A. Gurtu
Tata Institute of Fundamental Research,
Mumbai
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
• HO fully installed in YB+2, YB+1, YB0 and lowered by end-Feb 07.
• Work on vertical sectors that had to be done after lowering also carried out
• By end-June, YB-1 & YB-2 also “almost” installed in
CMS detector on the surface. YB-2: One RBX remains to be installed.
• YB-1: Test/commissioning of individual RBX’s done.
• Next: Mount last RBX on YB-2; test each RBX.
• Lowering of YB-2, YB-2: now in October 07.
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
• Commissioning of YB+2 was already done in MTCC
• YB+1, YB0, YB-1, YB-2 global commissioning to be done. YB0 start was expected in mid-July, but
- overall schedule may slip
- for HO, some cables are needed, which are expected to arrive only by end-July.
• Will go along with the evolving scenario of CMS & HO installation in accordance with the constraints.
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
• HF+
• Apr/May: completed
• HFwill be commissioned as soon as we get LV power!
• HO
• June: YB-1, YB-2 in SX5 hall
• July: HO on YB0 wheel
• August: YB+2, YB+1 (waiting for water cooling)
• HE
• June/July: start-up of YE+1 was delayed by lack of water cooling
• Nov/Dec: YE-1 (waiting to be lowered)
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Skuja: Test Beam 2007
• Calibration of ZDC prior to its installation in the LHC beamline has been completed. However one of the ZDC modules was damaged in shipment and its copper matrix must be re-machined.
• Combined EE/HE measurements in July.
• SiPMT measurements in August
• Lumi electronics verification in August (?)
• Manpower crunch between commissioning needs and test beam needs in summer of 2007 (TB mainly in July, while
HB commissioning starts in August). We have a gaggle of students assigned to the test beam but very few supervisors.
We invite our colleagues with Test Beam experience to help with the training/supervision of the students.
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
• HF+ is installed and commissioned as a prototype of CMS UX detector shake down.
• Revisit HO trigger
• HPD noise is not understood but is not a showstopper (HO z position altered)
• HCAL DPG and DCS have an enormous task list
• TB07 requires supervisors for students
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
•
Will hear from ELD regarding status of sensor fabrication & module production and testing.
•
Si-PSD beam test in August
• In lieu of 300 kCHF electronics contribution by BARC,
- provision of manpower for 70 kCHF (2 technical assts for 1 man-year equivalent, from 1 Aug 07.
- fabrication of OptoRx-12 module by ECIL, to be paid by BARC. Quotation sent to CERN by ECIL.
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
David Barney <Dave.Barney@cern.ch> Jul 19 (13 hours ago) to cadnps <cadnps@ecil.co.in> cc Atul Gurtu <atul.gurtu@cern.ch>,lalwanisk@yahoo.co.in,
Serge Reynaud <Serge.Reynaud@cern.ch>,
Paschalis Vichoudis <Paschalis.Vichoudis@cern.ch>,
Walter Snoeys <Walter.Snoeys@cern.ch>
Dear Sir date subject signed-by mailed-by
Jul 19, 2007 6:21 PM
RE: offer for OptoRx modules from ECIL, Hyd, India cern.ch
cern.ch
Many thanks for your offer for the production of "optoRx" modules dated June 29th.
I apologise for the delay in replying to you.
I believe that we can proceed with an eventual order, but before doing so we need to make some practical arrangements. Firstly I need to have a single technical contact person in India. This person should be directly responsible for overseeing the complete production and quality control etc. as well as liasing between BARC,
ECIL and CERN. Please could you agree, with Prof Gurtu and the representatives from
BARC, on a suitable person as soon as possible and inform me?
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Secondly, before the full order is placed, we would like you to produce a small pre-series, perhaps of 2-3 complete pieces. If you agree to do this, please let me know when you could produce them so that we can arrange to send you the optical receivers. At that point I will also send the final production (Gerber) files to you.
For the components (FPGA, all passive components etc.) please let me know how you would proceed for this pre-series of 2-3 pieces. i.e. would you procure all items yourself or do you wish to purchase them from CERN?
I look forward to your response to the above issues, with kind regards,
Dr. David Barney
CMS Preshower Coordinator
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
• New hardware (~20% of total) is now functional.
CPU’s, Storage, new UPS.
•
Status later by PVD/PN. Integration into overall CMS-
GRID, imminent, if not already operational.
• 34 Mbps 1:1 IPLC line operational between CDAC
(Juhu) and Milano. Is alternately connected with TIFR or VECC.
• Enhancement of bandwidth to 622 Mbps and later to 1
Gbps or more planned.
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
• Indent for remaining hardware (~80% of total) now being worked out. CPU’s, Storage, 2 nd UPS.
•
Enhancement of AC and electrical power points and other infrastructure given to TIFR central services team.
• Quotations for AC enhancement received
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
• Many of materials ordered for the first 12 chambers have been delivered. Some expected soon. Miscellaneous materials from CERN next month: LMP.
• For cosmic muon trigger paddles, some large plastic scintillator sheets have been transported to
BARC.
• PU students expected at BARC.
• DAE has endorsed re-appropriation of spill-over budget at TIFR (EHEP only) to Universities. DST response is awaited (DU to keep in contact).
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Engineering run originally foreseen at end 2007 now precluded by delays in installation and equipment commissioning.
450 GeV operation now part of normal setting up procedure for beam commissioning to high-energy
General schedule being reassessed, accounting for inner triplet repairs and their impact on sector commissioning
All technical systems commissioned to 7 TeV operation, and machine closed April 2008
Beam commissioning starts May 2008
First collisions at 14 TeV com July 2008
Pilot run pushed to 156 bunches for reaching 10 32 cm -2 s -1 by end 2008
No provision in success-oriented schedule for major mishaps, e.g. additional warm-up/cool-down of sector
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
45 56 12 23 34 67 78
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
.
Feb.
Mar.
Operation testing of available sectors
Apr.
Machine Checkout
May
Jun.
Jul.
Aug.
Sep.
Interconnection of the continuous cryostat
Oct.
Leak tests of the last sub-sectors
Nov.
Dec.
Inner Triplets repairs & interconnections
Beam Commissioning to 7 TeV
Global pressure test &Consolidation
Flushing
Cool-down
.
81
Warm up
Powering Tests
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
General co-ordination schedule - Milestones
Pressure test Cool-down Powering tests
Sector 12 27-28 Oct. 07 03 Dec. 07 25 Jan. 08 28 Jan.08
18 Apr.08
Sector 23 15 -16 Sep.07 05 Nov. 07 14 Dec.07
17 Dec. 07 21 Mar. 08
17 Sep. 07 26 Oct. 07 29 Oct. 07 30 Nov. 07
Sector 34 11-12 Aug. 07
03 Mar. 08 28 Mar. 08 31 Mar. 08 02 May 08
25 Jun. 07 14 Sep. 07 17 Sep. 07 30 Nov. 07
Sector 45 Done
10 Mar. 08 04 Apr. 08 07 Apr. 08 02 May 08
15 Feb.08
Sector 56 18 - 19 Aug. 07 01 Oct. 07 09 Nov. 07 12 Nov. 07
Sector 67 25-26 Sep. 07 22 Oct. 07 30 Nov. 07 03 Dec. 07 15 Feb.08
Sector 78 Done
Done Started 29 Jun. 07
08 Oct. 07 16 Nov. 07 19 Nov. 07 22 Feb. 08
Sector 81 16-17 Jun. 07 27 Aug. 07 09 Nov. 07 12 Nov. 07 22 Feb. 08
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
2008 LHC Accelerator schedule
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
2008 LHC Accelerator schedule
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Can use for planning
Vacuum chambers installed and baked out by end of
March 2008
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Cosmics Run, CMS Closed & Field ON - Mar 2008
Initial* CMS detector ready to take cosmics data. Use to commission and operate the detector and to prepare the Collaboration for data taking and analysis.
Working backwards
by end-September 07 Tracker insertion has to have started and in December 07 be recording cosmics with Tracker/EB/HB etc. (Expt open)
• Including one EE, and pixels
14 TeV Collisions: Mid-2008
Low luminosity CMS detector* commissioned and ready for efficient physics data taking, the CMS Collaboration trained and ready for analysis of data at 14 TeV
* including both EEs, and pixels
Two parallel paths
1. Detector Installation, Commissioning and Operation.
2. Preparation for Analysis - Computing, Offline and Physics
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
See Talk by M. Lamont Wed afternoon
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Very significant progress.
Main highlights are: i) the first phase of the heavy lowering of the elements of the experiment into the underground cavern, including that of the heaviest element, the
YB0, has been successfully completed.
ii) Commissioning of detectors installed in UX has started: HF+ has been commissioned, 4 DT sectors on YB0 ‘cosmics’ commissioned. First
CMS Global run (Lvl-1 Trigger, HF, DAQ, data transfer to T1/T2) conducted end May. iii) Commissioning of muon detectors still on the surface is proceeding well.
‘Cosmics” commissioning on DTs on YB-1 completed iv) The critical path: installation of services on the YB0 is proceeding.
Currently shows a delay of 1 mo. Investigating ways to mitigate.
v) Beam-pipe installation of -end (one of 3 parts) done, +end significant amount of work already carried out in January. Much has been learnt.
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
vi) Several million cosmic tracks have been recorded in the silicon strip tracker sitting inside the Tracker Support Tube since Mar 07.
Testing programme: several weeks at room temperature (DONE), 3 weeks at 0 °C (DONE), and now at -10 °C. The quality of the Tracker remains excellent. End surface commissioning mid-July.
vii) First half barrel ECAL installed at Point 5. Excellent quality (19 problem channels out of 30600). The last (of 36) barrel supermodule will be ready for installation early July. Barrel ECAL installation will be completed in July.
Endcap crystals production is proceeding well: over 3500 crystals now delivered(out of 14750 needed). The contract for the remaining 5500 endcap crystals is almost ready for signature - last EE crystal will be delivered endMar’08.
viii) DAQ and Trigger installation proceeding well.
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Situation in Cavern after 1 st Phase of Heavy Lowering (9Apr)
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Magnet Installation
The coil and all magnet systems transferred to the caverns: control, vacuum, cryogenics, powering and protection. Only re-connection work between subsystems is needed.
July-October: Commissioning
July: Start commissioning (signal checks, vacuum control system, MCS and MSS.
September: Ready for cool-down
Sept/Oct: Commission discharge & powering lines at 20kA, dump resistor.
Nov 07: Low current testing (about 400A) in the coil at 4.5K : power start, current regulation loop at low current, MSS and MCS.
March 08: Final commissioning of the magnet ( ~ 1 week)
Progressive current ramps : 3kA, 7kA, 10kA, 14kA, 17.5kA, and nominal,
One slow dump at 14kA.
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
The critical path , up to Tracker Insertion (in Sept), goes through the installation of services on YB0
+ end: Tracker patch panels (PP1s), & pipes installed and insulated, tracker cables being installed, then instal ECAL SMs in July, L0 scint, then ECAL/HCAL services
- end: tracker patch panels &ECAL, L0 scint. installed, start tracker pipes installation this week, then tracker cabling, ECAL/HCAL services
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Cosmics in the Tracker
Example of Performance
• The Quality of the CMS Tracker is Excellent:
• Dead or Noisy Strips < 3 / 1000
Normal Strips
Dead Strips
Noisy Strips
99.852 %
(241 313 Strips)
0.116 %
(275 Strips)
0.032 %
(76 Strips)
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
EB- Installation Completed
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Cosmics Intercalibration
Cross-checked in beam
= 1.5%
0 in test beam
140
0 / crys
50 GeV e
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Endcap ECAL (EE)
Crystals Production: last crystals to be delivered end-Mar08
Assembly Progress
20 supercrystals mounted on Dee4
Bat 186
test beam
29 s.c. assembled for Dee1 ( ~140/Dee), 1400 VPTs glued to crystals
Critical path components: HV boards, cooling bars, etc,
Start mounting s.c. on Dee1 2nd week of July
Schedule is very tight
Ist Dee ready only at the end of 2007
(Retrofit of motherborads in SMs has had an effect on progress in EE project.)
Issues
Adequate manpower (to speed up assembly and for management)
Work on the back of the Dee is complicated (LV cabling & looming)
Concerns
Limited experience so far. Much work still ahead. Will not know the exact time needed to get the last Dee until the first one has been completed and tested.
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
ECAL Preshower (ES)
From AR: Schedule: Effort is needed for the preshower endcaps to be ready for installation in January and March 2008.
Concerns
No contingency
Many unknowns in the larger-scale assembly stages (ladders mounting on Dees etc.)
Some manpower concerns, particularly technicians, but:
Significant help from CMA group recently
Additional resources found in CERN_DT groups for engineering/mechanics
Promises of manpower from collaborators for assembly and testing
CAEN LV supplies: sufficient modules to run one full endcap will not be available until ~ March 2008
Additional manpower will be needed.
NOTE: EE has higher priority than ES
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
MC Production
30Mevts/mth
HLT Exercise
Pre CSA07
50Mevts/mth
CSA07
Jan
Feb
Mar
April
May
June
July
Aug
Software Release Plan
End Nov: 1_2_0 - Released Dec 20
Production of Physics Validation and HLT samples (80M)
Mid Feb: 1_2_3 - Released Feb 20
Production of samples for 2007 Physics Studies (Spring07)
End Feb: 1_3_0 - Released March 28
Goal: (Re-)Reconstruction of HLT and Physics
Includes all algorithms needed for HLT exercise
End March: 1_4_0 - Released May 11, Prodn early June
Production of simulation samples for CSA07 (started June 4)
Commissioning tests (Global Runs) in May and June
Migration to & validation of Geant4 8.2, fixing geometry overlaps
Backward incompatible changes allowed: geometry model, material budget, data formats
DQM / Event Filter software used for Filter Farm tests
Mid May: 1_5_0 - Release expected ~June 20
Production of DIGI/RECO for CSA07 using Tier0
New cycle of commissioning tests
Framework changes : new plug-in manager, performance optimisations
New optimised reconstruction algorithms (input from PTF)
New calibration and alignment (ALCARECO) producer
Oct
Be ready to process and store CMS data at the startup of the LHC and give CMS users prompt
(and easy) access to their datasets.
Commission the global computing infrastructure
Transition from commissioning to stable operations while supporting on-going physics studies and detector commissioning throughout the year, and
Making end-to-end tests of computing systems through participation in 2007 physics exercise (50 Mevts/mo), global data taking and cosmic runs and Computing Software
Analysis challenge CSA07
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Scale of CMS data transfers has increased significantly. T0-T1 channels have reached production operations in reliability and performance.
Concerns
Facilities - short of manpower. Need 2 nd Level-2 convener full time at CERN.
User Support has to be re-enforced. Need 2 nd convener.
Mass storage - Storage Resource Manager, CASTOR
Global connectivity between T1-T2 sites
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
Global priorities:
Overall Plan & Physics
- Detector completion and commissioning
- Detector Performance
- Physics Objects
- Physics Analysis
Physics-wise: focus on discovery
Standard Model studies: a necessary step
- Obviously, lots of good physics there as well
- But priority is in preparing for the main physics (new) that the LHC is conceived for
And, to do physics we also need to:
- Complete and commission trigger
- Complete software
- Deploy computing model – and use it effectively
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
• Up to Nov 2007
• Concentrate on the physics that we can do with up to 1fb -1 .
– Work in being done in order to chart out the “how” we will do this work, and to prepare methods, tools and people.
• Two major milestones, namely
– HLT milestone (due now) Goal CPU within a factor 2 of 40ms/evt.
May 120 ms
now < 50 ms/event , very large effort (see Thurs Plenary).
– Completion of 1fb -1 exercise (Nov) Approach the “1fb -1 goal” in a set of successive approximations (10, 100 and 1000 pb -1 ).
• From Dec 07 to May 08
• Prepare for the actual data.
Goals:
– Have all the datasets and streams defined
– Have all of the HLT code in place
– Have all the trigger monitoring system (code + people) in place
– Have all the Monte Carlo events in place
– Have all the data-analysis organization (code + people) in place
– Have analyses (geared for 10 pb -1 & 100 pb -1 ) ready to absorb the data
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
CMS Schedule v36 has been prepared using the guidance from the DG.
Beam-pipe Closed and Baked-out by End March 2008 .
In v36 this point will be reached in mid-Feb 08.
Major Features of v36 .
• By end-September 07: Tracker insertion started
• In December 07 ; recording cosmics with Tracker/EB/HB etc. (Expt open)
• By end-March 08, CMS is closed (including pixels and one ECAL endcap) and taking cosmics with Field-ON
The main uses/consequences of the new guidance :
- commission the entire detector/data flow and analysis systems with cosmics data
- reduce risks (e.g. by separating tracker cabling from beam-pipe installation that was previously in parallel.
Time to carry out untried operations (HF riser system in UX, pixel comm. sys..
Open +end to allow commissioning to proceed
Repair/replace defective parts (RPC HV cables, DT fibres,…
Accommodate delay in YB0 services
1) Detector Installation,
Commissioning & Operation
Barrel ECAL Inserted
June
2) Preparation of Software,
Computing & Physics Analysis
HLT Exercise
July
Pre CSA07
S/w Release 1_6 ( CSA07, CCR1)
Aug
Trigger/DAQ Ready Commissioning
Tracker Inserted
Sep
CMS Cosmic Run (CCR) Phase 1 (+end)
Test Magnet at low current
Tracker cabled & Commissioned
Last Heavy Element Lowered
CMS Cosmic Run Phase 2 (YB0)
Oct
Nov
Dec
CMS Cosmic Run Phase 3 (-end,RE)
Jan
Beam-pipe Closed and Baked-out
≥ 2 EE Dees Installed, Pixels installed
Feb
CMS Cosmic Run Phase 4 (4T)
Mar
CSA07
S/w Release 1_7 ( CCR2, HLT Validation)
2007 Physics Analyses Completed
S/w Release 1_8 ( Lessons of ‘07)
S/w Release 2_0_x
(Production of startup MC samples)
MC Production for Startup
India-CMS: some physics studies
• S.S. Chauhan: Pooja Gupta:
• Quark compositeness with diphoton final state at LHC: update.Venue: SUSY/BSM meeting, CERN (VRVS),
29 Sept 2006
• Search for quark compositeness with diphoton final state at LHC: update:Venue: SUSY/BSM meeting, CERN (VRVS),
13 Nov. 2006, 8 Jun 2007.
• Gamma + N jets generation in
Alpgen meeting at CERN,
21 May 2007
•
Progress on Gamma + Jet analysis in CMS Standard
Model meeting at CERN,
23 June 2006
•
Gamma+Jet study at CMS in
CMS Physics meeting at
CERN – through VRVS,
8 Dec 2006
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007
A. Gurtu: "Report to the Collaboration", India-CMS Collaboration Meeting, PU, 5-6 April 2007