UNIVERSITY OF CINCINNATI CHE Design Project I Ethyl Benzene Process 20CHE5045 Super Group: Jacob Bolden, Ryan Cage, Connie Crum, Travis Duckro, Matt Miller, Jeremy Schirmer 12/10/2012 0 Contents Abstract ......................................................................................................................................................... 2 1. Scope Definition ........................................................................................................................................ 3 2. Design Basis............................................................................................................................................... 3 3. Process Description ................................................................................................................................... 4 3.1 Process Synthesis ................................................................................................................................ 4 3.2 Recommended Process ....................................................................................................................... 4 3.3 Process Control Philosophy................................................................................................................. 7 3.4 Environmental Performance ............................................................................................................... 8 3.5 Process Safety ..................................................................................................................................... 8 3.6 Preliminary Equipment Specifications .............................................................................................. 10 4. Process Economics .................................................................................................................................. 15 4.1 Estimated Capital and Operating Costs ............................................................................................ 15 4.2 Economic Analysis ............................................................................................................................. 18 5. Future Work ............................................................................................................................................ 18 6. References .............................................................................................................................................. 18 Appendix A .................................................................................................................................................. 18 Appendix B .................................................................................................................................................. 18 Appendix C .................................................................................................................................................. 18 Appendix D .................................................................................................................................................. 19 Appendix E .................................................................................................................................................. 19 Appendix F .................................................................................................................................................. 19 Appendix G .................................................................................................................................................. 19 1 Abstract The objective of this project is to design a process to produce 500,000 metric tons/year of ethyl benzene from a feed of ethylene and benzene. Additionally, we have a toluene mixture in our initial feed stream that must be removed and sold at greater than 99 weight percent purity. Our final design resulted in a production of 44,775 metric ton/year of toluene as well as 534,653 metric ton/year of ethylbenzene. Purification specification is 99.1 weight percent and 99.99 weight percent respectively. This process has a return on investment of 15.18% and a payback period 3.97 years assuming straightline depreciation of 10%. Recommendations for future work include further investigating mean by which toluene could be removed at the end of the process to understand the possible economic benefits. Additionally, more effort could be spent on temperature control for process monitoring and real-time operational changes. Finally, the addition of waste streams surrounding column 2 would reduce our cycle-up and effectively lower the sizing of the column. 2 1. Scope Definition The purpose of this project was to design a process capable of producing 500,000 metric tons per year of 99.9 % pure ethylbenzene. Additionally our feed is mixed with toluene and as such must be separated at a rate that maintains profitability for the process. Design conditions assume that operation of the plant will occur at 8000 hours per year. Average hourly feed rate for the benzene/toluene feed is 640 kmol per hour and 60 kmol per hour respectively. Average hourly feed rate for ethylene is 630 kmol per hour. Production rate for toluene is approximately 60 kmol per hour and production rate for ethylbenzene is approximately 630 kmol per hour. Both toluene and ethylbenzene maintain a purity of greater than 99%. 2. Design Basis The completed process operates with a feed rate of 700 kmol/hour with a composition of benzene at 640 kmol/hour and 60 kmol/hour toluene. The cost for this feedstock is $1,050/metric ton due to the presence of toluene. This feedstock is stored on-site at 30 degrees Celsius. The ethylene feedstock is fed into the process at 630 kmol/hour and stored on site at 40 degress Celsius. The cost for ethylene is $1,220/metric ton. Product rate for the process is 60 kmol/hour of toluene at a purity of 99.1%, discharged at a temperature of 39.85 degrees Celsius at 2 atm. The remaining 0.9% is comprised of pure benzene. The second product rate for this process is the ethylbenzene discharge at 630 kmol/hour. The stream is discharged at 39.85 degrees Celsius at 2 atm. The composition of this stream contains 0.9999238 ethylbenzene, 1.854871e-008 benzene, 2.244194e-005 toluene, 2.303265e-008 P-Diethylebenzene, and 5.3764e-005 1-Methyl-4-Ethyl. For our utility considerations, we used low, medium and high pressure stream with respective temperatures of 160 degrees Celsius, 184 degrees Celsius and 254 degrees Celsius. For our condensers, cooling water inlet was 90 degrees F and exited at 120 degrees F. The major by-products in this reaction are diethylbenzene and methylbenzene, but these products are not a waste stream as they are continuously recycled and reused in the process. 3 For this process, we did not utilize waste streams, rather recycled all reaction products. Although we do not incur the cost of waste disposal, our column 2 is significantly more expensive due to sizing. Plant layout would be to keep both reactors and all 3 columns within close proximity to each other for ease of operator use. Special safety requirements will be addressed in the PHA summary located later in this report. 3. Process Description 3.1 Process Synthesis In addition to the final process selected, we had initially went through iterations of a process where the toluene was removed at the end of the process in a separation between ethylbenzene and toluene, resulting in two product streams from one distillation column. This proved to be ineffective, as purity requirements were not able to be achieved with the given separation. It was determined that the process would not be in our best interest to further investigate, due to time constraints with iterations to improve separation quality. 3.2 Recommended Process For our reactors, we decided to use plug flow reactors for ease of catalyst use. The final design process begins with the benzene/toluene feed located on stream 1. This stream passes through an economizer (E-1) to become stream 24. Stream 24 is fed into a distillation column (C-1) where the toluene benzene mixture is separated into stream 2 (the distillate stream which passes through a condenser) and stream 3 (the bottoms stream which passes through a reboiler). Stream 3 composition is 99.1% toluene and 0.89% benzene. It is fed into pump P-1 where it becomes stream 21 to pass through economizer E-1. After economizer E-1 it becomes stream 23 (T-Product) and sent to a storage tank. Stream 2 (Benzene outlet) is fed through a pump (P-2) where it becomes stream 20 and is fed into a mixer. Additionally, stream 4 is fed into the mixer (M-1) which is the ethylene feed. One additional stream is included in the mixer, which is a benzene recycle stream , appropriately named Benzene M-1 inlet, (14,25) from the distillate of column 2. This inlet is preheated through an economizer (E-3). From mixer M-1 the stream becomes stream 5 to where it is fed into an economizer 4 E-2 to be additionally preheated. After the economizer E-1, the stream becomes stream 16 and is fed into the heat exchanger HX-1. Stream 16 becomes stream 6 where it is fed into the reactor R-1. The discharge from R-1 is stream 8 where it is fed into a second reactor, R-2. Additionally, stream 26 named DEB MEB R-2 is fed into reactor 2 and is the recycle stream from the bottoms of the column C-3. Stream 18 is fed into a pump P-5 to become stream 7, DEB MEB recycle. This recycle stream is preheated with the economizer E-3 before it is fed into the reactor R-2. Reactor 2 discharge is fed to an expander, EX-1, where it becomes stream 11 and is fed to the inlet of C-2. The distillate for C-2 has already been discussed, but the bottoms is stream 13 named EB out (ethylbenzene out). This is fed to pump P-4 where it becomes stream 12 and is the inlet to column 3. The bottoms of C-3 have already been discussed, and as such the distillate is the product ethyl benzene. It is pumped through P-6 where it becomes stream 22, EB Product Hot 1. This stream is fed through a series of 1 economizer (E-2) and 1 heat exchanger (HX-2) where it finally becomes stream 19, EB product. Appendix C located at the end of the report consists of an overall material and energy balance for the process. A summary is provided below: 5 Table 1 – Stream Specifications Stream ID Stream Name Molar Flow (Kmol/h) Mass Flow (kg/h) Flow (gpm) Temperature (K) Pressure (atm) Vapor Mole Fraction Enthalpy (MMBtu/h) ID (in) ID (in) Rounded Stream ID Stream Name Molar Flow (Kmol/h) Mass Flow (kg/h) Flow (gpm) Temperature (K) Pressure (atm) Vapor Mole Fraction Enthalpy (MMBtu/h) ID (in) ID (in) Rounded Stream ID Stream Name Molar Flow (Kmol/h) Mass Flow (kg/h) Flow (gpm) Temperature (K) Pressure (atm) Vapor Mole Fraction Enthalpy (MMBtu/h) ID (in) ID (in) Rounded Stream ID Stream Name Molar Flow (Kmol/h) Mass Flow (kg/h) Flow (gpm) Temperature (K) Pressure (atm) Vapor Mole Fraction Enthalpy (MMBtu/h) ID (in) ID (in) Rounded Stream ID Stream Name Molar Flow (Kmol/h) Mass Flow (kg/h) Flow (gpm) Temperature (K) Pressure (atm) 1 2 3 4 5 6 Benzene/Tolu Benzene Outl C-1 Bottoms Ethylene Fee Mixed R-1 Fe R-1 Feed 700.0001 639.1602 60.8401 630.6 12071.0596 12071.0596 55525.0898 49928.2109 5596.897 17690.8516 911550 911550 276.8242 248.5608 28.2629 222.5446 4669.0352 4669.0352 303 352.9624 383.3652 313 359.9948 434 1 1 1 29.6 21 20 0 0 0 1 0 0 31.606 34.705 1.568 30.77 661.16 790.91 4.701563045 4.601829805 1.602160861 11.17424436 15.5129682 15.99770695 5 5 2 11.5 16 16 7 8 9 10 11 12 DEB MEB Rec R-1 Out Benzene out R-2 Out C-2 Inlet C-3 Inlet 660.3389 11440.4805 10801.2998 12100.7959 12091.167 1289.8661 88138.0234 911550 843931 999688 998905 154973.2969 447.2481 4539.3628 4197.9302 4986.6226 4982.7114 784.7817 473.3013 434 352.9785 434 358.2408 427.0439 20 20 1 20 1 1.5 0 0 0 0 0.3805 0 -13.984 725.53 586.07 704.53 691.72 -14.143 6.471857527 15.79899527 14.90033742 16.18289987 23.31849869 8.121012168 6.5 16 15 16.5 23.5 8.5 13 14 15 16 17 18 EB Out Benzene Recy EB Out E-1 Feed Out EB Product H MEB DEB Out 1289.8661 10801.2998 629.5273 12071.0596 629.5273 660.3389 154973.2969 843931 66835.3047 911550 66835.3047 88138.0234 784.7817 4197.9302 337.5343 4669.0352 337.5343 447.2481 427.0284 353.6168 425.257 364.5097 369.9948 472.5461 1 20 1.5 21 2 1.5 0 0 0 0 0 0 -14.153 587.96 8.5598 668.34 1.3845 -14.208 8.120938661 14.90418568 5.526105078 15.53853167 5.34150458 6.468465552 8.5 15 6 16 5.5 6.5 19 20 21 22 23 24 EB Product Benzene Out Toluene Out EB Product H T Product E-1 Feed Out 629.5273 639.1602 60.8401 629.5273 60.8401 700.0001 66835.3047 49928.2109 5596.897 66835.3047 5596.897 55525.0898 337.5343 248.5608 28.2629 337.5343 28.2629 276.8242 313 353.659 383.4007 425.2763 313 311.1573 2 20 2 2 2 1 0 0 0 0 0 0 -5.1135 34.817 1.5687 8.5641 0.89828 32.276 5.184436171 4.603921632 1.602199067 5.526176676 1.535455351 4.723080196 5.5 5 2 6 2 5 25 26 Benzene M-1 DEB MEB R-2 10801.2998 660.3389 6 843931 88138.0234 4197.9302 447.2481 358.9542 434 20 20 A copy of the PFD is attached below: 3.3 Process Control Philosophy The overall control philosophy is set based upon a set of objectives for the plant. From the initial problem statement, we understand that we need a composition of 99.9% pure ethylbenzene from our discharge in addition to 99% pure toluene to be sold. Our process control surrounds maintaining those variables at optimal efficiency. As such our process control objectives are as follows: 1. Maintaining appropriate stream composition for output of product. 2. Keep the conversion of the plant at its highest permissible value. 3. Achieve constant composition in the liquid effluent from both reactors. The degree of automation for this process would not need to be too in-depth as it is a basic reaction and control valves can be used for control of the process. Control valves would need to be located at the discharge of each unit op, in addition to the feed locations to control reactant flow. Real-time data would be as follows: 1. Thermocouples on the discharge side of each reactor and distillation column. 2. Flow meters on the discharge end of pumps to maintain understanding of flow rate. The last process control need would be control valves at key locations within the process loop. These locations are listed below and reference the PFD. 1. 2. 3. 4. Stream 1 Stream 2 Stream 3 Stream 19 7 5. 6. 7. 8. 9. 10. 11. Stream 6 Stream 8 Stream 11 Stream 9 Stream 13 Stream 16 Stream 18 The locations of these control valves are based upon the need to possibly limit discharge from the end of key unit ops such as reactors and distillation columns. Additionally, these control valves are on the feed and product of the process. 3.4 Environmental Performance Environmental performance is essentially non-existent for this process as we do not bleed any of the excess benzene or by products off during the process. We did this recycle selection to avoid the incremental cost of dealing with waste disposal. No air emissions are necessary for this process; as such no costs are incurred. Environmental risks from using chemicals are prevalent for this process as each chemical has significant health hazard. To minimize these risks, control valves are put into key locations in response to any kind of runaway reactor and over pressurization situation. All piping is sized in accordance to specification to allow for corrosion. By doing this, pipe bursts due to corrosion over time are avoided with proper maintenance. 3.5 Process Safety A Process Hazard Analysis (PHA) is an organized and systematic method to identify and analyze the significance of potential hazards associated with processing or handling highly hazardous chemicals. A PHA helps when making decisions for improving safety and reducing the consequences of unwanted or unplanned releases of hazardous chemicals. For this process a What if-PHA was performed to analyze potential causes and consequences of fires, explosions, releases of toxic or flammable chemicals, and major spills of hazardous chemicals. It focuses on equipment, instrumentation, utilities, routine and non-routine human actions, and external factors that might impact the process. Some of the principle hazards identified in the PHA include overpressure of vessels, corrosion, external forces, spills and basic equipment failure. While not a frequently occurring hazard there is always concern that the column or vessels can become over pressurized due to unforeseen circumstances. This is a very high risk hazard that has potential to be 8 deadly. If a vessel bursts not only is there immediate danger to anyone around but also the contents of said vessel may be hazardous as well. To prevent this from happening pressure relief valves, set to the upper limits of the vessels specifications can be implemented to reduce risk of failure. Working with hazardous materials brings with it added danger of spills and accidental contact along with the corrosion of the system. Due to the nature of this system corrosion is not likely to occur during the lifetime of the system. However accidental contact due to bursting of a pipe or leak is a severe hazard. The chemical components being used have the potential to cause harm to employees that become exposed as well as harm the environment, and even cause explosions. To prevent this from happening pipes with sufficient safety factors and thickness should/will be implemented, along with insulation of pipes. To increase the safety, regular checks of the integrity of the equipment using air need to be performed. When designing a plant/ system external factors that are out of man’s control have to be taken into effect as well. Examples include earthquakes, flooding, and loss of power among others. These external sources have the potential to become hazards if not properly prepared for. By knowing site location and possible external forces that the system may come in contact with it can be designed in a safe manner to prevent any harm. In the case of our system we have accounted for earthquakes or external objects striking the system by properly choosing materials thick enough to with stand small disturbances from the outside and in. Also in case of a power outage due to storms or other reasons, so as not to lose operating time a backup generator should be implemented. A final component of the system that in was in question is a mechanical equipment failure, involving anything electrical or mechanical. It was determined that throughout the process with the number of moving parts present that there is a high risk for failure. At any time a temperature probe may go out, a valve may stop working or a pump may fail. To prevent this sensors and alarms are in place so that if a mechanical failure occurs the operators would be notified and able to fix it before damage is done. If the system is designed, built and run to appropriate standards as set forth in the design specs the hazard risks are greatly reduced. Table 2 – Hazards and Safeguards Hazard Safeguards Excessive Pressure Pressure relief valves 9 Equipment Failure Corrosion Power outage Slips/Falls Accidental contact with system piping Alarms to alert operator Correct piping size and thickness, periodical checks of integrity Back-up generator to run important system components Handrails/Guardrails/Non-slip surfaces Insulated piping 3.6 Preliminary Equipment Specifications Vessels Table 3 – Vessel Specifications – Reactor 1 Reactor R-1 Operating Pressure (atm) Design Pressure (psig) Operating Temperature (K) Design Temperature (K) Inside Diameter (rounded) (ft) Length (ft) Wall Thickness (in) Corrosion Allowance (in) Weight (lb) Material Bed Height Bed Configuration Control(s) Location Alarm(s) 20 336.3 434 450 7.66 80 1.3125 0.125 122972.7 304 SS N/A N/A Outlet Temperature Table 4 - Vessel Specifications – Reactor 2 Reactor R-2 Operating Pressure (atm) Design Pressure (psig) Operating Temperature (K) 20 336.3 434 10 Design Temperature (K) Inside Diameter (rounded) (ft) Length (ft) Wall Thickness (in) Corrosion Allowance (in) Weight (lb) Material Bed Height Bed Configuration Control(s) Location Alarm(s) 450 4.83 50 1.3125 0.125 60287.6 304 SS N/A N/A Outlet Temperature Table 5 - Vessel Specifications – Column 1 Column C-1 Operating Pressure (psia) Design Pressure (psig) Operating Temperature (K) Design Temperature (K) Inside Diameter (rounded) (ft) Height (ft) Wall Thickness (in) Corrosion Allowance (in) Weight (lb) Material Number of Trays Feed Tray Location Tray Spacing (in) Bed Height Bed Configuration 14.7 15 383.9 500 12 98 0.25 0.125 42422.6 304 SS 40 16 24 N/A N/A Control(s) Location Distillate & Bottoms Discharge Alarm(s) Temperature Table 6 - Vessel Specifications – Column 2 Column C-2 Operating Pressure (psia) Design Pressure (psig) Operating Temperature (K) Design Temperature (K) 14.7 15 412.6 500 11 Inside Diameter (rounded) (ft) Height (ft) Wall Thickness (in) Corrosion Allowance (in) Weight (lb) Material Number of Trays Feed Tray Location Tray Spacing (in) Bed Height Bed Configuration 32.5 94 0.3125 0.125 160019.5 304 SS 38 16 24 N/A N/A Control(s) Location Distillate & Bottoms Discharge Alarm(s) Temperature Table 7 - Vessel Specifications – Column 3 Column C-3 Operating Pressure (psia) Design Pressure (psig) 14.7 15 Operating Temperature (K) 450 Design Temperature (K) 500 Inside Diameter (rounded) (ft) 17 Height (ft) 100 Wall Thickness (in) Corrosion Allowance (in) Weight (lb) Material Number of Trays Feed Tray Location Tray Spacing (in) Bed Height Bed Configuration 0.3125 0.125 76296.2 304 SS 41 16 24 N/A N/A Control(s) Location Distillate & Bottoms Discharge Alarm(s) Temperature Heat Exchangers Table 8 - Heat Exchanger Specifications – HX-1 12 Type Flow (kg/hr) Heat Exchanger HX-1 Shell-and-Tube 910841 Temperature Hin (K) 527.00 Temperature Hout (K) 374.51 Temperature Cin (K) 364.51 Temperature Cout (K) 434.00 Fouling Factors (m2K/W) Operating Temperature Design Temperature (K) Operating Pressure (atm) Design Pressure (atm) Material of Construction Corrosion Allowance Special Considerations 0.00018 N/A 550 21 25 Stainless steel 0.125 None Table 9 - Heat Exchanger Specifications – HX-2 Type Flow (kg/hr) Heat Exchanger HX-2 Shell-and-Tube 66834.14 Temperature Hin (K) 369.99 Temperature Hout (K) 313.00 Temperature Cin (K) 303.15 Temperature Cout (K) 323.15 2 Fouling Factors (m K/W) Operating Temperature Design Temperature (K) Operating Pressure (atm) Design Pressure (atm) Material of Construction Corrosion Allowance Special Considerations 0.00018 N/A 400 2 5 Stainless steel 0.125 None Table 10 - Heat Exchanger Specifications – E-1 Economizer E-1 Type Flow (kg/hr) Temperature Hin (K) Temperature Hout (K) Shell-andTube 61122.0647 383.40 313.00 13 Temperature Cin (K) Temperature Cout (K) Fouling Factors (m2K/W) Operating Temperature Design Temperature (K) Operating Pressure (atm) Design Pressure (atm) Material of Construction Corrosion Allowance Special Considerations 303.00 311.16 0.00035 N/A 400 2 5 Stainless steel 0.125 None Table 11 - Heat Exchanger Specifications – E-2 Economizer E-2 Type Flow (kg/hr) Temperature Hin (K) Temperature Hout (K) Temperature Cin (K) Temperature Cout (K) Fouling Factors (m2K/W) Operating Temperature Design Temperature (K) Operating Pressure (atm) Design Pressure (atm) Material of Construction Corrosion Allowance Special Considerations Shell-andTube 977675.14 425.28 369.99 359.99 364.51 0.00018 N/A 450 21 25 Stainless steel 0.125 None Table 12 - Heat Exchanger Specifications – E-3 Economizer E-3 Type Shell-and14 Tube Flow (kg/hr) 931287 Temperature Hin (K) 473.30 Temperature Hout (K) 434.00 Temperature Cin (K) 353.62 Temperature Cout (K) 358.95 Fouling Factors (m2K/W) Operating Temperature Design Temperature (K) Operating Pressure (atm) Design Pressure (atm) Material of Construction Corrosion Allowance Special Considerations 0.00018 N/A 500 20 25 Stainless steel 0.125 None Pumps Table 13 – Pumps Specification – P-1 through P-6 Pumps Name P-1 P-2 P-3 T (K) 383.4 352.9 Flow (lbmol/hr) 134.1312 1409.1022 Pressure Drop (psi) 50 50 Pump Head (ft) 132.4541284 130.6561086 Specific Gravity 0.872 0.884 Density 0.7806625 0.8154425 Pump Brake Hpr (Pb) 13869.43046 150129.3329 Fractional Efficiency of Pump (np) 0.572710166 0.794910059 Fractional Efficiency of Motor (nm) 0.938692103 0.92165934 Power Consumption (Pc) 0.781783736 6.209593832 Sparing Requirement Material 304 SS 304 SS 304 SS Pump Type centrifigul pump centrifigul pump centrifigul pump Line Materials 99% Toluene/ 1% Benzene Benzene/Tolueneall Line Number 3 and 21 2 and 20 9 and 14 Special Considerations Special Seal requirements P-4 352.9 23792.7695 50 130.6561086 0.884 0.8154238 2534884.055 0.886455656 0.874655818 99.07177753 P-5 P-6 427 2842.4392 50 132.9113924 0.869 0.7439471 281057.6734 0.83551416 0.91374121 11.15589661 472.5 1454.5959 50 133.2179931 0.867 0.7001003 135664.2785 0.797003961 0.922804357 5.589609308 304 SS centrifigul pump All but Ethylene 13 and 12 304 SS centrifigul pump All but Ethylene 18 and 7 425.3 1387.8459 50 132.4541284 0.872 0.7435676 136686.9975 0.793899867 0.92272076 5.654279112 304 SS centrifigul pump All but Ethylene 15 and 22 4. Process Economics 4.1 Estimated Capital and Operating Costs The following table summarizes are total capital cost. At a CE Index of 500 are total purchase cost is approximately 14 million dollars. When the cost is scaled to a CE index of 593, it raises to approximately 16.5 million dollars. An additional operating cost will be located after the capital cost sheet. 15 Table 14 – Total Purchase Cost Total Purshase Cost Columns C1 C2 C3 Total columns $ 538,275.19 $ 10,566,010.54 $ 1,249,112.34 $ 12,353,398.08 Reactors R1 R2 Total Reactors $ $ $ 413,983.70 246,927.36 660,911.06 Heat Exchangers HX1 HX2 E-1 E-2 E-3 Total heat exchangers $ $ $ $ $ $ 415,758.33 65,469.86 34,338.94 75,436.51 43,504.76 634,508.39 Pumps and fans P-1 P-2 P-3 P-4 P-5 P-6 Total pumps and fans $ $ $ $ $ $ $ 8,455.74 6,422.00 75,330.42 6,819.05 6,380.65 6,390.13 109,797.99 Expander $ 1.00 Total Purshase Cost (CE Index 500) $ 13,758,616.52 Total Purshase Cost (2012 CE Index 593) $ 16,317,719.19 Total Capital Investment, TTCI $ 101,602,278.55 *uses Lang Factor of 5.93 Total Permanent Investment, TTPI $ 86,353,369.97 *uses Lang Factor of 5.04 16 Table 15 – Cost Sheet Outline 17 4.2 Economic Analysis For this process selection, it has been determined that the payback period will be approximately 4.28 years and with a return on investment of 15.18%. The venture profit for this process is $158.539. All sample calculations can be found in Appendix G. 5. Future Work There are a few open issues and areas of major uncertainty for this process. One of the largest issues that this process has is its energy usage. One column alone has a duty of over 500 MMBTu/hr which simply is not economically feasible. The reason for these duties is due to the reflux rate of the column and the overall mass flow rate. The columns we have designed for this process are rather large in terms of industry standards and as such the columns and reboilers have high duties. Additional work could be done in investigating the need for a waste stream for the excess benzene. 6. References 1. Seider, Warren D., J. D. Seader, and Daniel R. Lewin. Product And Process Design Principles, Synthesis, Analysis, And Evaluation. 3rd ed. Wiley, 2008. Print. 2. Lubyen Paper Appendix A Benzene.pdf Diethylbenzene.pdf ethylbenzene.pdf Ethylene.pdf p-ethyltoluene.pdf Toluene.pdf Appendix B physical properties.xlsx Appendix C Material and Energy Balances.xlsx 18 Appendix D Appendix E No emission calculations were completed for this report as we are a no discharge facility. Appendix F ePHA-UC Project II.xlsx Appendix G Process Design Final Economic Analysis 2.xlsx 19 20