Project Brief & Business Case Blackboard Analytics Project Project number: 608284 Prepared by: Cris Deagon Last modified: 14 March 2016 PAB request number: <PAB Request Number> Approved by PAB: DD/MM/YY Approved by ITAG: DD/MM/YY Governance Model: Steering Committee (or) AD Management (or) Team Management Blackboard Analytics 1 Business Case ....................................................................................................................... 3 1.1 Background ........................................................................................................................ 3 1.2 Business Rationale for the Project ..................................................................................... 3 1.3 Business Benefits / Rewards ............................................................................................. 3 1.4 Investment Appraisal.......................................................................................................... 3 1.5 Options Considered ........................................................................................................... 4 1.6 Potential for Collaboration .................................................................................................. 4 1.7 Capacity Requirements ...................................................................................................... 4 2 Project Definition .................................................................................................................... 5 2.1 Objectives .......................................................................................................................... 5 2.2 Approach ............................................................................................................................ 5 2.3 Scope ................................................................................................................................. 5 2.4 Deliverables ....................................................................................................................... 6 2.5 Constraints ......................................................................................................................... 6 2.5.1 Schedule ................................................................................................................. 6 2.5.2 Cost ......................................................................................................................... 7 2.5.3 Future/On-going Costs ............................................................................................ 8 2.6 Interfaces and Dependencies ............................................................................................ 9 2.7 Assumptions ..................................................................................................................... 10 3 Project Organisation Structure ............................................................................................. 11 4 Project Plan .......................................................................................................................... 12 4.1 Project Procurement Plans .............................................................................................. 12 5 Communication Plan ............................................................................................................ 13 6 Change Management Plan .................................................................................................. 14 7 Project Controls .................................................................................................................... 15 7.1 Project Tolerances ........................................................................................................... 15 7.2 Project manager Controls ................................................................................................ 15 7.3 Deviations from Plan ........................................................................................................ 15 8 Project Risks ........................................................................................................................ 16 9 Appendix 1: Detailed Project Schedule ................................................................................ 17 10 Appendix 2: High – level Data Design.................................................................................. 18 11 Appendix 3: TOGAF Pilot scope .......................................................................................... 19 14 March 16 page 2 Blackboard Analytics 1 Business Case 1.1 Background The Blackboard Analytics project provides self-service access to student and course data to support student retention, student engagement and instructional design and system oversight. 1.2 Business Rationale for the Project There is a direct and indirect relationship between loss of income for the university and student attrition. This is from lost fees through non-re-enrolments, as well an indirect losses from reputation damage. Student retention is also seen as an indicator or poor student engagement which is strongly linked to instructional design and instructor performance. Analytics of data is an emerging field provides many opportunities for the university to improve practice, improve data insight and measure the impact of initiatives as well as improve the ability for personalised support to be provided to students in a timely and meaningful way that encourages them to make a different decision (leave the university) before census the date. While there is a wide range of analytic tools and products on the market, the Blackboard Analytics solution integrates directly into SI-net and Blackboard (two of the most important data sources when identifying students at risk). This pre-available integration makes the Blackboard Analytics solution a very cost effective and quick tool to install compared to all other options, and includes ongoing upgrades, updates and support as Peoplesoft (SI-net) and Blackboard products mature over time. 1.3 Business Benefits / Rewards 1. Students at Risk: This should reduce in % as students are identified and support processes are actioned based no the analytic data and reports. 2. Student engagement: this should increase as students can see in near real time how their effort is impacting their progress in comparison to their peers. This is expected to result in a reduction of “show cause” letters and an improvement in course activity and results. 3. Instructor engagement: The reports will provide near real- time access to student activity and will allow instructors to monitor the impact of their course design and student outcomes in comparison to their peers. This is expected to result in an improvement in the adoption of Flipper classroom eLearning tools and an increase in attendance at eLearning training sessions. 4. Increased capacity to query and analyse learning data: This is expected to reduce the amount of time Application Services in ITS spends on writing manual, ad hoc queries for researchers and those wanting student learning data. 5. Improved decision making: This is expected to result in data-driven decisions that are a result of the executive dashboards which track school, faculty and cohort progress and trends. 6. Improved experience with learning analytics and a foundation capability to commence learning analytics in a more granular and personalised way. 1.4 Investment Appraisal The first year cost is expected to be $150 to install the system and pilot it. Second year costs will be between $50 and $150 to scale up the system to a university wide solution. With effective student retention results, this may equate to a saving of over $1M p.a. in retained student fees. Other universities have shown a 75 – 150% return on investment for similar initiatives. 14 March 16 page 3 Project Brief & Business Case 1.5 Options Considered The following options were considered: Do nothing Buy a suite of products (various products were evaluated). Build a custom solution (various designs were evaluated). Borrow a custom solution from another university. The following aspects of the solutions were evaluated: Cost, time, extensibility, support, maintenance integration with existing systems, lessons learnt from other organisations. 1.6 Potential for Collaboration There are many opportunities for collaboration on this project as many universities have similar programs in place. Several have already provided references for the selected vendor and provided several models for intervention. The vendor also has a very keen interest to collaborate with UQ as we will be the first PeopleSoft (SI-net) integration in Australia. 1.7 Capacity Requirements Areas Impacted: Servers Yes No Comment: Microsoft services has been involved in planning. Disc storage Yes No Comment: Infrastructure has been involved in planning. Network Yes No Comment: Network design has been involved in planning. Database Yes No Comment: Database and Operational data store have been involved in planning. Staff support Yes No Comment: training is included in implementation and eLearning training coordinator is involved in planning. User numbers Yes No Comment: Pilot scope is yet to be defined, but will include ITS for system, Few courses for pilot and all staff for full rollout. Other (please specify): There is a significant reliance on Student services to provide support services to convert the reports to retention. 14 March 16 page 4 Blackboard Analytics 2 Project Definition 2.1 Objectives This project aims to install the system and provide reports that can be used to identify students at risk. It will also aim to improve the university’s maturity with learning analytics. It will also be available for the other (secondary) benefits listed above, but these are not key drivers. 2.2 Approach The approach is to use software implementation partners to install and configure the system (Blackboard Analytics vendors). Then trial it within ITS to ensure it is stable and functional. Then pilot the system with a stratified sample of courses that demonstrate key characteristics of interest to Student Services and the faculties and student retention. Finally, the infrastructure can be scaled up after more is known about the system in preparation for a full university rollout and fully supported by ITS operationally. 2.3 Scope Is Is Not Installation, configuration and verification of the 89 off the shelf reports by vendor A fully redundant, high availability system. Integration with SI-net data Custom data sources and custom reports. Integration with Blackboard data All staff and students. A single server to install and test the software Data sources that do not exist in SI-net or Blackboard. Train the trainer mode for ITS staff to further train other stakeholders. Advanced security model Pilot report and recommendations for full rollout. Reports that do not support student retention – will be available but if they do not work, will not be a dependency for project completion. A basic roles-based security model. Student services support processes. Reports that support student retention Replace the reports reports. Integration with edEX Data cleansing activities for input data sources. Business changes to improve data capture in Blackboard or SI-net. The vendor has signed a fixed deliverable, fixed price contract and there is no contingency budget for the project. This means that there is no room for scope changes, except that wich the vendor agrees to without penalty. 14 March 16 page 5 Blackboard Analytics 2.4 Deliverables The deliverables includes: a project brief, terms of reference, project plan, procurement for the vendor engagement, architecture documents for approval by ITAG, System documentation for system owners, all analytics reports, dashboards and web services and supporting resources Software Pilot report with Scaling –up recommendations Student pilot report with recommendation for business support in the event of a full rollout, Operational support plan. Pilot closure. SharePoint site for stakeholders to track progress and collaborate with the project. https://projects.its.uq.edu.au/projects/eLearning/bb_analytics/SitePages/Home.aspx Reports as required. 2.5 Constraints Fixed Negotiable Budget: The financial decision has only requested funding for the Software licence from Bb Implementation costs. Additional staff costs are being covered from the Operational eLearning SLA resourcing (i.e. there are no dedicated project staff). There is no contingency budget for any additional costs that may arise during the life of the project. Time: The vendor’s implementation plan is for 26.5 days consulting (for set-up and training services), however, the contract is a fixed deliverable contract and this may be flexible within reason. Quality: There are 89 OOTB reports that are included with the system. This is the limit of reports that are provided by the vendor. While there is scope for customisation, this is not in scope for the pilot. Pilot schedule – once the product is installed and the vendor is completed, the piloting is flexible. Scope: The scope for the pilot and early benefits is to reduce the student retention drop-out rate. This could be increased to include other benefits if agreed by the project sponsor. 2.5.1 Schedule Milestone Duration / Date scheduled / Completed Start-up 6 weeks Dec 2013 / completed Initiation (funding decision) 2 weeks Jan 2014 / completed Vendor Implementation negotiations & procurement 2 weeks Feb 2014 / completed System design 1 week Feb 2014 / completed Stage 1: Software Pilot 14 March 16 page 6 Blackboard Analytics Implementation Phase 1: Planning & set-up 4 weeks Mar 2014 Implementation Phase 2: Installation 2 weeks Apr 2014 Implementation Phase 3: Orientation 1 week Apr 2014 Implementation Phase 4: Deployment preparation 3 weeks May 2014 Implementation Phase 5: Software Pilot 12 weeks Aug 2014 Stage 2: Student Support Pilot 6 months Dec 2014 Post-pilot report and recommendation for Golive 1 week Sep 2014 Preparation for Go-live 5 months Jun 2015 Go-live 1 day Jan 2015 Operational handover and support review 2 weeks Jan 2015 Continued trials and staged rollout 11 months Nov 2015 Project closure 2 weeks Dec 2015 Stage 3: System Expansion Stage 4: Full Rollout – staged approach 2.5.2 Cost Project Budget 2013 Item SLEP funding ITS Funded (allocated to 2014, committed in 2013) PM x 1 Hew 8 (0.5 FTE) x 6 months $28,901 Hardware $8,750 (Dell server) $15,322 (SQL licencing) Blackboard Analytics software $55,000 $11,000 Application Support Microsoft services $1,079 Application Support (AIS) Hew 7 x 2hrs / wk @ 3 months: Database support (EAS) Hew 7 x 4hrs / wk @ 3 months: Operational data Store Hew 7 x 2hrs / wk @ 3 months: $1264.80 $2529.60 $1264.80 Training & support 14 March 16 page 7 Blackboard Analytics Bb Analytics engagement $45,000 $16,856.42 $100,000 $86,967.62 Project consumables Summary Totals Grand totals: Budgeted: $186,968 Expended: $186,968 Balance: $0 Difference: +/- 0% 2.5.3 Future/On-going Costs Project Budget 2014 Item SLEP funding ITS Operationally funded PM x 1 Hew 8 (0.5 FTE) $57,802 Hardware Nil Needs funding for project If extra performance / sizing is required for full rollout $60,000 - $150,000* (depending on system specs and option selected – internally hosted physical, internally hosted virtual / externally hosted) Software $55,000 (expended) $61,300 SQL licences Remaining Bb Analyitcs contract plus SQL licences $32,000* (once –off – internally hosted option) Microsoft services $12,944 $2,000 set-up costs * Application Support (AIS) Hew 7 x 2hrs / wk @ 3 months: Application Support (Annual Maintenance of existing physical server) $1264.80 Hew 7 x 4hrs / day @ 3 months: Database support (EAS) $16,911.78 Hew 7 x 2hrs / wk @ 3 months: Operational data Store $1264.80 DBA – SQL training $5000 – 5 days + travel (if not available in Brisbane) Training & support Bb Analytics engagement $45,000 (expended) Project consumables Summary Totals $20,000 $100,000 (expended) $156,487.38 (+10%) $114,000 – $204,000* Grand totals: Project 2014 Required: $360,487 Funded: $156,487 , Balance: (- $204,000) * cost based on most expensive hosting option (internal physical) Note: Costs are based on the assumption that the pilot is successful and decision to scale out to redundant production system is made. 14 March 16 page 8 Blackboard Analytics Needs funding for operational support (SLA) – 2015+ Note: All resource assumptions are to be revised post-pilot during 2014 Item Recurring annual cost Software Recurring costs in eLearning SLA: $65,000 p.a. (all options) * Hosting $40,000 p.a. (externally hosted option) or Application support costs detailed below Application Support Recurring costs in eLearning SLA: Microsoft services $18,000 approx.* 0.5 FTE Hew 7 Application Support (AIS) $66,414* 0.2 FTE Hew 6-7 Database support (EAS) $20,869* 0.2 FTE Hew 7 Operational data Store $20,869* Training & support 1 x FTE Hew 7 $97,346 (TBC) Grand totals: Recurring Operational (required for eLearning SLA commencing 2015) Required: $288,498* Funded: $0, Balance: (-$288,498 p.a.) – * cost based on most expensive hosting option (internal physical) 2.6 Interfaces and Dependencies The project requires the input from almost all groups in ITS as well as other UQ stakeholders. System / TEAM Details Microsoft Services Environment installation Networks Environment set-up and security Teaching and Learning, AIS Blackboard Administration & system owners DBA Database administrators SI-net Business rules and SI-net technical Operational Data Store Business rules and SI-net data access Infrastructure Scale-up options Student Affairs / Student Services Support owners and course statistics 14 March 16 page 9 Project Brief & Business Case 2.7 Assumptions Permission model for application access will be defined and approved Access to the correct staff at the times required for the progress of the project High-level requirements agreed (functional and non-functional) will be able to be met from the OOTB config. Project steering committee and terms of reference agreed with timely access to ad hoc direction as required. Ability to use the Si-Net data and that there are no customisations that cause significant issues. Budget is approved for a vendor engagement in early 2014 and for scale-out when required. Australian People soft tables are mapped by the vendor before project commencement. The pilot will be installed on infrastructure that has already been installed and this will be sufficient to install and test the software and support processes before making a large redundant system scaled for enterprise deployment. The pilot participants will be available when required. There is ongoing support for the project until completion. 14 March 16 page 10 Blackboard Analytics 3 Project Organisation Structure Steering Committee Chair Role / Representing Phil Long Chair & Director Analytics Helen Harris Student Services Director (Business representative) Jodi Phillips Senior Supplier TBA AD(A) Secretary Andrew Jell Project Site URL https://projects.its.uq.edu.au/projects/eLearning/bb_analytics/SitePages/Home.aspx Project Manager Name Cris Deagon Project Team Name Kim Taylor Role: Environment installation, access and configuration Name Patrick Strong Role: Blackboard Administration and operational system owner Name Helen Harris Role: Student Services access Name: Andrew King Role: Database Administrators team Name: Greg Sutton Role: SI-net staff access and business rules Name: Vern Bawden Role: Operational data Store staff access and business rules Name: Marc Blum Role: Network Architecture and security Name: Cheryl Brugman Role: Pilot group instruction design and business representative Name: Ingrid Riener Role: Pilot group instruction design and business representative Name: Ailsa Dickie Role: ITS Training 14 March 16 page 11 Blackboard Analytics 4 Project Plan Project mandate approved and funding provided by the Student Lifecycle program in Nov 2013. Procurement and contract execution to be completed by the project manager in 2014. Project executive to approve the terms of reference and create the mechanism for additional product approvals (including the project plan) in Jan 2014. The environment is set up by Microsoft services and access to the environment provided to the vendors in Jan 2014. The vendors are to install and configure the system in Feb 2014. All testing and validation of the reports to be completed by ITS by March 2014. Pilot participants to be decided and approved by the steering committee by March 2014. Pilot report for system scale-up to be provided by the project manager. Pilot access to the reports is to be provided and training given to orient the users. Pilot participants to work with Student services representatives to trial a variety of support processes and business changes. Lessons learnt for the pilot will inform a support pilot report for the Student Lifecycle program for information on full rollout impacts. Operational support plan approved and SLA funding for the operational system is secured. Project closure report and lessons learnt. 4.1 Project Procurement Plans Procurement Plan Title Stage Cost Implementation services Initiation $130,000 Hardware and SQL licences Initiation $40,000 Scaled-up hosting services Delivery (Expansion) TBA 14 March 16 page 12 Project Brief & Business Case 5 Communication Plan Target audience: Key messages: Communication methods: Owner: Deadline: Date completed: ITS Employees Analytics awareness and impacts on team Emails, Meetings, PowerPoints, discussion Cris Deagon 2013 Jan 2014 UQ Employees Analytics and improvement to information and student data – pilot group Emails, Meetings, PowerPoints, discussion Cris Deagon June 2014 Students Access to support and assistance Face to face Instructors June 2014 UQ Researchers Self-services access to data Email / present ion at committees Cris Deagon June 2014 General public State of the art analytics and intervention strategies Articles, web site OMC 2015 14 March 16 page 13 Project Brief & Business Case 6 Change Management Plan The Analytics project is responsible for implementing the system. How the system\ is used will depend on the instructor, school, faculty needs and faculty priorities. The system will provide access to the reports, however it is likely that the business do not use the Blackboard system effectively to provide this data that generates the reports. Therefore the report quality and use will need to be improved with a change in data entry practices and improved system data consolidation. The adoption rate, change management and training and use of the reports to identify students at risk is the responsibility of the faculties. In addition, any student support changes will be the responsibility of Student Services or the faculty providing those services. ITS training will provide limited on-line self-help materials. 14 March 16 page 14 Blackboard Analytics 7 Project Controls The project plan outlines the baselines that form the basis of the project controls. Controls include: Integration controls (See appendix 2 – High level data design) Scope controls – refer to the project plan in-scope / out scope statement and Appendix 3 – TOGAF Pilot scope. Deviation requests will be outlined in the highlight report for decision. Schedule – refer to the schedule and milestones and any deviation requests outlined in the highlight report for decision. Cost – refer to the budget and any requests for additional funds via a business case and reported in the highlight report for endorsement. Quality – Refer to the high-level requirements that support Student retention and ITS performance assessment in the pilot report(s) and Blackboard Analytics contract for minimum vendor deliverables. Risk – Refer to the risk log and highlight report for risks that are new, increasing, eventuating or are near proximity. Urgent and important risks will be escalated for adhoc direction as required. Additional controls include informal ‘work packages’ via email and semi-regular meetings. 7.1 Project Tolerances Measure Tolerance Time + / 4 weeks Cost + / 0% (no tolerance for unapproved overspend) Scope + / - 1 mandatory report or 5 desirable reports 7.2 Project manager Controls Highlight report SharePoint site reporting traffic lights Weekly escalation / catch ups. Escalation to the Program Director / Associate Director(s) as necessary. Governance bodies – Steering committee, reference groups and assurance groups 7.3 Deviations from Plan Deviations from the project plan that exceed tolerances will need to be escalated depending on the tolerance measure: Financial deviations need to be approved via the line mangers through to ITS Director for approval for any expenditure. Time and scope deviations will need to be escalated to the Program Director for ad hoc advice. And further escalation to the steering committee if required. All deviations from the plan (both projected and actual) will be included in the monthly highlight reports. 14 March 16 page 15 8 Project Risks Refer to the project risk log online: https://projects.its.uq.edu.au/projects/eLearning/bb_analytics/Lists/Risks%20and%20Issues/AllItems.aspx Qualitative Risk Analysis Matrix – Level of Risk Risk Impact Minor Moderate Major Catastrophic Almost Certain (A) M H H E E Likely (B) M M H H E Possible (C) L M M H E Unlikely (D) L M M M H Rare (E) L L M M M Likelihood Insignificant 14 March 16 page 16 Blackboard Analytics 9 Appendix 1: Detailed Project Schedule 14 March 16 page 17 Blackboard Analytics 10 Appendix 2: High – level Data Design 14 March 16 page 18 11 Appendix 3: TOGAF Pilot scope 14 March 16 page 19