TRIMS Technical Risk Identification and Mitigation System Ralph Sickinger Presented By: PMWS Development Manager ralph@bmpcoe.org 25 August, 2008 The BMP Program www.bmpcoe.org Technical Risk Identification & Mitigation System 1 History of the BMP Program 1960-1980 Many programs failing or suffering cost/schedule overruns 1983-1984 Defense Science Board studies the problem; publishes findings in DOD 4245.7-M (The “Willoughby Templates”) 1985 Best Manufacturing Practices Program established to help the U.S. Defense Industrial Base - BMP conducts first Survey (Texas Instruments) 1986 BMP publishes NAVSO P-6071 (Best Practices Book) 1987 BMP contracts with Bell Labs to write more detail on each Template 1991 First version of PMWS is created 1993 BMP Center of Excellence established in College Park, MD 2000 BMP conducts 100th Survey (Northrop Grumman) www.bmpcoe.org Technical Risk Identification & Mitigation System 2 History of the BMP Program 1960-1980 Many programs failing or suffering cost/schedule overruns 1983-1984 Defense Science Board studies the problem; publishes findings in DOD 4245.7-M (The “Willoughby Templates”) 1985 Best Manufacturing Practices Program established to help the U.S. Defense Industrial Base - BMP conducts first Survey (Texas Instruments) 1986 BMP publishes NAVSO P-6071 (Best Practices Book) 1987 BMP contracts with Bell Labs to write more detail on each Template 1991 First version of PMWS is created 1993 BMP Center of Excellence established in College Park, MD 2000 BMP conducts 100th Survey (Northrop Grumman) www.bmpcoe.org Technical Risk Identification & Mitigation System 3 History of the BMP Program 1960-1980 Many programs failing or suffering cost/schedule overruns 1983-1984 Defense Science Board studies the problem; publishes findings in DOD 4245.7-M (The “Willoughby Templates”) 1985 Best Manufacturing Practices Program established to help the U.S. Defense Industrial Base - BMP conducts first Survey (Texas Instruments) 1986 BMP publishes NAVSO P-6071 (Best Practices Book) 1987 BMP contracts with Bell Labs to write more detail on each Template 1991 First version of PMWS is created 1993 BMP Center of Excellence established in College Park, MD 2000 BMP conducts 100th Survey (Northrop Grumman) www.bmpcoe.org Technical Risk Identification & Mitigation System 4 Problem Areas Identified by DSB Money Phasing Failure Reporting System Transition Plan Design Reference Mission Profile Uniform Test Report Modernization Design Requirements Software Test Factory Improvements Trade Studies Design Limit Productivity Center Design Policy Life Logistics Support Analysis Design Process Test, Analyze & Fix (TAAF) Manpower & Personnel Design Analysis Field Feedback Support & Test Equipment Parts & Material Selection Manufacturing Plan Training Materials & Equipment Software Design Qualify Manufacturing Process Spares Computer-Aided Design (CAD) Piece Part Control Technical Manuals Design for Testing Subcontractor Control Manufacturing Strategy Built-In Test (BIT) Defect Control Personnel Requirements Configuration Control Tool Planning Data Requirements Design Reviews Special Test Equipment (STE) Technical Risk Assessment Design Release Computer-Aided Manufacturing (CAM) Production Breaks Integrated Test Manufacturing Screening www.bmpcoe.org Technical Risk Identification & Mitigation System 5 Problem Areas Identified by DSB FUNDING: Money Phasing DESIGN: Design Reference Mission Profile Design Requirements Trade Studies Design Policy Design Process Design Analysis Parts & Material Selection Software Design Computer-Aided Design (CAD) Design for Testing Built-In Test (BIT) Configuration Control Design Reviews Design Release www.bmpcoe.org TEST: Integrated Test Failure Reporting System Uniform Test Report Software Test Design Limit Life Test, Analyze & Fix (TAAF) Field Feedback PRODUCTION: Manufacturing Plan Qualify Manufacturing Process Piece Part Control Subcontractor Control Defect Control Tool Planning Special Test Equipment (STE) Computer-Aided Manufacturing (CAM) Manufacturing Screening Technical Risk Identification & Mitigation System TRANSITION: Transition Plan FACILITIES: Modernization Factory Improvements Productivity Center LOGISTICS: Logistics Support Analysis Manpower & Personnel Support & Test Equipment Training Materials & Equipment Spares Technical Manuals MANAGEMENT: Manufacturing Strategy Personnel Requirements Data Requirements Technical Risk Assessment Production Breaks 6 DoD 4245.7-M “Willoughby Templates” www.bmpcoe.org Technical Risk Identification & Mitigation System 7 NAVSO P-6071 “Best Practices Book” www.bmpcoe.org Technical Risk Identification & Mitigation System 8 NAVSO P-6071 (Best Practices Book) www.bmpcoe.org Technical Risk Identification & Mitigation System 9 NAVSO P-6071 (Best Practices Book) www.bmpcoe.org Technical Risk Identification & Mitigation System 10 NAVSO P-6071 (Best Practices Book) www.bmpcoe.org Technical Risk Identification & Mitigation System 11 NAVSO P-6071 (Best Practices Book) www.bmpcoe.org Technical Risk Identification & Mitigation System 12 Some Things To Consider • Defense Science Board Studies Determined that 80% of all Programs that Fail, Fail for Engineering not Technology Reasons • Example: N43 Reports that Over 65% of all Fleet Reliability Problems are Due to Inadequate Design • February 1998 GAO Report to the Subcommittee on Acquisition & Technology, Committee on Armed Services, U. S. Senate – – • March 2005 GAO Report: • – • Since 1975 Schedule Overruns Average 24% Weapon Systems Overruns Cost 20% - 40% Average Cost Increase Will be 28.5% in Only 4 Years Reason: “Armed services order hardware with unproven technology, with too little time allowed for perfecting that technology before contractors attempt to insert it into weapons systems...” With Acquisition Reform and Performance Specifications, We Must Monitor the Engineering Process to Understand Program Risks Do Not Get Technology Tunnel Vision www.bmpcoe.org Technical Risk Identification & Mitigation System 13 TRIMS www.bmpcoe.org Technical Risk Identification & Mitigation System 14 What Is TRIMS? • TRIMS (Technical Risk Identification & Mitigation System): A Methodology for Doing Knowledge-Based, Process-Oriented Risk Management • Includes Set of Software Tools to Help Implement the Methodology (Navy Owned, Fixed Revision Cycle) • Outgrowth of DoD 4245.7-M and NAVSO P-6071 Templates • Fully Compatible with BMPCOE Combined Government / Industry Systems Engineering Model • Fully Supported: Training Classes, Computer-Based Training, On-line Help, 24-hour Help Desk Process Based And Predictive www.bmpcoe.org Technical Risk Identification & Mitigation System 15 TRIMS Proactive Methodology Risk Assessment Guidance Documents Engineering Process Model Statistics Probability Past Experience Effect Planning & Tracking System Architecture Mission Profile Schedule Quality Cost Risk Management Milestone Dates Personnel Assignments Question Weighting Due Dates Compliance Status References Risks TRIMS • Risk Management Next Actions • Snapshot Assessments Responsibilities • Multiple Program Rollups Action Item Tracking • Automatic Updates Understanding The Future Effects Of Today's Decisions www.bmpcoe.org Technical Risk Identification & Mitigation System 16 Proactive vs. Reactive Proactive Process Risks Technical Issues Schedule Slippage Reactive Cost Overruns TRIMS Identifies the Root Causes of Cost & Schedule Problems www.bmpcoe.org Technical Risk Identification & Mitigation System 17 Evolution of Risks T1 T2 Process Risks T3 T4 T5 Product Risks T6 Problems “A ‘Problem’ Is A Risk Whose Time Has Come” www.bmpcoe.org Technical Risk Identification & Mitigation System 18 Cost To Mitigate Increases Exponentially Design Test Production Cost to Mitigate $100 $10 $1 Time www.bmpcoe.org Technical Risk Identification & Mitigation System 19 Cost To Mitigate Increases Exponentially Design Test Production Cost to Mitigate Problems Product Risks Process Risks Time Risk Management or Damage Control? www.bmpcoe.org Technical Risk Identification & Mitigation System 20 TRIMS Baseline Templates DESIGN TEST PRODUCT TQM FUNDING Money Phasing PRODUCTION • Design Refer. Mission Profile • Integrated Test FACILITIES • Manufacturing Plan • Modernization • Failure Reporting System • Qualify Manufacturing Process • Factory Improvements • Design Policy • Uniform Test Report • Piece Part Control • Productivity Center • Design Process • Software Test • Design Analysis • Design Limit • Parts & Mater. Selection • Life • Software Design • Test, Analyze & Fix (TAAF) • Design Requirements • Trade Studies • Computer-Aided Design (CAD) • Design for Testing • Built-In Test (BIT) • Field Feedback • Subcontractor Control • Defect Control • Tool Planning • Special Test Equipment (STE) LOGISTICS • Logistics Support Analysis • Manpower & Personnel MANAGEMENT • Manufacturing Strategy • Personnel Requirements • Data Requirements • Support & Test Equipment • Technical Risk Assessment • Training Materials & Equipment • Production Breaks • Spares • Technical Manuals • CAM • Manufacturing Screening • Configuration Control • Design Reviews • Design Release TRANSITION PLAN www.bmpcoe.org Technical Risk Identification & Mitigation System 21 TRIMS Baseline Templates DESIGN TEST PRODUCT TQM FUNDING Money Phasing PRODUCTION • Design Refer. Mission Profile • Integrated Test FACILITIES • Manufacturing Plan • Modernization • Failure Reporting System • Qualify Manufacturing Process • Factory Improvements • Design Policy • Uniform Test Report • Piece Part Control • Productivity Center • Design Process • Software Test • Design Analysis • Design Limit • Parts & Mater. Selection • Life • Software Design • Test, Analyze & Fix (TAAF) • Design Requirements • Trade Studies • Computer-Aided Design (CAD) • Design for Testing • Built-In Test (BIT) • Configuration Control • Design Reviews • Design Release • Field Feedback • Subcontractor Control • Defect Control • Tool Planning • Special Test Equipment (STE) LOGISTICS • Logistics Support Analysis • Manpower & Personnel MANAGEMENT • Manufacturing Strategy • Personnel Requirements • Data Requirements • Support & Test Equipment • Technical Risk Assessment • Training Materials & Equipment • Production Breaks • Spares • Technical Manuals • CAM • Manufacturing Screening CAM •Manufacturing Screening TRANSITION PLAN www.bmpcoe.org Technical Risk Identification & Mitigation System 22 TRIMS Baseline Templates DESIGN TEST PRODUCT TQM FUNDING Money Phasing PRODUCTION • Design Refer. Mission Profile • Integrated Test FACILITIES • Manufacturing Plan • Modernization • Failure Reporting System • Qualify Manufacturing Process • Factory Improvements • Design Policy • Uniform Test Report • Piece Part Control • Productivity Center • Design Process • Software Test • Design Analysis • Design Limit • Parts & Mater. Selection • Life • Software Design • Test, Analyze & Fix (TAAF) • Design Requirements • Trade Studies • Computer-Aided Design (CAD) • Design for Testing • Field Feedback • Built-In Test (BIT) • TEMP Development/ Execution • Configuration Control • Design Reviews • Design Release • Concept Studies & Analysis • Bread Board Development • Brass Board Development • Specification Dev/Allocation/ Validation • Design for Assembly • Prototype Development & Review • Software Simulator Cost Assessment • Subcontractor Control • Defect Control • Tool Planning • Field Visits/Site Surveys LOGISTICS • Logistics Support Analysis • Manpower & Personnel • Manufacturing Strategy • Personnel Requirements • Data Requirements • Support & Test Equipment • Technical Risk Assessment • Training Materials & Equipment • Production Breaks • Special Test Equipment (STE) • Spares • CAM • Logistics Analysis Documentation • Manufacturing Screening MANAGEMENT • Technical Manuals • Determining Defining Need for System • Prepare Requirement Documents • Quality Assurance • Design/Milestone Review Planning CAM •Manufacturing Screening •Production Fabrication •Environmental Issues • Production Fabrication • Make or Buy Decisions • Environmental Issues • Technology Base Analysis • Schedule & Planning • Dim. Manuf. Sources & Mat. Shortage (DMSMS) New PMWS Templates TRANSITION PLAN www.bmpcoe.org Technical Risk Identification & Mitigation System 23 TRIMS Tailoring TRIMS Hierarchy Funding Design User Added Templates www.bmpcoe.org Test Production Facilities Management Logistics Transition Plan 3 Tiers: Category User Added Questions User Added Categories Template Knowledge Base Question Technical Risk Identification & Mitigation System 4.0 Design 4.6 Design Analysis 4.6.1 Do the contractor's corporate standards identify design analysis as an integral part of the design process? 24 TRIMS Tailoring User Created Model 3 Tiers: Category Template Knowledge Base Question www.bmpcoe.org Technical Risk Identification & Mitigation System 4.0 Design 4.6 Design Analysis 4.6.1 Do the contractor's corporate standards identify design analysis as an integral part of the design process? 25 Tailoring TRIMS To Your Needs • Identify Risks Before they Become Problems • Build YOUR Knowledge into TRIMS – Use the Systems Engineering Knowledge Base as a Starting Point for A Good Engineering Process • Create a Concrete, Repeatable Process for Evaluating & Comparing Programs & Contractors • Ease the Learning Curve for New Employees • Retain Knowledge of Lost Employees • Share Knowledge • To Maximize Benefits of Using TRIMS – Apply as Early as Possible in Program Life – Apply to All Subcontractors, Divisions & Vendors Involved – Use Tool Regularly to Prioritize Resources & Make Decisions www.bmpcoe.org Technical Risk Identification & Mitigation System 26 TRIMS Knowledge Models • Existing (Released) Models – – – – Systems Engineering Software Risk Engineering (Carnegie Mellon) Circuit Card Testability Interoperability and Integration • Existing (Beta) Models – Human Factors Engineering • Development (Prototype) Models – Management – Port Security/Force Protection – SBIR ◄ ◄ ◄ TRIMS Has Many Applications www.bmpcoe.org Technical Risk Identification & Mitigation System 27 TRIMS Version 4 www.bmpcoe.org Technical Risk Identification & Mitigation System 28 TRIMS - Total Risk Management 3 P RM Problem, Product & Process Risk Management, in a Single Tool! www.bmpcoe.org Technical Risk Identification & Mitigation System 29 Conclusion www.bmpcoe.org Technical Risk Identification & Mitigation System 30 How To Get Help Using TRIMS • Use the Help menus • Use the Computer-Based Training (CBT) Videos – Available on PMWS CD and on BMP’s Website – These are Animated & Narrated Tours Showing Each Step of Using TRIMS • Call our 24 Hour Helpdesk 301-405-9963 • E-Mail the BMP Center at helpdesk@bmpcoe.org • Arrange a Training Session Help Is Available www.bmpcoe.org Technical Risk Identification & Mitigation System 31 3 Things To Remember… • DoD 4245.7-M / NAVSO P-6071 – The Transition from Development to Production – The Best Practices Book • TRIMS – Free Tool – P3RM – Supports Problem, Product, and Process Risk Tracking! • BMP Enterprise / BMP Center of Excellence – An Available Resource – www.bmpcoe.org – Call our 24 Hour Helpdesk 301-405-9963 www.bmpcoe.org Technical Risk Identification & Mitigation System 32 [ End of Presentation ]