; - to evaluate bids for a PPP project;. Dealing with investors, the project IRR – i.e the IRR cash flow before debt service or equity returns – may be used to assess the general financial viability of a project without taking account of its financial structure. However the main measure for investors is the Equity IRR – i.e. the IRR of the equity cash flow (distributions) versus the original equity investment. This is commonly used as a hurdle rate for investments –i.e. in order for an investment to be justified the equity IRR must be x% or above. Dealing with PPP contracts, the equity IRR may be used to calculate: - the initial Service Fees; RuralE.Evolution - IEE/07/579/SI2.499063 Page 31 of 64 D2.3 Guidelines for PPP application - revisions to Service Fees, or compensation for changes in circumstances during the life of the PPP Contract in some cases; - refinancing-gain calculations; - compensation to investors for early termination of the PPP Contract, for which a DCF calculation may also be used. and the Project IRR may be used to calculate the payment due on termination for a default by the Project Company. Concerning lenders, they use the Project IRR to calculate their Loan-Life Cover Ratio. Another important economical issue dealing with PPP management is the public sector investment decision process. There are various measures which a Public Authority may use to determine if an investment in new public infrastructure is economically justifiable. Nevertheless additional factors need to be taken into account to make this decision: - value for money; - affordability; - balance-sheet treatment. When deciding if an investment is economically justifiable, a Public Authority: - identifies the benefits and costs of the project, including its indirect effects; - prepares a cost-benefit analysis, a key element of which is the discount rate to be applied to future benefits and costs; - or calculates the economic return of the project (i.e. an IRR calculation which uses the same economic data). Having decided that a new facility is economically justified, how can a public Authority decide whether the PPP route is the right one? This question has two aspects: - does the PPP offer good value for money compared to public-sector procurement? - is the project been procured.as a PPP in a way which offers good value for money? A Public Sector Comparator (PSC – also known as Public Sector Benchmark) is an attempt to answer the first of these questions. A PSC is an assumption of what the NPV cost (sometimes known as the net present cost (NPC)) of the project would have been had it been acquired through a conventional public-sector procurement, which is then compared with the NPV cost of the PPP. The latter may also be estimated, or it may be known if bids have been received for it. If the PPP’s NPV cost is lower than PSC, the PPP can be justified. (This is not the same as the economic cost-benefit analysis discussed above – here only the two sets of project costs are being compared). Even if payments are not made by the Public Authority, as in the case of a Concession, the user charges represent revenue foregone by the public sector, and hence the analysis is the same as for a PFI-Model Facility. But a PSC raises a number of difficult issues – in particular: - how comparable costs are to be produced; - what discount rate is to be used to make these costs comparable in NPV terms; - how adjustments are to be made for risk transfer and other differences between the two types of procurement, including tax. While Value for money is important for the public authority, an equally relevant question is that of ‘Affordability’, i.e. whether it can actually afford to pay the Service Fees (in the PFI model – Private Finance Initiative), as the Public Authority will probably have a set budget for the project, within which it has to work. Equally in the Concession Model, the Facility has to be affordable for users. Dealing with the balance sheet treatment, if it is clear that the choice is between a project which is outside the public-sector budget (at least in relation to its initial capex), and n o RuralE.Evolution - IEE/07/579/SI2.499063 Page 32 of 64 D2.3 Guidelines for PPP application project at all, which as discussed above is the unusal motive for going down the PPP path, then there needs to be a method for deciding whether or not a project is ‘on-balance sheet’ for the Public Authority and hence the public sector as a whole. It is clearly not an ideal approach for Governments to set their own public-accounting rules for PPPs, and there are international efforts to create consistency in this respect, based on the United Nations System of National Accounts (‘SNA’) last updated in 1993. The International Monetary Fund (IMF) has a ‘Task Force on the Harmonization of the Public Sector Accounting’, which covers, inter alia, the topic of ‘Government/Public Sector/Private Sector Delineation’. Within the European Union, Eurostat, the Statistical Office of the European Communities, provides the European Union with statistics from EU member countries on an harmonized basis, and as a part of this process has to decide what should and should not be included within the figures for publicsector budgets. Eurostat’s rules on government accounting which are based on SNA, are therefore a useful starting point in considering balance-sheet treatment for PPPs. Figurre 5: Decision tree for Eurostat balance-sheet treatment [5] Concerning financial structuring, it deals with the process by which bidders and their lenders structure the financing for a PPP project. The Service Fees are the final output of this process, since these have to cover the Project Company’s financing and operating costs and provide a return on the bidders’ equity investment. A financial model is used to make the required calculations for the bid, and at various other phases of the project; the model has to work within the constraints of: - the Public Authority’s requirements for the PPP Contract term and Service-Fee profile; - lenders’ requirements for term and payment profile of their debt; - lenders’ Cover Ratio requirements; - investors’ Equity IRR requirements; - and the complex interplay between all of these. RuralE.Evolution - IEE/07/579/SI2.499063 Page 33 of 64 D2.3 Guidelines for PPP application The financial model covers of the whole of the Project Company’s operations, not just the Facility itself, and thus takes into account tax and accounting issues that may affect the final cash flow of the Project Company. A financial model is used in different ways during the bidding and development phase of a PPP project: - initial feasibility from the Public Authority’s point of view: a ‘shadow’ financial model will be produced by the Public Authority’s financial adviser, which will attempt to predict the bidder’s costs, financing structure and other assumptions (in Australia this is called the Private Financing Predictor (‘PFP’)), and hence whether the outcome in terms of Service Fees is likely to be acceptable from the public-sector point of view; - structuring the bidders’ financing and reviewing the benefits of different financial terms and arrangements; - calculation of the Service Fees required to cover capex (Capital Expenditure), opex (Operating and Maintenance Costs), debt service and the investors’ return as a basis for the bid; - as part of the lenders’ due-diligence process; - fixing the Service Fees where these depend on interest rates at Financial Close. After Financial Close the model continues to be used: - as a basis for lenders to review the changing long-term prospects for the project and thus their continuing risk exposure; - to price variations and compensation payments in the PPP Contract; - to calculate any Refinancing Gain to be shared between the Public Authority and the Project Company; - as a budgeting tool for the Project Company. However, given that the original objective of the model has changed, it will require some adaptation to undertake these tasks, especially the last. As there are three parties involved – the Public Authority, the Sponsors and the lenders- there could theoretically be three parallel financial models, but this is seldom the case. The more usual course is for the Public Authority’s financial adviser and the lenders to review the model prepared by the Preferred Bidder (or the latter’s financial adviser), calibrate it against the Public Authority’s shadow financial model to ensure that the results are the same (given the same assumptions) and then use the bidders’ model thereafter, in the ways listed above. Alternatively, there is some merit in the Public Authority providing a template financial model to be used, with suitable adaptation, by all bidders, to make comparison of bids easier. It may be asked why the Public Authority should have access in this way to the Preferred Bidder’s financial model – isn’t the data in this model commercially confidential? But this is unlikely to be the case because: - the Public Authority needs to be able to check whether the bid is financially viable, and can thus deliver the initial investment in the PPP project and its long-term service requirements; - if the financial model is used to calculate the Sercice Fees at Financial Close it obviously has to be agreed by both parties; - there has to be an agreed Base Case, because should compensation be required later it has to be measured against the outcome in the PPP Contract which both parties originally agreed was reasonable. Therefore transparency between the parties on model assumptions and calculations is the better practice. RuralE.Evolution - IEE/07/579/SI2.499063 Page 34 of 64 D2.3 Guidelines for PPP application 5.3 Financial Implications of Risk Well prepared and implemented projects will have a higher chance of avoiding and/or dealing with problems that may arise. Experience demonstrates that for both conventional and PPP procurements poor drafting of the contract/performance requirements and/or poor contract management can lead to problems downstream. The key in entering into contracts of all kinds is to be aware of such possibilities, take expert advice, and manage the contract letting and negotiation processes accordingly. As with any project involving investments, the due diligence, risk allocation, and negotiation processes inherent in letting a PPP contract give the opportunity for many potential problems to be identified and resolved prior to contract finalization. Some potential problems and the means of addressing them are: 1) benefits not being shared with the public partner; rigorous negotiation by the public partner for terms to protect its interests and adequate supervision; 2) bottom line considerations assuming disproportionate importance; avoidance of underbidding by consortia, equitable variation conditions; 3) business culture co-existing uncomfortably with public service; identification of consortia with a clear commitment to public service; 4) buy-out costs of replacing a poorly performing operator; rigorous selection of consortia, early identification and rectification of poor performance; 5) disruption to service, and costs incurred, when exercising step-in rights; rigorous selection of consortia, maintenance of an appropriate level of market competition, adequate contingency arrangements; 6) high financing costs; appropriate allocation of risk and innovative financing arrangements; 7) inadequate accountability; rigorous selection of consortia and adequate supervision; 8) lack of competition; encouragement of the market through market testing/development and well managed contracting processes; 9) lack of flexibility, especially over the longer term; appropriate contractual change management/variations procedures; 10) liquidation and use of company structure to avoid liability; rigorous selection of consortia, strong step-in rights, linking payment to performance, requirement for parent company guarantees, additional security etc; 11) lock-in to an unsatisfactory contract - leading to costs of exercising a break clause; rigorous output/outcome based definition of requirements and contractor selection; 12) Loss of control; Clear service definition, effective contract management, early identification and rectification of poor performance; 13) unavailability of experienced/qualified PPP contractors; encouragement of the market through well managed contracting processes and a continuing deal flow; 14) unmitigated risks due to inappropriate allocation; management of risk allocation, drawing on expert advice; 15) unreliable levels of service; rigorous selection of consortia and adequate supervision. RuralE.Evolution - IEE/07/579/SI2.499063 Page 35 of 64 D2.3 Guidelines for PPP application 5.4 Definition of the strategic planning Once the client department has identified a project or a service that is required, and is considered to have potential as a PPP, a feasibility study should be conducted. A decision to proceed with the PPP approach would usually follow from the feasibility study recommendations which should address the following: providing service specifications, which can be agreed upon by stakeholders and tested in the market; assessing the financial viability of the project; assessing whether the client department has the necessary legal powers to let successfully a contract for the provision of the service in question and, if not, what can be done to address the absence of such powers e.g. amending existing legislation. 5.5 Definition of Legal & Contractual framework In drawing up the detailed arrangements for a PPP project, the client department will need to ensure that public partner’ interests are adequately protected. These provisions cover issues such as restrictions on assignment or disposal of rights and obligations, restrictions on mortgages and charges, claiming damages to make good defects/upon the service provider’s failure to perform obligations, compensation to the service provider for added value, control over change in equity ownership and shareholding etc. Subject to the proper construction and interpretation of any relevant legislation in any particular situation, the public partner has extensive constitutional and common law powers to make commercial contracts including PPP contracts. Public partner cannot transfer to the consortium its basic accountability and responsibility to the public for the delivery of public services. In addition, public partner may have a continuing, not delegable duty of care to recipients of certain services provided by the consortium – particularly those recipients in a position of vulnerability, to whom public partner owes a duty of care. This not delegable duty of care may arise at common law or under legislation. The existence of non-delegable duties limits the extent to which Government can transfer legal responsibility for the provision of services to the consortium. This is the case even where the financial consequences of a breach of the duty can be transferred e.g. by indemnification from the consortium, adequately supported by insurance carried by the consortium. Where public partner has a non-delegable duty in delivering a service, it may remain liable for any negligence on the part of the consortium engaged to provide the services on public partner’ behalf. In this way, a nondelegable duty imposes a similar liability on public partner for the acts of the consortium as for the acts of its own employees. RuralE.Evolution - IEE/07/579/SI2.499063 Page 36 of 64 D2.3 Guidelines for PPP application 6 Requirements of partnership contracts Regardless of the option selected, the essential elements to be included in a contract are: • the parties to the agreement; • interpretation: Sets forth the definitions of important terms and providing guidance on the interpretation of the contract’s provisions; • the scope, territorial jurisdiction, and duration of the agreement; • the objective of the contract; • circumstances of commencement, completion, modification, and termination of contract; • the rights and obligations of the contractor; • the rights and obligations of the government; • the requirement for performance bonds to provide security for government if the construction and/or the service delivery falls below standards; • insurance requirements to provide security for the insurable matters; • government warranties; • private sector warranties; • consequences to a change in law; • service quality, and performance and maintenance targets and schedules; • the identification of regulatory authorities, if any, and the extent of their roles and authority; • the responsibilities of the contractor and the government with regard to capital expenditures; • the form of remuneration of the contractor and how it will be covered, whether from fixed fee, fixed fee plus incentives, or another arrangement; • how key risks will be allocated and managed; • the contractor’s rights and responsibilities with regard to passing through or entering public or private property; • reporting requirements; • procedures for measuring, monitoring, and enforcing performance; • procedures for coordinating investment planning; • responsibility for environmental liabilities; • procedures for resolving disputes; • delay provisions describing what is and is not an excuse for a delay in construction or operations; • force majeure conditions and reactions; • procedures to be followed when either party to the PPP contract wishes to change any material portion (variation) of the contract; • identification circumstances; • the rights of each party to any intellectual property brought to the project or created during the project, including the steps to be taken to protect the intellectual property of third parties, such as information technology software manufacturers; • conflict of interests and dispute resolution; • description of the conditions under which either party may terminate the contract, the processes to be undertaken in that regard, and the consequences to each party of a termination; • the circumstances that may permit either the government or any financial institution to “step in” to the contract to protect its rights under the PPP contract; • consequences of a change in the ownership or key personnel of the private partner; RuralE.Evolution - IEE/07/579/SI2.499063 Page 37 of 64 D2.3 Guidelines for PPP application • mechanisms whereby the parties to the PPP contract will interact with each other going forward; • requirement that each party comply with all laws pertaining to the project, including obtaining environmental, zoning, planning, and other permits; • conditions by which public sector employees are employed by the private sector contractor, including any restrictions on terminations or redundancies for operational reasons; • conditions precedent: describes any conditions precedent to be fulfilled by either party before the contract takes effect. This list is illustrative and does not capture every clause required in a contract. The final content of the contract will depend on the project scope, local legal requirements and precedent, and advice of legal advisors. Normally there will be several contracts in a PPP project, including: the Project Agreement, which is the key document between the government and the consortium; the Direct Agreement(s); sponsor arrangements (equity; equity subscription and shareholders agreements); debt: subordinated loan agreements, and credit and security documentation; back-to-back contracts e.g. design, constructor, operation and maintenance. See Figure 6. Figure 6: Key Contractual Relationships in a PPP Project (DBFO Model) [2] A number of jurisdictions, including the UK and Australia, have produced some ‘standardized’ documents. These have taken into account a considerable amount of local RuralE.Evolution - IEE/07/579/SI2.499063 Page 38 of 64 D2.3 Guidelines for PPP application experience and are often credited with speeding up, and reducing the cost, of the bidding/negotiating stages. 6.1 Example: Italy The Italian legal framework for the realization of PPP operations contract are covered in most part by the Legislative Decree no. 163/2006. Within it, in line with the directives of the EC 2004, are defined and ruled the concessions of public works and service concessions, including the sponsorship contract. Also the approval of the Finance Act in 2007 made it possible the employment of property leasing contracts for the construction of public works. In Italy at the moment there are 7 forms of PPPs: 1) contract of concession to build and management based on public initiative (art.143 of “Code of public contracts for works, services and supplies” , D.Lgs. n.163 of 2006). This is the traditional concession to build and operate in which the public administration, once the infrastructural needs have been individuated, elaborates a preliminar project and inserts this in the programming instruments already approved. On the basis of the preliminar project made by the public administration it starts the private tenering procedure to inidividuate a winner. The private income is received during the operation phase while there are also risks of financial and technical nature. The public contribution aims to grant to the private the obtainement of an economic and financial balance. 2) contract of concession to build and operate based on private initiative (art. 153 and following of “Code of public contracts for works, services and supplies” , D.Lgs. n.163 of 2006). This is a particular procedure in which the private sector is the promotor for the realization of a public facility or service and presents to the public administration a specific project that is linked with infrastructures already inserted in the programming instruments of the administration itself. The private income is received during the operation phase while there are also risks of financial and technical nature. The public contribution aims to grant to the private the obtainement of an economic and financial balance. The proposal, once declared of public interest by administration, is the basis of a public tender, aimed to the identification of the dealer, articulated in two moments. 3) other concessions of operation; these are contracts between the public authority and a private subject for the supplying of a service. The private income is perceived during the operation of the service and can be linked to a price. This is balanced by the risks in operation the service. Compared to the previous two forms in this case the supplying of the service is not linked with the realization of a facility, and if a kind of facility is required, its value is not significative with respect to that generated by the supplying of the service. 4) mixed public-private company; the D.lgs n.267 of 2000 with art. 113 and following, identifies two typologies of public-private companies: stock companies with the purpose to realize with the contractual obligation of majority participation of public bodies, to which can be assigned the only operation of services with or without economic significance; companies limited by shares realized without the contractual obligation of the majority participation of local bodies, for the operation of public services that have no RuralE.Evolution - IEE/07/579/SI2.499063 Page 39 of 64 D2.3 Guidelines for PPP application economic significance and for the realization of the facilities necessary to the operation of services or for the realization of infrastructures and other works of public interest. 5) urban transformation company. Urban transformation companies have been introduced with art. 120 of dl.lgs 267/2000. These represent a particular typology of mixed companies and are based on a specific social purpose, that is the design and realization of urban transformation works, that will operate urban plans. Private income derives from the commercialization of the works realized on the upgraded area. 6) public sponsorship contract. These are contracts subscribed between a public body, that assumes the qualify of sponsee, and a private operator, sponsor; the first will display the name and/or logo of the private sponsor that will pay for this. 7) immovable leasing. These are contracts of lease of movable or immovable properties acquired or build by the lessor following indications of the leaseholder, who will assume all the risks, and who will have the possibility to become the proprietary of the leased properties at the end of the contract, by paying and established price. The law 27 December 2006, n. 296 (Finance Act 2007) art. 1, paragraphs 912-914 and 907.908 allows the use of the leasing contract for the construction, the acquisition and completion of public works or public utilities, by the commissioners required the application of the code of contracts public works, services and supplies. Procedures for awarding the concession contract and management. The above mentioned PPPs forms in Italy can be summarized in the following Table 10.2. Figure 7: PPP forms in Italy [6] RuralE.Evolution - IEE/07/579/SI2.499063 Page 40 of 64 D2.3 Guidelines for PPP application 6.2 Example: Greece The Legal Framework of PPPs Law 3389/2005 (Official Journal A 232/2005) establishes a new legal framework for the implementation of PPPs in Greece. This legal framework aims to promote the implementation of PPP projects, taking into consideration the experience gained from concession agreements that were successfully implemented in Greece, but also the important attempts over the last year to implement privately funded projects, many of which, however, were not successful because of the inadequate preparation of the contracting authority, the incomplete business justification or the unrealistic estimation of their feasibility. For the first time, Law 3389/2005 introduces a stable legal framework that overcomes the above mentioned obstacles. Specifically the law defines the Public Entities (Central Administration, local government organizations, legal entities under public law) that can implement partnership contracts with Private Entities, in areas falling within the scope of their competence. The private sector undertakes a significant part of risk, related with financing, constructing and providing infrastructure or services. Their investment is repaid either by the Contracting Authority or by the end users. This means that these projects are funded, in total or partly by funds and resources of the private sector. PPPs are not allowed to engage in projects or activities that are the direct and exclusive province of the State, under the terms of the Constitution of the Hellenic Republic, such as national defense, police work, the award of justice, and the execution of judicially imposed penalties and sentences. Law 3398/2005 provides incentives for both public and private entities to be engaged in partnerships for constructing infrastructure or delivering services, mainly through the simplification of relevant procedures. It defines the minimum content of a PPP contract, with clear description of the rights and obligations of both parties, regulating particular issues such as financing, the participation of public entities in partnerships, the payment mechanism, granting of permits, protection of the environment, treatment of archeological findings, expropriations and cases of projects undertaken by Public Utility companies. Moreover, legal issues related to these partnerships, such as the transfer of claims, validity of sureties in rem, taxation and resolution of disputes are clearly defined. Under Law 3389/2005, two new administrative bodies have been established, aiming at the support of Public Authorities, in order to improve the effective preparation and management of PPP projects: • the Inter-Ministerial Committee for PPPs (IM PPP Committee) is a collective governmental body that defines and specializes PPP policy, approves PPP projects that fall under Law 3385/2005 for the provision of infrastructure and the delivery of services by private funds, and coordinates and monitors the implementation of PPP projects; • the Special Secretariat for PPPs (PPP Unit) has been established within the Ministry of Economy and Finance. This Special Unit identifies projects that can be delivered via a PPP scheme, promotes their implementation and provides support and assistance to IM PPP Committee and to the Public Entities in the context of all necessary procedures for the finalization of a PPP project. According to the new legal framework, parliament ratification of PPP contracts is no longer needed, while specific issues related with risk allocation, which were difficult to be dealt in the case of traditional procurement methods, that fall under Law 3389/2005 are efficiently manipulated. Finally, the procurement procedures are in line with the EC Directive 2004/18, RuralE.Evolution - IEE/07/579/SI2.499063 Page 41 of 64 D2.3 Guidelines for PPP application aiming at the customization of relevant procedures and the improvement of the efficiency of public administration. Requirements of Inclusion to the Provisions of Law 3389/2005 Partnerships may be subject to the provisions of Law 3389/2005, provided that all the following conditions are met: • they aim at the construction of works or provision of services, which fall within the scope of the Public Entities pursuant to a provision of the law, or a contract, or their articles of incorporation, • they provide that the Private Entities, against payment to be made as a lump sum or in installments by the Public Entities or by final users of the works or services, shall assume a substantial part of the risks associated with the financing, construction, availability of or demand for the partnership object, and related risks, such as, for example, management and technical risk, • they provide that the financing, in whole or in part, of the construction of the works or provision of services, shall be accomplished with capital and resources secured by the Private Entities, and the total contractually budgeted cost for implementing the Partnership object does not exceed two hundred million Euros, not including the Value Added Tax payable. By unanimous decision of the Inter-Ministerial Committee for PPPs, it is possible, in exceptional circumstances, for Partnerships to be subject to the provisions of this law, even though one or more of the above conditions are not met. PPPs shall not be allowed to engage in projects or activities that are the direct and exclusive province of the State, under the terms of the Constitution of the Hellenic Republic, such as national defense, police work, the award of justice, and the execution of judicially imposed penalties and sentences. 6.3 Example: Spain PPP have existed in Spain for a long time and have been frequent in a wide range of areas such as local services provision, industrial and services land promotion, infrastructure management and economic promotion. Since the 90’s the political interest on PPP has increased by reinforcing the Spanish innovation system and improving the efficacy and efficiency of public policy by several fiscal and other measures. The most relevant ways of collaboration in PPPs are infrastructure provision and R&D promotion. In terms of infrastructure provision, the new Eurostat accounting treatment of PPPs has revealed that the existing Spanish model, which uses a wholly state-owned company as sponsor of a project is no longer viable. Thus, the Spanish government has recently launched a new legislation with the aim of offering a more attractive and secure framework for sponsors and financiers of infrastructure. A new public finance law, new general tax law, new public patrimony law, new Subsidies law and many others have come to existence although not all of them have come in force yet. Following the successful experience of UK in the development of PFIs, the Spanish Government has set aside a series of new regulations. The main reform affects the Public Works Law which regulates public concessions and the Private Finance Initiative (PFI) model has begun its development in Spain. RuralE.Evolution - IEE/07/579/SI2.499063 Page 42 of 64 D2.3 Guidelines for PPP application The higher and higher expenditures of the local and regional authorities, the obsolescence of the current infrastructures and the pressing need for new ones as well as the reduction of European funds together with the necessity of outsourcing some auxiliary services, have given rise to new contracting types in the form of Public Private Partnerships (PPP)/ Private Finance Initiative (PFI) which allow the public authorities to meet the investment needs of the public sector without increasing the deficit and also allow the private initiative not only to maintain but also increase its contracting activities at the time of reducing its risks. The PFI model facilitates and integrated real state solution to the public administration, which allows to transfer the risk of promotion and financing to a consortium set by several private companies able to finance the investment through own funds and external debt. By means of PFI, the public administration controls the key services and subcontracts the rest: construction, cleaning and maintenance, security, catering trade, logistics…with specialized companies. But the real attraction of the PFI model for governments is that it reduces the current capital expenditure, sending it out to the future by means of agreements of deferred rents. The changes introduced by the new Law 13/2003 provide greater certainty and flexibility in some respects. A number of interpretation difficulties and questions remain which could make some of the changes less useful in practice than is intended to be the case. However, the legislation is clearly aimed at encouraging PPP projects in Spain and greater involvement of the international capital markets. It raises interesting possibilities for a broader range of experienced private sector players to structure public works concession financings in more innovative ways. 6.4 Example: Portugal A specific law on PPPs exists in Portugal, which considers PPP in a broad sense, e.g. it only considers PPP for investments over 25 millions of Euro and for some specific areas, such as roads and health. A large number of transport PPP projects have been developed, including five motorways under the SCUT programme and four others, all with EIB involvement, to develop the Portugese transport infrastructure. Other projects include water and sewerage, subways, local transportation (e.g., light railway) and museums. There is no appliance of PPPs in the energy sector. There is also a public procurement law that applies to some cases of PPP, where the public actors include city halls or other public partners. Unlike other countries, there is no official registration of PPP in Portugal. 6.5 Example: Hungary As there is no official definition of PPP in Hungarian law, no clear distinctions can be made when categorising a project as a PPP project. Therefore, no one piece of legislation can be identified as the supreme law governing PPP; several legal provisions may be relevant depending on the characteristics of the project. Generally speaking, the legal framework consists of laws that are relevant to all PPPs and laws that are project specific. The most important piece of legislation is the Act on Public Procurement (Act 129 of 2003 and its modification Act 108 of 2008), which sets out the entire bidding procedure. The Act on Concessions (Act 16 of 1991) provides for additional procedural rules where the project matter is exclusively state or local government property RuralE.Evolution - IEE/07/579/SI2.499063 Page 43 of 64 D2.3 Guidelines for PPP application under the Civil Code (Act 4 of 1959). For local PPPs, the Act on Local Governments (Act 65 of 1990) is the relevant piece of legislation. For central government projects, the Act on the State Budget (Act 38 of 1992 and its modification Act 65 of 2006) and a number of corresponding government decrees apply. When preparing bids and project agreements, the Civil Code and sector-specific legislation must be taken into account. The first thing to consider is the procedural framework, which in most cases is dominated by the public procurement rules. The question of whether the contracting entity is considered a public entity under the Act on Public Procurement and the nature of services procured, together with the gross value of the PPP, determine whether or not a public procurement procedure must be followed. The European and national legislation governing public procurement clearly defines the entities and project values that necessitate the use of a transparent and competitive public procurement procedure when purchasing goods or services or facilitating construction projects. In most cases these criteria are fulfilled, making public procurement mandatory. However, as most of the public procurement rules were enacted before PPP projects became common, some provisions may hinder the development of PPP projects. The nature of the services to be provided in a PPP structure may mean that the tendering procedure set out in the Act on Concessions is also applied. In certain cases both the public procurement provisions and the tendering procedure set out in the Act on Concessions must be applied at the same time. Both the Act on Public Procurement and the Act on Concessions contain provisions governing the interaction of the two procedures to resolve any inconsistencies. Article 10/A of the Act on Concessions could be considered an example of specific PPP legislation. Where public services are provided by a concessionaire company in which the state or local government has a majority stake and that is being passed on to private investors, a tender must be issued for the provision of services that the concessionaire company has been performing and that fall under the Act on Concessions. This could be considered a case of the private sector taking over a public service, which may amount to a full blown PPP if, while purchasing majority stakes in the concessionaire, the buyers undertake to develop those public services further at their own expense and, even, at their own risk. The legislation leaves a number of questions unanswered, creating possible pitfalls for PPP projects. These inconsistencies are not necessarily caused by national legislation directly but may also go back to the problem of some EU-wide provisions not being completely PPP compatible. One example is the handling of perfected securities created over PPP assets where the private financing party steps in to replace an original service provider that failed to meet its financial obligations towards the financing party. In such cases there is a risk that the obligation to procure public services under the designated procedure laid down by the Act on Public Procurement may prevent the financing party from: (i) performing the services itself since it was awarded to the original service provider in a public procurement procedure; or (ii) if not providing the services itself, passing the assets gained by perfecting the securities to another enterprise that can provide the public services in question. Governmental body handling PPPs The Hungarian government has become reasonably active in using the PPP structures for an increasing number of deals and projects. It established the Inter-Departmental PPP Committee in 2003 to encourage the growth of PPP, spread information on PPP within different government departments and comment on plans for potential PPP projects before such plans are submitted to the decisionRuralE.Evolution - IEE/07/579/SI2.499063 Page 44 of 64 D2.3 Guidelines for PPP application makers. The committee also prepares proposals for shaping the legal basis of PPPs. It is chaired by the administrative secretary of state of the Ministry of Economy and Transport (Gazdasági és Közlekedési Minisztérium) and comprises representatives from the Ministry of Economy and Transport, Ministry of Finance (Pénzügyminisztérium), Ministry of Justice and Law Enforcement (Igazságügyi és Rendészeti Minisztérium), Prime Minister’s Office (Miniszterelnöki Hivatal) and Central Statistical Office (Központi Statisztikai Hivatal), as well as the National Development Agency (Nemzeti Fejlesztési Ügynökség). PPP units also exist within certain ministries. For example, the Ministry of Economy and Transport has its own department of property management; the Ministry of Finance has a PPP working group; and the National Sports Office has a PPP project office. At the Ministry of Justice and Law Enforcement, the department of penalty enforcement was formed to supervise prison PPPs. In 2005, one of the secretaries of state in the Prime Minister’s Office was also engaged in the coordination of governmental PPP projects, although how this worked in practice is not clear from the official description. The last Government Resolution No 2028/2007 (II 28) (Resolution) defined the provisions on the procedure of the PPP committee, which is the only piece of legislation dedicated to regulating PPP specific matters. Under the Resolution the PPP committee must: - evaluate and opine planned PPP projects; - ensure the professional background and conditions for encouraging and propagating the PPP structures in Hungary; - publish information within the public administration about PPP structures; - monitor and evaluate completed PPP projects; and - develop a methodology for planning PPP projects and for related public procurement procedures and contracting, as well as for monitoring such projects. The government has also adopted Government Decree 24/2007 (II 28) on the undertaking of long-term obligations with a specific view to the PPP concept, eg outlining the role of the PPP committee in evaluating whether a PPP structure or pure state financing is appropriate. As a result of the activity of the interdepartmental PPP committee, some laws have been slightly amended to facilitate PPPs. Projects over a certain value must have approvals in addition to the PPP committee opinion. The Act on the State Budget requires that long-term state undertakings with a net present value of between Ft10bn (€38m) and Ft50bn (€190m) must have the prior authorisation of the government, while projects with a net present value of over Ft50bn must be pre-approved by parliament. Also, if parliament approval is required, it must be provided with information on the main elements of the contract and the need for state financing. Procurement policy For purely local projects, the tenderer proceeds in accordance with its internal rules until the publication of the tender. For central government projects or local projects that are financially supported by central government initiatives, the tenderer needs to obtain prior approval for the project from central government, which in turn consults the interdepartmental PPP committee. This preparatory phase may take a considerable period of time for the tenderer (perhaps more than a year). A key element is conducting feasibility calculations on the proposed project and calculating the public sector comparator (PSC), which is a decisive factor. The PSC shows how much the proposed project would cost if it were financed purely from the state budget (or the budget of the local government concerned). The PSC should then be compared with the proposed budget of the PPP version of the project. The rest of the procedure is run in accordance with the Act on Public Procurements. Most PPP procurements are announced as negotiated procedures with a pre-qualification phase (ie ‘negotiated procedures with a published invitation to participate’ under the Act on Public Procurement). It is also RuralE.Evolution - IEE/07/579/SI2.499063 Page 45 of 64 D2.3 Guidelines for PPP application common for the tenderer to publish a preliminary summary on the potential project a few months before publication of the actual call for tender. Thereafter, the submission period for pre-qualification is usually around the legal minimum of 37 days and the tenderer evaluates the prequalification bids within a month. The negotiation period ranges from three to nine months, typically in two rounds. The fees payable for the detailed tender documents are usually less than €1,000. Other costs (without advisory fees) may amount to a few thousand euros. It is also common for bidders to be required to provide approximately €4,000-€20,000 as a bid bond to enter into the negotiation phase. These costs are regarded as an investment by the bidders and are not reimbursed by the tenderer. The procurement procedure is fairly transparent and each party has the right to file a remedy application with the Public Procurement Arbitration Committee (Közbeszerzési Döntőbizottság) and with the courts. Competition and market access Competition is primarily ensured by the compulsory application of open and transparent tendering procedures and the applicable laws expressly declare and acknowledge the principles of equal treatment and fair competition. The Hungarian PPP market is open to foreign bidders irrespective of whether international expertise is important. Although foreign bidders have been successful in sizeable projects, only Hungarian bidders have been successful in smaller projects such as those launched under the central initiatives co-ordinated by the Ministry of Education (Magyar Universitas Program) and the National Sports Office (Sport XXI). This may reflect a lack of interest in smaller projects by foreign investors, who have shown a lot of interest in major projects (eg the construction and operation of the M5 and M6 motorways, as well as the Electronic Road Toll Collection System). RuralE.Evolution - IEE/07/579/SI2.499063 Page 46 of 64 D2.3 Guidelines for PPP application 7 PPP process within RuraE-Evolution project 7.1 Preparation and signature Understanding (MoU) of the Memorandum of An ultimate objective of the project (representing at the same time a measurable prove of the soundness of PPP scheme for Agro-energy Districts) is the signature of five Memoranda of Understanding between Public Authorities, agricultural entrepreneurs (or their consortia), and eventual further financial players, in the five RuralE.Evolution target areas, expressing the intention to implement a PPP Agro-energy district in the near future. The methodology described in this guide will be applied in order to commit the local actors to become partners of the future PPP. Once a preferred partner is chosen, the two parties enter into negotiations. The scope of the negotiations is defined and both partners select a negotiating team. Once a draft contract has been prepared and the parties have come to an agreement, a memorandum of understanding is prepared and the formal process of ratifying the contract begins. Negotiations are concluded when Council or the Board and duly authorized representatives of the private partner authorize the contract. Once the contract is negotiated, the local government debriefs the other proponents. The long-term success of a new infrastructure project is dependent on the correct identification of both the benefits and the risks associated with it. Correct identification must be followed by appropriate allocation of these benefits and risks – the latter to the party best able to minimise or control them at realistic cost. The project sponsors and the SPV (Special Purpose Vehicle or Consortium) should, in conjunction with the SPV’s lawyers, analyze the risks arising under the project, identify each project contract to be put in place, and which party is to take these risks and ensure that the appropriate provisions appear in the relevant contracts to achieve this. The lenders and their advisers will need to satisfy themselves that this has been achieved under the contractual structure and other relevant laws, in a way that is consistent with the assumptions underlying the financial plan. Given that a number of parties with different interests will be involved in the project, the final pattern of risk allocation will be made within a contractual framework that reflects the outcome of negotiations and commercial compromise, and one that also takes into account the relevant legislative framework. There are several different perspectives to keep in mind in any general discussion of project contracts. These documents will be typically long term commercial agreements and designed to protect the interest of the project sponsors. Secondly, they will allocate the perceived risks associated with the project between the different participants. Finally the resulting allocation will need to be bankable. Each of these considerations will pull the parties to them in somewhat different directions as the documents are structured and negotiated. There is of course no single definition of the term ‘project contracts’. It tends to be used loosely to describe all the documents needed to allow the project to go ahead, other than the financing documents. It represents all of the commercial agreements, licenses, contracts, leases and corporate documents that underpin the project that is being financed. A typical list might include the following: a concession agreement or government license; a consortium (or other collaboration) agreement between the sponsors; RuralE.Evolution - IEE/07/579/SI2.499063 Page 47 of 64 D2.3 Guidelines for PPP application a shareholders or other joint venture agreement; corporate documents for the consortium and other project companies; management contract for the consortium; a construction contract (or engineering, procurement and construction contract (EPC); contractors sub-contracts, equipment supply agreements and warranties; security for the construction contractor’s ad, depending on the responsibility assumed by the construction contractor, the equipment supplier’s, performance; an operation and maintenance agreement of technical services agreement; an off-take agreement for the purchase of the completed facility’s product; a site lease or other document of entitlement to land; possibly specific enabling legislation; ancillary government permits and planning consents; agreement with local utilities; project insurance and related documents; technology/operating licences; It should be noted that not all the rights required by the consortium will be acquired by contract. Some rights might arise as a matter of general laws, while in other cases the rights to be granted as a part of a concession may result from the holding of a competitive tender. 7.2 Creation of the PPP and start up of the company Following the Memoranda of Understanding, the partners will be able to initiate the preparation activities based on the guidelines produced in this deliverable. A company will more likely be established to supervise the construction of the agro-energy plant and take up all the legal and financial responsibilities of the consortium. Its target area of the Rural_Evolution project aims to establish a different agro-energy district, so the results will only be available after the end of the project. One of the major challenges is that using the PPP approach imposes many more demands on public partner that are not works departments. In the traditional procurement of a building or a facility, a works department takes responsibility for conducting or overseeing the design and construction before handing it over to the client department upon commissioning. As a result most client departments do not possess the necessary contract management skills. It is unreasonable to expect non-work departments staff to develop rapidly the necessary contract/project management skills to manage large, complex, high value projects. It is more sensible, practical and cost-effective to employ someone who already has those skills. This will often involve engaging non-civil servants. Client departments should, as far as possible, structure their contracts in terms of capacity and technical standards on the basis of foreseeable, stable expectations. Ideally, changes should be avoided after finalization of the contract. However, in the case of lengthy contracts changes in services involving both construction and operational changes are almost inevitable. The contract needs to address these issues. Measures could include: - taking account of deflation/inflation and other price-related variables ensuring the service charges the public partner has agreed to pay in future years will not be in excess of future market prices for such services; - break clauses after a period of time, - renegotiation clauses; - periodic review mechanisms; RuralE.Evolution - IEE/07/579/SI2.499063 Page 48 of 64 D2.3 Guidelines for PPP application referrals to mediation, arbitration, etc. In particular, the contract should show whether the department or the consortium assumes the risk of certain classes of change. For example, general changes in economic conditions, costs of work and materials, as well as taxation and changes in general law may be met by the consortium; whereas discriminatory specific legislation affecting the project may be met by the department. However, consideration should be given to managing situations where such changes fall outside of normal bounds such that the consortium does not suffer unsustainable losses or enjoys unconscionable profits. Due to the uncertainties of inflation rates and the quantum of operating costs over a long term contract, the department will need to consider carefully the manner by which service charges are to be varied in certain specified circumstances. It would be unusual for prices to be fixed for the lengthy periods for which PPP projects are typically let. The public partner should therefore only permit appropriate indexation mechanisms to be incorporated when service charges are to be reviewed. For example, choosing an index that may be short lived, or is not independently produced, is not a sensible approach. Nor is it prudent to have too narrow a focus on a particular industry or sector. There will, of course, be many other issues to consider in this context, including the circumstances where the particular index specified in the contract is no longer published or the basis upon which it is calculated is changed. The public partner should ensure that the price it has agreed to pay in future years will not be in excess of future market prices for comparable services. Some form of benchmarking or market testing may be required for this purpose. Benchmarking would typically involve the consortium comparing either its own costs or the costs of its contractor against the market cost of such services. Market testing, on the other hand, might require the consortium to re-tender in the market any relevant contractor’s services to test the value for money of those services. - Agreement between the department and the consortium may be required on: - the amended method of services delivery; - the adjusted price for the services; - whether there are capital payment implications; - changes to the performance measurement system. The contract should contain clear terms and conditions governing the criteria for pricing a variation in the contract; any grounds on which the consortium may refuse to implement a variation; and any remedies available to the client department in the event of such a refusal. The department will specify the outputs that it requires from technical equipment/facilities, and the performance standards to be met, on the basis of known technologies and established standards. These standards will be set for a period for which the department is confident that they will remain valid - for example 10 years. Successive generations of equipment are likely to be developed which produce these outputs and meet these standards more efficiently and at a lower cost. Where the consortium believes that replacing equipment will lead to lower whole life costs, it will do so. It will not replace equipment that is functioning effectively and producing the required outputs where there is no economic justification for doing so - any more than the department would replace equipment in these circumstances. The department may make it a requirement of the contract that it shares in any realized costs savings from technology changes, or savings that might reasonably be expected from upgrades, which could have been implemented but were not. Whether such a provision is appropriate will depend on the likely impact on the contract price and other value for money considerations. RuralE.Evolution - IEE/07/579/SI2.499063 Page 49 of 64 D2.3 Guidelines for PPP application The public partner, rather than the client department, normally enters into an agreement with the contractor. If the client department’s functions are carried on by a different party within the government the contract will continue undisturbed. If the department’s functions are transferred to a quasi or non-government entity it may be necessary for the public partner to underwrite the credit worthiness of the successor entity with respect to the contract. If a function were discontinued altogether, the public partner would be faced with a service that it no longer needed. A break clause could be included in the contract to deal with this eventuality. If this had the effect of passing the risk of the service continuation to the consortium, it would be reflected in the contract price. In order for the contract to obtain financing, any break clause for the benefit of the Government would only be exercisable subject to compensating the consortium appropriately for the loss of the contract. 7.3 Follow-up and construction of the plant PSCom changes its role to monitoring and reporting the progress of the construction works of the project. PSCom should satisfy itself that standards specifications, quality of works and the operation of the facilities meet the minimum standards agreed in the contract PSCom to facilitate commissioning. PSCom to satisfy itself that the facility, where appropriate, is able to satisfy the delivery of contracted performance. Contract Manager takes up the day-to-day monitoring role of the project once it becomes operational. Establish and maintain close and regular contact (e.g. regular liaison meeting) with the consortium to resolve problems before they become serious. Ensure comprehensive records of all interactions are kept properly. RuralE.Evolution - IEE/07/579/SI2.499063 Page 50 of 64 D2.3 Guidelines for PPP application 8 Closing of PPP Dissolving a partnership at the end of the contract term is a legal process. This process is subject to both contract and statutory law. The original PPP contract between the parties should contain provisions to deal with dissolving the partnership. Provisions to this effect may include: • provision for disposal or transfer of assets (in cases where infrastructure or facilities are being transferred to the local government from the private sector partner, assurances of the state of the infrastructure or facilities need to be explicit in the contract); • allocation of net earnings or losses; • repayment of capital; • payment of liabilities. Depending on the complexity of the agreement or the infrastructure or services that it covers, the list of clauses that concern dissolving the partnership may vary considerably. Once a contract has ended and the partnership has been dissolved, the local government may find itself responsible for the provision of a service or infrastructure. The local government should have a plan at the outset of how service will continue to be provided to users. This plan may include: • the local government provides the service or infrastructure for users; • a new PPP arrangement is developed and is “solesourced” to the existing private partner. This strategy will depend largely on a local government’s policies relating to procurement, and inviting proposals for certain projects; • the local government can determine if there are others interested in providing the service or infrastructure after the initial contract is dissolved. RuralE.Evolution - IEE/07/579/SI2.499063 Page 51 of 64 D2.3 Guidelines for PPP application 9. PPP SCHEMES DISTRICT APPLIED TO THE AGRO-ENERGY Dealing with an agroenergy district four main possible directions can be chosen: 1 auto-producing energy; 2 selling heat; 3 selling power; 4 selling heat and power. Besides this other classification of biomass business can be made depending on the property of the biomass plant, or of the biomass itself; this can be: 1) Private property; 2) Public property; 3) Public-Private shared property. From the two above mentioned classifications the following schemes can be traced back: 1) Auto-producing Heat and or Power with public biomass Banks Public Biomass (ex Municipality owned Wood) Autosupply (No Contract) Public Body Municipality) PPA And/or Power (ex Concession Heat Plant Society) (Private Figure 8: Auto-producing Heat and or Power with public biomass Case Description This case presents the reality in which the Public body produces biomasses that uses to autoproduce heat for its own needs. The public biomass can be produced for example from a wood that is in the lands that belong to the Public Body. To reduce the investments and allocate risks the Public Body can choose to make a concession to leave the production and management of the biomass plant to a private society. In this agro-energy district model the PPP contracts are the following: - biomass conversion plant (BOT – Build Operate Transfer -, BOO – Build Own Operate -, BOOT – Build Own Operate Transfer -). Banks can be involved to finance the public body who is investing in a concession of a service (heat) and the private who is investing in a new plant. Referring to the case above the public Body can auto-produce heat and at the same time sell power to the grid to maximise the incomes. In this agro-energy district model the PPP contracts are the following: RuralE.Evolution - IEE/07/579/SI2.499063 Page 52 of 64 D2.3 Guidelines for PPP application - biomass conversion plant (BOT – Build Operate Transfer -, BOO – Build Own Operate -, BOOT – Build Own Operate Transfer -). - PPA (Power Purchase Agreement). This kind of contract links the producer to the public authority that buys the power produced. Example of this contract are attached to D2.2 deliverable. In the “CONTRACT REDACTION” phase, so besides the concession contracts (BOT, BOO and BOOT) there is also the PPA (Power Purchase Agreement) to be considered. Guidelines The steps required to realize this PPP are, as already explained above: PRELIMINARY ACTIONS: - study of the target area characteristics; Biomass assessment; Biomass Harvest cost estimation; Storage cost estimation. - identification of area’s needs; Analysis of public needs in terms of heat; Energy sinks individuation and characterization. - market testing; Individuation of the most favourable technology; Analysis of final costs of energy to the end user depending on the adopted technology. Chose whether produce heat or heat and power. - identification of potential actors; Identification of Banks; Identification of bioenergy plant producers; Identification of operation and maintenance enterprises. - communication campaign to reach stakeholders; Organization of a communication campaign. PPP IMPLEMENTATION: - Set up of the planning team (financing manager, technical manager, etc.); Individuate the chairman; Individuate subgroups; Individuate the Contract Manager. - Selection of suitable partners / Achievement of successful partnerships (banks, public entities, etc.; competence of the Public Entity to implement the project, determine both sectors of interest in PPP); Develop bid documents; Organize the bid conference; Prepare a predetermined scoring matrix. - Development of the business plan; The business model is: “Auto-producing Heat and or Power with public biomass”; Economical and financial issues are: the quantity of debt linked with the project, the costs of supplying biomass for the public, the costs of the plant and operation and maintenance phases; taking into account the incomes it is important to compare different incentivation programs if available, besides the possibility to produce only heat has to be compared with the cogeneration option. RuralE.Evolution - IEE/07/579/SI2.499063 Page 53 of 64 D2.3 Guidelines for PPP application Risk allocation is made reserving plant operation and maintenance phase to a private society; the right time to enter the market will be strongly linked with incentivation policies; definition of the strategic planning; for the definition of legal & contractual framework, it has to be considered the following section. - implementation of a Consensus Building Strategy; - organize stakeholders meeting; - organize local events; - set-up a web site of the project. - selection of a suitable technology/production plan according to local characteristics; - identification of the supply chain; - individuate logistic issues; - individuate production site layout; - define the logistic plan; - check for land availability - institutional structures and capacity building (PPP unit, technical assistance, etc.); - connect to PPP national agencies (ex. Italian UTFP, Technical Unit of Project Finance). CONTRACT REDACTION: In this case it has to be chosen, based on the Municipality needs, the type of contract, between: BOT, BOO and BOOT. These are all concession contracts, in which the diverse term have to be set depending on the different national laws legislations. Some examples are proposed in the attachment. PPP MONITORING: As above mentioned the monitoring process in the early stages will deal with: - oversee the design and construction phases; - monitor the project once it becomes operational; - establish and manage the day to day relationship with the consortium; - keep abrest of developments in the field covered by the project and consider the nee for charge; - manage the agreement of any changes during the life of the contract; - monitor the achievement of key performance indicators; - recommend and calculate payments/abatements; - report regularly to the PSCom (Project Steering Committee); Advantages and disadvantages ADVANTAGES -The public body reduces the total investment; - The public body allocates the risks; - The public body spares in heat costs; - The private has a granted supply of biomass fuel (because it is the owner); - The private has incomes coming from the concession of a public service; - if the private sells electricity to the grid the incomes will be higher and so also the added value of the starting fuel. So part of the incomes will be allocated also on the Public Body. DISADVANTAGES - The property of the plant can be not public (in case of BOO); RuralE.Evolution - IEE/07/579/SI2.499063 Page 54 of 64 D2.3 Guidelines for PPP application - The community can refuse the biomass energy plant if it is not strongly promoted; - The Public Body has to own biomass and grant a continuous supply with its own financial resources; - If the private doesn’t sell electricity the incomes will be lower and so also the allocation to the public body of these. - being not present a Special Purpose Vehicle (SPV) all the management of the Agroenergy district contracts will be on charge of the Public Body. 2) Auto-producing Heat with private biomass and/or selling electricity to the grid Banks Autosupply (No Contract) And/or Power Private Biomass (ex Private Short Rotation Forestry) PPA SPV PublicPrivate shared Heat O & M Contract Concession Public Body Municipality) (ex Ownership? Plant Society) (Private Figure 9: Auto-producing Heat with private biomass and/or selling electricity to the grid Case Description This case presents the Public body (ex. Municipality) that realizes a participated publicprivate Special Purpose Vehicle. Legally the special purpose vehicle is often a Limited Liability Company (LLC) of which some contracts are proposed in attachment. It is the Special Purpose Vehicle that deals with the Private Society that furnishes the plant, the public body that consumes heat and so spares money (ADVANTAGES), the SPV can own and operate the plant or just operate the plant that is owned by the public Body. Anyway the SPV must have contracts that regulate biomass acquisition from farmers and heat contracting with the public Body and land lease and so on. Also the ownership of the plant has to be cleared: is it of the public body or of the special Purpose Vehicle? Besides the private farmers can play a role in the SPV participating of the incomes given by heat contracting or just be suppliers of biomass being paid an agreed price for it. All these aspects have to be cited in the specific contracts. The case in which the Special Purpose Vehicle is involved also in selling electricity to the grid implies that PPA (Power Purchase Agreement) has to be added to the contract framework. As for case number 1 the private farmers can participate to the incomes coming from heat and electricity contracting or just be biomass suppliers and being paid for it. In this agro-energy district model the PPP contracts are the following: RuralE.Evolution - IEE/07/579/SI2.499063 Page 55 of 64 D2.3 Guidelines for PPP application - biomass conversion plant (BOT – Build Operate Transfer -, BOO – Build Own Operate -, BOOT – Build Own Operate Transfer -). This is a contract that will regulate the connections between the Special Purpose Entity (SPE) and the Public Body. - the SPV can also stipulate contracts for fuel (with private farmers) contracts for land and for Operation and Maintenance of the plant and for the property of the same. - PPA (Power Purchase Agreement) in case of power production. Banks are principally related with the SPV that attracts the most of the financing resources. The steps required to realize this PPP have been already explained above. In the “CONTRACT REDACTION” phase besides the concession contracts (BOT, BOO and BOOT) there is also the contract on which the SPV is based and also the fuel contract and land contract and the operation and maintenance contract etc. Guidelines The steps required to realize this PPP are, as already explained above: PRELIMINARY ACTIONS: - study of the target area characteristics; Biomass assessment Biomass cost estimation. - identification of area’s needs; Analysis of public needs in terms of heat; Energy sinks individuation and characterization. - market testing; Individuation of the most favourable technology; Analysis of final costs of energy to the end user depending on the adopted technology; Chose whether produce heat or heat and power. - identification of potential actors; Identification of Banks; Identification of bioenergy plant producers; Identification of operation and maintenance enterprises; Identification of private producers; Identification of Special Purpose Vehicle personal. - communication campaign to reach stakeholders; Organization of a communication campaign. PPP IMPLEMENTATION: - Set up of the planning team (financing manager, technical manager, etc.); Individuate the chairman; Individuate sub-groups (financing section, technical section etc.); Individuate the Contract Manager. - Selection of suitable partners / Achievement of successful partnerships (banks, public entities, etc.; competence of the Public Entity to implement the project, determine both sectors of interest in PPP); Develop bid documents; Organize the bid conference; Prepare a predetermined scoring matrix. - Development of the business plan; the business model is “Auto-producing Heat with private biomass and/or selling electricity to the grid”; RuralE.Evolution - IEE/07/579/SI2.499063 Page 56 of 64 D2.3 Guidelines for PPP application Economical and financial issues are: the quantity of debt linked with the project, the costs of supplying biomass, the costs of the plant and operation and maintenance phases; taking into account the incomes it is important to compare different incentivation programs if available, besides the possibility to produce only heat has to be compared with the cogeneration option; Risk allocation for the public is made committing plant operation and maintenance phase to a private society and creating a Special Purpose Vehicle to manage all the agro-energy district so joining all the public-private interests involved; The right time to enter the market is strongly linked with incentivation policies; definition of the strategic planning; for the definition of legal & contractual framework, it has to be considered the following section. - implementation of a Consensus Building Strategy; organize stakeholders meetings; organize local events; set-up a site of the project. - selection of a suitable technology/production plan according to local characteristics; identification of the supply chain; individuate logistic issues; individuate production site layout; define the logistic plan; check for land availability - institutional structures and capacity building (PPP unit, technical assistance, etc.); connect to PPP national agencies (ex. Italian UTFP, Technical Unit of Project Finance). CONTRACT REDACTION: The contract framework in this case is all referred to the Special Purpose Vehicle (SPV) that in this case is the reference point for all the financial, technical and economical activities of the agroenergy district. In this case it has to be chosen, based on the Municipality needs, the type of contract, between: BOT, BOO and BOOT. These are all concession contracts, in which the diverse term have to be set depending of the different national laws legislations. Some examples are proposed in the attachment. If it is sold also electricity to the grid a PPA (Power Purchase Agreement) has to be used. PPP MONITORING: As above mentioned the monitoring process in the early stages will deal with: - oversee the design and construction phases; - monitor the project once it becomes operational; - establish and manage the day to day relationship with the consortium; - keep abrest of developments in the field covered by the project and consider the nee for charge; - manage the agreement of any changes during the life of the contract; - monitor the achievement of key performance indicators; - recommend and calculate payments/abatements; - report regularly to the PSCom (Project Steering Committee); RuralE.Evolution - IEE/07/579/SI2.499063 Page 57 of 64 D2.3 Guidelines for PPP application Advantages and disadvantages ADVANTAGES - the public body reduces the total investment; - the public body allocates the risks; - the public body spares in heat costs. - in this case the Special Purpose vehicle created works as an attractor and reference point for investments in the agroenergy district; - the SPV will distribute incomes among its members (ex. Public Body, Privat biomass producers etc.); - the SPV will be not charged of technical management of the biomass plant, that will be done through an Operation and Maintenance contract with a private society. DISADVANTAGES - the SPV has to join the different public and private interests into one compact Body; there could be problems due to the lack of balance between them; - the SPV has to be adequately composed and able to cover technical, economical and management problems; - if the private biomass suppliers are not inserted in the SPV the biomass supply can be a very difficult aspect. 3) Selling heat to privates and possibly selling power to the grid Banks Fuel Contract Private Biomass (ex Private Short Rotation Forestry) Power SPV PublicPrivate shared Heat, Private buyers O & M Contract Incomes Ownership? Public Body Municipality) (ex Plant Society) (Private Figure 10: Selling heat to privates and possibly selling power to the grid Case Description In this case the Special Purpose Vehicle (SPV) buys biomass from private parties, contracts with the public for Land Lease for example, contracts with private for plant acquisition and operation and maintenance and contracts with private buyers for heat selling. This means that the public advantages are the heat contracting incomes, while in this case the private partners spare money. The private farmers that supply biomass can participate to incomes given by heat contracting or agree on a fixed price for the biomass making a fuel supply contract with the Special Purpose Vehicle (SPV). RuralE.Evolution - IEE/07/579/SI2.499063 Page 58 of 64 D2.3 Guidelines for PPP application The case in which the SPV sell electricity to the grid is similar to the previous but it adds the Power Purchase Agreement (PPA) to the contract framework. Guidelines The steps required to realize this PPP are, as already explained above: PRELIMINARY ACTIONS: - Study of the target area characteristics; Biomass assessment; Biomass harvest cost estimation; Storage cots estimation. - Identification of area’s needs; Analysis of public needs in terms of heat; Energy sinks individuation and characterization. - Market testing; Individuation of the most favourable technology; Analysis of final costs of energy to the end user depending on the adopted technology; Chose whether produce heat or heat and power. - Identification of potential actors; Identification of Banks; Identification of bioenergy plant producers; Identification of operation and maintenance enterprises; Identification of private producers; Identification of private heat consumers. Identification of Special Purpose Vehicle personal; - Communication campaign to reach stakeholders; Organization of a communication campaign. PPP IMPLEMENTATION: - Set up of the planning team (financing manager, technical manager, etc.); Individuate the chairman; Individuate sub-groups (financing section, technical section etc.); Individuate the Contract Manager. - Selection of suitable partners / Achievement of successful partnerships (banks, public entities, etc.; competence of the Public Entity to implement the project, determine both sectors of interest in PPP); Develop bid documents; Organize the bid conference; Prepare a predetermined scoring matrix. - Development of the business plan; The business model is “Selling heat to privates and possibly selling power to the grid”; Economical and financial issues are: the quantity of debt linked with the project, the costs of supplying biomass, the costs of the plant and operation and maintenance phases; taking into account the incomes it is important to compare different incentivation programs if available, besides the possibility to produce only heat has to be compared with the cogeneration option. It has to be evaluated RuralE.Evolution - IEE/07/579/SI2.499063 Page 59 of 64 D2.3 Guidelines for PPP application also the economical convenience to sell heat to private instead of sparing from renewable heat consumption for the Public Body. Risk allocation for the public is made committing plant operation and maintenance phase to a private society and creating a Special Purpose Vehicle to manage all the agro-energy district so joining all the public-private interests involved; The right time to enter the market is strongly linked with incentivation policies; Definition of the strategic planning; For the definition of legal & contractual framework, it has to be considered the following section. - implementation of a Consensus Building Strategy; organize stakeholders meetings; organize local events; set-up a site of the project. - selection of a suitable technology/production plan according to local characteristics; identification of the supply chain; individuate logistic issues; individuate production site layout; define the logistic plan; check for land availability - institutional structures and capacity building (PPP unit, technical assistance, etc.); connect to PPP national agencies (ex. Italian UTFP, Technical Unit of Project Finance). CONTRACT REDACTION: The contract framework in this case is all referred to the Special Purpose Vehicle (SPV) that in this case is the reference point for all the financial, technical and economical activities of the agroenergy district. The SPV will be responsible of the management of: O & M Contracts, Fuel Contracts, Plant Ownership contract, Heat contract etc. If it is sold also electricity to the grid a PPA has to be used. Also the contract for heat with private consumers has to be implemented. PPP MONITORING: As above mentioned the monitoring process in the early stages will deal with: - oversee the design and construction phases; - monitor the project once it becomes operational; - establish and manage the day to day relationship with the consortium; - keep abrest of developments in the field covered by the project and consider the nee for charge; - manage the agreement of any changes during the life of the contract; - monitor the achievement of key performance indicators; - recommend and calculate payments/abatements; - report regularly to the PSCom (Project Steering Committee); Advantages and disadvantages ADVANTAGES - the public body earns money by the property of a biomass plant that sells energy to private users; RuralE.Evolution - IEE/07/579/SI2.499063 Page 60 of 64 D2.3 Guidelines for PPP application - the public body allocates the risks given by the Operation and Maintenance costs, making a concession of Build and Operate to a private society; - in this case the Special Purpose vehicle created works as an attractor and reference point for investments in the agroenergy district; - the SPV will distribute incomes among its members (ex. Public Body, Private biomass producers etc.); - the SPV will be charged of technical management of the biomass plant so it will furnish the adequate know how, and contract management; - the SPV will work as an intermediate between public Body and private heat consumers. DISADVANTAGES - the SPV has to join the different public and private interests into one compact Body; there could be problems due to the lack of balance between them; - the SPV has to be adequately composed and able to cover technical, economical and management problems; - if the private biomass suppliers are not inserted in the SPV the biomass supply can be a very difficult aspect. 4) Private plant selling power to the public Private Biomass (ex Private Short Rotation Forestry) Power sold to the public PRIVATE PLANT Case Description This is a typical case of Power Purchase Agreement. In the field of renewable energies the public wants to increase the REN production, so it has to promote it with favourable contracts with the private plants. Guidelines The steps required to realize this PPP are, as already explained above: PRELIMINARY ACTIONS: - Study of the target area characteristics; Biomass assessment; Biomass harvest cost estimation; Storage cots estimation. - Identification of area’s needs; Analysis of public needs in terms of heat; Energy sinks individuation and characterization. - Market testing; RuralE.Evolution - IEE/07/579/SI2.499063 Page 61 of 64 D2.3 Guidelines for PPP application Individuation of the most favourable technology; Analysis of final costs of energy to the end user depending on the adopted technology; Chose whether produce heat or heat and power. - Identification of potential actors; Identification of bioenergy plant producer; Identification of biomass suppliers. - communication campaign to reach stakeholders; Organization of a communication campaign. PPP IMPLEMENTATION: - Set up of the planning team (financing manager, technical manager, etc.); Individuate the chairman; Individuate sub-groups (financing section, technical section etc.); Individuate the Contract Manager. - Selection of suitable partners / Achievement of successful partnerships (banks, public entities, etc.; competence of the Public Entity to implement the project, determine both sectors of interest in PPP); Develop bid documents; Organize the bid conference; Prepare a predetermined scoring matrix. - Development of the business plan; the business model is “Private plant selling power to the public”; definition of economic and financial issues (namely the feasibility, bankability and value for money of the project); Economical and financial issues are: the quantity of debt linked with the project, the costs of supplying biomass, the costs of the plant and operation and maintenance phases; taking into account the incomes it is important to compare different incentivation programs if available. Besides the possibility to produce only power has to be compared with the cogeneration option. Risk allocation: there is no risk for the public; The right time to enter the market is strongly linked with incentivation policies; Definition of the strategic planning; For the definition of legal & contractual framework, it has to be considered the following section. - implementation of a Consensus Building Strategy; organize stakeholders meetings; organize local events; set-up a site of the project. - selection of a suitable technology/production plan according to local characteristics; identification of the supply chain; individuate logistic issues; individuate production site layout; define the logistic plan; check for land availability - institutional structures and capacity building (PPP unit, technical assistance, etc.); RuralE.Evolution - IEE/07/579/SI2.499063 Page 62 of 64 D2.3 Guidelines for PPP application connect to PPP national agencies (ex. Italian UTFP, Technical Unit of Project Finance). CONTRACT REDACTION: In this case the most important contract is the PPA (Power Purchase Agreement). PPP MONITORING: As above mentioned the monitoring process in the early stages will deal with: - oversee the design and construction phases; - monitor the project once it becomes operational; - establish and manage the day to day relationship with the consortium; - keep abrest of developments in the field covered by the project and consider the nee for charge; - manage the agreement of any changes during the life of the contract; - monitor the achievement of key performance indicators; - recommend and calculate payments/abatements; - report regularly to the PSCom (Project Steering Committee); Advantages and disadvantages ADVANTAGES - There is no risk for the public; - the public authority buys renewable energy and accomplishes to its objectives; - the private partner sells electricity and obtains an income for it; - the private farmers have a granted income for the duration of the project and they diversify their activity becoming involved in energy production instead of conventional food commodities production. DISADVANTAGES - the plant doesn’t sell heat to the Municipality to maximize its electricity generating efficiency; RuralE.Evolution - IEE/07/579/SI2.499063 Page 63 of 64 D2.3 Guidelines for PPP application 9 References [1] Public-Private Partnership Handbook, Asian Development Bank; [2]: Serving the Community By Using the Private Sector, AN INTRODUCTORY GUIDE TO PUBLIC PRIVATE PARTNERSHIPS (PPPS), March 2008 (Second Edition) [3] P. McKendry, Energy production from biomass (part 2): conversion technologies, Bioresource Technology 83 (2002) 47–54; [4] Small-Scale Bioenergy Initiatives, FAO Final report, January 2009, Prepared by PISCES and FAO by Practical Action Consulting; [5] E. R. Yescombe, Public Private Partnerships Principles of Policy and Finance, Elsevier, ISBN 978-0-7506-8054-7; [6] G. Ferrante, Project Finance e Partenariato Pubblico Privato, FORUM RINNOVABILI 2008 Lo sviluppo delle fonti rinnovabili nella nuova politica energetica del Sistema Paese, Roma, 18 Giugno 2008; RuralE.Evolution - IEE/07/579/SI2.499063 Page 64 of 64 D2.3 Guidelines for PPP application