MICE The International Muon Ionization Cooling Experiment MUTAC meeting – 18-04-2007 Alain Blondel 1 MICE 1. Why, what and who? 2. MICE Funding/status/schedule -- Phase I -- Phase II 3. Conclusions Collaboration membership and organization in appendix http://mice.iit.edu MUTAC meeting – 18-04-2007 Alain Blondel 2 IONIZATION COOLING principle: this will surely work..! reality (simplified) ….maybe… A delicate technology and integration problem Need to build a realistic prototype and verify that it works (i.e. cools a beam) Can it be built? Operate reliably? What performance can one get? Difficulty: affordable prototype of cooling section only cools beam by 10%, while standard emittance measurements barely achieve this precision. Solution: measure the beam particle-by-particle state-of-the-art particle physics instrumentation will test state-of-the-art accelerator technology. MUTAC meeting – 18-04-2007 Alain Blondel 3 10% cooling of 200 MeV/c muons requires ~ 20 MV of RF single particle measurements => measurement precision can be as good as D ( e out/e in ) = 10-3 never done before either… Coupling Coils 1&2 Spectrometer solenoid 1 Matching coils 1&2 Focus coils 1 Focus coils 2 Focus coils 3 Matching coils 1&2 Spectrometer solenoid 2 m Beam PID TOF 0 Cherenkov TOF 1 RF cavities 1 Variable Diffuser Incoming muon beam RF cavities 2 Liquid Hydrogen absorbers 1,2,3 Downstream TOF 2 particle ID: KL and SW Calorimeter Trackers 1 & 2 measurement of emittance in and out MUTAC meeting – 18-04-2007 Alain Blondel 4 Challenges of MICE: (these things have never been done before) 1. Operate RF cavities of relatively low frequency (201 MHz) at high gradient (nominal 8MV/m in MICE, 16 MV/m with 8 MW and LN2 cooled RF cavities) in highly inhomogeneous magnetic fields (1-3 T) dark currents (can heat up LH2), breakdowns 2. Hydrogen safety (substantial amounts of LH2 in vicinity of RF cavities) 3. Emittance measurement to relative precision of 10-3 in environment of RF bkg requires low mass (low multiple scattering) and precise tracker fast and redundant to fight dark-current-induced background precision Time-of-Flight for particle phase determination (±3.60 = 50 ps) complete set of PID detectors to eliminate beam pions and decay electrons and… 4. Obtaining (substantial) funding for R&D towards a facility that is not (yet) in the plans of a major lab MUTAC meeting – 18-04-2007 Alain Blondel 5 MUTAC meeting – 18-04-2007 Alain Blondel 6 Design of MICE detectors and beam test results satisfy the above requirements MUTAC meeting – 18-04-2007 Alain Blondel 7 Aspirational MICE Schedule now (~unchanged since march 2006) m STEP I beam line + detector commissionning starts August 2007! STEP II December 2007 STEP III STEP IV R&D 1 October 2007 March 2008 PHASE I Early 2009 STEP V Summer 2009 STEP VI MUTAC meeting – 18-04-2007 Alain Blondel 2010 PHASE II 8 The MICE BEAM LINE MUTAC meeting – 18-04-2007 Alain Blondel 9 MICE Target ISIS pulses at 50Hz with flat top for ~2ms. Electromagnetic driver dips target in and out in~3ms. Resp: Sheffield, Glasgow actuator: in lab Target test succesful Oct-Nov06 beam at 50Hz/64 (1.28s) only 10 A target drive (need ~40) Review on 6 march 2007 Ballistic control of target critical… will be operated 3 months in beam before October run on the beam line MUTACdetectors meeting – 18-04-2007 shielded in place Alain Blondel 10 Beam line Construction at RAL is in full swing layout in the vault PSI solenoid PSI sol. cryo in the hall drilling holes quads refurbishment MUTAC meeting – 18-04-2007 Alain Blondel 11 MICE Hall and infrastructure: INSTALLATION Commissng Operation Vault closed Cycle start MUTAC meeting – 18-04-2007 Alain Blondel 12 No access target upstream beam line upstream beam monitors B1 controled PSI sol B2 Collimator CV and CH CKOV and TOF0 MUTAC meeting – 18-04-2007 Alain Blondel 13 Tracker resp: Japan,UK,US two identical trackers with 5 planes of 3-views, 440 mm point resolution achieved scintillating fiber detector read-out with VPLCs (7-fold ganging of 350 mm diameter fibers) Prototypes with 3, 4 triple-planes were built and tested on cosmics and test beam at KEK (in 1 T mag field) ==> curvature measurement OK. ~330 mm 1000 mm Improved QA procedures for final production Full production of tracker started in January 2007 Fibre preparation & ribbon production at FNAL complete First production VLPC cryostat is under construction (works at 50Hz mains!) COMMISSION AT RAL STARTING in JUNE 2007 MUTAC meeting – 18-04-2007 Alain Blondel 14 TOF0, TOF1, KL; SW TOF is Responsibility of M. Bonesini et al (INFN Milano, Pavia, Roma + Gva & Sofia) Technically: Two layers (x and y) of 4cm wide hodoscopes 60 ps resolution achieved in test beam Phototubes/electronics/magnetic shield defined construction of TOF0 and TOF1 underway all phototubes and scintillator purchased electronics purchased or under construction ==> on course for delivery at RAL in August 2007 Very useful tools for beam diagnostics alignment etc… KL calorimeter (4 X0 of lead sci-fibers sandwitch) first recognition of electrons Under construction at ROMA III (L. Tortora) delivery in october 2007 SW calorimeter (100X100 X 80 cm deep scintillator ranger for positive muon ID) First prototype layer under construction in Trieste (FNAL/Trieste/GVA collab.) aim is to be operational in 2008 for full downstream PID capability MUTAC meeting – 18-04-2007 Alain Blondel 15 KL calorimeter L=90 60 tracker L=60 65 SW calorimeter Spectrometer solenoid TOF and shielding MUTAC meeting – 18-04-2007 Alain Blondel 16 MICE DAQ & Trigger Gva, UK, IIT, Osaka data rate ~1MHz … DATE framework (ALICE expt @cern) Readout by VME Trigger signals and run modes established Control and monitoring established (Daresbury) February, 2007: DAQ test bench set up at Uni-Geneva March, 2007: Order MICE Stage 1 FEE hardware July, 2007: Move MICE DAQ system to RAL September, 2007: DAQ working in MICE Stage 1 MUTAC meeting – 18-04-2007 Alain Blondel 17 Preparing for PHASE I : software, analysis & DATA Challenge 1. Basic simulation and reconstruction of MICE is complete for the various steps Both G4MICE and MUCOOL are used. 2. Putting it all together to do analysis (particle reconstruction, particle ID algorithms Single particle amplitude and emittance calculations, etc…) 3. Data challenge launched in March 2007 4. Shortage of hands (general in MICE) is particularly felt here. Example Bias on emittance due to muon decays Would be ~0.5% (i.e. 5% error on cooling meast) Reduced to <<0.1% by PID+ tracker This uses tracker & TOF info and PID signals +Neural Network MUTAC meeting – 18-04-2007 Alain Blondel 18 Run plan -- steps I and II m STEP I Aug.- Nov. 2007 STEP II dec. 2007 to march 2008 Goal: Establish beam match and whether we have all knobs necessary to draw emittance vs. transmission curve. Measure emittance Runnng time: Take 200-400 muons per 1ms spill once per second In steps I-IV 1% (0.1%) emittance meast will take <1 (<100) minute 10 times longer in steps V and VI where phase matters. preliminary estimate total for steps I & II: 70 days STEP I requires 60 shifts (20 days of running) beam line commissionning, target tuning (rates), DAQ and detector shake down STEP II requires 150 shifts (50 days, will extend in 2008) Alignment of beam x,x’,y,y’, (Lack of) dispersion, check range of transverse emittance, and range of momenta measure emittance and… publish first paper MUTAC meeting – 18-04-2007 Alain Blondel 19 Instrumentation/commissioning strawman schedule 2007 (from february 2007) Task Milestone Commissioning period U/stream diagnostics 13Jul07 14Jul07 – 08Aug07 CKOV 1 14Jul07 21Jul07 – 08Aug07 D/stream diagnostics 14Aug07 15Aug07 – 22Agu07 TOF 0 14Aug07 15Aug07 – 22Aug07 Tracker (no solenoid) 22Aug07 23Aug07 – 30Aug07 TOF 1 22Aug07 23Aug07 – 30Aug07 Downstream scint. 22Aug07 23Aug07 – 30Aug07 KL 31Aug07 01Sep07 – 15Sep07 start phase I data taking 02Oct07 02 Oct07 - Tracker solenoid 01Nov07 02Nov07 – 22Nov07 Tracker+ diffuser +TOF1+KL in solenoid 22Nov07 22Nov07 – 30Nov07 Step II, first run start 30Nov07 23Nov07 – 21Dec07 End of run party 21Dec07 MUTAC meeting – 18-04-2007 Alain Blondel 20 2. Preparing for phase II LH2 Absorber (UK, US, Japan) AFC module (UK) RF R&D (Mucool-NFMCC) RF power (LBNL+ CERN -> Daresbury lab RAL) Coupling Coils (LBNL-Harbin ICST) SW calorimeter (GVA-FNAL-Trieste) Main technological uncertainty towards PHASEII is MUCOOL RF R&D. This emphasizes the need for the MUCOOL coupling coil! Main issue is funding. MUTAC meeting – 18-04-2007 Alain Blondel 21 The complete cell of the study II cooling channel is composed of two RF coupling-coil modules with an absorber-focus pair module in the middle This corresponds to step VI. Although ionization cooling could already be observed in step V, several aspects of the system such as -- flip between two modules and longitudinal emittance growth would not be covered fully. The complete MICE project extends to step VI (MICE needs two RFCC modules and three AFC modules) MUTAC meeting – 18-04-2007 Alain Blondel 22 RF power system completion of test stand in 2007 (Daresbury Lab) relationship with CERN & phase 2 FC Module Tender spec complete announcement in EU journal made Hydrogen System Spec almost ready for review Safety review and HAZOP for H2 system has been passed. MUTAC meeting – 18-04-2007 Alain Blondel Metal hydride storage tank with capacity of 20 m3 of hydrogen 23 Summary of funding situation (I) -- UK: PhaseI = 9.7M£ (OST+ rolling grants + CCLRC contributions) Phase II bid submitted in July 2007. Peer review positive; recommended 100% of support for engineering 2 + option for 3d focus pair modules support for exploitation Merge of CCLRC and PPARC into STFC leads to general review during next year reconcilitation for one year funding. Authorization to post official notice for FC module in EU journal (1st step in call for tender process) -- USA: funding from the NFMCC (DOE baseline scenario 4.125M$) + 4MW RF source + NSF grant (IIT) 300k$ + MRI grant (tracker + tracker solenoid) 750k$ (NB tracker part was reduced substantially by D0 electronics deal) + DOE suppl. for MUCOOL coupling coil 300k$ + Fermilab 800k$ + NSF tracker proposal by Pr G. Hanson 400 k$ (postdocX3 years) (+ equal amount of startup fund) further request submitted: NSF MRI for MUCOOL CC (should know by june) + other avenues being investigated (e.g. PIRES) MUTAC meeting – 18-04-2007 Alain Blondel 24 Summary of funding situation (II) -- Japan: Very important contribution by Osaka and KEK was interrupted in 2006 Bids have been resubmitted for US-Japan coll. and Japan No effect on tracker. Affects absorber bodies and controls. -- Switzerland: PSI solenoid Uni-Geneva+SNF (DAQ, trigger + TOF0 PMTS + 2PhD+1RA ~ 1000 kCHF so far) additional request for online (100kCHF) in preparation +Bulgaria collaboration (travel, PID electronics) (74kCHF granted) -- CERN: 1 RF station providing 4MW (173kCHF or 110k€ + 0.3 FTE) agreed on 3 Nov 2006: Maurizio Vretenar charged of execution -- Netherlands: (Mag probes) -- Italy: (TOF, Calorimeter) 500 k€ from INFN + 200 k€ from RAL end-of-year 2006 to completion project recognized within INFN NTA (New Techniques of Acceleration) -- China: (MICE propose to build + bid submitted (requires NFMCC coupling coils) first coupling coil with US funding (MUCOOL coupling coil) from ICST to HIT for + delivery of two MICE coupling coils to purchase the conductor and power supplies) MUTAC meeting – 18-04-2007 Alain Blondel 25 Summary of funding situation (III) Missing but requested: 1. 2. 3. 4. UK: Phase II bid US: Mucool coupling coil MRI bid (rest is within MICE 2005 5yrs plan) China: MICE coupling coils Japan: Absorbers bodies and controls + everywhere: manpower MUTAC meeting – 18-04-2007 Alain Blondel 26 Beyond PHASEII -- Ideas for « Phase III » ONCE PHASEII will be completed, having equipped the MICE hall with -- spectrometers, TOF and PID able to measure emittance to 10-3 -- 8 MW of 201MHz RF power -- 23 MV of RF acceleration -- Liquid Hydrogen infrastructure and safety MICE can become a facility to test new cooling ideas. Such ideas were proposed: A. with the existing MICE hardware to test optics beyond the neutrino Factory study II: non flip optics, low-beta optics (down to 5 cm vs 42 cm nominal) other absorber materials He, Li, LiH, etc.. LN2 cooled RF cavities B. with additional hardware: -- A. Skrinsky to test a lithium lense available at Novosibirsk -- Muons Inc. to test a section of helicoidal channel (MANX) MUTAC meeting – 18-04-2007 Alain Blondel 27 Conclusions 0. MICE will be taking data in 166 days 1. The collaboration is making excellent progress in all fronts: Simulations, R&D, engineering, prototyping and construction The funding for phase I is complete, but manpower is never in excess US contributions have been fundamental since the start of MICE (concept,engineering) and continue to be (detectors, electronics) 2. MICE will start phase I data taking in summer/fall 2007 Steps I, II, III will allow beam tuning, first measurement of emittance and verification of systematics. 3. The funding for phase II is submitted and under review. The MUCOOL R&D is critical to the continuation of the experiment and suffers from the lack of a coupling coil NOW. 4. MICE phase II requires 2 RFCC modules and 3 AFC modules to allow full benefit from MICE until step VI. 5. Our aim is to assure that step VI can be performed in good time for 2010. MUTAC support will be highly valuable for this. MUTAC meeting – 18-04-2007 Alain Blondel 28 Intense K physics Intense Low-E muons Neutrino Factory Higgs(es) Factory(ies) Energy Frontier -> 5 TeV circa 1997-1999 US, Europe, Japan MUTAC meeting – 18-04-2007 Alain Blondel Possible layout of a muon complex on 29 the CERN site. Major challenges tackled by R&D expts High-power target . 4MW . good transmission MERIT experiment (CERN) Fast muon cooling MICE experiment (RAL) Fast, large aperture accelerator (FFAG) EMMA (Daresbury) ISS baseline MUTAC meeting – 18-04-2007 Alain Blondel 30 Muon Ionization Cooling Experiment MICE FIRST BEAM IN OCTOBER 2007 Final PID: TOF Calorimeter Demonstrate feasibility and performance of a section of cooling channel by 2010 4T spectrometer II Cooling cell (~10%) b=5-45cm, liquid H2, RF Status: Approved at RAL(UK) First beam: 10-2007 Funded in: UK,CH,It,JP,NL,US Further requests: JP,UK,US, PRChina… 4T spectrometer I Single-m beam ~200 MeV/c TOF Liquid-hydrogen absorbers Prototyping: Scintillating-fiber tracker MUTAC meeting – 18-04-2007 Alain Blondel 200MHz RF cavity with beryllium31 windows MICE is an international effort from the start. NUFACT00 2000-2001 NUFACT01 7:00 am Sept. 2001 November 2001 January 2002 June 2002 January 2003 July 2003 October 2003 December 2003 June 2004 20 December 2004 March 2005 April 2005 June 2006 July 2006 October 2007 Re-activated the recognized need for muon cooling expt Workshops on Cooling Experiment (CERN, Chicago, London) Steering group formed Workshop at CERN where final experiment took shape. Letter of Intent (LOI) submitted to PSI and RAL PSI cannot host experiment, will collaborate (beam solenoid) RAL IPRP Review Panel encouraged submission of a proposal Proposal submitted Recommendation by International Peer Review Panel ‘Scientific approval’ letter by RAL CEO John Wood Gateway 1 review Gateway 1 passed on ‘amber’ Gateway 2/3 passed (MICE PHASE I) UK phase I funding approved by PPARC and CCLRC 9.7 M£ US NFMCC proposes a 5-year plan to fund MICE Harbin ICST joins MICE collaboration UK phase II bid submitted …. First beam in MICE step I MUTAC meeting – 18-04-2007 Alain Blondel 32 THE MICE COLLABORATION -128 collaborators- Universite Catholique de Louvain, Belgium University of Sofia, Bulgaria The Harbin Institute for Super Conducting Technologies PR China INFN Milano, INFN Napoli, INFN Pavia, INFN Roma III, INFN Trieste, Italy KEK, Kyoto University, Osaka University, Japan NIKHEF, The Netherlands CERN Geneva University, Paul Scherrer Institut Switzerland Brunel, Cockcroft/Lancaster, Glasgow, Liverpool, ICL London, Oxford, Darsbury, RAL, Sheffield Argonne National Laboratory, Brookhaven National Laboratory, Fairfield University, University of Chicago, Enrico Fermi Institute, Fermilab, Illinois Institute of Technology, Jefferson Lab, Lawrence Berkeley National Laboratory, UCLA, Northern Illinois University, University of Iowa, University of Mississippi, UC Riverside, University of Illinois at Urbana-Champaign USA MUTAC meeting – 18-04-2007 Alain Blondel 33 UK Internal MICE Organization numbers of meetings per year MICE charter was voted in 2003. Spokesperson election concluded 15/4/2007 Collaboration board 3 1 rep/institute elects spokesperson reviews EB activity votes on decisions prepared by EB chair: Dan Kaplan (IIT) 3 collaboration meetings/yr 1 video conf/month Executive Board 12 spokesperson deputy Project manager software coord. analysis coord. 2 reps from UK,US,EU,JP manages collaboration life nominates personels prepares decisions for CB Editorial board ~3 Chair Dan Kaplan controls quality of publications proposes publication policy Speakers bureau ~3 Chair Ken Long solicits talks at conferences and proposes speakers MUTAC meeting – 18-04-2007 Alain Blondel Technical Board 12 Project manager: Paul Drumm Deputies Bross, Lau, Virostek management of the project reports to EB +spokesperson +deputy +software coord. +level 2 WBS coordinators enforces design and safety reviews change control documents exp.design Installation/Commissionning/Operations (MICO) NEW 1 representative of each MICE subsystem 12 Analysis forum Chair John Cobb discusses how to achieve the physics goals of the experiment 34 Single particle Amplitude Measurements in MICE Increase of central phase space density Transmission versus amplitude Large emittance beam Transmission versus amplitude Large emittance beam Empty channel Channel with absorbers & RF Emittance = RMS amplitude of muons in beam MICE can measure the amplitudes of single muons (6D radius in emittance ellipsoid) Increase in central phase space density Dramatic demonstration of Cooling MUTAC meeting – 18-04-2007 Alain Blondel 35 RF cavity test at fermilab: MUTAC meeting – 18-04-2007 Alain Blondel 36 201MHz cavity in magnetic field? At this point we do not know if a 200 MHz cavity can operate reliably with 4T fields from the focus pairs Performance of NUFACT is strongly affected by this (muon decays!) NUFACT performance assumes 12 MV/m MICE normal operation is 8MV/m (8MW on 8 cavities at room Temp) MICE can reach 12 MV/m this by cooling all cavities with LiqN2 MICE can reach up to 16MV/m (8MW on 2 cavities or 4 LiqN2-cooled) MUCOOL single cavity can reach 16 MV/m but present MUCOOL magnet only allows 0.2T on window with very divergent B field will be tried anyway - instrum. ready strong multipactor was observed in 800 MHz cavity--> What is really needed here is MUCOOL Coupling coil MUTAC meeting – 18-04-2007 Alain Blondel 37 Total channel length 10 m Total energy 10-15 MJ Z axis muon beam injection LHe absorber inside the channel LHe vessel diameter 1.1 m Outer diameter 1.4 m Front end 3 m matching section LHe volume (1.1m dia.) 10 m³ LHe volume absorber (0.5m dia.) 3 m³ 4 m Cooling Channel Far end 3 m matching section MUTAC meeting – 18-04-2007 Alain Blondel 38