Overview

advertisement
Federal Highway Administration
Emergency Relief (ER) Program
Brian Hogge
Field Operations Team Leader
July 2013
Background
Authorized by Congress in 23 USC, Section 125.
Repair or reconstruction of federal-aid highways and roads on
federal lands damaged by:
 Natural disasters (floods, hurricanes,
earthquakes, tornadoes, landslides,
wildfires, severe storms)
 Catastrophic failures from an
external cause (barge striking a
bridge pier or truck crash and fire)
2
General Requirements
 Disaster Declaration
 Federal-aid highway or federal lands
roadway
 Minimum event threshold is $700,000
 Minimum site threshold is $5,000
Funds Available
 Annual Authorization of $100,000,000
 Supplemental Appropriations provided by Congress
 Unneeded funds withdrawn from states
4
Federal-aid Highways
Federal-aid highways other than those functionally classified
as:
a) Local Road
b) Rural Minor Collector
Local roads and rural minor collectors may be eligible for
other federal aid, but they are not eligible for FHWA ER
funds.
Two Categories of Repair
1. Emergency Repairs
 Restore essential traffic, minimize the extent of damage,
or protect the remaining facilities
 Eligible at 100% within 180 days
 Eligible at normal share beyond 180 days*
*The 180 day time period for 100% eligibility of emergency
repairs will be extended if a State cannot access a site to
evaluate damages and the cost of repair.
Two Categories of Repair
2a. Permanent Repairs concurrent with Emergency Repairs
 NEPA not required
 Follow Emergency Repair contracting method
 Eligible at normal pro rata share (not 100%)
7
Two Categories of Repair
2. Permanent Repairs
Restore highway to pre-disaster conditions*
*The total cost of a project may not exceed the cost of
repair or reconstruction of a comparable facility. A
“comparable facility” is a facility that meets the current
geometric and construction standards required for the
types and volume that the facility will carry over its
design life.
Eligible at normal pro rata share
8
Resilience
Design and construction of repairs should consider the longterm resilience of the facility. Resilience as the capability to
anticipate, prepare for, respond to, and recover from
significant multi-hazard threats with minimum damage to
social well-being, the economy, and the environment. A riskbased analysis should be used when designing and
constructing repairs to ensure they are cost effective and to
reduce the potential for future losses. The analysis should
apply the best available scientific and economic information to
forecast and assess future risk factors.
9
Betterments
 Betterments are added protective features
 Changes that modify highway function or character
 Betterments are generally not eligible
 May be eligible if economically justified as beneficial to the
ER program
10
Eligible Items
 Preliminary Engineering
 Construction Engineering
 Right-of-Way
 Designated Detours
 Traffic Damages (limited applicability)
 Debris Removal
 Traffic Control Devices
 Roadside Appurtenances
11
Debris Removal
 Debris deposited as a direct result of the disaster
 Other debris may be eligible for FEMA funding*
 Some debris removal may be considered “emergency repair”
 Removal to outside edge of shoulder
 Debris considered to be a safety hazard
 Additional debris removal (within right-of-way) is eligible as
permanent repair
*In certain instances, debris removal previously eligible for ER
funding will only be eligible for FEMA funding. See the ER
Manual for details.
12
Contract Requirements
 Emergency repairs do not require prior FHWA authorization
 Permanent repairs require prior FHWA authorization
 Generally, ER contract requirements are the same as regular
federal-aid projects
 Pre-established emergency repair contracts may be used
13
Davis-Bacon
 Required for any construction work
 Not required for debris removal only without any incidental
construction
 Davis-Bacon requirements may only be waived by a
Presidential Executive Order
14
Environmental Documents
Emergency Repairs:
 23 CFR 771.117(c): The following actions meet the
criteria for CEs… and normally do not require any
further NEPA approvals by the Administration.
 Emergency repairs are classified as categorical
exclusions under 23 CFR 771.117(c)(9)(i).
 Other “c list” activities include landscaping, rideshare
activities, bus and rail car rehabilitation, etc.
15
Environmental Documents
Permanent Repairs:
 23 CFR 771.117(c): The following actions meet the
criteria for CEs… and normally do not require any
further NEPA approvals by the Administration.
 Permanent repairs are classified as categorical
exclusions under 23 CFR 771.117(c)(9)(ii).
 Other laws still apply
 Threatened & Endangered Species Act
 Clean Water Act
 Etc.
16
ER Program Changes
The State should submit to the FHWA Division Administrator
a program of projects which defines the work needed to
restore or replace the damaged facilities within 3 months of
the receipt of the initial disaster notification.
States are required to submit an application for ER funding to
FHWA within two calendar years of the date of the disaster.
The application must include a comprehensive list of all
eligible project sites and repair costs.
ER projects shall be promptly constructed. Projects that have
not advanced to the construction obligation stage by the end
of the second fiscal year following the disaster occurrence will
not be advanced unless suitable justification is provided to
warrant retention is furnished to the FHWA.
17
Programmatic Agreement
 Signed in March 2012
 Allows programmatic approval instead of case-by-case
approvals
 Permanent repairs performed concurrently with emergency repairs
 Force account work and contracting methods
 Sets a threshold for programmatic approvals of $150,000 per
site
 Allows MnDOT to sign DDIRs under $150,000 per site
 Outlines eligibility and guidance for each type of work
 Requires DDIR completion within 12 weeks of completion of
work for Emergency Repairs and within 180 days of date of
disaster for Permanent Repairs
18
Questions?
Image from June 2012 flood in Duluth, MN
19
Download