BLOCK 2 STUDENT SERVICES PROJECT – Summer 2015 Electrical Works Student Services Area and Corridor Remove all redundant lighting and power circuits, conduits and trunking fixed to the ceiling and walls. Remove all redundant data, phone, fire, security and CCTV cabling fixed to the ceilings and walls. Place the remaining data ,phone ,fire ,security ,CCTV, lighting and power cabling in suitable trunking re- routing where necessary. Replace the local Distribution Board located in the Kitchen and connect all new and existing circuits to it. Move the Data Panel from the Student Services Area to the Kitchen. Locate it adjacent to the new Distribution Board and connect all new and existing data cables to it. Install circuits for LED lighting to be fitted in the new suspended ceiling grid in the Student Services Area and Corridor. Allow for two-way switching in the Student Services Area. Switches to be located by each entrance. The type of Led fittings to be specified by the Interior Designer. Allow a Provisional sum for 30 No. 600mm x 600mm LED panels. 27 to be located in the Student Services Area and 3 in the Corridor. 5 of the 30 to be Emergency light fittings. Install 3 compartment skirting trunking plus power and data circuits around the perimeter of the Student Services Area. Allow for 42m of trunking and 30 -13A twin socket outlets and 30 data points. Details of socket and data locations to be confirmed once the interior design is complete. Install one 13A cleaners socket in the corridor. Replace the light fittings in the Kitchen and Exam room with 600mm x 600mm LED panels. Install 8 - 13A twin socket outlets and 4 twin data points at the foot of each of the six columns in the Student Services Area. The circuits to be routed above the suspended ceiling and down one face of each column using trunking or some other suitable containment. Reception Area Reposition the Fire and Full Access Toilet Emergency Alert panels to suit the location of the new reception desk. The location to be determined by the Interior Designer. Re-route power, data and telephone cables to suit the location of the new reception desk. Replace the light fittings with LED units. The type of LED fitting to be specified by the Interior Designer. Allocate Provisional sums for each of the Reception items allowing for 8 LED down lighters 2 of which to be emergency units. External Doors and Windows Student Services Area and Corridor Replace 6 high level wooden framed windows numbered – W3,W5,W6,W7,W8 and W9 on Elevations drawing, with aluminium framed double glazed units. Opening lights to be top hung and fitted with winder opening mechanisms. Opening lights to be in the same locations as the existing units were possible. Frame colour to match the buildings other aluminium framed double glazed units. Replace existing wooden framed entry doors location W1 on Elevations drawing with aluminium framed double glazed units with a double glazed side panel on the LH side. Note: Allow sufficient frame width between the door and glazed side panel for the new corridor wall to fix to. Frame colour as above. Enlarge the openings of windows W2,W4 and W10 and install aluminium double glazed windows with top hung opening lights. Window size for W2 and W4 – 3m Wide x 2m High with 2 opening lights each 800mm wide. Frame colour as above. Window size for W10 – 2m Wide x 2m High with 1 opening light 800mm wide. Replace wooden framed fire exit door D8 with a aluminium framed double glazed entry door. Frame colour as above. Note: Door furniture to match existing. Euro cylinder locks to be supplied by the College. Internal Alterations Student Services Area and Corridor Remove high level window bars and security grills and place in the metals skip provided by the College. Replace wooden double doors from Student Services Area to Reception with fully glazed units. Install a double skinned plaster board partition wall to form an entrance lobby, corridor and store room. Install a pair of fully glazed double doors from the lobby into the Student Services Area Double Doors from Lobby to Corridor to be supplied by College Store room door to be supplied by College. Construct double skinned plasterboard and glazed partitions to form two adjacent offices. Install a suspended ceiling at 2.8m. Overall dimensions for the offices 3m x 5.2m. Individual size 3m x 2.6m. Glazing panels on one wall of each office. Each panel 1m high x 1.2m wide fixed at 1.2m above floor level. Office doors to be supplied by College. The location of the two offices and full specification is to be provided by the Interior Designer so allow a provisional sum based on the information above. Construct 2.8m high partitions. Fully glazed to 2.1m with plaster board over to form two adjacent Interview Rooms with glass doors. Install a 600 x 600 grid suspended ceiling at 2.8m. Overall dimensions for the Interview rooms 2.4m x 4.8m. Individual size 2.4m x 2.4m. The dividing partition to be double skinned plaster board. The location of the two offices and full specification to be provided by the Interior Designer so allow a Provisional Sum based on the information above. Install a 600mm x 600mm grid suspended ceiling throughout the rest of the Student Services Area, lobby and corridor tailored to accommodate the ceiling mounted heating panels. Ceiling tile type to be specified by the interior designer. Allocate a Provisional Sum for medium quality tiles. FLOORING Replace flooring in the lobby, corridor, Student Services Area,offices and interview rooms. Flooring materials to be specified by the Interior designer . Allocate a Provisional Sum based on medium quality carpet tiles. DECORATION Re-paint the walls ,woodwork and ceiling mounted heating panels in the lobby, corridor,Student Services Area, offices and interview rooms. Colour scheme to be specified by the Interior Designer. Allocate a provisional sum based on mixed paint colours. Note: Work to commence 13 July 2015. Completion by 14 August 2015. Site visits by arrangement with :Jim Diston 0121 602 7749 ( on holiday until 15/6/15) Tim Crees 0121 602 7777 x 521 JDI May 15.