Multi-year Cases Humanitarian Lessons Review 01 May 2014 to 26 February 2015 CHASE 26 February 2015 Business Executive Summary The Humanitarian Emergency Response Review (HERR) of 2010 noted that DFID can use the way it funds to change the incentives facing players in the global humanitarian system. It recommended a “step change” in greater predictability of funding, particularly through multi-year arrangements, to create an incentive to tackle protracted crises. Following this, several DFID country offices (as well as two regional programmes managed from London) began to test multi-year humanitarian funding arrangements. CHASE carried out a review to identify the lessons learned from these early experiences of designing and implementing multi-year humanitarian programming. The main lessons identified are below; the lessons can be used as links to the relevant discussion on them in the text. Lessons identified 1. Multi-year arrangements save time on ‘process’ over their full life (see 2. below though). Staff report using this time for strategic thinking, support to more complex partner arrangements (e.g. consortia or more strategic relationships), and enhanced monitoring & evaluation. 2. A multi-year arrangement is more time intensive in the design phase with more DFID and partner resources needed at this stage. 3. Alignment of relevant cycles – DFID’s planning and reporting cycle, partners’ planning and reporting cycle, and relevant seasonal cycles – should be factored in from the outset; mis-timing in business case approval can undermine longer-term programmes’ chances of demonstrating success. 4. Extra DFID efforts will be needed to communicate to partners and other donors that a multi-year arrangement is in place /possible, and to continually advocate for higher-order (resilience) results on that basis. 5. Providing multi-year funding does not automatically lead to multi-year programmes; the ‘cascading’ of funds from DFID to ‘downstream’ partners may continue to be handled on an annual basis. 6. Partners need time to make organisational adjustments to reflect the ambition and innovation proposed in multi-year business cases. This should be taken into account, with options for a ‘transition period’ or bridge between activities to maximise the use of DFID funds. 7. Multi-year arrangements can facilitate programmes that deliver ‘system strengthening’ for the humanitarian system in-country more easily than annual approaches. 8. Existing standard monitoring tools – designed on an implicit assumption of annual programming – are flexible enough to monitor multi-year funding as long as the supporting documents explicitly determine multiyear targets, and review teams address multi-year issues in the process. 9. Flexibility in multi-year design is essential. Although the optimal level of contingency funds is unclear, they are considered essential to respond to unexpected humanitarian need and unexpected humanitarian response system faults alike. 2 Contents Executive Summary ......................................................................................... 2 A. The Theory of multi-year humanitarian funding ...................................... 6 B. Practice of multi-year humanitarian funding ........................................... 7 C. Lessons Identified .................................................................................. 9 i. Time saving and timing .......................................................................... 9 ii. ‘Cascading’ funds ................................................................................. 13 iii. Partner and government relationships .............................................. 15 iv. Types of programmes ....................................................................... 16 v. Monitoring, evaluation, and learning .................................................... 17 vi. Contingency and preparedness ........................................................ 19 D. Annex 1: Grid of approaches to multi-year arrangements .................... 21 E. Annex 2: Methodology ......................................................................... 22 F. References .............................................................................................. 23 Figure 1: Map of countries where multi-year humanitarian programmes are running ............................................................................................................. 4 Figure 2: Generic Theory of Change for multi-year humanitarian funding ....... 5 Figure 3: Indicative timelines for developing the multi-year business case .... 12 Figure 4: Bottlenecks in funds transfer? ......................................................... 14 3 Figure 1: Map of countries where multi-year humanitarian programmes are running (click to edit) Multi-year humanitarian business cases Syria region (Syria, Lebanon, Jordan, Turkey): £700m over approx. 2 years Pakistan: £100m over 4 years Bangladesh: £20m over 5 years Sahel (Mauritania, Niger, Mali, Chad, Burkina Faso): £139m over 3.25 years Sudan: £109m over 3 years Burma: £40.7m (27.2+13.5) over 2.5/3 years DR Congo: £135m over 4 years Mozambique: £4.89m over 5 years Yemen: £55.5m (38+12.6+4.9) over 2 years Ethiopia: £115m (75+25+22) over 3 years Key Umbrella approach Thematic approach Partner-specific approach Kenya: £60.8m (44+16.8) over 3 years Somalia: £145m over 4 years Total: £1.7 billion Total ex. Syria: £947 million 4 Figure 2: Generic Theory of Change for multi-year humanitarian funding Can’t tackle root causes Can't measure long-term success Projects needing high trust excluded Gains reversed by (foreseeable) spikes in need Funding cycles are linked to systemic shorttermist features e.g. short contracts Annualised funding cycle constitutional for many donors Make multi-year funding available to: INGOs; Multilateral agencies High (recurring) costs Build contingency funds into multiyear business cases Problems DFID Actions Assuming Outcomes Outputs 1. MY approval passed through to end implementers 2. Funds used for long-term activities, not urgent gapfilling 3. Implementers invest in longterm relationships 4. Partners can set up adequate finance/admin support for MY 5. Early warning data sufficient to support contingency triggers Reduced admin & operational costs for DFID & partners Mid-term aims to: Build assets; Address structural challenges; Reduce extreme vulnerability; Build resilience; become more common Fuller, sustained dialogue with national & local authorities Better access to beneficiaries & better beneficiary feedback mechanisms Partners tailor admin processes to MY Greater partner flexibility to changing conditions e.g. scale-up Partners increase investment in long-term (national) staff capacity Trigger indicators preagreed 6. Cost savings go to improving quality of programm -ing 7. Implemen ters and authorities learn & adapt 8. Oversight of triggers does not slow action More resources to learning ‘what works’ Longer-term, tailored, strategic programmes emerge Smoother transition to development More skilled implementing staff Greater partner confidence in advocacy Improved DFID financial management 9. Learning & VFM raise quality 10. Review frequency, optimism bias & remedial action are the same (or higher) as for annual funds Impact: Humanitarian programming manages risk, addresses root causes, and ultimately shortens suffering More timely interventions based on triggers 5 A. The Theory of multi-year humanitarian funding The theory behind multi-year humanitarian funding for protracted humanitarian settings is that a multi-year approach will “improve cost and administrative efficiency [and] improve the effectiveness [and] the timeliness of interventions”. These improvements will come through administrative and operational cost savings (e.g. through advance procurement), through creating time and space for trying and learning from new programmes, and through making investments in relationships and capacity to be able to implement more strategic long-term programmes.1 Many of the foreseen benefits of multi-year approaches are simply the removal of some of the absurdities of annualised (or even shorter) funding cycles in years/decades long humanitarian settings – yearly preparation of new proposals for similar activities, short and unpredictable contracts that lead to high staff turnover, procurement at short notice and high cost, etc.. There are also higher order potential benefits, related to strengthening the skills, relationships, and systems that are used to respond to humanitarian needs and so changing the nature of possible interventions. There are several types of multi-year funding solutions within DFID. Some arrangements are managed centrally, such as Programme Partnership Arrangements (PPAs) with NGO partners or multilateral partnerships in disaster preparedness and climate adaptation. But much of the investment in multi-year funding has been at country and regional level, and this is what the practice discussed here focuses on. The theory of this kind of country level multi-year humanitarian financing has been outlined in many places. The ‘generic’ Theory of Change in Figure 2 tries to unify these sources. It draws mostly on the Humanitarian Emergency Response Review (HERR), the Guidance on Multi-year Humanitarian funding, a study on the value for money of multi-year humanitarian funding, and from insights from interviews done for this review (you can see all the document sources in the References section). 1 DFID CHASE, 2013, Responding to chronic crises, vulnerability and predictable spikes in need: the design of effective humanitarian and development financing instruments 6 B. Practice of multi-year humanitarian funding Multi-year humanitarian funding was stepped up in DFID from 2011 on, although some multi-year funding (e.g. through pooled fund mechanisms) had been done before that. There are now ten country offices running 15 multiyear humanitarian programmes – Bangladesh, Burma, Democratic Republic of Congo, Ethiopia, Kenya, Mozambique, Pakistan, Somalia, Sudan, and Yemen. There are also two regions covered from London – the Sahel, and Syria region – with another three multi-year business cases active for a total of 18.2 A multi-year business case is being developed for Afghanistan. The business cases range from two to five years, although the most common length is three years. The total amount programmed is almost £1.7 billion, or £947 million if Syria is excluded, with an average size of £63 million (excluding Syria). During the 2012-2013 DFID financial year, multi-year humanitarian funding made up an estimated 12 percent of all bilateral humanitarian funding. A majority of the business cases are written for contexts that face both natural and conflict hazards. These range from conflicts that are very dynamic (Syria) to currently less visible (Burma), and from highly predictable natural hazards (monsoon in Bangladesh) to chronic underlying natural risks that are less easily predicted (drought risk in Horn of Africa). DFID has partnered with a wide range of organisations to implement the overall design of each business case. The most frequent partners are ICRC, UNICEF, WFP, and UNHCR from the multilateral side; a wide range of NGOs are partners with Save the Children, CARE, and Oxfam most frequent. This range of partners expands when downstream partners are considered though it hasn’t been possible to map these in the context of this review. In practice, three ways of doing multi-year funding have emerged in DFID. The first is a kind of ‘umbrella’ arrangement, that covers many sectors and many partners, and in the case of regional approaches, many countries. A second is a ‘thematic’ arrangement that covers many partners, but a single, often cross-sectoral, ‘theme’. Finally, there are ‘partner-specific’ arrangements where a single partner may cover one or many sectors. For example, both DFID Ethiopia and DFID Kenya fund nutrition-focused multi-year programmes. DFID Ethiopia has a single partner (WFP), DFID Kenya works through both UNICEF and NGOs; the first is a partner-specific approach, the second ‘thematic’. This paper tries to separate lessons related to each of these specific arrangements, though this isn’t often possible. A grid showing suggested advantages and disadvantages of each approach is at Annex 1. 2 Some of these have ‘sister’ business cases designed to work on institutional capacity for disaster risk reduction, climate change adaptation, social protection etc. The ‘BRACED’ business case for the Sahel, a disaster resilience business case for Pakistan, and separate programmes such as the Productive Safety Nets Programme in Ethiopia are closely connected to the business cases discussed here. 7 This is a snapshot of where multi-year humanitarian programming is at the end of 2014; the next section goes into more detail on the process of developing the business cases, their content and the programming that’s come from them, and the lessons learned from the early experiences of implementation. The methodology used to identify lessons is at Annex 2. 8 C. Lessons Identified i. Time saving and timing One of the major anticipated benefits of multi-year funding was that it would shift time and money away from the ‘transaction costs’ of requesting, approving, and managing funds to implementation tasks such as planning, monitoring, and learning. This benefit was widely, though not universally reported among DFID advisers. Feedback was that the "admin burden is a lot less" with multi-year arrangements. Part of this is attributable to a business case process that was considered “onerous” anyway, and that may improve with introduction of the ‘Smart Rules’. However, the multi-year nature of the business case itself was reported by most to still save time just from “not having to do same thing every year”. One adviser estimated the time saving was equivalent to about two months in each year subsequent to approval. There was a strong feeling that these admin time-savings alone meant that multi-year funding “just makes sense" and that cutting down business case writing time has “got to be a good benefit”. Expected time savings weren’t always realised – the complexity of some business cases, with many partners, sectors, and areas to cover (‘umbrella’ business cases) resulted in heavier design and, later, review processes than normal. For the Syria business case, the largest that DFID has worked with, this was a considerable challenge. What did advisers do with the time saved in subsequent years? It was reported that this went into planning (including strategic planning) and monitoring. It also seems that a lot of saved time was diverted to partner relationships.3 Many countries have quarterly meetings with partners, additional to the agreed reporting as a kind of governance forum and to discuss progress (see below under Partner and Government relationships). In these, Advisers reported the feeling that they are still ‘selling’ the multi-year approach to some partners. 1) Multi-year arrangements save time on ‘process’ over their full life (see 2) below though). Staff report using this time for strategic thinking, support to more complex partner arrangements (e.g. consortia or more strategic relationships), and enhanced monitoring & evaluation. That said, it was clear that multi-year funding was found to become timesaving only after the first year. Doing the business cases in the first place was at least as, but often more time consuming than for an annual programme. 3 This may be linked to consortia arrangements. Many countries opted to work with consortia of NGOs, including Yemen, DRC, and Somalia. Yemen produced a list of their lessons learned from releasing the call for proposals for this arrangement. 9 This extra time mostly came from more complex design. Deeper analysis for complex design means “slowing [the] whole process down”, new arrangements with partners such as consortia added complexity, and it was pointed out that as multi-year business cases are also likely to be larger in funding they will meet with more compulsory scrutiny processes such as needing review by the Quality Assurance Unit. For this reason, some Advisers felt that requesting a longer timeframe – or an option to easily extend the business case for more years – would have been a good idea. UN agencies have fed back that multi-year commitments are felt to bring more flexibility overall, even if monies are still programmed on an annual basis UNHCR HQ). Further than that, the confidence of having multi-year funding allows an increased risk-appetite for and confidence in working in some difficult contexts (ICRC HQ).4 Not just time, but cost savings are part of the rationale for many multi-year arrangements. Efficiency savings, security to negotiate longer-term agreements, and greater flexibility in procurement are the main anticipated drivers of such savings. A general calculation of the rate of cost savings realised couldn’t be made in the course of this lessons review, although there is a long-term evaluation that will be able to look into more detail on ‘value for money’ questions. Early indications from the Ethiopia multi-year programme with WFP however, are that savings of up to a third of the standard cost have been possible through advance planning for local procurement of food relief at the lowest prices (immediately after local harvests). This saving has been translated not just into more of the same general relief, but was also used to flexibly target specific groups such as pregnant and lactating women.5 2) A multi-year arrangement is more time intensive in the design phase with more DFID and partner resources needed at this stage. There are other interesting aspects of timing distinct from time-saving that affect multi-year business cases. The actual date of the launch of the business case, the inception phase, and the start of full implementation emerged as an important element in interviews. Many Advisers reported that one of the things they would do differently in the business case was to time it better in relation to three other cycles – DFID’s planning and reporting cycle; partners’ planning and reporting cycle; and to a lesser extent the seasonal cycle (some countries don’t have strong seasonal effects). For some, misalignment with these cycles caused minor “awkwardness” e.g. necessitating an ‘extra’ Annual Review to make sure future Annual Reviews could be done once partner reporting had been received and yearly from then on. In other cases, having a number of activities under a single business case 4 This effect was noted in an evaluation of the Swedish Development Authority’s multi-year frameworks for humanitarian assistance. See Mowjee and Randel, 2010, ‘Evaluation of Sida’s Humanitarian Assistance: Final Synthesis Report’. 5 Ethiopia WFP 2014 Annual Review 10 led to a heavy process to complete many Annual Reviews simultaneously. But it might have larger effects. One Adviser mentioned that a late release of funds “undermined [the] evidence base from the outset” because a baseline survey could not be carried out at the appropriate time. Unlike with annual funding, this second example could have knock-on effects for the life of the business case and make some work – multi-year livelihoods work is a good example – harder to achieve or to demonstrate achievement even with multiple years to invest in working on it. The inception phase of multi-year business cases has varied though it’s reported that the inception period is often hurried with agreements partfinished before it closes. This is not least because the multi-year funding is in contexts where agencies typically have established systems, and to some extent a mind-set, for delivering response programming. For example, it is clear By the nature and ambition of multi-year financing, the inception phase may need to include an emphasis on DFID joint policy planning. This would facilitate more of a common vision on the aims of the business case and policy collaboration. A single appropriate timeframe for developing a business case can’t be identified but Figure 3 below contains some examples that might provide orientation for time management. 3) Alignment of cycles – DFID’s planning and reporting cycle, partners’ planning and reporting cycle, and relevant seasonal cycles – should be factored in from the outset; mis-timing in business case approval, for example, can undermine longer-term programmes’ chances of demonstrating success. 11 Figure 3: Indicative timelines for developing the multi-year business case June Somalia Start writing Business case August Strategic case approved February April October QAU and other vetting Approval of Business Case Start of implementation March/April January Framework approved Publication of strategy and call for proposals July August December Approval of Business Case Evacuation of Yemen office! Start of Implementation Yemen November May July September January First discussion of ideas with NGOs Business case submitted for quality assurance Cleared through Quality Assurance Unit Approval of Business Case Projected start of implementation Sahel 12 ii. ‘Cascading’ funds One lesson was neatly summed up by an Adviser as “just because you give people multi-year money doesn’t mean you get multi-year strategies”. It might be expected that there will be a certain lag-time between the approval of multi-year funds and adaptation of strategies and programmes to take full advantage of it. However, the feedback from advisers is that the rate of adaptation is slower than expected and needed. This was attributed partly to just being something that needs more time to emerge as “It’s very new, a learning process”. Some partners may even have overlooked that there wouldn’t be an annual chance to apply for funding in the same way as with repeated annual processes. Even in the earlier business cases approved in 2011 which are now nearing the end of their term, Advisers reported that some partners have still not “got it”. A Bangladesh partner reported that there is a “shift in the mindset” involved. In one case, a partner returned funds when the humanitarian space contracted and they were unable to utilise it – this was a large amount of funding as it was intended for multiyear use, and caused “a heap of headaches internally”. However, feedback from this partner was that the flexibility to use funding as needed rather than multi-year funding per se was required (see more on the need for flexibility under Monitoring, evaluation, and learning below). This review did not include discussions with funded agencies at the country level, though feedback from DFID country offices suggests that agencies have a stronger opportunity to reap benefits from multi-year funds if it is well communicated, jointly planned, and comes with sufficient pre-agreed contingency measures should the operational situation deteriorate. There is still a sense in which "it's not clear what [implementers] are going to do differently". Many Advisers stressed that the ‘big wins’ of multi-year funding in terms of changed, resilient programming are not demonstrated (although uncertainty about what resilience means in a given context confuses this). Nevertheless, this applies very unevenly across partners, with some responding well to the multi-year arrangement. At least in some cases there have been proposals that are “a lot smarter, a lot more ambitious”. One of the clearest possible benefits of moving to a multi-year arrangement is to allow for programmes that seek to build resilience – that tackle underlying vulnerabilities to prevent crises having repeated severe consequences for affected people. Resilience-building programmes were probably the most common kind that was mentioned by Advisers. However, it’s clear that since resilience as a policy position and the multi-year funding that seeks to support it are relatively new, there is still debate on resilience programmes. What constitutes a good resilience programme, how does it differ to similar past programmes, how do development actors fit in, and what resilience could multi-year funding enable in contexts where wider aid machinery remains geared towards response to shocks? As one Adviser said "you know that's 13 the right answer [resilience]... [but] no one really knows what that really means". 4) Extra DFID efforts will be needed to communicate to partners and other donors that a multi-year arrangement is in place /possible, and to continually advocate for higher-order (resilience) results on that basis. As well as a sense that not all partners have grasped the opportunity presented by multi-year funding, there is a large practical obstacle. Multi-year funds approved in business cases are not ‘cascading’ through relevant managing and implementing partners. This was found particularly in Kenya and Ethiopia (two of the ‘oldest’ multi-year arrangements having started in 2011). Kenya found that “one of the disadvantages of funding directly to the UN is the lack of flexibility in passing on multi-year funding grants (and the potential subsequent benefits) to operational partners”6 and Ethiopia that “[t]he major issues with the [refugee support] programme during year one have derived from delays within UNHCR’s sub-granting systems”.7 In the case of Ethiopia, some downstream partners required two agreements in a single year (rather than one that might cover several years) as their administrative year covered part of two UNHCR administrative years. DFID (HQ or CO) Multilateral Agency INGO Local implementer Figure 4: Bottlenecks in funds transfer? This seems a much more durable obstacle than the ‘lag-time’ needed for partners to ‘bed in’ the idea of multi-year funding. It relates to internal processes (e.g UNHCR sub-granting) which DFID has no direct influence on, and would require an organisational change for each relevant partner to alter, with all the attendant difficulties of that. There is only the most tenuous suggestion that multi-year funding might act as an incentive to such a change, e.g. it was reported that UNHCR and WFP Ethiopia offices managed to negotiate higher levels of delegated authority for the multi-year funds.8 6 DFID Kenya, 2014, Support for Refugees in Kenya 2012-2014: Annual Review 2 DFID Ethiopia, 2013, Medium Term Assistance to Refugees in Ethiopia Annual Review 8 DFID Kenya, 2014, Support for Refugees in Kenya 2012-2014: Annual Review 2, p. 11. 7 14 The consequences are potentially significant as it leaves the advantages of multi-year funding restricted to the time and cost-saving benefits for DFID and perhaps the immediate partner. “[A] lot of these benefits don’t make it down to implementers” so changes in programming can’t be made even if a downstream partner does ‘get it’. More than that, it may mean that the ‘big wins’ of multi-year funding are not just delayed but fully out of reach wherever a chain of partners is needed to implement programmes. Where a UN agency partner is directly operational, for example like WFP in Ethiopia, multi-year funding has significantly cut down on operational costs – making an already efficient procurement process more so and preventing gaps in the pipeline for food items. Several countries have opted to support implementing partners directly through a consortium of INGOs9 – Yemen, Somalia, Mozambique, Sudan, and Kenya have done this. The consortia programming is not far enough advanced to comment on how the proposals are being realised. The ultimate lesson that should be taken from this situation is unclear, since multilateral agencies will continue to play a role. Avoiding ‘intermediate’ partners would likely leave DFID’s administration capacity overburdened by a higher number of smaller partners. Devoting effort to improving the ‘cascade’ of funds would likely reap some rewards but as above it’s unsure due to the partner-specific internal processes involved. Spreading our bets by funding some large intermediary partners, while also directly funding implementing partners might offset some of the risks of funds getting ‘stuck’ within one partner; but this could also represent the worst of both worlds by increasing DFID’s admin burden but retaining the cascade problem. However, the cascade problem and the need to allow for a period to make any possible organisational adjustments are clear. 5) Providing multi-year funding does not automatically lead to multiyear programmes; the ‘cascading’ of funds from DFID to some or all funded partners may continue to be handled as annual funding. 6) Partners need time to make organisational adjustments to reflect the ambition and innovation proposed in multiyear business cases. This should be taken into account, possibly with options for a ‘transition period’ from annual activities to maximise the use of DFID funds. iii. Partner and government relationships Advisers generally reported some changes in their relationships with partners as a result of moving to a multi-year arrangement, although this wasn’t particularly emphasised. There is much that is the same across multi-year and annual arrangements including type of partners, reports generated etc. A 9 However, there is also a blind spot on how funds supplied to a directly operational partner (most likely to be an INGO) are then passed on to, say, local organisations for some of the implementation. It’s been argued that such local actors are key in protracted crises, GSDRC (2011), p.9. 15 possible difference is that multi-year may favour established partners where there is already a relationship of trust as a number of Advisers said they looked for a ‘track record’ of performance when deciding on a longer-term funding relationship. Some changes in the relationship came in the form of governance arrangements, especially quarterly meetings that covered horizon scanning or ‘mini annual reviews’. There may be more face to face meeting to discuss the less conventional aspects of a programme, or to discuss “mid to longer-term strategy”. In general, changes in partnership relationships seem to converge around having a more strategic and less ‘transactional’ conversation as the multi-year arrangement frees up time on both sides. A partner in Bangladesh confirmed that the “relationship…is very different” under a multi-year arrangement – suggesting the long-term investment gives DFID itself incentive to support activities in other ways, such as attending meetings, or liaising with government. However, as most offices worked with the same partners on an annual funding basis as well as a multi-year basis, these changes to relationships weren’t particularly striking. Changes in relations to government were also mentioned. In stable environments like Kenya multi-year funding enabled a closer cooperation with government. This was partly attributed to multi-year commitments giving DFID greater credibility, and partly as the multi-year approach allowed advisers to adapt to government planning cycles even where they were different to DFID’s or partners’. Contexts that are less stable or where the statehumanitarian relationship is antagonistic are more problematic. However, the same effect was also noted at least in the early part of the multi-year arrangement in Yemen, as DFID’s credibility as a partner was boosted through its multi-year commitment. However, it’s not clear how this has evolved with the deterioration in security and DFID evacuation. Other donors seem to have reacted with interest to DFID’s adoption of multiyear financing at country level, but this hasn’t created any notable momentum towards changing approaches (although the Sahel seems an exception to this, as most donors and partners are moving to at least stronger multi-year planning). While humanitarian country programmes are pushing ahead with multi-year programming, DFID as a whole is generally reducing multi-year commitments to partners – the percentage of funds provided by DFID to partners as “3-year forward stipulations” has fallen from 90% in 2008 to 54% in 2012 (a trend noted in other donors also).10 This is partly explained by the shift in funding to fewer, generally poorer countries, and an increase in the proportion of DFID priority countries that are classed as ‘fragile’ (20 out of 28 countries), where the risks of long-term development (not humanitarian) funding are higher. iv. Types of programmes 10 National Audit Office, ‘The performance of the Department for International Development 2013-14’, p. 33. 16 When asked about changes to programmes under multi-year arrangements many of the examples mentioned seem to fit into the category of ‘system strengthening’ programmes. These programmes are aimed at building useful information banks and processes across the country humanitarian system – bio-metric registration of refugees in Kenya, beneficiary information management in Somalia, health surveillance systems in DRC, and support to predictable flights and (possibly) better needs assessments in Bangladesh.11 Under an annualised model, it wasn’t considered impossible that these kinds of programmes could be done – but certainly a lot more difficult. It would have made it difficult for the partner to justify even starting this kind of programme, quite apart from the need to have more than a year to set them up and start to see returns. Since many of these programmes operate at a ‘system’ level, they seem less dependent on multi-year funding being passed to downstream partners (the cascade problem, above). A single large partner can steward the programme even if there are several downstream partners, or in other cases the system support is delivered by a single specialised organisation. There was some suggestion that working on this system level also makes the performance of such programmes vulnerable to systemic barriers – for example, slow government approval processes that eat into even multi-year timeframes. 7) Multi-year arrangements can facilitate programmes that deliver ‘system strengthening’ for the humanitarian system in-country more easily than annual approaches. The longer programmes also mean that it’s unlikely an Adviser will have experience of the full programme life cycle. At some point, an Adviser will probably either leave a multi-year programme that they’ve designed, or step in to one that is mid-implementation. This seems likely to throw even more weight on to the importance of handovers between staff. v. Monitoring, evaluation, and learning It came across very strongly from interviews that one of the major benefits that a multi-year business case can deliver is flexibility. Advisers felt that there is nothing that makes multi-year arrangements inherently more flexible than annual ones, so the need to consciously design for flexibility was mentioned again and again. Although multi-year arrangements intended for relatively predictable risks and crises, it is naturally only possible to reliably predict that the situation will continue not exactly how it will develop – "we don't know 11 Through Mission Aviation Fellowship and ACAPS respectively. The needs assessment work is still in the planning stage due to 17 what the needs will be in year 2". Related to this, the need for more focused risk analysis was highlighted. This flexibility can be designed for in measures such as contingency funds (see below), adjustable targeting, etc. It also has a lot of implications for how monitoring, evaluation, and learning are approached. Some of the suggestions made are: A separate overarching logframe is preferable to a complex aggregate of ‘nested’ logframes [Kenya, Yemen] Targets should be adjustable for ‘spikes’ but the core indicators should be the same in and out of ‘spikes’ in need [Kenya] Logframe indicators should be identified very early on as a main output of the inception phase [Ethiopia] ‘System strengthening’ indicators should be included in logframes [Bangladesh] Work in multiyear indicators to the annual review processes – building a consensus on which level of information should be collected [DRC]. It was also asked whether Advisers found existing monitoring processes, especially the Annual Review process, adequate to monitor multi-year programmes. This was asked because of the output-based nature of the Annual Review and the scoring of programmes on the basis of outputs. Where programmes were designed towards longer-term outcomes, an output scoring might not reflect the performance of the programme. Although some Advisers noted that this emphasis wasn’t helpful, it was felt that the Annual Review could still be made to do what’s needed. The way the Review process is approached, and the qualitative information that can be included alongside the scoring element, make a big difference. 8) Existing standard monitoring tools – designed on an implicit assumption of annual programming – are flexible enough to monitor multi-year funding as long as the supporting documents explicitly determine multiyear targets, and review teams address multi-year issues in the process. Although the Annual Review and other monitoring processes such as logframe targets were felt to be usable for multi-year programmes, some countries have also made an unusually large investment in monitoring and evaluation.12 Somalia is devoting 3% of the value of the business case to evaluation. Many of the business cases have a separate output on ‘building the evidence base’ for the multi-year programmes specifically. In terms of monitoring performance within DFID’s existing systems, the example of Syria is instructive. The two Syria business cases are both ‘umbrella’ designs, and cover a wide range of partners and several countries. 12 The median value of programmes devoted to evaluation in DFID is 1.9%, ‘Rapid Review of Embedding Evaluation in UK Department for International Development’, p. 49. 18 Since DFID systems (ARIES) can only enter a single ‘component’ per country, it was not possible to track both which country and which partner funding was allocated to, only one or the other. This led to a blind spot on the level of inputs that were going to each affected country in the region. To overcome this, the Syria team will switch to several partner-specific business cases instead. There are relatively few partner-specific business cases so far so it’s not clear how this will go, but it is an example of where DFID systems necessitated a design change, rather than showing the flexibility that was possible in the case of Annual Reviews. vi. Contingency and preparedness Humanitarian programmes still have to be ready to provide urgent assistance to people affected by crises even if aiming for longer-term gains in resilience. Paying for both is something that Advisers acknowledge could be hard when faced with the “brutal reality of budgeting”. This is why some kind of ‘contingency’13 is built in to many but not all [9/18] of the multi-year business cases.14 The total contingency in the business cases varies widely – from three per cent of the business case value to 30% (the average contingency size is 14%). The typical size of contingency is probably not enough to respond to a serious crisis; indeed in DRC, the contingency was found to be inadequate when humanitarian needs spiked and instead it was agreed that the life of the programme would be reduced from five to four years to meet the needs that had arisen in between. The planned and ‘ad hoc’ contingency arrangements have in common that they both aim towards smoothing ‘spikes’ in need by intervening early. Some of the programme elements that are being delivered through the main (not contingency) funding of multi-year programmes have a similar effect. For example, advance funding that allows WFP to forwardpurchase and position food relief stocks for preparedness has some of the same effects as cash contingency. Much of the Mozambique multi-year arrangement is built around this pre-positioning, with a preparedness rather than contingency focus. Six of the eight countries with contingency (Ethiopia, Kenya, Somalia, Sudan, Syria, Burma) have drawn on it so far (Yemen, Sahel, Pakistan have not yet). Examples include use of contingency to respond to resurgence of conflict in Sudan and Burma, and response to seasonal malnutrition spikes in southcentral Somalia, and refugee influxes in Ethiopia. In several cases the contingency was used more to smooth bumps in the humanitarian system than to respond to a change in humanitarian needs e.g. the Ethiopia contingency was used to ensure the WFP pipeline was not interrupted; Syria used contingency funding to ‘bridge’ a period when a new business case was 13 Contingency measures are sometimes referred to as reserves, risk financing mechanisms, or other terms. Contingency is used as an umbrella term here. 14 Country offices still have access to the Africa Regional Division humanitarian reserve and the Conflict, Humanitarian, and Security Division reserve in the event of crisis. A given tranche of contingency may be a mix of country and central reserve funding. 19 being designed. The end goal of the use of contingency was the same however, to intervene early to prevent escalating needs. Advisers repeatedly emphasised the contingency measure as a design options for ensuring that multi-year commitments retain flexibility. This was considered vital when working in even relatively predictable humanitarian situations; experience of the use of contingency so far also suggests that it is as important in responding to sudden gaps within the country humanitarian response system itself. 9) Flexibility in multi-year design is essential. Although the optimal level of contingency funds is unclear, they are considered essential to respond to unexpected humanitarian need and unexpected humanitarian response system faults alike. 20 D. Annex 1: Grid of approaches to multi-year arrangements Design Time savings Partners Strategy Monitoring and Learning Umbrella 9 business cases £958,000,000 82% Bangladesh, Burma, DRC, Pakistan, Sahel, Somalia, Sudan, Syria, Yemen Thematic 6 business cases £110,700,000 9% Partner-specific 3 business cases £102,600,000 9% Burma, Ethiopia, Kenya, Mozambique Ethiopia, Yemen (soon to be Syria region) -Time consuming design phase for DFID and partners /Relatively time consuming design phase (depends on range of partners) -Many individual partnerspecific agreements time consuming to design, with repetition +Later time savings greater +Later time savings greater -Later time savings present but smaller (e.g. need to manage separate agreements/relationships) -Not possible to space effort, e.g. a single large business case will result in a single large discrete review processes /Problematic to space effort, e.g. a few large business cases will result in a few large discrete review processes +Possible to space effort, if original commencement of business cases was spaced +Incentive to consortia or other collaborative arrangements +Incentive to consortia or other collaborative arrangements -No incentive to consortia or other collaborative arrangements +Can include ‘intermediate’ partners (e.g. UN agency with its own downstream partners) and direct implementing partners (e.g. INGOs) +Can include ‘intermediate’ partners (e.g. UN agency with its own downstream partners) and direct implementing partners (e.g. INGOs) -Single partner means full dependence on whether they cascade multi-year funding to downstream partners +Can function as the country humanitarian strategy rather than being 'just' a set of programmes /Can slot in to existing country strategy /Can slot in to existing country strategy -Complex and/or multiple logframes +Relatively straightforward logframes +Relatively straightforward logframes +Incentive to impact-level measurement -Individual partner performance tracking difficult (esp. for regional approaches, see Syria) +Incentive to impact-level measurement /no evident (dis)incentive to impact measurement -Individual partner performance tracking difficult +Performance tracking and management simpler 21 E. Annex 2: Methodology The lessons review focused mostly on operational lessons identified rather than results or impacts. This was due to timing (it was too early to recognise impacts) and to avoid duplication with the planned multi-country thematic evaluation that was commencing at the same time. The review started with a document review that incorporated the 17 business cases that were complete at the time (i.e. all except Pakistan), and the Annual Reviews of two programmes that had already been reviewed (refugee programmes in Ethiopia and Kenya). These reviews are used for more detailed case examples throughout the report. Other documents reviewed can be seen in the References section. Primary information was collected through semi-structured interviews with key staff in country offices and in London teams, and supplemented with feedback from partners collected through meetings and phone interviews. Eighteen interviews with key DFID staff from ten country offices/regional team, eight by phone and ten in person were conducted (again, all except Pakistan). The interview questions were analysed for common themes, and only recurring points have been used to draw lessons – although interesting single cases have been highlighted in the body of the report. Feedback from partners was collected through a modified version of the semi-structured interview questions over phone interview (Bangladesh), and through a request for open feedback at a set of HQ level meetings in Geneva. The findings of the review were validated through a video conference with a small number of the interviewees, and through comments on the draft materials for those not able to make the video conference date. All comments are reflected in this version of the report. 22 F. References Ashdown, 2011, Humanitarian Emergency Response Review (HERR) Cabot-Venton, 2013, Value for Money of Multi-year Approaches to Humanitarian Funding DFID, 2014, Rapid Review of Embedding Evaluation in UK Department for International Development DFID CHASE, 2013, Responding to chronic crises, vulnerability and predictable spikes in need: the design of effective humanitarian and development financing instruments DFID Ethiopia, 2013, Medium Term Assistance to Refugees in Ethiopia Annual Review DFID Kenya, 2014, Support for Refugees in Kenya 2012-2014: Annual Review 2 DFID Mozambique, 2014, Annual Review- Disaster Risk Reduction- 12 November 2014 DFID Yemen, 2013, Lessons Learned for Call for Proposals GSDRC, 2011, Multi-Year Funding to Humanitarian Organisations in Protracted Crises Mowjee and Randel, 2010, Evaluation of Sida’s Humanitarian Assistance Final Synthesis Report National Audit Office, 2014, The performance of the Department for International Development 2013-14 23