Division 1 – General Requirements
Review Questions
1.
a.
b.
c.
d.
Section 011100- Summary of Work—
specifies administrative details and
responsibilities of the:
A/E
Owner and A/E
Contractor and Subcontractor
None of the above
Section 011100 – Summary of Work-specifies administrative details and responsibilities
of the:
1.
a.
b.
c.
d.
A/E
Owner and A/E
Contractor and Subcontractor
None of the above
2.
Administrative provision of the construction
contract are:
a. Fully specified in the Conditions of the Contract
b. The Contractor’s responsibility and should not
be specified
c. Written in Division 1 to expand on provision in
the Conditions of the Contract
d. Written in a manner to avoid Owner
responsibilities.
2.
Administrative provision of the construction
contract are:
a. Fully specified in the Conditions of the Contract
b. The Contractor’s responsibility and should not
be specified
c. Written in Division 1 to expand on provision in
the Conditions of the Contract
d. Written in a manner to avoid Owner
responsibilities.
3.
Division 1 sections specify:
a. Administrative requirements, procedural
matters, and temporary construction
facilities
b. Legal requirements that would not
normally be included in standard General
Conditions
c. Special Conditions of the Contract
3.
Division 1 sections specify:
a. Administrative requirements, procedural
matters, and temporary construction
facilities
b. Legal requirements that would not
normally be included in standard General
Conditions
c. Special Conditions of the Contract
4.
a.
Which is true regarding the Drawings?
Have no direct relationship to Division 1 of the
specifications
b. Need not be coordinated with Division 1
c. Graphically define certain subject matter specified
in Division 1, such as “Scope of Work”
d. May define related work that may or may not be
part of Contract
e. Provide the coordination between administrative
sections of Division 1
f. Both c and d
4.
a.
Which is true regarding the Drawings?
Have no direct relationship to Division 1 of the
specifications
b. Need not be coordinated with Division 1
c. Graphically define certain subject matter specified
in Division 1, such as “Scope of Work”
d. May define related work that may or may not be
part of Contract
e. Provide the coordination between administrative
sections of Division 1
f. Both c and d
5.
Owner occupancy of the premises during
construction:
a. Should not be specified in section covering
temporary facilities
b. Is specified in Section 011100 – Summary of
Work
c. Is not a concern of the specifier
d. Precludes Contractor’s use of existing
facilities such as stair’s, elevators, and
sanitary facilities
5.
Owner occupancy of the premises during
construction:
a. Should not be specified in section covering
temporary facilities
b. Is specified in Section 01110 – Summary of
Work
c. Is not a concern of the specifier
d. Precludes Contractor’s use of existing
facilities such as stair’s, elevators, and
sanitary facilities
6.
Which of the following items should not be
included in Section 011100?
a.
b.
c.
d.
Owner-furnished items of work
Site traffic regulations during construction
Sequence of work and Owner occupancy
Contractor’s use of site
6. Which of the following items should
not be included in Section 01110?
a.
b.
c.
d.
Owner-furnished items of work
Site traffic regulations during construction
Sequence of work and Owner occupancy
Contractor’s use of site
7.
Submittal requirements for Mechanical and
Electrical work are specified in:
a.
b.
c.
d.
General Conditions
Supplementary Conditions
Division 1
Divisions 15 and 16
7.
Submittal requirements for Mechanical and
Electrical work are specified in:
a.
b.
c.
d.
General Conditions
Supplementary Conditions
Division 1
Divisions 15 and 16
8.
Division 1 sections:
a. Cover general requirements for execution
of the work, and must be written in broad
language
b. Reinforce the concept “say it once” by
stating procedural matters only once
c. Should be bound in a separate volume of
the Project Manual
d. Both a and b
8.
Division 1 sections:
a. Cover general requirements for execution
of the work, and must be written in broad
language
b. Reinforce the concept “say it once” by
stating procedural matters only once
c. Should be bound in a separate volume of
the Project Manual
d. Both a and b
9.
Bidding Requirements:
a. Are not enforceable during administration
of contract
b. Should not repeat Division 1
c. Should be referenced to the General
Conditions
d. Bear no relationship to the Contract
Documents
e. Both a and b
9.
Bidding Requirements:
a. Are not enforceable during administration
of contract
b. Should not repeat Division 1
c. Should be referenced to the General
Conditions
d. Bear no relationship to the Contract
Documents
e. Both a and b
10.
Provisions in the Conditions of the Contract:
a. Have priority over Division 1
b. Are superseded by Division 1
c. Are expanded by the provisions of
Division1
d. Are independent and Division 1
provisions have no effect
10.
Provisions in the Conditions of the Contract:
a. Have priority over Division 1
b. Are superseded by Division 1
c. Are expanded by the provisions of
Division1
d. Are independent and Division 1
provisions have no effect
11. Which statements are true concerning
Supplementary Conditions:
a. They should not contain general
references to Division 1
b. They should be used to expand and
modify basic provision stated in the
General Conditions
c. a only
d. Both a and b
11. Which statements are true concerning
Supplementary Conditions:
a. They should not contain general
references to Division 1
b. They should be used to expand and
modify basic provision stated in the
General Conditions
c. a only
d. Both a and b
Answers
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
d
c
a
f
b
b
c
d
e
c
d