University of Oxford

advertisement
Version 1 – July 2014
University of Oxford Estates Services
Planning Procedures
1. Appointment of a planning consultant
Whenever a planning application is necessary, project managers should consider whether a
planning consultant should be appointed to prepare the application for planning permission,
negotiate with the local authority and arranging for discharge of conditions.
Where a planning consultant is to be appointed, the work should be tendered in accordance
with usual OUES procedures. The Director of Asset and Space Management should be
consulted on the planning consultants to be included on the tender list. Planning consultants
should be appointed on the Estates Services (“OUES”) standard terms of appointment as
early as possible.
Where the University considers that an Environmental Impact Assessment (EIA) should be
submitted with the application, the University will appoint an EIA consultant to prepare the
information and manage the process. This may not be carried out by the planning
consultant.
The University may also appoint a specialist communications agency to manage the
consultation process. Where a specialist agency is not appointed for the communications
process, this will be the responsibility of the planning consultant in accordance with the
requirements of this note.
2. Discussions with the Local Planning Authority (“LPA”)
The LPA should be consulted when a feasibility study is started for a development which
may require planning permission or listed building consent.
Where the development is taking place within the Oxford City Council administrative area,
Project managers should advise the Head of Conservation and Buildings that the proposals
should be considered at the regular meetings between the University and City Council
unless project specific meetings are taking place.
Minutes of all meetings and telephone calls with local authorities, statutory consultees and
interested parties must be taken and agreed by both the LPA and Estates. The project
manager should review these minutes and note any actions arising. The project manager is
responsible for ensuring that the planning consultant is aware of any outstanding actions. All
minutes should be copied to the Director of Capital Projects and Property Management and
the Director of Asset and Space Management.
The Director of Estates and the Director of Asset and Space Management have regular
meetings with Oxford City LPA at which strategic planning issues are discussed. Where a
development proposal may have strategic importance to the University, or affects a site on
which more than one development will eventually take place, the Director of Estates must be
made aware of the development so that any strategic issues arising from this development
have been discussed with the LPA at the earliest possible opportunity.
Version 1 – July 2014
3. Pre-application consultation
The Project Manager must comply with the consultation requirements set out below and
advise the PSG of the programme implications as a result of the consultation process itself
and where changes to the development become necessary to respond to consultation
responses.
The Project Manager must comply with any pre-application procedural requirements adopted
by the LPA, and ensure that evidence is collected and retained to show that these
procedural requirements have been met.
A detailed pre-application consultation procedure should be adopted for all applications,
unless the Director of Estates or Director of Asset and Space Management has agreed to a
reduced level of consultation on any particular development. The pre-application
consultation procedure should include letters to potentially affected residents and a public
exhibition. The date, place and times of the exhibition should be published in the local press.
A record should be kept of all attendees at the public exhibition and of any comments made
as a result of the consultation exercise.
“Major development”, which involves the provision of housing where the site has an area of
0.5 ha or more, or the construction of a building with floor space of 1000m2 or more, or
development on a site with an area of 1ha or more will generally require two consultation
events and the project manager must allow sufficient time for these to take place with an
opportunity to review feedback and potentially alter the design after each event.
Ward Councillors for the development should be invited to each consultation event.
All local community groups should be informed of the application and invited to the public
exhibition. Copy letters sent to local community groups must be retained for future reference.
Local residents who are or may be affected by the proposed development should be
informed of the proposals, the dates of the public meetings and be invited to participate in
the consultation process. Copies of the letters sent to local community groups must be
retained for future reference.
Minutes should be taken of all meetings with the local authority, statutory consultees and
local interest groups. These minutes should be issued to the consultee and agreed.
The University should be separately informed of the consultation events and a
representative of the University will attend public meetings and exhibitions, meetings with the
LPA and meetings with statutory consultees. Sarah Walton, the Head of Communications for
Estates should be informed of the need for consultation and kept fully involved in the
process.
The Director of Asset and Space Management should be invited to PSG meetings during the
planning application process.
Feedback from the public consultations on planning applications must be provided to the
Project Sponsor Groups.
Version 1 – July 2014
Where consultees are strongly opposed to the development, these objections should be
reported to the PSG, the Design Team, the Director of Capital Projects and Property
Management and the Director of Asset and Space Management (or other nominated Estates
representative). The PSG should consider whether to instruct the Design Team to prepare
alterations to the proposed development. If the PSG decides to proceed without addressing
the consultation responses, the PSG minutes should record the discussion which took place
and the reasons.
If the PSG considers that amendments should be made to the proposals to address
consultation responses, or indeed that some objections are not sustainable, a further full
round of consultation should be carried out to ensure the public and interest groups are
aware of the proposals.
Where a statutory consultee has objected to the development, the reasons for the objection
and the options for resolving the objection must be recorded by the PSG. Where the
objection is capable of being addressed by a condition, the Project Manager should ensure
that the PSG is made aware of the implications of the condition including on timescales for
carrying out the development.
Departures from this process may be considered where the application is for a development
which would normally be treated as permitted development1 or for minor alterations to
existing buildings where the determination process for the local authority will not exceed 8
weeks. Any proposals for departures from this procedure must be approved in writing in
advance by the Director of Estates. In these cases, LPA consent to the abbreviated
procedure should also be obtained in writing.
4. Environmental Impact Assessment
The EIA implications must be considered on each development. EIA should only be readily
discounted for those applications which involve only internal restructuring or minimal new
building work.
The Director of Asset and Space Management will advise in conjunction with the LSO as to
whether an EIA is required. Where project managers are advised that this is necessary, they
must allow time for preparing an EIA in accordance with the Regulations and the extended
time for consideration by the Council in the development programme.
Where the Director of Asset and Space Management and the LSO consider that an EIA is
advisable but not necessary, the PSG must consider whether an EIA should be carried out in
the particular circumstances of the proposed development. If the PSG consider that an EIA
should not be volunteered, the planning consultant must ask the LPA to issue a screening
opinion which should be accompanied by a detailed screening report setting out why the
development is not EIA development.
Where an EIA or screening report is necessary, an EIA consultant should be appointed by
the University. The project manager and full design team will need to provide the consultant
with all the information necessary to assess the development.
1
Please consult the LSO if you think the application may constitute permitted development. Do not proceed
until the position has been confirmed either by the LSO or the LPA.
Version 1 – July 2014
When an EIA has been prepared for a development, the development must be built in
absolute accordance with the details which have been assessed.
Outline applications for development accompanied by an EIA will need to have the EIA
updated to accompany each reserved matters submission.
Developments which either require an EIA or which are subject to a screening opinion that
the development is an EIA development which does not have an effect on the environment,
must be either accompanied by an updated EIA for the discharge of pre-commencement
conditions, or be screened again to determine whether the discharge of the precommencement conditions will result in a significant environmental effect.
5. University approval of submission of planning application
A planning application must be approved by the necessary University committees prior to
submission i.e. PSG, BESC and PMSC.
Once University committee approval has been obtained, the application should be prepared
by the planning consultant (if appointed) or project manager. The project manager should
check the application carefully before submission to ensure that the applicant details are
correct; the description of the site area and contamination status is correct and the details of
the application including the red line boundary are accurate.
The completed planning application form and submitted documents must be approved by the
Director of Asset and Space Management before submission.
The project manager should confirm the land ownership arrangements with the Estates
Information Management Team. All landowners need to be notified of the application, it
cannot be assumed that the University own the entire site.
6. During the application process
Consultation requirements.
Where a planning consultant is appointed, he must ensure that the LPA has published the
necessary site and newspaper notices and informed the relevant statutory agencies of the
application. Where a planning consultant is not appointed, the project manager will be
responsible for checking the notices. The site notices should be monitored and additional
notices provided if necessary. The project manager and planning consultant should send a
copy of the application through directly to the statutory agencies and the recognised local
interest groups including the Oxford Preservation Trust, the Oxford Civic Society and any
other organisations specified by the LPA.
Request for additional information
Where there is a request for additional information from an LPA or one of the statutory
agencies, this information should be prepared and provided as quickly as possible. If this
request relates to an EIA application, further consultation will be needed to comply with the
Regulations and it may also be necessary to post additional site and newspaper notices.
Version 1 – July 2014
Amendments to the application
Where amendments to the application are proposed, these need to be submitted to the LPA
with a revised EIA report (if necessary). At least 21 days for additional consultation should
be allowed with any submission of amended plans. Consultation should be carried out on the
amendments as set out in section 2 and it may also be necessary to post additional site and
newspaper notices.
Section 106 Agreements (Oxford City only)
Section 106 Agreements are now only required for elements of the development which apply
specifically to the site and the LSO can advise on whether a particular requirement is likely
to warrant a S106 obligation. Where a S106 is required, sufficient time should be allowed to
enable this to be agreed. The heads of terms should be agreed with the City, relevant local
planning authority and County Council officers so far as possible before the application goes
to Committee.
7. Committee meeting
The planning consultant and/or project manager should liaise with the planning officers to
invite the committee members to visit the site before the committee meeting and ensure the
committee has all the information it can usefully require to take the decision on the
development.
The project manager and planning consultant should attend the committee meeting with a
prepared presentation which has been approved by the PSG in advance. It may also be
appropriate for a member of the University to speak in support of the application. This should
be discussed with the Director of Asset and Space Management and the PSG.
8. Following committee decision / grant of planning permission
Community Infrastructure Levy / Section 106 Agreement
The Community Infrastructure Levy (“CIL”) will be due for payment on all new development
within Oxford City unless the University is able to rely on the charitable exemption under
Regulation 43 of the CIL Regulations.
CIL is payable within 60 days of the commencement of development. The standard rate is
£100sqm for uses falling within Use Classes A1-5, C3, C4 and student accommodation. All
remaining uses will be charged at £20sqm.
The charitable exemption can only be granted before the commencement of development.
Both the application for exemption and the LPA’s decision on the application for exemption
must be received before the development starts. Failure to obtain confirmation of the
exemption will mean that CIL is payable.
For Section 106 Agreements see (6) above.
Please discuss potential CIL liability and Section 106 payments with the LSO as soon as
possible after the application has been made.
Version 1 – July 2014
Discharge of conditions
The planning consultant and project manager must provide the PSG, the Director of Capital
Projects and Property Management and the Director of Asset and Space Management with
a tracker list of all the conditions attached to the planning permission, which should
particularly identify any which need to be discharged before the works begin or before
occupation is allowed. The tracker should be updated regularly and an up to date version
should be included in the PSG report.
Details of any conditions which need to be discharged before works start on site must be
approved by the LPA before any works on the site begin, even if the LPA’s planning
officers have verbally consented to the works.
Pre-commencement conditions on EIA development must be accompanied by an updated
EIA.
A schedule should be prepared of the remaining conditions together with timescales for
discharge. This schedule should be monitored at PSG meetings to ensure that the
arrangements for discharge of the conditions are being complied with. The PSG should be
informed when the details to discharge the condition is submitted to the LPA, and when
approval of the details has been received. The project manager and planning consultant
should ensure that details are discharged within the timescales set out in the planning
permission.
Non-material amendments.
Amendments to the design of the building should be kept to an absolute minimum, especially
where EIA is involved. If non-material amendments are necessary, details should be
submitted to the LPA with accompanying drawings at the earliest possible opportunity and
before the works are actually carried out.
Work should not take place in accordance with the revised details until written approval has
been received from the LPA. If any works are undertaken before the approval has been
received from the LPA, there is a risk that these changes will be treated as unauthorised and
the original proposals must be reinstated. The PSG should be advised of this risk.
Planning records
Copies of the planning permission, the accompanying drawings, public comments, an EIA
and any details submitted to discharge conditions should be recorded electronically as pdfs
and sent to Estates Information Management to add to the site records.
Download