National Institutes of Health Building 37 Modernization Katie L. McGimpsey Mechanical Option The Pennsylvania State University Department of Architectural Engineering Spring 2005 Thesis Presentation Outline • General Project Information • Project Team • Existing Conditions • Redesign Goals • Mechanical Redesign • Solar Analysis • Structural Analysis • Conclusions • Acknowledgements • Questions Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University General Project Information • Located in Bethesda, Maryland on the National Institutes of Health (NIH) campus • Began modernization phases in 1997 • $82.8 million Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Presentation Outline • General Project Information • Project Team • Existing Conditions • Redesign Goals • Mechanical Redesign • Solar Analysis • Structural Analysis • Conclusions • Acknowledgements • Questions Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Project Team • Owners: – National Institutes of Health (NIH) – National Cancer Institute (NCI) • Architects: – FLAD & Associates, Inc. – Louviere, Stratton & Yokel (LSY) • Engineers: – AEPA Architects & Engineers, P.C. – Affiliated Engineers, Inc. (MEP) – James Posey Associates, Inc. (Consulting Engineers) – Aerosol Monitoring & Analysis (Environmental) – Rathgeber/Goss Associates (Structural) – JBG Engineers (Audiovisual) • General Contractor: – Whiting Turner • CM: – Smith Management Construction, Inc. Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Presentation Outline • General Project Information • Project Team • Existing Conditions • Redesign Goals • Mechanical Redesign • Solar Analysis • Structural Analysis • Conclusions • Acknowledgements • Questions Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Existing Conditions • Architectural Features – Two circulation towers – Four utility corridors • Architectural Design – – – – 21,889 m2 (235,613 ft2) 6 stories above grade Offices & laboratories Mechanical penthouse Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Existing Conditions • Electrical/Lighting – Underground duct system from Bldg 36 – Main distribution: 4000A, 480Y/277V, 3-phase, 4-wire – Transformers: (3) 2500kVA, 13.8kV to 480Y/277V, 3phase, 4-wire – Fluorescent light fixtures: RF suppression ballasts – Laboratory lighting density = 2.5 W/m2 Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Existing Conditions • Structural – Steel column grid matrix – Pre-cast concrete panels – Pre-tensioned concrete floor slabs • Roof System – Concrete slab on metal roof deck – Roof drains Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Existing Conditions • Mechanical – (8) 100% OA AHUs supplying to a zoned VAV system • Approximately 28,000-29,000 L/s (59,000-61,000 cfm) – (8) Fume exhaust fans 32,000 L/s (68,000 cfm) – District heating/cooling • Chilled water: 6ºC, (3) constant speed tertiary pumps • Steam: 20,000 lbs/hr, 165 psi • Fire Protection – Passive System • Corridors: 1 hour fire rating • Independent risers for fume hoods – Active System • Zoned automatic sprinkler system Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Presentation Outline • General Project Information • Project Team • Existing Conditions • Redesign Goals • Mechanical Redesign • Solar Analysis • Structural Analysis • Conclusions • Acknowledgements • Questions Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Redesign Goals • Mechanical – – – – Energy Efficient Decreased Cooling Load Cost Savings State-of-the-Art Laboratory and Research Facility • Solar – Decrease Peak Electrical Load – Cost Efficient • Structural – Support Additional Loads of New Equipment Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Redesign Goals • Mechanical Design Conditions Outdoor Design Conditions Cooling Heating DBT ºC WBT ºC 34.3 24.1 -10.3 N/A Indoor Design Conditions Cooling Heating Katie L. McGimpsey Mechanical Option DBT ºC % RH 23 50 21 50 NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Presentation Outline • General Project Information • Project Team • Existing Conditions • Redesign Goals • Mechanical Redesign • Solar Analysis • Structural Analysis • Conclusions • Acknowledgements • Questions Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Mechanical Redesign • Passive Desiccant Dehumidification – Energy Recovery – Cross-contamination concerns with fume hoods – Based on SEMCO model: EXCLU-SIEVE 3 วบ molecular sieve desiccant coating Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Mechanical Redesign • SEMCO EXCLU-SIEVE TE3-70 Model AHU Face Velocity Pressure Loss Effectiveness Purge Volume Chiller Reduction Capacity Boiler Reduction Capacity Fpm In. wg % Supply Return Supply Return cfm tons boiler hp AHU-1 800 0.8 83.5 1.73 0.63 1.22 0.51 3800 336.23 147.12 AHU-2 850 0.9 82.5 1.73 0.63 1.22 0.51 3800 347.44 152.03 AHU-3 850 0.9 82.5 1.73 0.63 1.22 0.51 3800 347.44 152.03 AHU-4 800 0.8 83.5 1.73 0.63 1.22 0.51 3800 336.23 147.12 AHU-5 800 0.8 83.5 1.73 0.63 1.22 0.51 3800 336.23 147.12 AHU-6 800 0.8 83.5 1.73 0.63 1.22 0.51 3800 336.23 147.12 AHU-7 850 0.9 82.5 1.73 0.63 1.22 0.51 3800 347.44 152.03 AHU-8 850 0.9 82.5 1.73 0.63 1.22 0.51 3800 347.44 152.03 Katie L. McGimpsey Mechanical Option Unit Effectiveness Cooling Unit Effectiveness Heating NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Mechanical Redesign • Performance Data – – – – – Velocity: 900 fpm Wheel efficiency: 76% Pressure drop: 0.94 in. wg Wheel model size: 70 Airflow rate: 29,900 L/s (63,360 cfm) C = 89.4 in B = 79.1 in • Unit Dimensions – Net weight: 4680 lbs – Flow area/side: 70.4 ft2 – Nominal airflow: 26,500 L/s A = 171.5 in (56,000 cfm) Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 W = 23.0 in D = 84.3 in The Pennsylvania State University Mechanical Redesign AHU-# Equipment First Cost ($) Installation Cost ($) First Cost Savings ($) Immediate Payback w/ Positive PCV ($) Cooling Capacity Required (tons) Existing Cooling Load (tons) Heating Capacity Required (MBH) Existing Heating Load (MBH) AHU-1 45,000 22,500 60,362 233,838 161.59 178.6 1165 415.7 AHU-2 45,000 22,500 64,030 241,280 168.02 204 1217 105.8 AHU-3 45,000 22,500 64,030 241,280 168.02 175 1217 104.1 AHU-4 45,000 22,500 60,362 233,838 161.59 168.2 1165 87.1 AHU-5 45,000 22,500 60,362 233,838 161.59 167.8 1165 80.3 AHU-6 45,000 22,500 60,362 233,838 161.59 167.1 1165 72.4 AHU-7 45,000 22,500 64,030 241,280 168.02 167.4 1217 74.3 AHU-8 45,000 22,500 64,030 241,280 168.02 165.7 1217 80.9 Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Presentation Outline • General Project Information • Project Team • Existing Conditions • Redesign Goals • Mechanical Redesign • Solar Analysis • Structural Analysis • Conclusions • Acknowledgements • Questions Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Solar Analysis • Photovoltaic (PV) Solar Cells – Converts solar radiation into electric power – Feasibility • 4-5kWh/m2/day – Peak Electric Load • 5,846,644 kWh – BP Solar 4160 S • 62.7”x31.1” • 2480 modules • 512,216 kWh Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Solar Analysis Total Initial Costs = $3,424,712 Photovoltaic Project Cumulative Cash Flows NIH Building 37 Modern., Bethesda, Maryland Total Initial Costs: Renewable energy delivered (MWh/yr): 512.216 $ 3,424,712 13 14 Net average GHG reduction (tCO2/yr): 241.47 30,000,000 25,000,000 Cumulative Cash Flows ($) 20,000,000 15,000,000 10,000,000 5,000,000 0 0 1 2 3 4 5 6 7 8 9 10 11 12 15 16 17 18 19 20 21 22 23 24 25 (5,000,000) IRR and ROI: 52.2% Katie L. McGimpsey Mechanical Option 2.1 years Years Year-to-positive cash flow: 2.1 yr NIH Building 37 Modernization Spring 2005 Net Present Value: $ 8,150,422 The Pennsylvania State University Presentation Outline • General Project Information • Project Team • Existing Conditions • Redesign Goals • Mechanical Redesign • Solar Analysis • Structural Analysis • Conclusions • Acknowledgements • Questions Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Structural Impact Analysis • Increased Loading Mechanical Equip. 4,680 lbs PV Solar Modules 84,320 lbs Total 121,760 lbs = 121.8 kips • ASCE 7-98 – Roof Live Load (Lr=20R1R2=16 psf) – Reduction in Live Load • LRFD – Member sizing (Columns and Composite Beams) Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Structural Impact Analysis Roof Design NonColumn Design Mechanical Floor composite Design 1.3C24 with t=3.3” LW concrete slab W12x26 Composite Beam 253 kips 203kips 516 kips 413 kips 165N4k Joist Girder 778 kips 623 kips Composite 3VLI17 with t=6.5” NW concrete slabs Katie L. McGimpsey Mechanical Option 1040 kips 16K2 Joists 833 kips with 2 Rows Bridging NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Presentation Outline • General Project Information • Project Team • Existing Conditions • Redesign Goals • Mechanical Redesign • Solar Analysis • Structural Analysis • Conclusions • Acknowledgements • Questions Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Conclusions • Recommendations Total Equipment First Cost ($) Installation Cost ($) First Cost Savings ($) Immediate Payback w/ Positive PCV ($) Cooling Capacity Required (tons) Existing Cooling Load (tons) Heating Capacity Required (MBH) Existing Heating Load (MBH) 360,000 180,000 497,568 1,900,472 1318.44 1393.8 9530 10206 Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Presentation Outline • General Project Information • Project Team • Existing Conditions • Redesign Goals • Mechanical Redesign • Solar Analysis • Structural Analysis • Conclusions • Acknowledgements • Questions Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Acknowledgements • Special Thanks to… – – – – – – – The AE Department, Staff & Faculty AEI sponsor: Michael Soong LSY sponsors: James Louviere and Christine Ward Smith Management sponsor: Randy Baer Mechanical Professors, especially Dr. Jim Freihaut My Family and Friends AE Class of 2005 Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University Questions Katie L. McGimpsey Mechanical Option NIH Building 37 Modernization Spring 2005 The Pennsylvania State University