48260 EPM Project Plan and Abstract 2 Group 32 Ahmad Rabie Ahmad Suleiman Andrew Guanzon Oliver De Paz Cecilia Saldivar Phillip Do Safwan Mabud 10828871 10828921 10638486 10574616 11140201 10607442 10800670 Date of submission: 26/05/2011 Due Date: 26/05/2011 Word Count: 5700 0|Page Andrew Guanzon & Co. 26 Harris Street University of technology, Sydney, Building 4, level 3, Room 27 0421876299 Group32@uts.edu.au The Chief Executive Officer 24 May, 2011 HiPowa Conference Organisers 15 Broadway Street Ultimo, 2007 Dear Sir, Please consider our group qualifications as summarized below, for the Project Manager position with your organisation. As a group of consultants, we believe that the experience we have gained over the past 3 years of working together as a team on many projects and the knowledge we received as an engineering project management students in the University of Technology, Sydney would benefit your organisation. As a group of project management consultants, our group has completed many projects in the areas of project management processes and documentation. Our group is motivated, well organised and able to achieve any task within the required quality and time constraints given. Our Progress and Status Report documents of the project will keep us on top of the project and would give us the strength during any audit with another Group's Project Management process. Our group has also acquired considerable knowledge and experience from the following: Successfully interviewed Mr. Clarke, a project manager in Crown Projects Company 1|Page A range of practical skills such as surveying, circuit analysis, concrete/materials design, etc if services are ever required Our qualifications also include: Our group is consisted of undergraduate engineering students ( Mechanical, Civil, ICT, and Electrical) at the University of Technology, Sydney Professional users of computer Softwares such as Microsoft office (Excel, Word and Power Point), MSProject 2007. Various forms of training qualifications such as WorkCover construction induction training, traffic control training and International computer driving licence In addition, we as individuals from this group have been recognised for our hard working, intelligent and industrious approach to any task we have been given. This has been evident from our previous employment experiences in engineering, whether in civil, mechanical, ICT and electrical engineering. In all work related situations, we always aim to utilise our accumulated experience and knowledge to our maximum possible potential in order to prove as an asset for any company we liaise with. We would greatly appreciate an opportunity work with your organisation and look forward to hearing from you soon. Yours faithfully, Andrew Guanzon & Co. 2|Page Contents Abstract .............................................................................................................................................................. 4 Project Scope Statement.............................................................................................................................. 5 Project objective ............................................................................................................................................. 5 Deliverables ................................................................................................................................................. 6 Summarised Major Milestones: ........................................................................................................... 6 Milestones due: .......................................................................................................................................... 7 Technical requirements .......................................................................................................................... 7 Limits and exclusions .............................................................................................................................. 7 Work Breakdown Structure: ..................................................................................................................... 8 Responsibility matrix (Actual Vs Planned): ....................................................................................... 13 Information on monitoring and control .............................................................................................. 16 Creation of a detailed schedule .......................................................................................................... 16 Monitoring progress .............................................................................................................................. 16 Comparison between the planned against actual ....................................................................... 16 Implementation of corrective actions ............................................................................................. 17 RISK MANAGEMENT................................................................................................................................... 18 QUALITY ASSESSMENT ........................................................................................................................ 23 Appendix A: .................................................................................................................................................... 25 Group Charter ........................................................................................................................................... 26 Meeting times: ..................................................................................................................................... 26 Meeting locations: .............................................................................................................................. 26 Forms of communication: ............................................................................................................... 26 Poor contribution to team work: .................................................................................................. 27 Decision making process: ................................................................................................................ 27 Submission of group work to Turnitin:...................................................................................... 28 Appendix B: .................................................................................................................................................... 29 References ...................................................................................................................................................... 28 Belbin Team Roles Results .................................................................................................................. 38 Appendix C: Scheduling Details (Network Diagram & Gantt Chart) ........................................ 39 3|Page Abstract Group 32 has chosen to contact and interview the general manager of Crown Projects, Jeffrey Clarke for this project. Jeffrey has degree in Bachelor of building from University of New South Wales, which he acquired in 1987. Crown Projects has over 40 employees based in Sydney. Crown also has an office in Brisbane where the company manages projects in areas around Queensland. Jeffrey can be contacted from the following details: A. Level 15, 3 Spring St, Sydney T. (02) 9252 4420 E. jeffrey.clarke@crownprojects.com.au The team has decided to use topic two, “Failed Projects and how to avoid them” to discuss with Jeffrey at the interview. 4|Page Project Scope Statement Project Name: Group Project Prepared by: Group 32 Date (DD/MM/YYYY): 07/04/2011 Version History (insert rows as needed): Version Date (MM/DD/YYYY) Comments 1.0 07/04/2011 Plan and Abstract 1 / 2 2.0 24/05/2011 Plan and Abstract 2 / 2 Project objective Group 32 aims to determine the needs for a seminar regarding the topic of choice “Failed projects and how to avoid them”. This team aims to achieve this goal by producing a formal report concerning the above mentioned topic. The report will consist of several main documents such as progress reports, status reports, a plan and an abstract. Group 32 will also present its findings to the CEO of HiPowa to convey their competency in this task. Information will be found from online and University library journals. Additionally, information obtained from an interview with an experienced project manager will also be utilised as a reference for the report. Group 32 aims to complete this task by week 13, 23rd May, 2011. 5|Page Deliverables Progress and Status reports (3 Parts) Plan and Abstract (2 Parts) Report Presentation Audit and presentation Reflection Summarised Major Milestones: Group formed Group chose topic 2 “Failed Projects and how to avoid them” Chose Jeffrey Clarke from Crown Projects to be our interviewee Confirmed date, time and location to interview Jeffrey Clarke Delegated work between group members for the first Progress and Status reports Progress report (Andrew, Suleiman, Ahmad) Status report (Phillip, Cecilia, Safwan) Gantt chart (Oliver) Prepare questions for the interview and sent a copy to Jeffrey Clarke Group interviewed Jeffrey Clarke at Crown Projects Delegate work between group members for the first Plan and Abstract report Abstract, Covering Letter and Group charter (Andrew, Ahmad) 6|Page Scope Statement, Work breakdown Structure, Responsibility Matrix (Cecilia, Suleiman) Diagrams, Scheduling details (Oliver) Budget details, Information on monitoring and control, Risk and quality(Phillip, Safwan) *A detailed layout of the milestone of this project is provided in the work breakdown structure. Milestones due: Plan and Abstract report (2) 26/5/11 Submit Report and Turnitin 26/5/11 Progress and Status report (3) 26/5/11 Audit report 2/6/11 Oral Presentation 9/6/11 Technical requirements Computers/laptops Computer software: Microsoft Word, Excel, Project, PowerPoint, etc Mobile phones Internet: Emails, electronic journals Limits and exclusions Limits: Other commitments to university subjects (classes, exams, assessments). Work. Exclusions: Only team leader to submit each group assessment to turnitin. 7|Page Training session for Microsoft Project provided, but will not include tutorials on how to produce every task. Do not give handouts at presentation. Work Breakdown Structure: 1. Start 1.1 Form Group 1.1.1 Contact details 1.1.1.1 Send contact details to group members 1.1.2 Define responsibilities and penalties 1.1.3 Elect manager & secretary 1.2 Meetings 1.2.1 Weekly meeting 1.2.1.1 Deliver weekly meeting minutes 1.2.1.2 Send meeting minutes to group members 1.2.2 Discuss deliverables 1.2.3 Allocate tasks 1.3 Interview 1.3.1 Find manager 1.3.2 Organise date & time 1.3.3 Develop questions 1.3.3.1 Send questions to Jeffrey Clarke 1.3.4 Interview Mr. Clarke 1.3.4.1 Record interview 1.3.4.2 Review interview 1.3.4.3 Summarise interview 1.3.5 Send to group members 1.4 Progress & Status Reports 1.4.1 Research on progress report 8|Page 1.4.2 Research on status report 1.4.3 Use Microsoft Project 1.4.3.1 Produce Gantt chart 1.4.3.2 Produce network diagram 1.4.4 Compile progress & status report 1.4.5 Review Progress & status report 1.4.6 Print Progress & status report 1.4.7 Submission 1.4.7.1 Submit hard copy 1.4.7.2 Submit to Turnitin 1.4.8 Send to group members 1.5 Plan & Abstract 1.5.1 Plan 1.5.1.1 Scope statement 1.5.1.2 Work breakdown structure 1.5.1.3 Responsibility matrix 1.5.1.4 Scheduling details 1.5.1.4.1 Gantt chart 1.5.1.4.2 Network diagram 1.5.1.5 Budget details “Estimation” 1.5.1.6 Risks 1.5.1.6.1 Identify risks 1.5.1.6.2 Risk analysis 1.5.1.6.3 Comments 1.5.1.7 Quality check 1.5.1.7.1 Comments on Quality 1.5.1.8 Information on monitoring 1.5.1.9 Information on control 1.5.1.10 Final draft 1.5.2 Abstract 1.5.2.1 Topic chosen 9|Page 1.5.2.2 Information about Jeffery Clarke 1.5.2.3 Information about Crown Projects 1.5.2.4 Produce draft 1.5.2.4.1 Send abstract to Jeffery Clarke for approval 1.5.2.5 Final draft 1.5.3 Produce cover letter 1.5.4 Produce final document 1.5.4 Compile abstract and plan 1.5.4.2 Review document 1.5.4.3 Print document 1.5.4.4 Bind document 1.5.4.5 Submission 1.5.4.5.1 Submit to lecturer 1.5.4.5.2 Submit to Turnitin 1.5.5 Send to group members 1.6 Report 1.6.1 Review and discuss interview 1.6.1.1 Make a summary 1.6.1.2 Extract main ideas from interview 1.6.2 Individual research on chosen topic 1.6.3 Introduction 1.6.3.1 Organisation 1.6.3.2 Core business 1.6.3.3 Organisation structure 1.6.3.3.1 Advantages 1.6.3.3.2 Disadvantages 1.6.4 Tools and techniques 1.6.5 Failed projects definition and how to avoid them 1.6.6 Monitoring young project manager, three areas to avoid project failure 1.6.7 Identify cost, risk, quality and time 1.6.8 Write report 10 | P a g e 1.6.9 Finalising report 1.6.9.1 All members to check the final document 1.6.9.2 Print final report 1.6.9.3 Bind report 1.6.9.4 Submit to Turnitin 1.6.9.5 Submit hard copy to lecturer 1.7 Oral Presentation 1.7.1 Summery of main points (interview & report) 1.7.2 Divide up section for each member 1.7.3 Produce power point slides 1.7.4 Review work 1.7.4.1 Make any changes 1.7.5 Practice 1.7.5.1 Individual 1.7.5.1.1 Check duration 1.7.5.2.2 Relevance information 1.7.5.2 Group practice 1.7.5.2.1 Check duration 1.7.5.2.2 Relevance information 1.7.6 Prepare for questions 1.8 Audit Report & Presentation 1.8.1 Reviewing progress & status report 1.8.2 Reviewing plan & abstract 1.8.3 Find another groups’ assignment 1.8.3.1 Check their effectiveness 1.8.3 Prepare short audit report 1.8.3.1 Print two copies 1.8.4 Prepare short audit presentation 1.8.5 Presentation rehearsal 1.8.6 Submit report 11 | P a g e 1.9 SPARK 1.9.1 Give feedback 1.10 Reflection 1.10.1 Individual reflection on learning experience 1.10.2 Identify any problems 1.10.3 Discuss during class 1.10.4 Give feedback 12 | P a g e Responsibility matrix (Actual Vs Planned): Task Primary P Secondary S Highlighted Actuals Red letter Added to Actual Ahmad Suleiman Andrew Phillip Cecilia Oliver Safwan Form Group P P P P P P P Attend meetings P P P P P P P Send meetings minutes P Interview Find manager P Organise date & time S Develop questions P Interview Mr Clarke S P S S S S Review and summarise key points S S S S S P S P S Progress & Status Reports Research on progress report S S P Research on status report S P Use Microsoft Project S S Compile progress & status report S P Review S Print and submit Progress & status report S S S S P P P S S S S S P Cover Letter Write a cover letter P S Abstract 13 | P a g e Topic chosen S S P S information about organisation information about manager Produce draft P S S S S P P S S P S S P P S S Plan Scope statement S Work breakdown Structure S P Responsibility matrix P S S S Scheduling details P Budget details P Risks S P S S Quality check S Information on Monitoring P Information on control P Produce draft S S Compile plan & abstract P S Review final document S S Bind document P Submit P P S P P S S S S S Plan & Abstract Send to group members S P P S S S S S S S P P P S S P P P S S S P Report Extracting the main points of interview S P Summarising interview S S Research on chosen topic S S S S Compile parts P S P S check the final document S S S S Print final report Bind report P S P P P P 14 | P a g e Submit to Turnitin P submit to lecturer P P Oral Presentation Summery of main points S Divide up section for each member S S P P Produce power point slides P Review work S S S S S S S Group Practice S S S S S S S Present to class P P P P P P P Audit Report & Presentation Reviewing progress & status report Reviewing plan & abstract S S S P Find other groups’ assignment P S P Check other groups’ effectiveness S Prepare short audit report S P P Present to class P P Print and submit report P P SPARK P Reflection P S S P P P P P P P P P P P P P P P P P 15 | P a g e Information on monitoring and control Monitoring and Controlling processes play a critical role as part of a project’s management plan, as these processes ensure that performance is carried out according to a pre-defined schedule and that objectives set has been achieved. These mechanisms allow the project manager or project team leader to monitor and control the processes required to finish the project as well as maintaining a professional and an effective quality of work throughout the project. By monitoring the project, the team leader is able to thoroughly collect information about the performance and progress data of the project and compare it to a specific and pre-defined schedule. If in any particular reason that the project has not followed schedule, then the controlling process is able to create and implement corrective actions deem necessary for the project to finish on time, within cost and a quality standard of work. The project can be broken down into four steps in terms of control: Creation of a detailed schedule The detailed schedule was based off a work breakdown structure (WBS). The WBS breaks down the entire project into its different components and within them are smaller work packages which are allocated to various team members. Monitoring progress Creating a Gantt chart measures time by setting out a start and finish time allocation for different work packages while a budget plan was created for cost in terms of approximate student hours spent for completing each work package. Another monitoring tool used in this project is through the use of weekly group meetings as well as e-mails, used to track progress and encourage staying on track of time. Comparison between the planned against actual Monitoring of the work packages allows the team leader to measure performance and progress, and is then able to compare between the planned and actual 16 | P a g e performance for any discrepancies in time allocation as well as level of quality of work input. By comparing the planned and actual performances, progress and status reports can be made on a weekly basis where they are documented and integrated into the weekly meeting minutes during the group meeting sessions. Implementation of corrective actions More than often, milestones and work packages will not finished by a certain deadline due to unforeseen circumstances. To account for variances in time, the planned budget of allocated time must allow for these variances and hence add them to the total budget as a precaution. Miscommunication between members is another big factor that can put the project behind schedule, so the appropriate corrective action to counter this is to allocate extra human resources to finish off the task. 17 | P a g e RISK MANAGEMENT Risks can be often fatal to the success of a project. Very early in the preparation and planning stage, it was essential that potential risks were identified, categorized and evaluated. We drew up a list of categories and then identified potential risks within each category, by which common influences, factors, causes, potential impacts and potential preventative and or corrective actions were discussed and agreed on. We realized that setting a risk tolerance level is a dangerous business. So, each potential risks were carefully analysed. The project team, supporting teams and individuals, and the organization(s) involved in managing the project were evaluated to determine whether there is the capability to manage the risk successfully, should it arise. The gaps in the capability identified were corrected by proper actions taken. Conflict over resources often arise during the middle to later stages of a project, because, often unexpected other, newer demands arise which are seen as being of higher priority. This can lead to resources that were originally allocated to the project being taken away, or reduced in quantity or quality, almost certainly to the detriment of the project. To avoid this, our team included "conflict over resources during the life of the project" as a major potential risk and planned for it accordingly by securing agreements and then monitoring the situation continuously. So that, if a dispute arises, there is a role here for the project champion and or the client to ensure that the allocated resources are not taken away. Failed projects show that project managers in such projects were frequently unaware of the big hammer that was about to hit them. The frightening finding was that frequently someone of the project organization actually did see that hammer, but didn't inform the project manager of its existence. A good approach is to consistently include risk communication in the tasks we carry out. Whenever we had a team meeting, we made project risks part of the default agenda (and not the final item on the list!). This showed that risks are important to the project manager and gave the team members a "natural moment" to discuss them and report new ones. 18 | P a g e We realized that implementing risk response would essentially add value to our project. By using execution as the key here, we made sure to prevent threat occurring and minimized the negative effects. We basically dealt with the threats using the three options: Risk avoidance (organizing our project in a way that we don’t encounter risk anymore) Risk minimization (by decreasing the negative effects) and Risk acceptance (if its effect on the project are minimal, it’s a conscious choice to accept a certain risk). 1. List of risk events 1. Dropping the subject. 2. The absence of any group member due to any external circumstances. 3. Team member not completing their work on time. 4. Lack of communication between team members. 5. Technical problems such as, printer, internet, file corruption and USB failure. 6. Poor understanding of the task by team members. 7. Unavailability of the project manager on interview day. 8. Irrelevant information included in the report. 9. Missing information from interview. 10. UTS Online website is not working. 11. Plagiarism. 12. Work not submitted on time. 13. The final work is not reviewed. 14. Unclear scope of work. 15. Certain tasks assigned to inappropriate member. 16. Poor quality deliverables. 19 | P a g e 2. Risk assessment Risk Likelihood Impact Detection difficulty Risk When event (1-5) (1-5) (1-5) value 1 1 3 4 12 Length of project 2 4 3 4 48 Meetings 3 3 4 2 24 Compiling document 4 3 4 4 48 Throughout the project 5 1 4 1 4 printing or Submitting documents 6 2 4 3 24 Meetings 7 2 4 2 16 Organising interview 8 2 3 3 18 Checking and reviewing draft 9 2 4 4 32 Reviewing information recorded from interview 10 1 4 1 4 Trying to log in 11 3 4 3 48 Turnitin detection 12 2 4 3 24 Submitting the document 13 1 4 4 16 Submitting the document 14 2 4 2 16 Researching and gathering information 15 2 4 3 24 Meetings 16 4 4 4 64 Reviewing or compiling information 20 | P a g e 3. Risk response Risk event response Contingency plan 1 Share Other members will take responsibility to complete project Extra time spent in order to complete project on time Group discussion, reallocate tasks, take proper decision Give feedback on the task by other members, ask questions Use another facilities 2 Mitigate, Avoid 3 Share, Mitigate 4 Share 5 Transfer 6 7 Avoid, Share Transfer 8 Share 9 10 Share, Reduce Reduce 11 Avoid 12 Retain 13 Retain Review again, make effective changes 14 Avoid 15 Share Enhance communication tools, organise more effective meetings Re-allocate members to do tasks 16 Retain Search for professional information, seek help Find another project manager More reasonable research on the topic, Review document Organise another interview and bring a back up device Use email, speak to lecturer Check Turnitin, make changes, resubmit Speak to the lecturer Re-allocate members to do tasks Trigger Who is responsible Extra load on members Everyone Falling behind schedule due to missing meetings Everyone Falling behind schedule Andrew Irrelevant or missing information Everyone late submission, being late to lecture missing information, and poor quality deliverable Organize another interview Irrelevant or missing information Particular members Missing information Oliver and Philip Subject documents cannot be reached Extra load, late submission Late submission, receive penalty Everyone Extra time needed to produce the final document Loss of marks Everyone Falling behind schedule Andrew and Ahmad Falling behind schedule Andrew Everyone Suleiman, Ahmad and Andrew Everyone Safwan, Cecilia Particular members Everyone 21 | P a g e 4. Risk severity matrix Colour key Implication Major Risks Project halted Moderate Risks Probable loss of marks Minor Risks ignore Probability × Impact × Detection = Risk Value 5 2 4 16 3 3, 4, 11 2 8 6, 7, 9, 12, 14, 15 1 1 5, 10, 13 3 4 Likelihood 1 2 5 Impact 22 | P a g e QUALITY ASSESSMENT Quality is sometimes seen as an incidental to each client delivery, as opposed to an independent, critical phase of the delivery. Because quality control is commonly compressed at the tail end of a project, the overall commitment to the calibre of work produced is inherently compromised (Gina Lijoi, 2010). However, in our case it was different. Each member in our group tried their best to find out and make sure that the desired quality and standards were maintained. The main person behind the assessment was our Monitor-Evaluator, Cecilia Saldivar. There were a number of key factors we identified in order to keep up the quality of our project. A Good Plan: Primarily, we realized the importance of a plan, do and check cycle for the quality improvement. Thus our coordinator, Andrew Guanzon along with the rest of the team discussed what the plan would be. The checking and implementation were then followed by Cecilia Saldivar (Monitor-Evaluator), Phillip Do and Safwan Mabud (Implementers). Appropriate Communication: It is very obvious that poor communication between the team members and the stakeholder ( Mary Walmsley ) and within the team members themselves would lead to a project failure. Hence, we chose e-mails and messaging through facebook as the mode of our communication since we know that everyone would check their e-mails and facebook frequently. It cannot be denied that we had to face several difficulties while trying to communicate with each other. Problems like internet connection failure would not allow some of the members to send or receive any useful information or work which would hamper the progress a great deal. During times like this our coordinator would make sure that everything was taken care of. Good Measurement and Constant Review: 23 | P a g e Early in the process it is important to identify the key outcomes and outputs of the project and how you will measure whether they have been delivered. Implement processes that measure progress, both qualitatively and quantitatively, throughout the project at individual, team and whole project levels. This ensures that problems can be identified early and successful tactics can be promulgated throughout the project (Michael L Young, 2010). Keeping this in mind, the implementers in our group carried out the necessary procedures to ensure the upkeep of the quality we wanted to achieve. Along with good measurement go good review mechanisms. Some of the important aspects such as budgeting, scheduling and quality elements of the projects were constantly reviewed for the team members to be successful with the project. There were times when one of the team members would not be able to attend the meetings due to a clash of the class schedule with his/her allocated time for meeting. For this period of time, someone else in the group made sure that he took over the other person’s responsibility and completed the work. Act Early: To avoid last moment distresses, the team members worked earlier on solving the simple or complex issues found out by reviewing the important factors needed in managing a project. Our coordinator confirmed that all the issues were resolved before we moved on with our work any further. We found it necessary to continue to stress the agreed scope of our project as our client was impressed with our progress during our weekly meetings. We offered our further consultancy services to fulfil the additional request to find appropriate speakers for the seminar as part of a new project to be commenced upon finalization of the current project. After our last meeting to discuss our weekly report, our client mentioned that they were impressed by our commitment to monitor, report and provide quality assurance during the implementation of the project. 24 | P a g e References Eager D.M., Bagia, R., Walmsley, M., & University of Technology Sydney, Faculty of Engineering, 2011, 49002 and 48260 Project Management in Engineering and Information Technology, McGraw-Hill Custom Publishing Australia Pty Ltd. Walmsley, M., 2011, ‘48260 Engineering Project Management Subject Outline’, unpublished, University of Technology Sydney. 25 | P a g e Appendix A: Group Charter Reporting Period: 10/03/2011 to 07/04/2011 Group ground rules Meeting times: Our group have mutually agreed to meet at least once a week for task allocation and updates on ongoing and completed tasks. The group is to meet weekly on Tuesdays at 1pm, followed by a half hour meeting after Thursday’s EPM lecture. Group meetings are not restricted to the mentioned dates and times as we will organise extra meetings if required. These situations can occur if the meeting times on Tuesday and Thursday are insufficient to properly organise and plan given tasks. Meeting locations: Our team meeting location is generally held at building 2, level 4 at any of the open group work rooms (near building 2 I.T. centre). Our team meeting location is often relocated to an engineering lab whenever our team needs to use Microsoft Project for diagram work, for working as a group in regards to a documentation task and also for finalising any other work requiring the use of Microsoft Office. Forms of communication: Our team utilises several forms of communication to notify team members of any update, status report or other kinds of notification regarding upcoming tasks, distribution of work, group deadlines, group meetings and follow-ups on tasks given to each responsible member of the group. The main forms of communication used are: Mobile phone: Calls and text messages Internet: Email, Facebook Face to face: Group meetings, before and after EPM lecture 26 | P a g e Each team member uses the above forms of communication to also inform the whole team if he/she experiences difficulty in an allocated task, is late for team meetings or cannot attend meetings, appointments, and other events where the team is required to meet together. Poor contribution to team work: If there is any suspected poor team contribution occuring, the group will need to pinpoint team member(s) lacking in team contribution. The group leader/respectable team member will need to privately speak with the team member in an assertive manner to encourage the team member to participate more, be more consistent in attendance and/or exert more effort in the group work. If there does not seem to be a change in the attitude and quality of participation of the team member(s), it will result in the following team member(s) receiving a poor SPARK grade. In the scenario of a team member contributing, but submitting work that does not meet team standards, the group leader/respectable team member will need to privately speak with the contributing team member. The leader/fellow member will need to ask for a redo of the work to meet the standards. If the team member is unable to carry out or complete the task up to standard, then the task will need to be redistributed to another team member. Decision making process: Our group will be making its decisions primarily during group discussions (group meetings, group email conversations, etc). Decisions will be made using a group evaluation of the suggested idea(s), a screening process, and a team vote. This will usually be followed by a final decision made by the team leader/coordinator to finalise the decision. For example, a team member suggests for meeting minutes to be documented for every meeting. If this idea seems achievable, beneficial to the project, can be completed within the given deadlines and contains importance as to why it needs to be done, then the decision process will be carried out. Of course, simple decisions, such as the meeting location can easily be decided by one team member or 27 | P a g e leader, whereas other decisions such as, changing the arranged meeting time would need an evaluation, a vote and the agreement of the team before a decision can be made. Submission of group work to Turnitin: Our group has chosen Safwan, to submit tasks required to be uploaded to turnitin. 28 | P a g e Appendix B: Meeting minutes: ENGINEERING PROJECT MANAGEMENT 48260 MEETING MINUTES TUESDAY 10th May, 2011 Start Time: 1pm End Time: 4pm Present: Andrew, Oliver, Ahmad, Suleiman, Safwan, Cecilia Absent: Phillip Location: UTS Civil Engineering Computer Lab 02.05.43 Agenda 1. Discuss status on incomplete tasks from previous meeting Task Description Allocation of Plan & Abstract 2 work: Scope Statement Work Breakdown Structure Responsible Member(s) Status Cecilia Incomplete Oliver Incomplete Ahmad and Suleiman Incomplete Deadline 26/05/11 26/05/11 Responsibility Matrix Budget Summary Risk and Quality 26/05/11 29 | P a g e 26/05/11 Compile and Finalise report Phillip Incomplete 26/05/11 Safwan Incomplete 26/05/11 Andrew Incomplete Notes: - Plan and Abstract 2: Each team member allocated same tasks as to previously completed Plan and Abstract 1 2. Main Agenda a. Discuss issues with current incomplete tasks b. Make changes to current incomplete tasks c. Other questions, issues and comments 3. New tasks a. Discuss new upcoming tasks b. Delegate new tasks to each team members 4. Next Meeting a. Schedule time and location Thursday 19.05.11 @ UTS 04.03.27 b. Delegate: i. Chairperson – Andrew ii. Timekeeper – Phil iii. Minute Taking – Cecilia iv. Distribution of minutes – Cecilia 5. AOB (Any Other Business) Tasks required for next meeting: Task Description Responsible Deadline Member(s) 30 | P a g e Status updates Plan & Abstract 2 Allocation of work Progress & Status Report 3 All All (Andrew to Final Report 26/05/11 26/05/11 allocate) All (Andrew to 26/05/11 allocate) Notes: - Progress and Status Report 3: Each team member allocated same tasks as to Progress and Status Report 2 31 | P a g e ENGINEERING PROJECT MANAGEMENT 48260 MEETING MINUTES THURSDAY 19th May, 2011 Start Time: 5pm End Time: 6pm Present: Phillip, Andrew, Oliver, Ahmad, Suleiman Absent: Safwan, Cecilia Location: UTS 04.03.27 Agenda 6. Discuss status on incomplete tasks from previous meeting Task Description Responsible Status Deadline Member(s) Allocation of Plan & Abstract 2 Safwan Incomplete Phillip Incomplete Ahmad Incomplete Suleiman Incomplete Andrew Incomplete Oliver Incomplete 26/05/11 work: Progress & Status Report 3 26/05/11 Final Report - Introduction & Interview - Organisational Structure & Company - Failed Projects - Symptoms of Failed 26/05/11 26/05/11 Projects - Interview Manuscript 26/05/11 26/05/11 32 | P a g e Cecilia Incomplete 26/05/11 Notes: - Stayed back after lecture and delegated work for each member of the group - Group thought it was best to delegate work this way so that attention to detail and quality of work produced was maximised and that members don’t an overload of work 7. Main Agenda a. Discuss issues with current incomplete tasks b. Make changes to current incomplete tasks c. Other questions, issues and comments 8. New tasks a. Discuss new upcoming tasks b. Delegate new tasks to each team members 9. Next Meeting a. Schedule time and location Tuesday 24.05.11 @ UTS Civil Engineering Computer Lab 02.05.43 b. Delegate: i. Chairperson – Andrew ii. Timekeeper – Phil iii. Minute Taking – Cecilia iv. Distribution of minutes – Cecilia 10. AOB (Any Other Business) 33 | P a g e Tasks required for next meeting: Task Description Responsible Deadline Member(s) Status updates Plan & Abstract 2 Safwan Progress & Status Report 3 Phillip 26/05/11 26/05/11 Final Report Ahmad 26/05/11 Suleiman Andrew Oliver Cecilia Notes: - Phillip to send Safwan Budget Baseline structure 34 | P a g e ENGINEERING PROJECT MANAGEMENT 48260 MEETING MINUTES TUESDAY 24th May, 2011 Start Time: 1pm End Time: 4pm Present: Andrew, Oliver, Ahmad, Suleiman, Safwan, Cecilia Absent: Phillip Location: UTS 04.03.27 Agenda 11. Discuss status on incomplete tasks from previous meeting Task Description Responsible Status Deadline Member(s) Status Updates Plan & Abstract Report 2 Safwan Complete Phillip Complete Ahmad Complete Suleiman Complete Andrew Complete Oliver Complete Progress & Status Report 3 26/05/11 26/05/11 Final Report - Introduction & Interview - Organisational Structure & Company - Failed Projects - Symptoms of Failed Projects - Interview Manuscript Plan & Abstract Report 2 Progress & Status Report 3 Final Report 26/05/11 26/05/11 26/05/11 26/05/11 26/05/11 35 | P a g e All 3 reports to be submitted to Cecilia Complete Turnitin Print, Compile, 26/05/11 Submit All Complete Submit Online 26/05/11 Andrew Complete Notes: - Group to meet up and submit their finished sections for it to be compiled into a report 12. Main Agenda a. Discuss issues with current incomplete tasks b. Make changes to current incomplete tasks c. Other questions, issues and comments 13. New tasks a. Discuss new upcoming tasks b. Delegate new tasks to each team members 14. Next Meeting (if necessary) a. Schedule time and location Tuesday 31.05.11 @ UTS Civil Engineering Computer Lab 02.05.43 b. Delegate: i. Chairperson – Andrew ii. Timekeeper – Phil iii. Minute Taking – Cecilia iv. Distribution of minutes – Cecilia 15. AOB (Any Other Business) Tasks required for next meeting (if necessary): 36 | P a g e Task Description Responsible Deadline Member(s) Discuss Audit Report Formation of group presentation All All 02/06/11 02/06/11 Practice Presentation Group Reflection All All 02/06/11 09/06/11 Notes: 37 | P a g e Belbin Team Roles Results Team member’s name Phillip Do Oliver De Paz Andrew Guanzon Ahmad Suleiman Ahmad Rabie Cecilia Saldivar Safwan Mabud Plant (Ideas Person) 10 10 0 5 6 5 3 Coordinator (Chairperson) 11 4 16 12 12 11 17 Monitor – Evaluator (Critic) 11 5 5 13 7 12 3 Implementer (Company Worker) 15 15 9 16 11 5 16 Team Worker (Team Builder) 11 5 30 11 14 15 11 Shaper (Unofficial Chairperson) 0 8 2 17 7 8 17 Resource Investigator (Contacts) 0 10 6 4 10 9 4 Completer-Finisher (Inspector) 12 8 2 0 15 5 0 Primary Role Implementer Implementer Team Worker Shaper Completer Team worker Shaper/Coordinator Secondary Role Team Worker/ Coordinator Plant/ Resource Investigator Coordinator Implementer Team Worker MonitorEvaluator Implementer Team role(s) to be adopted in this group Implementer Plant/ Resource Investigator Coordinator Shaper Team Worker MonitorEvaluator Implementer Team Role 38 | P a g e Appendix C: Scheduling Details (Network Diagram & Gantt Chart) 39 | P a g e