SEC Cardboard Bumper Assembly Jig for the NISH AbilityOne Design Challenge Client: Institute for Economic Empowerment Semester: Fall 2011 Ref: SEC F11-75-NISH 1 | P75a g e Prepared by: Saluki Engineering Team SEC 8 November 2011 Saluki Engineering Company Attn: F. Harackiewicz, K. Purcell, A. Weston SIUC College of Engineering – Mailcode 6603 Carbondale IL 62901-6603 Dear Ms. Harackiewicz, Ms. Purcell, and Mr. Weston, The letter is in response to your request for proposal for the NISH AbilityOne Design Network Challenge. Our team, SEC Team 75, has developed a cardboard banding jig designed for production and completion of cardboard bumper systems through START and its subsidiaries. Further, we believe that our design will not only increase production numbers dramatically, but will help to aid and assist the operator of said jig. This proposal is based on simple, clean, and efficient incorporation of electronic and mechanical systems. The goal of this design is to be able to create cardboard bumpers rapidly and easily through the use of racking, clamping, and counting assemblies. Overall, START is producing approximately 1200 units per week while their demand from their current subsidiary is 4000 (Please see Appendix A). We hope to exceed this projected number through our jig. Finally, SEC Team 75 would like to thank you for the opportunity to submit a design proposal to your company and we hope to hear from you soon. Sincerely, Jordan John Project Manager – Team 75 Saluki Engineering Company jjohn89@siu.edu (618) 303-0975 2|Page Executive Summary The Saluki Engineering Company in collaboration with the Institute for Economic Empowerment has put out a request for proposal that states, “Client wants a device or a system that will solve a real workplace problem for at least one group of severely handicapped workers.” Our goal is to design a cardboard bumper assembly jig. The design will be simple, efficient, and cost effective. Team 75’s approach to this request is a multifaceted design that will increase ease of assembly as well as increase production rates. The project will consist of an electrical and mechanical subassembly working together to create an overall project. The assembly will consist of the following: The mechanical system will be a racking and clamping system. The rack will be a plate that will be supported by rigid rectangular shafts. As the cardboard pieces are fed into the rack, the electrical system will allow for the user to know if the system is under filled, filled, or overfilled through the use of LED indicators. These indicators will be housed and attached to the racking system and controlled by a microcontroller. Once the rack is filled, the clamping system will swing downward and hold the pieces together allowing the operator to band the cardboard slivers. Initial research and development began September 9th, 2011 after receipt of the RFP and will conclude in early April with a detailed design report submitted by April 19th, 2012. The estimated cost of the final design will be $247.56. 3|Page Non-Disclosure Information The information provided in or for this proposal is the confidential, proprietary property of the Saluki Engineering Company of Carbondale, Illinois, USA. Such information may be used solely by the party to whom the proposal has been submitted by the Saluki Engineering Company and solely for the purpose of evaluating this proposal. The submittal of this proposal confers no right in, or license to use, or right to disclose to others for any purpose, the subject matter, or such information or data, nor confers the right to reproduce or offer such information for sale. All drawings, specifications, and other writings supplied with this proposal are to be returned to Saluki Engineering Company promptly upon request. The use of this information, other than for the purpose of evaluating this proposal, is subject to the terms of agreement under which services are to be performed pursuant to this proposal. 4|Page Table of Contents Transmittal Letter (JJ)……………………………………………………………………………..2 Executive Summary (LE)..………..………………………………………………………………3 Nondisclosure Statement……………………………………………………...…………………..4 Table of Contents………………………………………………………………………………….5 List of Tables and Figures…………………………………………………………………………6 Introduction (JH)...……….………………………....………………………………………..……6 Literature Review (All, Revised by BB)…………. ……....………………………..………..……7 Project Description (JJ).……………………………………………………………………….…17 Project Organization (JJ)..…………………………………………………………………..……19 Design Basis (JJ)…....……………………………………………………………………………19 Scope of Work (JJ)……………………………………………………………………………….19 Subsystem Design………………………………………………………………………………..20 Clamping System (BB)…………………………………………………………………….20 Racking System (JJ)…………………....…………………..………………………………21 Power Source (LE)…………………...…………………………………………………….24 Microcontroller (JH)……..…………...…………………………………………………….25 Sensors (JH)………………………………………………………………………………..27 LEDs (LE)…………………………………………………………………………………28 Ventilation and Filters (LE)………………………………………………………………..30 Training Aids (JH, LE)…………………………………………………………………….30 Material Selection (BB)…....………………………………………………………………….…31 Action Item List (All)……...………………………………………………………………….…31 Draft Schedule (JJ)…..…………………………………………………………………………...33 Resources Needed (JJ, JH)…………………………………………………………………….…34 List of Analysis (All)…………………………………………………………………………….34 Works Cited……………………………………………………………………………………...36 Appendix A: Communications……..……………………………………………………………37 Appendix B: RFP Documents…………………………………………………………………....38 Appendix C: 3-D Renderings of Mechanical System (JJ)…………………………….…………46 Appendix D: Microcontroller Wiring Diagram…...…………………………………..…………49 Appendix E: Resumes……………………………………………………………………………50 5|Page List of Tables and Figures Figures Figure 1: Cardboard Bumper Picture…………………………………………………………….11 Figure 2: Jig Design………………..…………………………………………………………….12 Figure 3: Cost of Binding Machine..…………………………………………………………….13 Figure 4: Banding Machine…….………………………………………………………………..14 Figure 5: Shirt Press……....…….………………………………………………………………..16 Figure 6: Supports………………………………………………………………………………..22 Figure 7: Racking Plate………………………………………………………………………..…23 Figure 8: Draft Assembly……………………………………………………………………...…24 Figure 9: Microcontroller Wiring Diagram…………………………………………..………….26 Figure 10: Sensor Placement Diagram………………………………………………..…………27 Figure 11: Sample LED……………………………………………………………….…………29 Figure 12: LED Setup…………………………………………………………………..………..29 Tables Table 1: Block Diagram……………………………….…………………………………………18 Table 2: Organizational Chart………………………….………………………………………...19 Table 3: Basis of Design…………………………………………………………………………19 Table 4: Material Selection Matrix………………………………………………………………31 Table 5: Action Item List……………………………….………………………………………..31 Table 6: Proposed Schedule…………………………….………………………………………..33 Table 7: Resources Needed………………………………………………………………………34 Introduction In the early 1960’s a movement began; A movement that would finally allow those with severe handicaps, mental and physical alike, to no longer feel ostracized in the workplace. This movement, known as the Disability Rights Movement, would lead to numerous national organizations aimed to aid those with handicaps to find work and succeed in industry. One of the organizations formed during these trying times was NISH. 6|Page Through the years, NISH has developed into an international organization helping hundreds of thousands people find work despite their handicaps. One of the biggest challenges NISH has encountered is being able to place clients in to work that has numerous restrictions. These restrictions are often based on ergonomics and movement controlled assembly. Because of this, NISH has developed the AbilityOne Network Challenge. The NISH AbilityOne Network Challenge sponsors competition throughout the nation aimed at the design and manufacturing of “enabling devices”. These devices seek to aid those with handicaps to perform complex tasks easily. In other words, these devices create a solution to problems affecting those with handicaps in the workplace. START, a NPO based out of Murphysboro, Illinois that is a subsidiary of NISH. START has in house facilities in which they employ individuals with handicaps. One of their current projects is creating cardboard bumpers that are used by local companies for shipping and packing. Currently, they are able to produce 1200 units per week. Their current client has increased their demand to 4000 units per week. Through the development of an assistive jig, SEC Team 75 hopes to expedite their current assembly process. The concept of this design includes a jig in which they will be able to rack, clamp, and count cardboard pieces allowing faster wrapping and assembly of cardboard bumpers. Literature Review The American Heritage Stedman’s Medical Dictionary defines handicap as a physical, mental, or emotional condition that interferes with ones normal functioning [1]. When most people think of the word handicap, they instantly envision someone in a wheelchair; however, 7|Page there are other disabilities such as being hearing impaired, having a long term illness, a brain injury, or even intellectual disabilities just to name a few. The 2010 census reports that in the United States as a whole, around twelve percent of the population, nearly thirty-six million people have some level of disability. Individuals who suffer from disabilities have reported difficulties in obtaining jobs, keeping a job once obtained, and performing job duties. The average employment rate of disabled citizens across the United States is a paltry 33.4 percent [2]. NISH, the National Institute for the Severely Handicapped, is an organization that is focused on helping people with disabilities gain employment. NISH’s mission is “Create employment opportunities for people with significant disabilities.” [3] NISH been helping handicapped people since 1974. NISH is affiliated with the AbilityOne program. The AbilityOne program is composed of 600 nonprofit organizations across the United States. One of these organizations is START in Murphysboro. These organizations are dedicated to providing work to disabled people and providing them income. They work toward finding jobs for people with all types of disabilities, from the blind to those with mental disabilities like autism. The AbilityOne network currently employees around 47,000 people, making them the largest employer of disabled people in the United States. [3] Every year NISH supports a competition called the AbilityOne Design Challenge. In this competition students are encourage to make something that can assist people with disabilities in their everyday careers. These designs are required to help make their daily task easier. The teams must registered by the 20th of April. In their entry each group must submit a final report with full details of their design, as well as a video of their design in use. 8|Page These designs are put though strict judging criteria. These criteria are based on a series of questions. “• Is the assistive technology device/system a solution to a barrier that prevents a person with a significant disability from entering or advancing in the workplace? If the answer is “No”, the submission will not be reviewed further and will be considered to be out of contention. • Was a prototype built? If the answer is “No”, the submission will not be reviewed further and will be considered to be out of contention. • Was the device/system designed in collaboration with a person who has a disability? If the answer is “No”, the submission will not be reviewed further and will be considered to be out of contention. • Is the device/system currently being used or intended for use? by the end of the current school year? Additional consideration is given to those devices that are in use. • Was the design developed with consultation from a NISH affiliated NPA? Additional consideration is given to those that worked with a NISH affiliate.” [5] The final results depend on how well each group answers the questions above, as well as a few additional things such as safety and overall ease of use. The better the design solves a 9|Page problem but at the same time meets these judging criteria the more highly rated the entry will place in the competition. Workforce Concerns The closest organization in the AbilityOne network is Specialized Training for Adult Rehabilitation Inc., also known as S.T.A.R.T. This not-for profit organization has been around since 1969. The S.T.A.R.T. program caters to disabled adults by offering six different rehabilitation programs that serve over one hundred and fifty, not limited to just working opportunities. The organization had very humble beginnings, when it was first founded it operated out of a church basement. Now the program utilizes over thirty-six thousand square feet of space for its programs [6]. “Work opportunities include mobile custodial crews, subcontracting services for area businesses, janitorial services at the rest area on Interstate 57, and state of the art microfilming and digital scanning services.” [6] Current System and Proposed Design The S.T.A.R.T. factory in Murphysboro currently uses a binding system that workers use to double-bind stacks of cardboard strips. This system relies heavily on the use of human labor, because the current system calls for the stack to be manually counted, stack, held, and bound. These stacks of cardboard strips are used as packing bumpers by Penn Aluminum. Penn Aluminum uses the bumpers to pack and protect the products they send out on a daily basis. Penn has been a long-time contractor with S.T.A.R.T., starting nearly fifteen years ago, and S.T.A.R.T has been producing these bumpers for them nearly the same amount of time. 10 | P a g e Figure 1: Cardboard bumper Recently, Penn has led S.T.A.R.T. to increase the production of bumpers per month to double what their current production rate is at making the current quota nearly 4000 bumpers a month. While S.T.A.R.T. has been able to slightly increase their production of the bumpers, they are not able to fully meet the demand at this point. With a slight amount of simple adjustments the productivity will be able to be increased. With the adjustments the productivity will hopefully increase from the current 15 bumpers an hour a goal 25 bumpers an hour. To make the bumpers, employees currently hand count out 15 pieces of cardboard of a set length and width. Then they hold the cardboard pieces together and wrap them in tape on both ends, producing the cardboard bumpers. One problem is that it takes a lot of motor skills to hold all 15 pieces together while wrapping the bumper with tape that is dispensed from a wet tape machine. This causes production to be slow because many of the disabled people that work at START have disabilities that limit their motor skills. When our team visited the factory during production hours they noticed that even though S.T.A.R.T. has two tape dispensers, they are unable to use them because there is only one worker per shift with the necessary motor skills to 11 | P a g e hold the cardboard bundle while simultaneously cranking out a length of tape and then wrapping the tape around the cardboard. Figure 2: Jig Design As seen in Figure 2 above one idea on how to assist the operator is to include a jig device to hold the cardboard stacks in place as the operator binds the stack. Another idea is to build a system that allows the pieces to be held, much like the clamping system above, but also to rotate to ease the process of wrapping the band around the unit. While a system that uses mechanical components to lessen the amount of dexterity required to perform the task is great, a completely autonomous system is not what we are striving 12 | P a g e for. The whole reason S.T.A.R.T. exists is to help people with disabilities find work. Rather than creating an expensive machine to do the task for them, we are striving to make an efficient, affordable, and easy to use mechanism to assist the process. The plan is to incorporate electronics into the design via sensors and possible electro mechanics, but due to the nature of S.T.A.R.T the design must not be a financial burden on them, therefore target unit cost is between two and five hundred dollars. Most automatic banding units cost over one thousand dollars, with high-end units selling for nearly ten thousand dollars. Model Cost Pac SM65 Arch Strapping Machine $9986 Signode TABLE-TYER Plastic Strapping Machine $2566 Signode 430999 Power Strapping Machine $1082 Figure 3: Cost of Binding Machines The current tape dispenser system looks much like the machine in figure 4 below. S.T.A.R.T. had considered helping to make the job easier by buying automatic tape dispensers, but even those units were much too expensive. By utilize the existing units in the design, since they have proven reliable and the employees are used to using them, the total cost of the design may to be reduced. 13 | P a g e Figure 4: Banding Machine [7] The way the strips are stacked is a major point that could be improved. By decreasing the time required to count out the strips and then arrange them in a neat row could significantly increase daily output of the cardboard bumpers. The amount of time that is takes to make count the bumpers and stack them is close to 2 minutes. To make the job of counting the strips easier, the idea to using sensors to detect when the correct number of cardboard strips have been placed into the machine. The most cost-effective option seems to be using an infra-red sensor and connecting it to a microcontroller inside the unit. Infra-red sensors are widely used in robotics and are fairly cheap and easy to maintain most costing roughly $25-$100 [8]. 14 | P a g e There are a couple different ways to program the sensor. The first way, and probably the easiest is to program the sensor to count each strip as it is loaded into the holding tray. When the sensor has counted the correct number of cardboard strips, a green LED will light up on the unit and the employee will know that it is time to activate the holding system and wrap the tape around the bundle. The second way to program the sensor would be to make it so that the green LED lights up after the cardboard reaches a certain height. The microcontroller for the unit will also be fairly inexpensive and will probably be the best option to handle the input from the sensor A third way is measure the weight of the stack and allowing the sensor to engage between a certain tolerances, which would again activate a green stating the jig is full. Included in all of these would be a red light that allows the user to know when the jig is overfilled. After looking at various competing systems, both in terms of binding and in terms of tape dispensing, none of the other products seem to be near to what is needed by S.T.A.R.T., and if a product is similar to a possible desired component design it is out of the price range that an organization like S.T.A.R.T. could afford. The option of a stacking system could also speed up the bumper production process. A patent for a device that is used to stack fanfold paper was fold and reviewed. Creating a system similar to this device will be of benefit to S.T.A.R.T. This design is a very good design because of its simplicity. It uses very few moving parts and is fairly inexpensive [9]. The design allows sheets to slide down a chute that only allows the sheets to fall flat on the bottom of a tank that holds all of the paper. A problem may arise in the case when the cardboard trying to be stacked may not fall flat. This is a very small flaw though, since employees could easily reach in and fix 15 | P a g e the problem. The design allows stacks to be made easily, by a simple process. This is ideal for the design that can be used by the S.T.A.R.T. facility because the simplicity means it can be easily used and taught to the employees. The problem with the design mentioned above is that a hopper system would need to be included to render the stacking system improvement. Due to the size of the cardboard strips, 11x2x.25 inches, a hopper that would hold a considerable amount of cardboard strips that would allow steady production would have to be of substantial size. This depending on S.T.A.R.T.’s work space may cause a problem by consuming to large of area making it impractical in S.T.A.R.T’s limited workspace for this project which is 15x8. The Last component the design could include is a clamping device. Since one of the largest problems in production is the holding of the cardboard in place, a clamp may be put in place to hold the stack steady in a jig while being bound. The clamp would resemble something that is used in presses, with a handle the must be pulled down to lock in place until released. A shirt press like seen in figure 5 below contains a sample clamp that would apply pressure on the stack in the jig. Figure 5: Shirt Press [10] 16 | P a g e The biggest considerations for the design are as follows. First, is ease of use? Since the competition is focus on simplicity, but more importantly the S.T. A.R.T. facility is focused toward providing jobs that mental disabled employees can accomplish. So the easier the design can be taught and used the more useful the final product will be. The second thing is the cost of the design. Since S.T.A.R.T. has limited funding the cost of the system must not place them in a finical burden. Ultimately these constraints will determine which of the above options for design will be able to be included in an effective manner. Project Description Team 75’s objective is to create a device that will assist the racking, holding, and banding of cardboard bumpers. The basis of this design is to create a base racking system. As the operator fills this racking system, three LED indicators will give insight on how full the jig is. The LED’s will light up as the sensors, controlled by a microcontroller, indicate capacity. The first LED will allow the user to know the jig is not filled full, but is actively powered. The second will tell the operator the jig is at proper capacity (15 cardboard slivers). The last will tell the operator the jig is over capacity. Once the jig is properly filled, a swing clamp will come down and apply pressure to the bunch. Once this is done, the operator can then band the bumper and production is complete. By speeding the counting process and assisting with holding while banding, the operator will be able to speed production time and will also see an ease in doing so. The organization of this jig is seen in the following flow chart: 17 | P a g e Overflow LED Fill LED Underflow LED Electrical System AC to DC Power Supply Arduino Uno Microcontroller Fill Sensor Carboard Banding System Mechanical System Racking Mechanism Feed Overflow Sensor Clamping Mechanism Ventilation and Filters Table 1: Block Diagram Currently, the process is done completely by hand. Therefore, any implementation of assistance will increase production. Overall, we are hoping to increase production from 1200 units to 4000+ allowing not only an order increase, but an increase in salary for the operators. Currently, they are paid on a by-piece basis. So, if we are able to speed units produced, we will also be able to help the operator make more during a shift. 18 | P a g e Project Organization Project Manager: Jordan John (ME) Responsibilities: 3-D Rendering/Material Selection/Racking System John Hughey (CpE) Responsibilities: Programming/Software Mapping and Integration Linden Eason (EE) Ben Blair Responsibilities: Responsibilities: Electrical Wiring and Integration/Harness Wiring and Integration Material Selection/Clamping System/Fabrication Table 2: Organizational Chart Design Basis Documents Request for Proposal SEC RFP Project Definition SEC RFP List of Deliverables Draft Proposal Final Proposal* End of Proposal Memo Progress Report Design Report Notebooks and End of Project Memo Date 9-Sep-11 9-Sep-11 9-Sep-11 8-Nov-11 8-Dec-11 8-Dec-11 23-Feb-12 19-Apr-12 5-May-12 Table 3: Basis of Design (Please see appendix B for home documents) *Final Proposal overrules any statements made in the draft proposal Scope of Work List of Deliverables as Required Literature Review Technical description of all work done for every solution 19 | P a g e Equipment, component, and materials take-off lists and costs for each solution Technical Drawings Selected solution with Pugh chart Technical description of recommended system and how it works Summary of lab tests and analysis performed relevant to solution Complete specification including all drawings necessary for production and installation as well as repair Complete list of components and signal processes Table of performance data Technical list of problems and limitations derived during design and testing Analysis of electromagnetic compatibility including coding Fault analysis Technical Manual Users Guide Conclusion and recommendation section Estimated cost of production Timeline to construct, build, or manufacture Appendix Subsystem Designs Clamping System Summary of Components Clamping device Lever Pressure applying plate Jig Mounting Unit List of Deliverables Clamping Prototype Analysis of maximum force needed on handle Analysis of mechanical advantage Analysis of minimum pressure needed for plate clamping 3-D Renderings 20 | P a g e Due to the current problem that S.T.A.R.T. has with holding the bumper stacks while taping them together, the use of a clamp will be included in the design. The clamp’s purpose is to apply pressure to the stack so that it the stack will be firmly held in place in the jig. The clamp doesn’t not need to apply a lot of force, only enough to keep the stack solid seated in the jig. The clamp will resemble that of a shirt press machine. It will have a handle that extends forward that the employee will be able to pull down with minimal force to apply the pressure of the clamp. The clamp will be composed of a four bar mechanism which when the force of the lever is applied the four bar mechanism will move until weigh is over center causing the mechanism to lock in place. To release the mechanism the level will need to be lifted to allow the center of mass to return to its original position. The length of the handle will be determined to allow the greatest mechanical advantage so it will be user friendly to the people who will use it on an everyday basis. Racking System Summary of Components Rack Jig Supports Racking Plate Assembly Sensor Housing List of Deliverables Racking Prototype Analysis of proper sensor placement Analysis of maximum force applied on supports Analysis of tolerance through system Analysis of clamping attachment placement 3-D Renderings 21 | P a g e The basis of the rack design will be a support set with a plate assembly mounted on the inside of the supports. Along the back support, the clamping device will be mounted. First, for an ease of visualization, please refer to appendix C. Appendix C has drawings that show the proposed design on a drafted model. The supports of the racking system will be made from steel rectangular tubes. The left and right will be identical with drilled holes through the body of each to mount the plate assembly. The back tube will be longer to allow the clamping device to be attached. As proposed, the left, right, and back tubes will be cut to 12”, 12”, and 14” respectively. Again, this is just a drafted model and said measurements can change. Figure 6: Supports Next, the rack assembly will be mounted within the thresholds of the supports. This is where the operator will put the cardboard slivers into the rack allowing the operator to work 22 | P a g e hands free during this process. The plate will be cut to 11.5” W by 2” deep. The height of the rack will be anywhere from 4.5” to 6.5” depending on the final design. Figure 7: Racking Plate The rack will also be home to the clamping assembly. As seen in the appendices, a proposed clamping assembly will attach to the rear support shaft and swing downwards into the rack allowing pressure to be applied to the stack of cardboard slivers. This design will have to be prototyped once force analysis is done on the clamping system. Finally, the sensor placement has yet to be determined. Because of the nature of sensors and how they react to different reflections of materials, direct sensor placement will derive from adequate testing and analysis allowing for the precise placement. 23 | P a g e All subassemblies of the rack system will be attached with fasteners of 1/4” diameter and varying lengths. Some will be direct carriage style bolts; some will be counter bored screws allowing for flush design. The assembly will appear similar to the following: Figure 8: Draft Assembly Power Source Summary of Components Power Source List of Deliverables Functioning power source Analysis of output power 24 | P a g e The most important item to complete the electrical sub-system is the power source. The microcontroller can be operated within a power range of six volts to twenty volts but operates optimally between seven volts and twelve volts and uses a wall power adapter. The wall power adapter chosen to power the selected microcontroller has an output of nine volts. Microcontroller Summary of Components Microcontroller List of Deliverables Working prototype Documented C code structure The individual inputs from the sensors will need to be processed in order for the correct LED to light up. While this could be done using a physical circuit, the amount of data transmitted by the sensors that would then need to be transmitted to the LEDs makes using a physical circuit a poor option. Since power is required to operate the sensors and LEDs, it is a small step to incorporate a microcontroller into the design. The microcontroller that fits our design the based is part of the Arduino series of microcontrollers. These microcontrollers are based on an open source platform that allows for easy development. The wiring diagram for the sensors we plan to use is as follows (Also in appendix D): 25 | P a g e Figure 9: Microcontroller Wiring Diagram [11] To connect the LEDs to the microcontroller, it will be necessary to use a 330 Ohm resistor in series with each LED to prevent them from burning out. The microcontroller will need to be programmed to handle the sensor inputs and convert them into the proper outputs for the LED indicators. Arduino microcontrollers can be programmed in C, which is fortunately one of the most wide-spread programming languages. The C language is very versatile, which is 26 | P a g e fortunate since it allows the programmer to develop custom functions through which to run inputs and outputs. This allows the code for the microcontroller to be minimal. Sensors Summary of Components IR Photosensors List of Deliverables Report of sensor placement on the jig Report of sensor placement angles Functional prototype Analysis of sensor accuracy Figure 10: Sensor Placement Diagram Based on the project design, two sensors are needed. The term “sensor(s)” as used in this subsection refers to both parts of the sensor unit, the emitter and the receiver. The first sensor will be placed 4.25 inches above the base of the jig. This sensor will return a “low” value when it detects under-fill and return a “high” value when the jig is full, indicating the correct number of cardboard strips have been inserted. The second sensor will be placed .25 inches above the under-fill sensor, and will be utilized to prevent over-fill of the jig, returning a “high” value 27 | P a g e when the jig is not over-filled and a “low” value when the jig is over-filled. The over-fill indicator is necessary in the event that an employee loads too many strips into the jig, going over the specified amount of cardboard strips. This can easily happen due to the need for an increased production rate of nearly four hundred percent as requested by the contract holder for the cardboard bumper project (see appendix A). The biggest concern when selecting which sensor to utilize is the range which the sensor produces accurate measurements. Another concern when selecting the sensor is the level of background noise produced by ambient light. In order to produce a final product that maximizes cost effectiveness and fits within size specifications, photo sensors that work off the infrared spectrum of light will be implemented. The sensor works based on an LED that sends infrared light into the jig that will then be reflected into the photo sensor when the cardboard strips reach the required height. Indicator LEDs Summary of Components: Green LED (power on) Red LED (capacity) Yellow LED (over capacity) List of Deliverables: Analysis of viewing placement of LEDs Analysis of LED placement on rack Analysis LEDs colors and brightness Functioning indicator system 28 | P a g e Figure 11: Sample LED Once the photo sensors are inserted in the proper place, the use of red-green-blue light emitting diodes (RGB LEDs) will be used to indicate the states of the cardboard strips placed in the jig. A system of three LEDs will be used to specify if the jig has enough cardboard strips to continue with the binding process. The first of the three LEDs will light up green and stay lit most of the time to inform the employee operating the jig to keep inserting material. The second LED will light up red once the jig is filled to correct height which in this design is measure at 4.25 inches. The third and final LED will light up yellow as fail safe to notify the operator that the machine is over-filled which will be measured at 4.5 inches and strips must be removed until the second LED displays the color red. Although one RGB LED is able to produce multiple colors, the decision to go with three separate diodes was to take into account any employees that may have problems distinguishing color. Therefore, the LEDs will be placed in an adjacent vertical position so that the LEDs can mimic the fill process with the bottom light meaning fill, the middle light meaning stop and the top light meaning over fill. This is shown below: Figure 12: LED Setup 29 | P a g e Ventilation and Filter Summary of Components: Fan Exhaust Vents Housing List of Deliverables: Diagram of electrical sub-system placement Analysis of filters efficiency Analysis of airflow and operating temperatures Analysis of exhaust vent placement Functioning cooling and protective layout The other electrical sub-systems will need to be enclosed within a case to protect them from any damage due to the working environment. The goal is to make this case rugged and breathable with a light weight material. The design include two exhaust vents and a fan that will be used to give the parts better air flow and keep internal temperature to a minimum. One of the exhaust vents will be placed facing away from the jig while the other facing the side as intake. A filter will be placed inside of the exhaust vent for intake to prevent any dust entering the case and causing damage to the parts inside. The type of fan, filter and even vent placement has not been completely determined until we have complete analysis of airflow and the operating temperatures produced by the other electrical sub-systems. Training Aids Summary of Compononents: Training media for employees Training Manuals List of Deliverables: Training media for employees Documentation of all subsystems for START to use if maintenance is needed 30 | P a g e In order for both current and future employees of the START facility to use the prototype, training materials will need to be designed. The directors of the facility will need to be interviewed to determine the most effective training materials currently in use at the facility so that the materials provided for this product are as effective as possible. Possible training mediums include training videos, training manuals, and posters with helpful reminders. Regardless of the medium used, the training materials will provide a step-by-step walkthrough of the operation of the jig. A manual will also be provided to the directors of the START facility in order for them to have full documentation of the components used. Included in this manual will be instructions for basic maintenance. Material Selection Material type ASTM A681 AISI 1020 Al 2024 Al 5052 Yield strength MPa 380 350 324 228 Density lb/in^3 0.282 0.284 0.1 0.097 Cost $/ton Overall rating 1000 3000 2100 1000 8.6 5.5 7.2 8.5 Table 4: Material Selection Matrix From this material selection matrix, we can see that a steel subsidiary is the best choice for cost effectiveness in this application. Action Item List # 1 2 3 Activity Arrange Meeting with FTA Email START, get detailed production figures Sample Dimensionalized Person Assigned Due Status BB 21 - Sept. 27 - Sept. Complete JH 21 - Sept. 27 - Sept. Complete JJ 21 - Sept. 29 - Sept. Complete Comments 31 | P a g e 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 3-D Rendering of Sample Contact START about necessary safety precautions Additional NISH Safety Requirements Norms and Expectations Memo Begin Researching sensors/sensor feedback for lit. review Begin Researching sensor feedback/LED indicators for lit. review Begin Researching Racking System for lit. review Begin Researching Banding System for lit. review NISH Deadlines Compile Lit. Review Arrange Meeting with Dave Allabastro Start Working on Design Specifications Discuss sensor specifics with Dave Allabastro Start Working on Block Diagram (mechanical subsystems) Start Working on Block Diagram (electrical subsystems) Draft Schedule Begin Proposal Draft Meet with START to review workstation Start Designing a feeder system Start Designing a hopper system Look into pricing options for photosensors and microcontrollers Finalize Mechanical Design Finalize Electrical JJ 21 - Sept. 29 - Sept. Complete JH 21 - Sept. 29 - Sept. Complete BB 21 - Sept. 29 - Sept. Complete all 21 - Sept. 29 - Sept. Complete all 21 - Sept. 29 - Sept. Complete JH 21 - Sept. 4- Oct. Complete LE 21 - Sept. 4- Oct. Complete BB 21 - Sept. 4- Oct. Complete JJ 21 - Sept. 4- Oct. Complete LE JJ 21 - Sept. 4 - Oct. 4 - Oct. 6 - Oct. Complete Complete 4 - Oct. 6 - Oct. Complete 6 - Oct. 13 - Oct. Complete 12 - Oct. 13 - Oct. Complete 12 - Oct. 17 - Oct. Complete JH all JH, LE JJ 12 - Oct. 17 - Oct. Complete JJ JJ all 18 - Oct. 18 - Oct. 27 - Oct. 11 - Nov. Complete Complete JH 18 - Oct. 24 - Oct. Complete BB 18 - Oct. 25 - Oct. Complete JJ 18 - Oct. 25 - Oct. Complete LE 18 - Oct. 25 - Oct. Complete JJ, BB 25 - Oct. 27 - Oct. Complete JH, LE 25 - Oct. 27 - Oct. Complete 32 | P a g e 28 29 30 31 32 33 34 35 Design Proposal Scheduling Video START Production Revise Lit. Review 3-D Rendering Jig Subsystem Clamping Subsystem Electrical Subsystem Sensor Subsystem JJ 25 - Oct. 27 - Oct. Complete LE 25 - Oct. 1 - Nov. Complete BB JJ JJ BB LE JH 25 - Oct. 2 - Nov. 2 - Nov. 2 - Nov. 2 - Nov. 2 - Nov. 2 - Nov. 4 - Nov. 4 - Nov. 4 - Nov. 4 - Nov. 4 - Nov. Complete Complete Complete Complete Complete Complete Table 5: Action Item List Proposed Spring 2012 Schedule Project #: F11-75-NISH Activity Design/Assembly AC Power Source 17-Jan-11 24-Jan-11 31-Jan-11 7-Feb-11 14-Feb-11 21-Feb-11 28-Feb-11 6-Mar-11 13-Mar-11 20-Mar-11 27-Mar-11 3-Apr-11 10-Apr-11 17-Apr-11 24-Apr-11 1-May-11 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Hopper Feed Infared Sensor Programming Alignment Mechanism Microprosessor Programming Alignment Mechanism Indicator LED's Clamping Mechanism Banding Mechanism Assembly/Testing Prototype Build/Assembly # Prototype Test 1 Redesign/Rebuild Prototype Test 2 # Intruction Manual Reports Written Progress Report NISH Ability One Report Drafting NISH Ability One Report # Mechanical Subsystem Report Drafting Electrical Subsystem Report Drafting SEC Design Report # Poster # Final Presentations # Notebooks Team Evals and Course Assessment End of Project Memo Legend Bid Activity Milestone # Worked ! Revised * Table 6: Proposed Schedule 33 | P a g e Resources Needed Item 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Description Quantity Individual Price Overall Price Subtotal (w/on hand) Subtotal (w/o on hand) AutoDesk Inventor Software 1 $1,500.00 On Hand MEEP Machine Shop Work 5 hours $25.00 On Hand Misc. Costs $0.00 $1,625.00 Arduino Uno 1 $30.00 $30.00 AC Adapter 1 $7.00 $7.00 Optical Phototransistor (QRD1114) 5 $1.13 $5.65 T1-3/4 (5mm) Multicolor RGB LED with White Diffused Lens 10 $1.75 $17.50 CanaKit 1/4W Resistor Kit 1 $15.00 $15.00 Wire (6 colors) 60 foot $0.1-0 per foot $6.00 Electrical Costs $81.15 $81.15 Steel Plate (48"x48" 1/4"thickness) 1 $118.86 $118.86 Steel Rectangular Shaft (2"x2" 1/4"thickness) 50 $0.54 per inch $27.05 Pins for Clamp (1/2" diameter) 2 $1.00 $2.00 Steel Clamp arms 2 $2.00 $4.00 Neoprene Handle 1 $4.50 $4.50 Misc. Bolts 100 $0.10 $10.00 Mechanical Costs $166.41 $166.41 Total $247.56 $1,872.56 Table 7: Resources Needed List of Analyses General Durability Analysis Reliability Analysis Prototype Implementation for Analysis Employee Strength Test Motion Capture for Production Rates Mechanical Analysis of maximum force needed on handle Analysis of mechanical advantage Analysis of minimum pressure needed for plate clamping Analysis of proper sensor placement Analysis of maximum force applied on supports Analysis of tolerance through system Analysis of clamping attachment placement Wear and fatigue testing Electrical Analysis of output power Coding revision and testing Analysis of proper housing placement on jig Analysis of sensor accuracy 34 | P a g e Analysis of viewing placement of LEDs Analysis of LED placement on rack Analysis LEDs colors and brightness Analysis of filters efficiency Analysis of airflow and operating temperatures Analysis of exhaust vent placement 35 | P a g e Works Cited 1. Dictionary.com, "handicap," in The American Heritage® Stedman's Medical Dictionary. Source location: Houghton Mifflin Company. http://dictionary.reference.com/browse/handicap. [Oct 5, 2011] 2. American Fact Finder, U.S. Census Bureau, [Oct 2, 2011] http://factfinder2.census.gov/faces/tableservices/jsf/pages/productview.xhtml?fpt=table 3. “About NISH.” Internet: http://www.nish.org/NISH/ [Oct 5, 2011] 4. AbilityOne Network Fact Sheet [Oct 4, 2011] http://www.nish.org/NISH/Rooms/DisplayPages/LayoutInitial?Container=com.webridge.enti ty.Entity%5BOID%5B3A204683BB46664D9DEFF5408A4A0613%5D%5D 5. “Judging Criteria.” [Oct 5, 2011] http://www.instituteforempowerment.org/designchallenge/judging-criteria 6. Specialized Training for Adult Rehabilitation. [Oct 3, 2011] http://www.startinc.org/AboutUs.php 7. Better Packages, Inc. “Better Pack® 333 Plus water-activated paper tape dispenser.” 2008. [Oct 5, 2011] http://www.betterpackages.com/products/dispensers/manual/bp333plus.shtml, 8. Seattle Robotics Society [Oct 4, 2011] http://www.seattlerobotics.org/guide/infrared.html 9. R.A. McIntosh, R. G. Bernier, D. A. Estabrooks. “Stacking System for Fanfold Paper and The Like,” U.S Patent 4,226,410, Oct. 7, 1980. 10. Powerpress, Inc. “15 X15 Digital High Press Sublimation Clamp Shell T Shirt Heat Press Transfer Screen Printing Machine.” 2010 [Nov 4 2011] 11. Bildr.org. “Are we getting close? Proximity Sensors + Arduino” [Nov 7, 2011] http://bildr.org/2011/03/various-proximity-sensors-arduino/ 36 | P a g e Appendix A From: Carl Hartmann <carlhartmann1@gmail.com> Date: Tue, Oct 18, 2011 at 12:25 PM Subject: Re: NISH To: John Hughey <jcwh129@siu.edu> Good Morning, We have recently purchased two new tape machines, which brings our total to 4. In full production, if we have the cardboard cut, we can utilize two people per tape machine. We currently have trouble getting the cardboard cut, so we are utilizing only three or four clients per day. ( We have a large crate building operation which is utilizing our saws in the woodshop for another 4 weeks. After that we should be able to cut enough cardboard to utilize all of the tape machines.) Presently per client, they are producing 80 - 90 bundles per day, per client. Presently we are producing an average of 250 per day, or about 1200 per week. We are being told, that the ideal production, per our customer , is 4,000 per week. Hope this is helpful, please ask if you have other questions. Carl On Tue, Oct 18, 2011 at 11:15 AM, John Hughey <jcwh129@siu.edu> wrote: Hi Carl, This is John Hughey, the project manager from the NISH design team. For the purpose of our design we were hoping you could provide us with the production figures for the carboard bumpers. When we first toured the facility Kathy mentioned that the Aluminum Company had recently increased demands so we need to know how many units they need per month and how many you are currently producing. Thanks, John Hughey 37 | P a g e Saluki Engineering Company Senior Engineering Design Center College of Engineering – Mailcode 6603 Carbondale IL 62901-6603 618-453-7837, -7031, -7025 Appendix B Request for Proposals (RFP) 9 September 2011 Subject: AbilityOne Network Design Challenge Client: Institute for Economic Empowerment Project Number: F11-75-NISH Since the passage of the Americans with Disabilities Act of 1990 employers have been required to make adjustments in the work environment to make reasonable accommodation those with disabilities. The purpose of NISH goes beyond reasonable accommodation to a mission to create employment opportunities for people with severe disabilities by securing federal contracts through the AbilityOne Program for its network of community-based, nonprofit agencies. In keeping with this mission, the AbilityOne Network Design Challenge was founded to encourage the development of creative technological solutions for barriers that prevent people with disabilities from entering or advancing in the workplace. Saluki Engineering Company, hereinafter SEC, has been appointed Architect-Engineer Coordinator for the referenced study on behalf of Institute for Economic Empowerment, hereafter Client, to make an engineering study of the referenced project. SEC has divided the work into packages by engineering team capability and will coordinate the overall work. SEC has sent this bid package to three competitive engineering teams, hereinafter Engineer, of equal capability including your team. SEC is hereby requesting a proposal from Engineer for Client’s approval to do the defined work. The timeline for this project will be as follows: 38 | P a g e Saluki Engineering Company Senior Engineering Design Center College of Engineering – Mailcode 6603 Carbondale IL 62901-6603 618-453-7837, -7031, -7025 8 November 2011 Proposal FINAL draft due posted on website by 11AM. This proposal will be evaluated for compensation (grade in the course). 8 November – 17 November 2011 First Design Reviews teams 70-77 29 Nov – 8 Dec 2011 Oral presentations of proposals 11:00-11:50 am in EGR A111 8 December 2011 Spiral bound hardcopy AND proposal posted to website with required modifications, if any 17 January 2012 Phase II work begins. 23 February 2012 Progress Reports posted to web space by 1PM 19 April 2012 Design Reports (6 copies: 3-ring binder + 4CDs + Website) due at 1PM 24-26 April 2012 Demonstrations of projects E215 1PM 24-26 April 2012 Presentations of posters E215 1PM (may be required on an earlier date) 1-3 May 2012 Design oral presentations Your proposal will receive conditional acceptance on 12 Dec 2011; you may have to make additional changes in January after Management and Client review it and new data become available. 39 | P a g e Saluki Engineering Company SEC Request For Proposal Letter 9 September 2011 Project # F11-75-NISH Page 40 Engineer will present the drawings, specifications, and explanatory text in a final Design Report together with the capital cost estimate and schedule to construct, install, or manufacture the product. One written and one oral progress report will be required during the design as indicated above. In addition, one to three design review meetings will be required. The proposal, which you will submit by noon according to the attached schedule, must include: 1. 2. 3. 4. 5. 6. 7. A cover and title page A transmittal letter An abstract or executive summary of 300 to 500 words A non-disclosure statement A table of contents An introduction that indicates that you understand the study and why it is being undertaken. A literature survey that lays out the following: a. An introduction that outlines the content of the literature review b. what is already known about projects of this type, including similar existing systems c. what the required design procedures are d. the relevant content of the applicable codes and standards e. the relevant materials and components available on the market f. a summary of how the reviewed literature relates to this project 8. An over all project description that indicates the subsystems and their relationships to each other, including a site plan or block diagram to visually show how the subsystems are related, and how this system will be different from existing systems 9. The design basis 10. For each subsystem, a. a description of what each subsystem will be or do b. a description of how each subsystem relates to the other subsystems, including references to the site plan or block diagram to show the relationships, c. a list of the elements which will define the subsystem design, d. a list of deliverables, including all drawings, tables, lists, write-ups and other elements, that you can now identify as probable parts of the Design Report you will submit at the completion of the project e. a list of design activities required to produce the deliverables listed 11. A project organization chart indicating project manager and showing for each nominee: name, principal area of responsibility, and discipline (ME, EE, or CpE); 12. An action item list that shows detailed action items for the first two weeks and significant action items for weeks thereafter 13. Team timeline indicating major design activities and significant milestones in either a. Excel or Word table, b. Microsoft Project, or c. other project tracking software package. [Note that there is a lot of redundancy between 10e, 11, and 12. Be aware that self-consistency is one item on which your proposal will be evaluated.] 40 | P a g e Saluki Engineering Company SEC Request For Proposal Letter 9 September 2011 Project # F11-75-NISH Page 41 14. A list of all resources you will need including space, computers and specialized software required, and including – for design and build projects – a list of all components that you can now anticipate needing and their actual costs, or current location if they are to be borrowed 15. List of data analyses, experiments, and simulations to be performed 16. Description of what is to be built and demonstrated or software to be written and demonstrated 17. An appendix that includes a. the resumes for all candidates for the team b. copies of any communications your team has with Client, other companies, or individuals. Any literature that your team requests that vendors send to the College of Engineering during the course of the writing of this proposal will be addressed as follows: A. Weston, F. Harackiewicz, or K. Purcell College of Engineering – Mailcode 6603 Southern Illinois University Carbondale IL 62901-6603 In addition, any information you request to be faxed should be sent to A. Weston, F. Harackiewicz, or K. Purcell FAX: 618-453-7455 Voice: 618-453-7837 (Weston), -7031 (Harackiewicz) 618-559-6190 (Purcell) Please note: If any material that arrives is sent to YOUR name at the college, you will never see the material because students are not known by name to the mailroom staff. Be sure to give SEC management a memo indicating (1) what and from whom you ordered and (2) the SEC Reference Number of the team that is to get it. This is to alert management to watch for your material and recognize it when it comes in. Engineer will adjust the Scope of Work so that it is suitable for each of the engineers who will be working on the project. If significant design components of the project must be omitted because of time or staff limitations, clearly identify them in your proposal. Your final cost analysis must, in any event, account for them. The attachments to this letter are listed below: 1. Client’s project definition 2. Design Report deliverables checklist 3. Spring 2012 tentative schedule 41 | P a g e Saluki Engineering Company SEC Request For Proposal Letter 9 September 2011 Project # F11-75-NISH Page 42 SEC management looks forward to receiving your proposal. Engineer shall deliver the proposal to the SIU Engineering College complex in Carbondale, Illinois, addressed to the attention of Dr. F. Harackiewicz and Mrs. Purcell, SEC's Managers of ECE Projects or Dr. A. Weston, SEC’s Manager of ME Projects. Sincerely, F J Harackiewicz Manager of ECE Projects <fran@engr.siu.edu> 42 | P a g e Saluki Engineering Company SEC Request For Proposal Letter Attachment 1 - Project Definition 9 September 2011 Project # F11-75-NISH Page 43 Client wants a device or a system that will solve a real workplace problem for at least one group of severely handicapped workers. The winning proposal for the device or system will have verifiable, quantified goals. The proposal will describe technologies that have been used in the past as well as those currently being used to overcome the problem. The functional description of the proposed device or system will include a statement of how it is different from, and better than, what currently exists. The proposed schedule will allow for at least three design-build-test-modify iterations. The proposal will incorporate all of the requirements for a winning design. The device or system itself will have complete documentation so that it may be reproduced for use with others of similar handicap. The documentation will contain a thorough failure analysis and data from validation and revalidation of the design with members of the group it will serve. More information on the design challenge for 2011-2012 can be found here: http://www.instituteforempowerment.org/design-challenge Challenge requirements can be found here: http://www.instituteforempowerment.org/design-challenge/submission-specifications For online registration go to: http://www.instituteforempowerment.org/design-challenge/registration/college-entrants For Judging criteria: http://www.instituteforempowerment.org/design-challenge/judging-criteria In case of a conflict between this RFP and Client's design requests, Client's design requests control. As new data become available, Client may give Engineer additional data and criteria that Engineer will incorporate into the design. 43 | P a g e Saluki Engineering Company 9 September 2011 SEC Request For Proposal Letter Attachment 2 - Design Report Deliverables Checklist Project # F11-75-NISH Page 44 The proposal Engineer submits will indicate that these items will be included in the Design Report (not the Proposal!): 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. A literature review relevant to the design submitted (not a copy of the literature review in this proposal) A complete technical description and the results of all work done for all solution options studied Equipment, component, materials take-off lists and costs for each solution studied Engineering drawings defining the solutions A recommended solution and a detailed justification for the choice recommended or implemented, including a Pugh chart or some similar matrix comparison chart that is discussed in the text A complete technical description of the recommended system and how it works Incorporate into descriptions a summary and the significance of any laboratory work, computer simulations, or mathematical analysis performed. A complete engineering specification for the system including all engineering drawings necessary for construction, manufacture, or installation and maintenance and repair A complete list of the components and signals in the process, and a list of the ones that are included in the model, if any, with the corresponding part of the model identified Tables of performance data – individual subsystem and overall – expected and, for the part that was built, achieved Identification of the important technical problems and limitations encountered during design, construction and debugging, e.g., time, accuracy of results, reproducibility of results, limitations on input An analysis of electromagnetic compatibility issues and changes necessary in the design to meet EMC code specifications A fault analysis of the recommended system, including identification of all faults that could occur, a technical solution to eliminate their consequences, and the cost for incorporating the improvement For the working model, Technical Manual that includes a technical description of both the hardware and the software, together with, but not limited to: appropriate hardware engineering drawings and component lists; software flowcharts, listings, and disks; and instructions for construction, maintenance, trouble shooting, and modification If a prototype of the device was built, User's Guide for the individual using the prototype, including both instructions on how to connect and use the hardware, how to set up and use the software, what performance can be expected, and what limitations the prototype has A conclusion and recommendations section that a. summarizes the performance, b. includes recommendations for improvement, enhancement, and manufacture, and c. discusses the economic, societal, environmental, manufacturability, health, and safety issues related to this project if it is implemented An estimate of the amount of capital required to construct, build, manufacture, or install the designed system, whichever is appropriate A timeline schedule to construct, build, manufacture, or install the designed system, whichever is appropriate 44 | P a g e Saluki Engineering Company 9 September 2011 Project # F11-75-NISH SEC Request For Proposal Letter Page 45 Attachment 2 - Design Report Deliverables Checklist 19. In an appendix: a. the actual itemized cost to construct the prototype, including costs of ruined components and components for options not included in the prototype b. any calculations, spreadsheets, computer simulation results, or other data that should be a part of the report but is too numerous or too bulky to be included in the report itself, this material will be be referenced and summarized in tables in the report, c. formal laboratory reports for all laboratory work performed with the results referenced and summarized in the report, and d. for projects NOT having a working prototype with a Technical Manual, a listing of any software developed as a part of the project. 45 | P a g e Appendix C 46 | P a g e 47 | P a g e 48 | P a g e Appendix D 49 | P a g e Benjamin W. Blair 13536 Mary’s Creek Rd. Sparta, IL 62286 (618) 317-1926 bwblair10@gmail.com OBJECTIVE Seeking full time employment in the mechanical engineering field. EDUCATION Southern Illinois University Bachelor of Science in Mechanical Engineering, May 2012 Related Coursework: Thermodynamics Mechanical Design Heat Transfer Engineering Economics EXPERIENCE Carbondale, IL GPA: 3.58/4.00 Fluid Mechanics Internal Combustion Engines Computer-Aided Drawing Material Selection Farmhand, Blair Farms Inc. 2006-Present Operated and maintained mechanical equipment, obtaining understanding of how different machines work. Assistant, Sparta Animal Clinic Performed office duties, building skills filing paperwork and improving my customer interaction. SKILLS Computer Skills: Microsoft Office, AutoCAD, C++, MATLAB LEADERSHIP AND AWARDS Academic Scholarship, SIUC, 2008-2010 Volunteer Track and Field Coach, Sparta High School, 2010-2011 Volunteer Math Team Coach, Sparta High School, 2010 50 | P a g e LINDEN EASON, A.A. Contact info lindeneason@gmail.com 905 East Park Street Apt D5 Carbondale, IL 62901 (815) 519-3741 Objective: To seek an internship position with a company requiring me to utilize my technical abilities and further develop my engineering knowledge. Education: Southern Illinois University Carbondale Major: Electrical And Computer Engineering Cumulative GPA: 3.0/4.0 Major GPA: 3.3/4.0 Expected Graduate Graduation: Fall 2012 Minor: Mathematics Rock Valley College A.A. Cumulative GPA: 3.0/4.0 Experience: Skills: Volunteer Work: Southern Illinois University Carbondale - Teacher’s Assistant Provided students with diverse ways to approach technical assignments Graded all of the class assignments Foot Locker Inc. – Champs Sports Sales Representative Worked to provide customers with the best customer care Helped organize and monitor inventory The Kroger Co. – Hilander Foods Gas Clerk & Deli Worker 2. Managed the gas clerk area 3. Managed deli area MATLAB simulink Visual Studio, C++ Microsoft Office Suite Xilinx ACT preparation program -Helped to develop students test taking skills Engineering Day SIUC -Hovercraft demonstration Erma Hayes Center -Served as a mentor for children at the Erma Hayes Center Adopt a Spot NSBE -Helped to clean excess garbage off a stretch of road Dean’s List Awarded Smart Grant Awarded Minority Engineering Program Scholarship Honors and Activities: Extracurricular Activities: National Society of Black Engineers member SIUC -Helped in the organization of volunteer work, fundraising and events. - Serve as one of the chapter’s senators Fall 2011-present March 2006 – September 2007 May 2005 – December 2005 Fall 2006-present Fall 2008 Fall 09-Spring 11 Fall 2011-Spring 2012 Fall 2011-present 51 | P a g e John C. Hughey jcwh129@siu.edu Permanent Address: College Address: 102 DLK Drive 221 Bailey Hall Anna, IL 62906 1225 Point Drive 618-833-3772 Carbondale, IL 62901 618-536-7979 Objective: A career in computer engineering. Education Southern Illinois University Carbondale (SIUC), Carbondale, Illinois August 2007 - Present Course work toward Bachelors of Science in Computer Engineering with a Minor in Management GPA: 3.0/4.0 Relevant Coursework Digital Circuit Design Intro to Software Engineering Verilog and VHDL Synthesis Experience Resident Assistant, Southern Illinois University Carbondale August 2009-Present Help Residents with both academic and personal issues. Provide programming and other services to help improve the college experience. Help achieve the mission and vision of SIUC University Housing. Cook/Delivery Driver, Pizza Hut Inc. August 2006 – August 2008 Help satisfy customer complaints. Skills Microsoft Office Suite: Word, Excel, PowerPoint Awards & Honors College of Engineering Scholarship Fall 2008 – Spring 2010 Dean’s List, SIUC Spring 2007 – Fall 2008 Activities Residence Halls of Horror – Director, Room Coordinator Fall 2009 – Fall 2011 Thompson Point Executive Council (TPEC) – Vice President Fall 2008 – Spring 2009 SIUC Leadership Council Fall 2007 – Spring 2008 52 | P a g e Jordan John Permanent Address 13132 Fenwick Street Fishers, IN 46037 Cell: 618-303-0975 Email: jjohn89@siu.edu School Address (Until 5/15/2012) 900 S. Elizabeth Street Apartment #3 Carbondale, IL 62901 Objective An entry level position in Mechanical Engineering beginning May 2012. Skills Excellent written and oral communication skills Numerous leadership experiences Works well in a team or an independent setting Education Southern Illinois University; Carbondale, Illinois Carbondale, Illinois 62901 Pursuing Bachelor’s in Mechanical Engineering Pursuing Minor in Mathematics Projected Graduation Date: Spring 2012 GPA: 3.19/4.00 Specialized CAD/CAM Energy in Society Course Energy Systems and Management Work Material Science Material Selection for Design Pneumatic/Hydraulic Design Relevant Boeing Integrated Defense Systems Externship - Joint Helmet Mounted Cueing System (JHMCS) integration for F-15’s and F/A 18’s; St. Louis, MO (March 2011) Work SIUC Resident Assistant; SIUC University Housing (August 2009-May 2010) Experience SIUC College of Engineering Peer Mentor; SIUC University Housing (August 2008-May 2009) Relevant Projects Vacuum Flask Drinking Apparatus (Spring 2011) Individualized design of flask with in depth material selection based on Thermos® technology “A Renewable Home”: A Project on Sustainability and Renewable Energy Sources for the Modern Home (Spring 2009) Project Manager Research and development of a completely self-sustained living unit complete with energy flow analysis and renewable energy systems design Awards SIUC Dean’s List and College of Engineering Honor Roll (Fall 2007, Summer 2009) Two time recipient of the Highway District #9 Engineering Scholarship (Fall 2008, Fall 2009) Phi Sigma Kappa Fraternity 2008-2009 “Brother of the Year” Activities Order of Omega Honor Society (April 2010-Present) Golden Key Honor Society (October 2008-Present) Alpha Lambda Delta Honor Society (May 2008-Present) Phi Sigma Kappa Fraternity (May 2008-Present) President (November 2009-November 2010) Vice-President (November 2010-April 2010) 53 | P a g e