The Channel Tunnel (Chunnel) Project Case Study

advertisement
Background
0 An underground tunnel connecting England and
France.
0 The largest privately funded project ever undertaken.
0 Bankers underwriting the funding for the project.
Project Proposal
0 A 32-mile (51.5 km) double-rail tunnel
0 Will accommodate through-trains & special car-and-
truck-carrying shuttle trains.
0 Their bid was US$5.5 billion.
0 The country with the highest standard would prevail.
New Technology
0 New technology being used.
0 State-of-the-art laser and computer tech.
0 The Chunnel project was completed but it was late
and over budget.
0 The new technology required significant
modifications during the project due to unexpected
conditions and changes required by various parties.
Phases for the Project
0 1-Inception-Historical background, overall objectives,
political climate, and pre-feasibility studies.
0 2-Development-Overall planning, feasibility studies,
financing, and conceptual design.
0 3-Implementation-Detail design, construction, installation,
testing, and commissioning.
0 4-Closeout-Reflection on overall performance, settlement of
claims, financial status, and post-project evaluation.
Inception Phase
0 The ideas was to create a fixed transportation link
between England and France.
0 This would create a spur of economic development.
0 Improve trade using the new alternative high-speed
transportation.
Ground Rules & Time Line
0 1974- Initial tunnel ideas gather but abandoned.
0 1978-British & French discussions resumed.
0 1983-Frensh & British banks & contractors propose
tunnel scheme.
0 1984 British and French agree to common safety,
environmental, and security concerns.
Ground Rules & Time Line
0 1985-French & British governments ask for fixed-link
proposals.
0 1986 The project was awarded to Channel Tunnel
Group/FranceManche a.k.a. Eurotunnel and declared
owner of 55-year concession for the link.
Ground Rules & Time Line
0 1987 the “Concession Contract” was awarded to
Channel Tunnel Group/FranceMache (CTG/FM) bid
for US$5.5 billion and ended on Dec. 15, 1994 with a
fully operational station.
0 The project was 19 months late and had a cost
overrun of some US$3 billion (total construction cost
of US$7.1 billion).
0 On 1 December 1990, Englishman Graham Fagg and
Frenchman Phillippe Cozette broke through the
service tunnel with the media watching.
The Implementation Phase
0 Not agreeing in details resulted in eventual delays and
cost overruns.
0 Warning signs of rolling stock had not yet been
designed (vehicle and freight cars).
0 No contingency was set aside to cover “unknown
unknonws” (Ventilation system).
0 The specifications for British rolling stock and French
rolling stock were not the same.
The Implementation Phase
0 With costs out of control, fixed-priced contract were
awarded to contractors in order to have any chance of
winning the bid and not risk losing the bid to next
lowest bidder.
0 Contractors assumed an optimistic case, and since
underground construction is rife with changed
conditions.
Early Problems
0 No air-conditioning was included costing US$200
million more.
0 The Intergovernmental Commission (IGC) approved
designs that weren’t within the original concession
agreement.
0 Thus indicating possible problems with initiation and
planning.
Early Problems
0 The lack of defined scope makes resource planning,
cost estimating, and budgeting difficult.
0 Return on Investment (R.O.I.) assumptions made in
the planning stages may not prove accurate. Leaving a
trail of unhappy investors and stakeholders.
Early Problems
0 From US$5.5 Billion to US$7.1 Billion
0 Ongoing safety requirements changes sought by ICG
continued to create negative impact.
0 Not enough was understood to limit the impact of
known and unknown risks.
0 Contractual errors were made in the estimates and
risk allocation method, costing additional US$2.25
billion.
Early Problems
0 Passenger doors be widened from 600mm to 700mm.
Cost increase from US$9 million to US$7O million.
0 Objectives of a project need to be identified and
communicated clearly from the beginning. This was
the largest and most damaging failure of both
governments.
Early Problems
0 By not having the real goals, objectives, and scope
defined early, and by not implementation a contract
method that directly linked the rewards to contractors
at all levels of the procurement chain to those
objectives.
0 The project was essentially run by bankers.
Finances
0 The Chunnel project had to be financed through
private sources without government aid or loan
guarantees.
0 The government was prohibited from regulating
prices except in monopolies.
0 Financing was pursed via equity and loan capital
markets.
Finances
0 Most shareholders seeking equity interest were
mostly in France and eventually Britain.
0 206 banks world wide participated with the loan.
0 The refinancing had to be pursued, should negative
variances in time and cost estimates occur.
Success From a Project
Management Perspective
0 Contracts are a critical part of the procurement
management process.
0 Contracts define the scope of work, cost, timeline and
rules of engagement.
0 Risk planning and mitigation needs to be ongoing part
of each project.
0 The hope is that most material risk are identified,
quantified, and prioritized early enough so that an
effective risk response strategy can be establish.
Success From a
Project Management Perspective
0 3 tunnels total North, South, and Service.
0 46 contractors were hired.
0 The tunneling itself was finished 3 months ahead of
schedule.
0 Each team member has a responsibility for quality.
0 Quality requirements were mostly defined up-front,
quality planning, quality assurance, and quality
control.
Success From a
Project Management Perspective
0 Team work was necessary to complete this project.
0 It was estimated that 15,000 workers were employed
on the project.
0 From a P.O.V. quality management was a success.
The Development Phase
0 Consisted of detailed planning, communication,
agreements, and government approvals.
0 A large part of the struggles were do to inflexibility of
some characteristics of the project, and cross-cultural
exchange between 2 countries.
The Development Phase
0 A scope creep played a large part in the substantial
increase from its initial cost estimates, and its
completion behind schedule.
0 The scope was not fully assessed and the proper
precautions to prevent scope creep weren’t put in
place.
0 The project team were able to understand the
complexity and were able to use previous research on
the soil, but in the end, the lack of continued focus on
the scope resulted in the frustrations of trying to do
too much.
Closeout
0 The completion of the project was rushed to allow
operations to begin before the entire effort was
completed.
0 The tunnel was actually completed.
0 Teamwork and communication were broken down
into several key areas.
Financial Issues during Closing
0 Focused on minimizing their losses, refused to accept
negotiated arrangements for settling some of the key
contracts disputes.
0 International Chamber of Commerce was involved
with helping the various competing sides to
bargaining table in an attempt to resolve key portions.
From a Management P.O.V.
0 Even with a high-level design and respective rough-
order-of-magnitude estimates were appropriate.
0 In 1996 the American Society of Civil Engineers
identified the tunnel as one of the Seven Wonders of
the Modern World.
Rating Scale:
5-Excellent, 4-Very Good, 3-good, 2-poor, 1-Very
Poor
Project Management Area
Scope Management
Time Management
Quality Management
Human Resource Management
Communication Management
Risk Management
Procurement Management
Integration Management
Implementation Phase
3
1
3
5
2
4
3
2
Download