CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES CONFIRMED MINUTES FEBRUARY, 18-21, 2013 WESTIN PARK CENTRAL HOTEL DALLAS, TEXAS, USA These minutes are not final until confirmed by the Task Group in writing or by vote at a subsequent meeting. Information herein does not constitute a communication or recommendation from the Task Group and shall not be considered as such by any agency. MONDAY, 18-FEB-13 to THURSDAY, 21-FEB-13 1.0 OPENING COMMENTS – CLOSED The CHEMICAL PROCESSING (CP) Task Group was called to order at 8:00a.m., 18-FEB-13. Code of Ethics/Antitrust and Meeting Conduct presentations were reviewed. It was verified that only SUBSCRIBER MEMBERS were in attendance during the closed portion of the meeting. A quorum was established with the following representatives in attendance: Subscriber Members/Participants Present (* Indicates Voting Member) * * * * * * * * * * * * * * * * * * * * Hal Cary Malik David Manuel Judith Michael Terry Karyn Bob Peter Robert Aleck Alan Frederick Greg Tommy Robert John Martin Serge Marc-Andre Eric Susan Nick Veronique Bibiana Joel Tom Winton Micheal Jim Abel Baker Boutoba Burke Cabrera Camacho Coleman Curtland Deming Denney Droste Faticanti Featherston Gilbert Girard Haataja Howland Knicely Koenig Kolinko Labbe Lefebvre LeFort Lewis Magnapera Marcel Marquez Mohnacky Moreland Mullen Narowitz O'Shea Raytheon Co The Boeing Company Eurocopter BAE Systems - E & I The Boeing Company Goodrich (UTAS) The Boeing Company Ball Aerospace & Technologies Goodrich (UTAS) Honeywell Aerospace Airbus Textron Systems Bell Helicopter Textron Cessna Aircraft Company Pratt & Whitney Canada Bell Helicopter Textron Spirit AeroSystems Inc. The Boeing Company The Boeing Company Eaton Aerospace Heroux Devtek Inc. Heroux Devtek Inc. SONACA Lockheed Martin Corporation BAE Systems - E & I SAFRAN Group Goodrich (UTAS) Hamilton Sundstrand Bombardier Inc. Spirit AeroSystems Inc. Lockheed Martin Corporation GE Aviation 1 Vice Chairperson CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES * * * * * * * * * * * * * Fabrizio Minh Jesse Carl Jerry John Ralph Richard Paul Steve Mike Yuhui Zia Shawn Debbie Michael Gene Miao Wei Sergey Quadrini Quan Reeves Roche Satchwell Sattler Sekkel Shain Slater Starr Stolze Sun Usmani Vierthaler Vogel Vosatka Wallace Wang Wang Yesilevich AgustaWestland Triumph Group 309th Maintenance Wing-Hill AFB Goodrich (UTAS) Rolls-Royce PLC Hawker Beechcraft Corporation Lockheed Martin Corporation Gulfstream Aerospace Rockwell Collins Inc. Honeywell Aerospace Northrop Grumman Corporation COMAC BAE Systems Air & Information (MAI) Spirit AeroSystems Inc. Triumph Aerostructures - VAD Rockwell Collins Triumph Aerostructures - VAD COMAC COMAC Hamilton Sundstrand Chairperson Other Members/Participants Present (* Indicates Voting Member) * * * * * * * * * * * * * * * Ali Martin Fred Lee Eric Stephane Charles Steve Mark Jim Robert Warren Jim Bruce Greg William Ben Gary Ann Melany Timothy Hirohiko Jonathan Bill Eric Jeff Richard Keven Dean Randy Dusty Sharon Denis Bakr Belanger Binda Bruce Carlson Chaumeil Costello Crest Crevier Cummings Custer DeCuir Denton Dobbins Excell Ferris Flores Fox Gill Guzman Hamlett Hattori Hebben Heeter Jacklin Jones Kline Kudelka Kux Layton Little Mack Mailloux Nico Products, Inc. Sonaca Montreal Ozark Mountain Technologies LLC Robert Stuart Ltd. Hytek Finishes Company Galion Sun-Glo Plating Company Stabile Plating Morton Manufacturing Metal Finishing Co. AAA Plating & Inspection Inc. Lisi Aerospace Torrance B-D Industries Inc. Aetna Plating Company Coast Plating Inc TechMetals Inc. Applied Aerospace Structures Corp Anodyne, Inc. Lord Corporation Centro de Investigación en Materiales Avanzados, S. C. Certified Metal Finishing Mitsubishi Heavy Industries Ltd Ducommun AeroStructures Gardena Skills Inc. F.M. Callahan & Son Inc. Alloy Processing X-R-I Testing Westfield Electroplating Co. Har-Conn Aerospace Hytek Finishes Company Ducommun AeroStructures PM Testing Laboratory Inc. Sonaca Montreal 2 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES Maria Selene Hugh Silvia Abdillah Charles Maru Maxwell Miranda Mohamed Morgan * Laura Moyer * * Simone Abdul Thomas Dinh Michael Jerker Mante Mahlogonolo Hector Kim Dennis Ken Jim William Cynthia Frank Colin Tammi Tony David Ken Greg Vittorio John Ronald Dawn Steve Yoshiomi Levi David Jim Mike Gerald Wilfried Stephen Murphy-Fickenworth Nathani Newton Ngo Noettl Nordh Bombardier Transportation Mexico Robert Stuart LTD Centro de Investigación en Materiales Avanzados, S. C. Lord Corporation Triple Cities Metal Finishing Corp Howmet Castings and Services, Inc. Dover Casting (AHDC) Chrome Plus International Hi-Tech Metal Finishing Aircraft X-Ray Laboratories Inc. GKN Aerospace Chem-tronics Inc. Magnetic Inspection Laboratory Inc. GKN Aerospace Sweden AB Pahakathi Turbomeca Africa Pichardo Porter Reidy Rettger Ringer Roman Roth Saenz Schiewe Schubert Schmaltz Sexton Shouse Smotherman Jr Stana Stevens Stewart Stokes Stone Sukesada Talamantes Thompson Tuminello Turbett Wahlin Weber Wright Curtiss Wright Controls Inc Eng Systems Poly-Metal Finishing CIL Metal Finishing Lord Corporation Tech Met Magnetic Inspection Laboratory Team Industrial Services Hi Tech Metal Finishing Magnetic Inspection Laboratory LMI Finishing Inc. Protective Coatings, Inc. Certified Metal Finishing Inc. Lord Corporation Ozark Mountain Technologies LLC Avcorp Industries Inc. Weatherford Aerospace Ellison Surface Technologies PTI Industries Inc Saporito Finishing Company Asahi Kinzoku Kogyo Inc. Metal Finishing Co DCI Aerotech Div. of Detroit Chrome Inc. Tech Met Quality Plating Co of Tulsa Inc. AAA Plating & Inspection Inc. PFW Aerospace AG Brazonics Inc. * * * * * * * * * * * * * Staff Present Nigel Michael Robert 2.0 Cook Graham Nixon DELEGATION OVERSIGHT – CLOSED The delegation trackers for all delegated audit reviewers were reviewed. All delegated reviewers had exceeded the requirements to maintain delegation. 3.0 NUCAP – CLOSED 3 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES The status of the NUCAP scope exceptions was reviewed. One was awaiting completion of the ballot of AC7108/2 before it could be closed and there were four others that were awaiting internal corrective action. 4.0 PROFICIENCY EXAMS – CLOSED The proficiency exams for conversion coating, painting and plating were reviewed. There were a number of questions that needed further amendment. ACTION ITEM: Staff Engineers to amend the auditor proficiency exams and email them to prime voting members for comment. (Due Date: 31-Mar-13) 5.0 AUDITOR OVERSIGHT – CLOSED Mike Stolze and Robert Nixon gave a presentation on the go forward plans for auditor oversight. Further data analysis is still required to identify which auditors need to be observed. In addition to the auditors identified by data analysis, the sub-team proposed that new auditors should also be reviewed. The following Prime members volunteered to assist in the oversight program. On Site Observation: Mike Stolze, John Koenig, Alan Gilbert, Mike Coleman, Aleck Featherston, Karyn Deming, Serge Labbe, Zia Usmani, Hal Abel, Jerry Satchwell, Malik Boutoba, Bob Cashman, Paul Slater, Carl Roche, Jerker Nordh Desk Top Observation: Mike Stolze, Alan Gilbert, Susan Lewis, Serge Labbe, Yuhui Sun ACTION ITEM: Observation oversight team to analyze auditor consistency data and create an observation audit schedule. (Due Date: 31-Mar-13) 6.0 RESOLUTION BY TASK GROUP ISSUES – CLOSED Audit 146391: The auditor did not receive the Visa in time to complete the audit required to support their Jan 2013 expiration date. Another auditor is scheduled for an audit in Pakistan on 13-15th March. Would the Task Group be agreeable to extending the current accreditation from 1/31/2013 to 4/30/2013 to allow time for this with a possible further extension to 31st July 2013 if needed? Their last audit (#139764) was conducted July 2011 and resulted in zero (0) findings as did the previous audit. Their current accreditation expires January 31, 2013. Task Group agreed to grant an extension to 31st July 2013 if required. Are the Task Group Subscriber members notified by automatic email if an audit accreditation is extended? ACTION ITEM: Nigel Cook to determine if Primes are automatically notified of audit accreditation extensions and report out at the June meeting. (Due Date: 3-Jun-13) Audit 151330 NCR#1: The NCR stated: Tank 2.02 & 2.03 Hot water seals- No Conductivity records AC7108 Rev. E paragraph (6.3.3.11) states: Solution and/or material testing (e.g. reviewed and acceptable, if material testing (paint) what was done) Supplier does not have any records available to show the conductivity value for Tank 2.02 and 2.03 as required by specification MT-SL-1829 Issue C paragraph 7.1 which flows down specification MT-SL-4674 Issue A Table 1. Frequency of testing is defined as monthly. 4 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES During review of corrective action it became apparent that the make-up water was controlled to <20uS but during use the records show the conductivity in the tank exceeded 200uS and the supplier’s self-appointed limits were 700uS. The supplier works to a customer specification and MIL-A-8625 and none of them define a water purity for the in tank de-ionized water. Task Group agreed this should not be an NCR. Audit 148472 NCR#8: The Supplier does Type III anodize to MIL-A-8625. In the audit it was identified that for the two abrasion test samples one met the abrasion requirement and the other did not. The supplier accepted the result as compliant because the average of the two tests met the requirement. MIL-A-8625 does not talk about averaging the values; however ASTM D4060 requires the test report to include the result for each sample and the average. The Task Group agreed that both test pieces should meet the requirement and that this is an NCR. AMS 2433 Plating: Nickel-Thallium-Boron or Nickel-Boron Electroless Deposition specification has a requirement for a wear test, 3.4.5 Wear Resistance: A standard test block with 0.001 inch (25 μm) plating thickness, post treated as in 3.3.1, and subjected to a 150 pound (68 kg) load with filtered mineral spirits as a lubricant, shall exhibit a wear scar with an average width not greater than 0.032 inch (0.81 mm) after 5000 test cycles, determined in accordance with ASTM D 2714. ASTM D 2714 Standard Test Method for Calibration and Operation of the Falex Block-on-Ring Friction and Wear Testing Machine. The problem comes from the fact that Falex is the manufactures of both the testing machine and the ring and blocks used in the testing and offer testing, however, they do not have any third party certification. They are self-certified and are on “several boards”. According to AC 7108 both revisions E & F section 1.2 we still are not allowed to use them as a testing source. The Task Group agreed this would be a finding to AC7108. Note: During report out in the open meeting it was stated that AMS2433 requires the test to be done to ASTM D2714 and that this specification identifies Falex as the approved source. ACTION ITEM: Staff Engineers to verify what the MTL Group do and bring back a recommendation to the June 2013 meeting. (Due Date: 3-Jun-13) Adding Specifications to an Audit Scope: Under what circumstances can specifications be added to the scope of a supplier’s accreditation after the audit is conducted. The current (undocumented) practice is a specification can be added if the specification was included in a job audit or the specification was in their previous scope and it was obviously an oversight. Other than these cases additional specifications are not added unless an Add Scope audit is conducted. Can NTGOP-001 App CP be amended to include the circumstances under which additional specifications can be added. ACTION ITEM: Nigel Cook, Hal Abel, Susan Lewis to amend NTGOP-001 CP to include verbiage and bring to the June meeting. (Due Date: 3-Jun-13) Prime Information on eAuditNet: Prime Specific Information currently posted in eAuditnet at Resources/Public Documents/Chemical Processing/Supplier Information/Prime Specific Information has not been updated for quite some time. Should these documents be addressed in the same manner as Prime Table1’s, i.e. remove from eAuditNet, email the document to the Prime Rep and replace when updated. The most recent posting date is 2005 with some going back to 2002. The Task Group agreed that the documents should be removed and replaced only when updated. 5 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES ACTION ITEM: Robert Nixon to remove the documents and email them to the Prime representative for update. (Due Date: 31-Mar-13) Audit 146723 NCR 2: “OBSERVATION: Was lot testing in conformance with specification and/or customer requirements? Passivation Paper trail Job 169009 P/N 1159BM979-23, parts were subjected to the water immersion test as per SOP-05-8.2.4.E, AMS-STD-753 Method 100. The parts were too large to fit completely in the water immersion test tank, thus they were run twice, flipping them 180 degrees after 24 hours, so as to achieve complete testing. The spec requirement is: "Parts shall be alternately immersed in reagent grade water for one hour, removed from the tank, and allowed to dry for one hour for a minimum of 24 hours.", where the auditor interprets immersed to mean 100% immersion due to the increased possibility of a false positive due to the water/air interface. The Task Group agreed this this was not a finding and needs to be voided. Audit 146170 NCR#6: Requirement: WI DMS STD 101 sequence 16: After clean, drying is to be performed by oven air dry at 180F +/- 25F. Identified Nonconformance: Parts with outside diameters (OD) greater than approximately 35" do not fit and oven doors are left partially open. This is a low temperature drying oven subject to AC7108 section 5.5 and the supplier is therefore permitted to define their own TUS requirement. Although the normal expectation would be to have the oven doors closed the TUS demonstrates the 180° ± 25°F internal requirement is being met. Supplier responses state the only customer requirement is a maximum drying temperature of 250°F. The Task Group agreed this is not an NCR. Incident Report 727: Audit 149298 was only in TG Review for 1 day. The ballot end date in eAuditNet was incorrect causing the audit to show as having completed the ballot process. An eAuditNet report was run and this was the only audit less than 7 days in TG review. The eAuditNet amendment log was also reviewed and there had not been any manual amendment of the ballot end date. The Task Group agreed that this was a one off incident and no further action is required. Audit 151722: The Supplier has AC7108/7 Vacuum Cadmium in their scope but the auditor was not able to conduct a job audit because the vacuum gauge failed during the audit. The previous audit also included an historic job audit. Is the Task Group happy to grant accreditation based on conducting another historic job audit? The Audit Handbook states: A supplier can retain listing a process/specification in their scope so long as: • They have an internal procedure for that process that lists the specification and is compliant to its requirements. • The supplier has previously processed parts, within the last 5 years, to the processing requirements and has evidence that acceptance test requirements were met. • The supplier has previously processed test pieces, within the last 5 years, to the processing requirements and has evidence that the periodic testing requirements have been met. These items are not required to be part of the audit but shall be made available to the auditor if requested. If the supplier cannot provide evidence for any of the above the auditor will document in 4.1.1 of the AC7108 checklist what scope items were removed and the reason why. The Task Group agreed that accreditation can be granted based on historic job audits in the last two Nadcap audits. 6 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES 7.0 NEW VOTING MEMBER APPROVAL & COMPLIANCE WITH VOTING REQUIREMENTS – OPEN Requests to become a voting member were received from: Title First Name Surname Company Ms. Kim Porter Ms. Gardiner Rynne Mr. Bob Denney Mr. Mitchell Tanner Mr. Mr. Milt Marc-André Stevenson Jr Lefebvre Mr. Sergey Yesilevich Mr. Mr. Dennis Michael Reidy Vosatka Mr. Mr. Mr. Ms. Yuhui Wei Miao Laura Sun Wang Wang Moyer Poly-Metal Finishing Chem Processing Inc. Honeywell Aerospace Triumph Processing – Embee Division Inc. Anoplate Corp Heroux Devtek Inc. Hamilton Sundstrand (UTAS) CIL Rockwell Collins Inc. COMAC COMAC COMAC Howmet Castings and Services, Inc. Dover Casting (AHDC) Voting Member Type Supplier Voting Member (SVM) SVM Meetings Attended Feb 12 Oct 12 Feb 12 Oct 12 Alternate Subscriber Voting Member (ALT/UVM) SVM Oct 12 Feb 13 Feb 12 Oct 12 SVM ALT/UVM Oct 11 Oct 12 Oct 12 Feb 13 Subscriber Voting Member (UVM) Feb 12 Jun 12 SVM ALT/UVM Oct 12 Oct 12 Feb 13 Feb 13 UVM ALT/UVM ALT/UVM SVM Oct 12 Oct 12 Oct 12 Oct 12 Feb 13 Feb 13 Feb 13 Feb 13 Note: You must be registered on eAuditNet before you can be made a Voting Member. The Task Group agreed to grant voting privilege to all of the above. Compliance to voting requirements was reviewed. American Tinning had failed to meet requirements for both meeting attendance and balloting and their voting privilege is to be removed. Various other Suppliers and Subscribers (3P Processing, The Boeing Company, BAE Systems, Bombardier Areospace, EADS CASA, Heroux Devtek Inc, Parker Aerospace, Harr Conn, Tech Met) failed to meet one or other of the requirements, typically ballot responses.. These were all reviewed with the Task Group Chair and it was agreed that they retain their voting privileges based on the work they do for the Task Group, e.g. sub-team work, auditor observation, etc. Alenia’s voting privileges were removed as a result of actions from the last meeting. Alenia are working to identify a replacement. ACTION ITEM: PRI Staff to amend voting status of the identified Subscriber Representatives. (Due Date: 15-Mar-13) 8.0 NEW SUPPLIER ORIENTATION – OPEN 7 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES Mike Noettl presented the new supplier orientation presentation. 9.0 FRENCH TRANSLATION OF CHECKLISTS – OPEN AC7108 Rev F – Translated, to be posted on eAuditNet AC7108/1 Rev B – Translated and posted on eAuditNet AC7108/2 Rev B - Translated and posted on eAuditNet Audit Handbook (Feb 2012) – Translated and on eAuditNet Audit Handbook (Oct 2012) – In progress and due this week ACTION ITEM: Nigel Cook to post AC7108 Rev F and the Audit Handbook in eAuditNet. (Due Date: 31Mar-13) 10.0 NMC METRICS, REGIONAL AUDITOR CAPACITY – OPEN The NMC metrics and auditor capacity metrics were reviewed. The metrics were generally meeting requirements but the following items needed to be watched. Overall auditor capacity was green but there was lack of capacity in Asia. Because ITAR audits cannot be conducted by Asian auditors the data does not reflect the true capacity and the situation needs to be re-assessed based on non-ITAR audits. Staff cycle time was red for Initial Audits and was generally trending upwards for all audits. The Task Group questioned if there was sufficient reviewer capacity and expressed concern that the need to meet the metric may result in acceptance of corrective actions that would not normally be accepted. Would it be possible to produce an audit reviewer capacity/workload metric? ACTION ITEM: PRI Staff to review the possibility of an audit reviewer capacity/workload metric. (Due Date: 3-Jun-13) 11.0 NOP-011 MODE B FAILURE CRITERIA – OPEN The Task Group reviewed the present Mode B failure criteria and the new 95% and 98% 2012 criteria. Initial Audit Data: Present 1 Day Audit 2 Day Audit 3+ Day Audit Major 2 (95%) 4 (95%) 6(95%) Total 7 (95%) 14 (95%) 21 (95%) 95% Proposed 1 Day Audit 2 Day Audit 3+ Day Audit 2 3 5 5 9 14 98% Proposed 1 Day Audit 2 Day Audit 3+ Day Audit 2 4 6 6 12 19 Reaccreditation Audit Data: Major 8 Total CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES Present 1 Day Audit 2 Day Audit 3+ Day Audit 2 (98%) 4 (98%) 6 (98%) 4 (98%) 9 (98%) 13 (98%) 95% Proposed 1 Day Audit 2 Day Audit 3+ Day Audit 1 2 3 3 5 8 98% Proposed 1 Day Audit 2 Day Audit 3+ Day Audit 2 3 5 3 7 10 The Task Group agreed to retain the present failure criteria. ACTION ITEM: Nigel Cook to advise Mike Graham that the NOP-011 Mode B failure criteria will remain the same. (Due Date: 31-Mar-13) 12.0 CHEMICAL PROCESS AUDIT HANDBOOK APPROVAL – OPEN The Task Group reviewed and approved the amendments to the Chemical Processing Audit Handbook. ACTION ITEM: Nigel Cook to post the amended Chemical Processing Audit Handbook. (Due Date: 31Mar-13) 13.0 AUDITOR CONFERENCE – OPEN Robert Nixon will be responsible for overall coordination of the October Auditor Conference for the Chemical Processing (CP) Task Group. Will Calvert is part of the PRI team for the general section of the Auditor Conference. The status of the sub-team presentations were reviewed: Subjects for Next Auditor Conference: New paint systems – Have not yet met. Prime specific presentation – Have not yet met. AC7108/6 - Cleanliness Verification – Draft presentation reviewed. New anodize techniques, e.g. BSA, TSA. – Outline plan for content reviewed. 9 Members- Leads (L) Staff Engineer (SE) Zia Usmani (L) Alan Gilbert Mike Graham (SE) John Koenig (L) Bob Cashman Mike Stolze Will Calvert (SE) Jim O'Shea (L) Jim Ringer Vitorio Stana Debbie Vogel Nigel Cook (SE) Jerry Satchwell (L) Neil Cowan Jim Cumming Karyn Deming Mike Noettl Tammy Shubert Stephan Simacek CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES Will Calvert (SE) Pyrometry (including Prime requirements) – First meeting arranged for early March. Masking technology – First meeting arranged for early March. Electroless plating including masking issues First meeting arranged for early March. 14.0 Mike Coleman (L) Jonathan Hebben Vitorio Stana Robert Nixon (SE) Hal Abel (L) Jonathon Hebben Keven Kedelka Mike Noettl Shawn Vierthaler Robert Nixon (SE) Bob Cashman (L) Dan Backus Keven Kedelka Steve Starr Robert Nixon (SE) REVIEW OF AUDITOR ADVISORIES – OPEN The two auditor advisories issued since the last meeting were reviewed. 15.0 TECHNICAL DATA SHEETS – OPEN Mike Stolze gave a presentation on the sub-team status for Technical Datasheets. The Task Group agreed that the requirements in AC7108 documents for compliance to technical datasheet parameters are not compliant with NOP-002 checklist criteria. In addition the Task Group agreed the sub-team is to continue and amend the relevant checklist paragraphs to remove compliance with technical datasheet parameters and replace it with compliance to technical data and to also define what constitutes technical data. Mike Stolze (Lead), Hal Abel, Karyn Deming, Susan Lewis, Nicholas Magnapera, Yohands Armando Rey, John Koenig, Steve Crest, Jim Cummings, Mike Noettl, Keven Kudelka, Jonathan Hebben, Warren De Cuir, Will Calvert. ACTION ITEM: Mike Stolze and sub-team to amend the relevant checklist paragraphs to remove compliance with technical datasheet parameters and replace it with compliance to technical data and to also define what constitutes technical data. (Due Date: 3-Jun-13) 16.0 CHECKLIST STRATEGIC PLAN – OPEN Jerry Satchwell reviewed the Task Group member’s responses for the proposed new Base and Anodize Checklists and defined the next steps which were to create the remaining checklists and obtain feedback on them from Task Group members. The following members agreed to provide feedback for specific checklist. Other members are also welcome to respond. AC 7108/1: Jim Cummings, Alan Gilbert, Mike Stolze, Gene Wallace AC 7108/2: Steve Starr, Tammi Schubert, Frederic Girard AC 7108/3: Alec Featherston, John Koenig, Kim Porter, Mike Stolze, Abdillah Mohamed AC 7108/4: Jim Cummings, Dennis Reidy, Alec Featherston, Jonathan Hebben, Cindy Klinger 10 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES AC 7108/5: Mike Noettl, Jerker Nordh, Zia Usmani, Jonathan Hebben, Jim Ringer, Dinh Ngo AC 7108/6: Jerker Nordh, Abdillah Mohamed, Jim O’Shea AC 7108/7: Mike Stolze, Warren DeCuir, Tim Hitchcock, Jerry Wahlin, AC 7108/9: Hal Abel, Dennis Reidy, Sergey Yesilevich, William Ferris AC 7108/10: Susan Lewis, Nick Magnapera, Lee Bruce AC 7108/11: Hal Abel, Kim Porter or Nick Magnapera, John Koenig, Alec Featherston, Tammi Schubert, Dinh Ngo AC 7108/12: Dinh Ngo, Mike Noettl, Keven Kudelka, Warren DeCuir AC 7108/13: Bob Cashman, Hal Abel, Karyn Deming, Bill Ferris AC 7108/14: Keven Kudelka, Steve Starr, Hal Abel, Alan Gilbert There were a number of concerns expressed about audit duration and how s-frm-16 and the audit scope would be amended to ensure audit durations are not increased as a result of this restructure of the checklists. ACTION ITEM: A sub-team of Mike Stolze (Lead), Alan Gilbert, Jerry Satchwell, Bill Ferris, Bill Heeter and Nigel Cook was assigned to review s-frm-16 and the electronic scope document to ensure audit durations were not increased as a result of the checklist restructure. (Due Date: 3-Jun-13) 17.0 NDT AC7108/2 PROPOSAL – OPEN The sub-team put their proposal to the NMC after the October 2012 meeting and a number of questions were raised by the NMC. The sub-team had a meeting to resolve these questions and have provided a response to the NMC that will be reviewed after this meeting. The main points of the present proposal are: The checklist will be split into two sections, one for pre-penetrant etch and one for etch inspection. Additional questions on qualification/certification, acceptance standards, IGA/EGP will be added. CP and NDT auditors will be trained to conduct the audits. Additional job audits will be required, a minimum of one job audit for each etch method (PPE, Nital Etch, Macro Etch, Blue Etch Anodize). The duration of etch audits, and audits that contain etch, will increase for a number of suppliers dependent on etch scope and present audit length. The etch checklist will be owned by CP but balloted to CP & NDT. The supplier can chose to have the audit done, subject to 5 day rule, as part of its CP or NDT accreditation. 18.0 CHEMICAL PROCESS TASK GROUP SUPPLIER SEMINAR – OPEN Jerry Satchwell led a discussion on selecting subject matter for a supplier seminar at the next 3 Nadcap meetings. The new Smart Checklist and Top 10 NCRS were the only topics proposed and it is unlikely that this would take much more than 1 hour to present. Dave Michaud said that the eAuditNet team has a very slick presentation for the Smart Checklist that we may be able to use or get them to present. 11 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES If anybody has any suggestions then please let Jerry Satchwell, Karyn Deming or PRI Staff know. ACTION ITEM: Nigel Cook to talk to eAuditNet team about presenting their presentation at the June meeting. (Due Date: 31-Mar-13) 19.0 VISCOSITY TESTING – ZAHN CUPS – OPEN Jeff Jones gave a presentation on the issues with Zahn viscosity cups. There are two types of Zahn viscosity cups (EZ and Signature) and they are basically identical apart from the size of the orifice. The problem is that the paint specifications do not always identify which cup to use and the results can be significantly different. AC7108/1 para 3.11 only requires viscosity to be tested when it is required by the paint application specification and although this limits the problem it does not eliminate it. In some cases the Primes do not know what cup should be used because the viscosity data is provided by the paint manufacturer. 20.0 WATER BREAK FREE TESTING – OPEN Bill Heeter gave a presentation on the sub-team’s proposal to replace Water Break Free Testing with Cleanliness Verification. The Task Group agreed to move forward with the concept and implement it after completion of the checklist strategic plan. There were some comments raised where it was felt the proposal needed additional work: Cleanliness verification if cleaning is the final step. Confusion of the term with the Cleanliness Verification Checklist, AC7108/6. The wording in the checklist needs to ensure the verification method is effective and carried out. ACTION ITEM: Cleanliness Verification team to review the new checklists after implementation of the checklist strategic plan and provide alternative wording for the relevant paragraphs. (Due Date: 20-Feb-14) 21.0 INTERNATIONAL PROCESS SPECIFICATIONS/STANDARDS – OPEN An email requesting a list of European Specifications and National Specifications for countries in Europe was sent to European prime and supplier voting members. One response was received from GKN Aerospace who stated that they used AMS and ASTM specifications, no other responses were received. This is the third time the CPTG has been approached for information and on each occasion the response has been minimal. Veronique Marcel had a list and will provide it to Nigel Cook. ACTION ITEM: Nigel Cook to review the European specification list provided by Veronique Marcel and incorporate into the Chemical Process QML. (Due Date: 30-Jun-13) 22.0 REACH – OPEN Jerry Satchwell and Zia Usmani gave presentations on how their respective companies, RollsRoyce PLC and BAE Systems are addressing REACH. ACTION ITEM: Nigel Cook to get clearance from Rolls-Royce PLC and BAE Systems to post their presentations on eAuditNet. (Due Date: 15-Mar-13) 23.0 SMART CHECKLISTS – OPEN 12 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES The Smart Checklist is a modification of the eAuditNet system to incorporate the modified scope audit process used by the Chemical Process Task Group. The fundamentals of the system are: The first three audits, initial audit and first two re-accreditation audits, will be full scope and will ask all questions in the checklist(s) Later (mature) audits will not be required ask the questions that have been identified as NA due to modified scope status. These questions will still be able to be answered if the auditor identifies a non-conformance against them. If a checklist is technically revised, revision letter change, a mature audit will be reset at cycle 3 for that checklist, i.e. treated as the 2nd reaccred audit. If a supplier adds additional scope the auditor will need to confirm that the additional questions have been asked. Checklist Cycle 1 2 3 4 5 6 Standard S S S S S S Frequency (**) Modified S&Mod S&Mod S&Mod S S S&Mod Frequency (**) A standard frequency audit only has standard frequency questions. 7 S 8 S 9 S 10 S S S S&Mod S The programming should be completed by the end of February and we will then need to modify the electronic checklist to identify if a question is Standard or Modified. Release is expected to be October 2013. 24.0 AMS2750 REV E – OPEN Karyn Deming presented the sub-teams comparison between AC7108 and AMS 2750 Rev E. The results of the comparison are that all the AC7108 questions are still consistent with the new AMS 2750 revision. 25.0 RECORDING OF PROCESS PARAMETERS – OPEN Zia Usmani gave a presentation on the sub-teams methodology and recommendation for recording of process parameters. The sub-team used a risk assessment approach based on whether the parameter is a special parameter, has a significant potential to impact hardware, is for compliance or for process control. ACTION ITEM: Nigel Cook to tabulate the result in a before and after table to clearly identify what parameters would no longer be required to be recorded and send out to all voting members for comment. (Due Date: 30-Apr-13) 26.0 REPORT OUTS: NMC (MICHAUD), SSC (JACKLIN), P&O/CLOSED, STEERING (LEWIS), CP-SAT (CUMMINGS) – OPEN Reports outs were received on NMC, SSC, P&O, Closed Meeting, Steering and CP-SAT. ACTION ITEM: PRI Staff to issue an auditor advisory regarding both taber wear test pieces are to meet acceptance criteria defined in Mil-A-8625. (Due Date: 31-Mar-13) 27.0 3M TAPE - THE REAL STORY – OPEN David Johnson from 3Ms gave a presentation to the Task Group on the changes to the 250 tape. The tape manufacture was moved a couple of times as the market for the product declined. Eventually the machinery to make it because obsolete and 3Ms set about re-formulating its 13 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES manufacturing method so that it could be manufactured on available tape making machinery. Although the backing and adhesive are similar there has been an increase in the peel strength of the tape. Part of the reason for the increased peel strength was a change in the formulation to ensure all tapes exceeded to 60oz/in peel strength when pulled at 12 in/min. Although the 3Ms results show a significant increase in peel strength, the value determined by some independent tests was even higher still. David asked people who had a concern to contact him and he would try to address their concerns. David was asked if he would be prepared to give this presentation in the June meeting in Europe. ACTION ITEM: Nigel Cook to liaise with David Johnson of 3Ms to see if he can attend the June meeting and provide a similar presentation on 250 tape. (Due Date: 31-Mar-13) 28.0 ANY OTHER BUSINESS – OPEN Are there suppliers who would be willing to host Primes on site to aid their training/knowledge of chemical processing.(F M Callahan, Robert Stuart, Metal Finishing, Aetna Plating, Sun Glo, Lisi Aerospace, DCI Aerotech, Aircraft X-Ray) Specification list: The Task Group presently requires a specification list to be attached in the AC7108 checklist at paragraph 4.1.1. The present requirement is that this list identifies all specifications done by the supplier that are applicable to their scope. Some auditors have requested if this list can contain as a minimum the specifications that are done but are not available to be selected in the eAuditNet scope, e.g. European Consensus Specifications, Prime Specifications. CP-SAT agreed to look at this. ACTION ITEM: PRI Staff to issue an auditor advisory regarding the content of the specification list and amend AC7108 section 2.1 to identify the need for an editable list. (Due Date: 31-Mar-13) Subscriber Customer Identification: eAuditNet has recently been updated to allow suppliers to identify which Primes’ hardware they process. Specification list can be added to as free text so suppliers may be adding Prime names that the Primes do not want including. AC7108 Rev F: For a supplier that has achieved modified scope, does the first audit to AC7108 Rev F need to be full scope or can it be modified scope with the amended/new questions asked. Staff Engineer recommendation is that if the previous audit was to AC7108 Rev D then it should be full scope and if the previous audit was to AC7108 Rev E it should be modified scope with the amended/new questions asked. The Task Group agreed to work to the staff engineer recommendation. During the AQS Liaison meeting last night we were asked to bring the following question to our Task Groups and provide an answer back to the AQS Task Group today if at all possible: - How does your TG have confidence in initial audit results when there is no actual parts in house? We run scrap parts or test panels as if they were parts with required documentation (e.g. route card work instructions), supplier must have a least one set of acceptable periodic test results and the job need to meet lot test requirements. - Do you have guidance in your handbook or checklist for the auditors? No, was raised in October 2007 minutes, reconfirmed in June 2010 minutes, but has disappeared over time from the command media. NTGOP-001 App CP, or AC7108 checklist, to be amended to include requirements. A minimum of I set of acceptable periodic tests and lot tests. Scrap hardware is preferred for job audit processing but test pieces would be acceptable if scrap hardware not available. 14 CHEMICAL PROCESSING FEBRUARY 2013 CONFIRMED MINUTES ACTION ITEM: PRI Staff review and amend most relevant document to capture the Task Group decision. (Due Date: 31-Jun-13) 29.0 DEVELOP AGENDA FOR FEBRUARY 2013 TASK GROUP MEETING – OPEN Minutes Prepared by: Nigel Cook nigel.cook@pri-europe.org.uk /Joyce Benkart jbenkart@sae.org ***** For PRI Staff use only: ****** Is procedural/form changes required based on changes/actions approved during this meeting? (select one) YES* NO *If yes, the following information is required: Documents requiring revision: Who is responsible: Due date: CP Audit Handbook Nigel Cook 31-Mar -13 15