UCPath Project Update

Presentation to Chancellor’s Campus

Community Council

March 20, 2015

Presentation Overview

 What We’ve Done So Far

• Who We Are

• Why UCPath?

• Central Team/UCOP Go-Live

• UC Davis Accomplishments

 What are We Doing Now?

• Operational Alignment

• Business Process Reviews

• Infrastructure Development

• Assisting the Central Effort

 What is the Plan Forward?

• Overall objectives and tasks by deployment groups

• UC Davis schedule and next steps

2

Who We Are

Governance/Leadership

 Dave Lawlor , Vice Chancellor and Chief Financial Officer - Finance, Operations & Administration

 UCPath Executive Leadership Team, UC Davis Project Sponsor

 Tim Maurice , UCDHS Chief Financial Officer

 UCDHS Project Sponsor

 Mike Allred , Associate Vice Chancellor, Finance/Controller

(System-wide UCPath Steering Committee,

UCPath Center Advisory Board, UCPath local Steering Committee Co-Chair)

 Susan Gilbert , Associate Vice Chancellor, Human Resources

(UCPath local Steering Committee Co-Chair)

 Steve Chilcott , Executive Director, Human Resources (System-wide UCPath Steering Committee)

Project Team

• Radhika Prabhu, Project Director

• Susan McCutcheon, Program Manager

• Marion Randall, Functional Co-Lead

• Cindy Jones, Functional Co-Lead

• Bobbie Lasky, Academic Affairs

• Kush Arora, Business Intelligence

• Susana Lee, IT Lead, UCDHS

• Anantha Kadur, Project Manager

• Ilvana Mesic, IDM Systems

• Drew Pokorney, Project Manager, UCDHS

• Linda Durst, Workstream Lead

• Kelly Crabtree, Training Lead

• Other functional and technical resources

3

Why UCPath?

WHY:

Our UC HR/Payroll tools and processes are outdated.

 UC’s Personnel/Payroll Systems (PPS) is 35 years old and difficult to use

 PPS has 11 versions, with data definitions and policy/rules applied differently by each location

 UCPath includes the Human Resources

Information System (HRIS) modules which is currently a gap at UC Davis

 UC employees are performing manual calculations, workarounds, corrections and significant paper processing

 Is not able to meet the needs of UC’s complex and diverse employee population

WHO:

UC Board of Regents,

President, Leadership,

Chancellors, Controllers,

CHROs, and APDs.

 Recommended replacing PPS with a single, integrated UC-wide HR/Payroll solution

 Agreed to work toward conforming business practices

 Committed themselves to systemwide representation

4

System-wide Team Accomplishments

 Standardized and streamlined approximately 100 systemwide processes in the areas of payroll, benefits, finance/GL integration, absence management, compensation, and human resources/workforce administration

 Set up a systemwide shared services center in Riverside, CA that will process certain HR/payroll transactional work for the UC system. While awaiting the UCOP go live, these resources are currently providing PPS transaction processing support to pilot locations (UCLA, UCSC)

 Coordinated the design of a system-wide data model to allow locations to leverage design and development of common reporting and analytical tools

 During testing, converted data, successfully ran monthly payroll and sent information to downstream systems at UCLA

 Began foundational work on defining the UC-wide

IT Shared Services and identifying key move forward activities (role validation, knowledge management, end-to-end simulation, service level management)

 Put in place metrics reporting to track the status of testing and deploy

5

Some Significant Improvements

Paychecks

• Employees will have the option of splitting their direct deposit between as many three financial institutions.

• Paper paychecks will be printed by Wells Fargo and sent via U.S. mail.

Verification of employment

• A secure online automated application enables employees (or preauthorized verifiers with whom they are doing business) to quickly and securely confirm UC employment and/or income.

• Available 24 hours a day, seven days a week.

• Employees have control of the verification process by authorizing access to their information.

Streamlined onboarding

• Newly hired employees will have day-one access to benefits enrollments and other online resources.

• Transfer procedure will be standardized and centralized at UCPath, providing a more efficient relocation process.

6

UCPath Center - How will my questions get answered?

• Contact options include online portal, telephone, e-mail, regular mail and fax.

• Chat will be available in a future release.

• Employee services will be the first point of contact

• Call routing system will ensure calls are forwarded to the appropriate staff.

• Cases will be created for each inquiry

• A tiered escalation process will route complex cases to experts within the

UCPath Center.

7

Timeline and Implementation

September 2015 Throughout 2016

UCOP

Pilots

(UCLA, UCSC, UCM,

ASUCLA)

Mid 2017

Location Group A

TBD

(UC Davis is aiming for this group)

Late 2017

Location Group B

TBD

An Engagement Team will visit each location to determine the optimum go live date and will review:

 Current State of Project

Governance, funding, project resources, plan

 Contextual Concerns

Organizational model, business process alignment, location concurrent activities, current technologies

 Engagement Needs

Project structure, roles and responsibilities, escalation path, future development, tools and templates needed by location

8

UCOP Go Live Schedule

• The UCPath Executive Steering

Committee reviewed the proposed

UCOP deployment timeline and approach on February 18 th

• Of immediate concern is the timely completion of functional unit testing (FUT), which is currently behind expected pace

• Both UCOP and the UCPath Center are prepared for September go-live and support some operational tradeoffs, if necessary

• A final go-live timeline for UCOP isn’t expected until March when FUT results are known; however, all teams are currently operating under a project schedule based on a

September go-live

9

UC Davis Accomplishments

Local Business Process Inventory by Module

Local Future State Process Designs

 Created a framework

 Created inventory of processes to develop

 Prioritized and scheduled inventory

 Began development of processes

Absence Management (10)

Benefits (34)

Configuration (5)

Compensation (3)

General Ledger (28)

Payroll (30)

TAM/ePerformance (5)

Workforce Administration (43)

UCPath Data Warehouse & Analytics

 Created overall architecture

 Standardize tools and technologies

 Deployed a proof of concept

 Leveraged work done by the

Business Intelligence Collaboration

Group (BICG)

10

UC Davis Accomplishments

(cont.)

Communications Infrastructure

 Created ucpath.ucdavis.edu

 Created Confluence collaboration site

 Microsoft Project scheduling and reporting

 JIRA Issue tracking system

Central Team Interaction

 Each week, the Central Team requests information and input from the location

 From July through December 2014, 164 requests were received – averaging over

5 per week

40

30

20

10

0

Responses Sent to

Central Team

July - December 2014

11

Current UCPath Activities at UC Davis

Local Future State Business

Process Design

 Current state review

 Future state development

 Roles and responsibilities determination

 Alignment with operating model

Interaction with

Central Team on design, development and deployments

Operating Model Optimization

 Ensures alignment of all organizational units to a common vision

 Enables transformation

 Maximizes efficiencies

 Provides a consistent model for performance measurement

Infrastructure Development

 Hardware to enable real time data processing with UCPath

 Interfaces to integrate information from location downstream systems

 Business Intelligence reporting and analytics

Collaboration with other locations on design, development and deployment strategies and execution

12

13

Future Objectives

Estimated Go-

Live

90 Day

Location

Objectives

UCOP

2015

Complete Functional Unit Testing

(FUT) and begin System Integration

Testing (SIT)

Validate and improve conversion design and deployment

Pilots

(UCLA, UCSC, UCM,

ASUCLA)

Remaining

Locations

2016

Location Group A: Mid 2017

Location Group B: Late 2017

Agree to common implementation methodology and timelline sequencing

Complete resource based, bottomup project plan

Define and analyze business requirements to validate system and business needs achieved

Define resource needs to support

2015 prerequisite work

Onboard newly defined resource needs

Onboard newly defined resource needs

Operationalize project plan

Analyze prerequisiste work tools and templates for process and planning

Operationalize 2015 prerequisite work

2016

Location

Objectives

Post production Live on uCPath system and services

Full implementation mode and on schedule per project plans

2016 Central

Support

Post-porduction support Advance Team

Location Group A: Delivery Team

Location Group B: Advance Team when finished post-prod support for

Pilots

2016 Overall

Project

Governance

Full SC: meeting quarterly or as needed

SC-Subset:

UCLA/UCSC/UCM/ASUCLA steering team: meeting frequrency TBD, thru go-live

SC-Subset 'remaining locations' steering team - meeting frequency

TBD through go-live

Full SC: meeting quarterly or as needed

Full SC: meeting quarterly or as needed

14

UC Davis Schedule and Next Steps

Assuming a mid-2017 go live, our location schedule would be:

Jan Feb Mar Apr May Jun

2015

Jul Aug Sep Oct Nov Dec Jan

2016

Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

2017

Feb Mar Apr May Jun Jul

Design/Development Develop/Unit Testing

Finalize

Interfaces for

Testing

Functional Unit

Testing

SIT1

Review SIT

1 & Plan

SIT 2

PPT1

SIT2

PPT 2

UAT

Go

Live

Hyper

Support

Manual Data

Conversion

Test Data

Conversion 1

Test Data

Conversion 2

Test Data

Conversion 3

I/F Dev

Complete

Full Data Conversion 1

Full Data

Conversion 2

Final Data

Conversion

2015 Activities

 Analyze operating model

 Agree to common implementation methodology and timeline sequencing

 Define resource needs to support 2015 prerequisite work

 Onboard newly defined resource needs

 Complete design and development of local business processes

 Operationalize 2015 prerequisite work

2016 Activities

 Unit testing of local business processes

 Operating model alignment

 Finalize interfaces

 Data conversion analysis and testing

 Training and transitional tools development

15

Information Resources

 The UCPath Initiative’s Working Smarter website is the primary source for project information for faculty & staff: http://workingsmarter.universityofcalifornia.edu/projects/ucpath/overview/

 Campus site for UCPath information at http://ucpath.ucdavis.edu

 FAQs and Fact Sheets to inform, engage and involve on a timely basis

 Questions can be sent to ucpath@ucdavis.edu

16

Questions?